VALORIZACION Nro.

01 (PERIODO 1ro AL 31 DE MAYO DEL 2018)

CLIENTE : H PS.A.C.
OBRA : P ICA PRESUPUESTO BASE 89,009.55 MODALIDAD DE EJECUCION A SUMA ALZADA
CONTRATISTA : H CONTRATISTAS GENERALES S.A.C PRESUPUESTO OFERTADO85,685.93 FECHA : Junio 2017

Item DESCRIPCION PRESUPUESTO CONTRACTUAL VALORIZACION ANTERIORVALORIZACION ACTUALVALORIZACION ACUMULADA AMORTIZACION MONTO DE SALDO
Und. Metrado PU Parcial (S/.) Metrado Parcial Metrado Parcial Metrado Parcial ADELANTO ADELANTO DE TOTAL ADELANTOS DESMBOLSO Metrado Parcial
DIRECTO (10%) MATERIALES POR
(20%) VALORIZACION
01 OBRAS PROVISIONALES Y PRELIMINARES
01.01 OBRAS PROVISIONALES
01.01.01 ALMACEN DE OBRA Y GUARDIANIA m2 9.00 64.67 582.03 0.00 9.00 582.03 9.00 582.03 58.20 116.41 174.61 407.42 0.00 0.00
01.01.02 EQUIPO E IMPLEMENTOS DE SEGURIDAD DE OBRA GLB 1.00 1,533.15 1,533.15 0.00 1.00 1,533.15 1.00 1,533.15 153.32 306.63 459.95 1,073.21 0.00 0.00
01.02 TRABAJOS PRELIMINARES 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.02.01 TRAZO Y REPLANTEO DURANTE LA EJECUCION DE LA OBRA m2 104.78 1.63 170.79 0.00 104.78 170.79 104.78 170.79 17.08 34.16 51.24 119.55 0.00 0.00
01.02.02 LIMPIEZA MANUAL DE TERRENO m2 104.78 14.28 1,496.26 0.00 104.78 1,496.26 104.78 1,496.26 149.63 299.25 448.88 1,047.38 0.00 0.00
02 ESTRUCTURAS 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.01 MOVIMIENTO DE TIERRAS 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.01.01 EXCAVACIÓN MANUAL DE CIMIENTO CORRIDOS m3 41.14 40.02 1,646.42 0.00 41.14 1,646.42 41.14 1,646.42 164.64 329.28 493.93 1,152.50 0.00 0.00
02.01.02 EXCAVACIÓN MANUAL DE ZAPATAS EN SUELO NORMAL m3 23.11 24.06 556.03 0.00 23.11 556.03 23.11 556.03 55.60 111.21 166.81 389.22 0.00 0.00
02.01.03 ELIMINACION MATERIAL EXCEDENTE CON EQUIPO m3 80.32 27.80 2,232.90 0.00 80.32 2,232.90 80.32 2,232.90 223.29 446.58 669.87 1,563.03 0.00 0.00
02.02 OBRAS DE CONCRETO SIMPLE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02.01 CIMIENTO CORRIDO 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02.01.01 CONCRETO F'C=100 KG/CM2 EN CIMIENTOS CORRIDOS m3 28.57 255.00 7,285.35 0.00 28.57 7,285.35 28.57 7,285.35 728.54 1,457.07 2,185.61 5,099.75 0.00 0.00
02.02.02 SOLADOS 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02.02.01 SOLADO E=3'' m2 21.73 26.00 564.98 0.00 21.73 564.98 21.73 564.98 56.50 113.00 169.49 395.49 0.00 0.00
02.02.03 SOBRECIMIENTOS 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02.03.01 CONCRETO F'C=140 KG/CM2 EN SOBRECIMIENTOS m3 4.69 262.00 1,228.78 0.00 2.00 524.00 2.00 524.00 52.40 104.80 157.20 366.80 2.69 704.78
02.02.03.02 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTOS m2 62.48 31.58 1,973.12 0.00 30.00 947.40 30.00 947.40 94.74 189.48 284.22 663.18 32.48 1,025.72
02.02.04 FALSO PISO 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02.04.01 CONCRETO F'C= 100 KG/CM2 (E=4'') EN FALSO PISO m3 10.50 260.00 2,730.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.50 2,730.00
02.03 OBRAS DE CONCRETO ARMADO 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.03.01 ZAPATAS 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.03.01.01 CONCRETO F'C= 175 KG/CM2 EN ZAPATAS m3 10.92 310.16 3,386.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.92 3,386.95
02.03.01.02 ACERO CORRUGADOS F'Y=4200 KG/CM2 EN ZAPATAS kg 20.00 4.10 82.00 0.00 10.00 41.00 10.00 41.00 4.10 8.20 12.30 28.70 10.00 41.00
02.03.02 VIGAS DE CIMENTACION 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.03.02.01 CONCRETO F'C= 175 KG/CM2 EN VIGA DE CIMENTACION m3 3.23 329.51 1,064.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.23 1,064.32
02.03.02.02 ENCOFRADO Y DESENCOFRADO VIGA DE CIMENTACION m2 40.40 56.29 2,274.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 40.40 2,274.12
02.03.02.03 ACERO CORRUGADOS F'Y=4200 KG/CM2 VIGA CIMENTACION kg 19.00 4.10 77.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 19.00 77.90
02.03.03 COLUMNAS 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.03.03.01 CONCRETO F'C= 280 KG/CM2 EN COLUMNAS m3 14.52 491.73 7,139.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14.52 7,139.92
02.03.03.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS m2 53.85 65.06 3,503.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 53.85 3,503.48
02.03.03.03 ACERO CORRUGADOS F'Y=4200 KG/CM2 kg 20.00 4.93 98.60 0.00 10.00 49.30 10.00 49.30 4.93 9.86 14.79 34.51 10.00 49.30
02.03.04 VIGAS 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.03.04.01 CONCRETO F'C=210 KG/CM2 EN VIGAS m3 15.53 369.99 5,745.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 15.53 5,745.94
02.03.04.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS m2 35.25 66.82 2,355.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 35.25 2,355.41
02.03.04.03 ACERO CORRUGADOS F'Y=4200 KG/CM2 kg 25.50 4.93 125.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 25.50 125.72
02.03.05 LOSAS ALIGERADAS 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.03.05.01 CONCRETO F'C=210 KG/CM2 EN LOSA ALIGERADA m3 21.50 348.51 7,492.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 21.50 7,492.97
02.03.05.02 ENCOFRADO Y DESENCOFRADO EN LOSA ALIGERADA m2 100.50 42.59 4,280.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 100.50 4,280.30
02.03.05.03 ACERO CORRUGADOS F'Y=4200 KG/CM2 kg 750.22 4.93 3,698.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 750.22 3,698.58
02.03.05.04 LADRILLO DE TECHO 0.30 X 0.30 X 0.15 m pza 921.50 2.46 2,266.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 921.50 2,266.89

TOTAL COSTO DIRECTO S/. 65,592.88 0.00 17,629.61 17,629.61 1,762.96 3,525.92 5,288.88 12,340.72 47,963.28
GASTOS GENERALES 10% 6,559.29 0.00 1,762.96 1,762.96 176.30 352.59 528.89 1,234.07 4,796.33
UTILIDAD 5.00% 3,279.64 0.00 881.48 881.48 88.15 176.30 264.44 617.04 2,398.16
SUB TOTAL 75,431.82 0.00 20,274.05 20,274.05 2,027.40 4,054.81 6,082.21 14,191.83 55,157.77
FACTOR DE RELACION 0.96266 0.96 0.96 0.96 0.96 0.96 0.96 0.96
SUB TOTAL x FR 72,615.19 19,517.01 19,517.01 1,951.70 3,903.40 5,855.10 13,661.91 53,098.18
IMPUESTO GENERAL A LAS VENTAS 18% 13,070.73 0.00 3,513.06 3,513.06 351.31 702.61 1,053.92 2,459.14 9,557.67
TOTAL PRESUPUESTO (S/.) 85,685.93 0.00 23,030.08 23,030.08 2,303.01 4,606.02 6,909.02 16,121.05 62,655.85
% DE AVANCE FISICO 26.88% 26.88% 23,030.08 73.12% 100.00%