PERHITUNGAN WAKTU KERJA CONTAINER ER-1 (8059*

TIME ACCOUNT
m h d
420 7 1

JUMLAH CYCLE TIME/Pcs TOTAL CYCLE TIME Time schedule


NO ITEM PEKERJAAN Qty MANPOWER
MANPOWER (MINUTE) (MINUTE) munite hour day
Baseframe
A. Cutting Process
1 Cutting Profile Perimeter Beam 4 Tri s. 1 10.00 40.00
2 Cutting Purlin 7 Tri s. 2 10.00 35.00
3 Cutting Support 7 Tri s. 1 5.00 35.00
B. Finishing Process
1 Finishing After Profil 18 Tahajul, Tri p. 2 20.00 180.00
C. Setting Process
1 Fit up Joint Perimeter Beam 4
2 Fit up Joint Perimeter Beam & Purlin 7
3 Fit up Joint Perimeter Beam &Support 7
4 Leveling after Welding
5 Marking Lifting Lug
6 Drilling Lifting lug
TOTAL 290.00 290.00 4.8333 1
Welding Process
1 Welding Joint Perimeter Beam 4 Budi 1 30.00 120.00
2 Welding Joint Perimeter Beam & Purlin 7 Budi 1 20.00 140.00
3 Welding Joint Perimeter Beam &Support 7 Budi 1 20.00 140.00
4 Finishing After Welding 18 Tahajul, Tri p. 2 20.00 180.00
TOTAL 870.00 870.00 14.5 2
Blasting & Painting Process

TOTAL Pcs/DAY (PROSES 1 + PROSES 2)(SENIN-KAMIS)


TOTAL Pcs/DAY (PROSES 1 + PROSES 2) (JUMAT)
TOTAL Pcs/WEEK (PROSES 1 + PROSES 2)
TOTAL Pcs/MONTH (PROSES 1 + PROSES 2)
TOTAL TIME/DAY (SENIN-KAMIS) (MINUTE)
TOTAL TIME/DAY (JUMAT) (MINUTE)
TOTAL TIME/WEEK (MINUTE)
TOTAL TIME/MONTH (MINUTE)
ASSEMBLING FRONT AXLE
1 PERAKITAN GEAR DIFFERENTIAL (SETTING) RIO + RONI 2 26.20
2 PERAKITAN DIFERENTIAL KE BENJO RONI + ADE 2 19.20

3 PERAKITAN STEERING KNUCKLE,SPINDLE KNUCKLE, DAN BRAKE PLATE RIO 1 60.00 142.20
PEMASANGAN LONG TIE ROD, SPOORING DAN SETTING STOPPER
4 1 15.00
STEER
5 PENGECATAN FRONT AXLE ASEP 1 21.80
TOTAL Pcs/DAY (PROSES 1 + PROSES 2 + PROSES 3 + PROSES 4)(SENIN-KAMIS)
TOTAL Pcs/DAY (PROSES 1 + PROSES 2 + PROSES 3 + PROSES 4) (JUMAT)
TOTAL Pcs/WEEK (PROSES 1 + PROSES 2 + PROSES 3 + PROSES 4)
TOTAL Pcs/MONTH (PROSES 1 + PROSES 2 + PROSES 3 + PROSES 4)
TOTAL TIME/DAY (SENIN-KAMIS) (MINUTE)
TOTAL TIME/DAY (JUMAT) (MINUTE)
TOTAL TIME/WEEK (MINUTE)
TOTAL TIME/MONTH (MINUTE)
WELDING FRONT AXLE
1 PERAKITAN BENJO,ADAPTOR DAN TRUNION DARMA 1 83.50
168.20
2 PERAKITAN TEMPAT U-BOLT ANWAR 1 84.70
TOTAL Pcs/DAY (PROSES 1 + PROSES 2)(SENIN-KAMIS)
TOTAL Pcs/DAY (PROSES 1 + PROSES 2) (JUMAT)
TOTAL Pcs/WEEK (PROSES 1 + PROSES 2)
TOTAL Pcs/MONTH (PROSES 1 + PROSES 2)
TOTAL TIME/DAY (SENIN-KAMIS) (MINUTE)
TOTAL TIME/DAY (JUMAT) (MINUTE)
TOTAL TIME/WEEK (MINUTE)
TOTAL TIME/MONTH (MINUTE)
WELDING CHASSIS BOOGIE (KOMPONEN
1 CHASSIS BOOGIE DEPAN KIRI DARMA 1 19.40 BUTUH 4 ORG)
2 CHASSIS BOOGIE DEPAN KANAN DARMA 1 20.60
113.40
3 CHASSIS BOOGIE BELAKANG KIRI DARMA 1 37.50
4 CHASSIS BOOGIE BELAKANG KANAN DARMA 1 35.90
TOTAL Pcs/DAY (PROSES 1 + PROSES 2 + PROSES 3 + PROSES 4)(SENIN-KAMIS)
TOTAL Pcs/DAY (PROSES 1 + PROSES 2 + PROSES 3 + PROSES 4) (JUMAT)
TOTAL Pcs/WEEK (PROSES 1 + PROSES 2 + PROSES 3 + PROSES 4)
TOTAL Pcs/MONTH (PROSES 1 + PROSES 2 + PROSES 3 + PROSES 4)
TOTAL TIME/DAY (SENIN-KAMIS) (MINUTE)
TOTAL TIME/DAY (JUMAT) (MINUTE)
TOTAL TIME/WEEK (MINUTE)
TOTAL TIME/MONTH (MINUTE)
No PROCESS NAME

CONTAINER ER-1
1 FABRIKASI BASEFRAME
Cutting Profile Perimeter Beam
Cutting Purlin
Cutting Support
Finishing After Profil
Setting Perimeter Beam
Setting Purlin
Setting Support floor plate
SettingSuport cable tray
Setting Floor Plate
Welding Floor plate
Setting Grounding Pad
Lubang lifting lug
Cut hole floor plate
Welding Beam Perimeter,purlin,support
Finishing after welding
Leveling After welding
2 NDT BASE FRAME & SPREADER BAR
Penetran Test & Inspection Basframe
Penetran Test & Inspection Spreader Bar
3 FABRIKASI DAN PEMASANGAN OMEGA FLOOR
Cutting & Setting
Welding joint Beam
4 PEMASANGAN PLAT LANTAI
Setting
Welding joint Plate & Beam
Finishing after welding
5 BLASTING & PAINTING BASEFRAME
Blasting
Painting
6 PEMASANGAN Z BAR U BAR
Setting Z-BAR
7 PEMASANGAN DINDING PARTISI SANDWICH
Cutting Wall
Install wall
Sealent inner wall
Sealent Outer wall
8 ROOF
Cutting Wall
Install Roof
Install Flashing Roof
9 ACCESORIES (PINTU DAN VYNIL DLL)
Install Frame & Single Door
Install Frame & Double Door
Install Canopy
Additional Blank Plate Floor Plate
Cutting & Finishing
Drilling
Install
Install Vinyl
Instal Plint
Rankeng Out Door AC
10 PAINTING WALL
Surface preparetion
Primer
Top Coat
11 PEMBUATAN DUDUKAN AC OUT DOOR DAN PENGECETAN
Cutting
Finishing after Cutting
Painting
Install
12 FABRIKASI SPREADER BAR, LIFTING LUG dan PAINTING
Cutting Lifting lug
Cutting Pad eye
Cutting Spreader Bar & Finishing
Assy spreader Bar
Assy Lifting Lug
Welding Spreader bar
Welding Lifting Lug & NDT Process (PT)
Painting Spreader bar & Lifting Lug
13 FABRIKASI CONDUIT DAN CABLE TRAY
Cutting & Marking
Setting
14 PEMASANGAN CABLE TRAY & CONDUIT
Install
15 PEMASANGAN LAMPU & SMOKE DETECTOR
Install
16 PEMASANGAN SWITCH,RECEPTACLE AND SOCKET
Install
17 WIRING CABLE
Pengkabelan
18 PEMASANGAN AC
Install AC Indoor
Install AC OUT door
19 INSTALATION PDB & FIRE EXT
Install PDB
FireExt
Lain-lain
MANPOWER JUMLAH CYCLE TIME/Pcs TOTAL CYCLE TIME Time schedule
Qty
Name MANPOWER (MINUTE) (MINUTE) munite hour

4 Tri s. 1 10.00 40.00

7 Tri s. 2 10.00 35.00

7 Tri s. 1 5.00 35.00


18 Tahajul, Tri p. 2 20 180.00
ime schedule
day
SUB ASSY
NAMA PEKERJAAN WAKTU PER 1 UNIT (MENIT) MINIMAL JUMLAH PRODUKSI TOTAL WAKTU (MENIT)
2 ORANG PERAKITAN GEAR SHAFT ASSY A,B,C, DAN D 10.00 5 50
PERAKITAN GEAR DIFFERENTIAL (SETTING) 26.20 5 131
PERAKITAN DIFERENTIAL KE BENJO 19.20 5 96

2 ORANG PERAKITAN TRANSFER + SETTING 10.00 5 50

HELPER 1 ORG PENGECATAN FRONT AXLE 21.80 5 109


COATING TRANSFER 1 LAPIS man hour

PERAKITAN STEERING KNUCKLE,SPINDLE KNUCKLE, DAN BRAKE PLATE


1 ORANG 75.00 5 375
PEMASANGAN LONG TIE ROD, SPOORING DAN SETTING STOPPER STEER

Ket.
No Man power Sub Assy
1 Rio Kadiv
2 feri Installer sub Assy
3 roni Installer sub Assy
4 saiful anwar Installer sub Assy
5 jaenudin Helper
6 andreas Helper