Documente Academic
Documente Profesional
Documente Cultură
BY
B Balwant Rao 8 C. Muthuswamv
CONTENTS
Introduction
Forces Acting on Well Foundations
Scour Around Wells
Property of Materials in which a
Well is likely to rest
Well Shapes
Evaluation of Lateral Earth Support to
Well Foundations
Design of Well Steining
Design of Well Curb and Cutting Edge
Design of a Well Cap
Materials for Construction of Wells
Sinking of Wells and Its Problems
Testing of Well Foundations
Conclusions
SYNOPSS
Collecting information fr?m different sou- and giving the e-cl~p Of
the Authors in this Paper, it I S s m e d to focus anentlon of the E n m a r s On
the procedure for design and sinking of wells for foundation of bridges.
Tho Paper deals with the subject both from considerations of d e d m .ad
d d requirements and includes suggestiona of the Authors.
This Paper docs not represent the views of the Cwaulcial Engfne8r
(Road Development). Ministry of Transport, Roads Wing.
A u v s of th&Pepcr were awarded e Indian Roads CoaensMcdal;
epuly ridges ccr. Addl. ~ircctorfeeneral(Bridges) (Rctd.) M l n b l n
of Shippin &Transport (Roads Win ) Government of India.
t)~ivisiooa? Enginem. Consultant. !dads Wine. Government oflqdb
[now Director of Designs (Ports), Ministry of Transport & Avhtron.
Transport Wing, Ncw Delhi].
1
2 BALWANTRAO & MUTHUSWAMY
ON
I . INTRODUCTION
PRECSUSC
OIAGRAH
Fig. 2.1
For practical purposes, the pressure curve is assumed to vary
linearly with maximum value of ~ ' - 2 p at H.F.L., vide Fig. 2.1.
The pressure and moment between any two sections yy and zz are
as given below :
J
Centre of pressure 5 =-- Y
P -r
where H - Y
length of pier in ft in the direction of Bow, and
Z = depth of water in ft between maximum scour level and
'free surface of water
D ~ I GAND
N SINKINGOQ WELL FOUNDATIONS
FOR BRIWES 5
fiv) According to I.R.C. Bridge Code, if the bed is rocky
water pressure acting simultaneourly on all the piers
between their opposite faces equivalent to pressure caused
by a differential head of 0.75 ft of water should also be
considered. Greater of the two forces given in (iii) and
(iv) above shall govern the design.
2.6. Wind and Seismic Forces
26.1 Wind force8
(i) The relationship between wind and seismic forces for
design purposes is well rccogniscd. The ampted design
practice is to consider one of these in combination with
other forces and take the combination causing most
severe stresses. Wind and seismic forces are not considered
as acting together or simultaneously.
(ii) Magnitude of the horizontal wind pressure on a bridge
depends on the area ejtposed and the location of the
bridge ;it is determined according to the provisions made
in the I.R.C. Bridge Code.
(iii) Wind blowing at an angle to the longitudinal axis of the
bridge produces longitudinal and transverse wind forces.
its effect cannot be resolved into simple trigonometric
components, Lateral and longitudinal load co-efficient
factors for various angles of skew of the direction of wind
for girder bridges are given iu Table 2. I.
TABLE
2.1
where,
f -
Q = discharge in cubic feet per second, and
silt factor, varying from 0.4 for very fine d1ts to
2.00 For very heavy sand.
If the waterway is contracted from the regime width, tacey's
modification for such a condition is given by-
Fig. 3.1
It is. therefore. recommended that for design purposes even in
the care of sin& span bridges, the maximum scour should also be
taken equal to 2 D.
An important point is that the maximum scour in the case of
abutments occurs a t the upstream corner and not a t the downstream
end while in the case of a pier, the maximum scour occurs at the
downstream end.
3.2. Researches conducted recently by the Iowa Research
Laboratory on models and proto-types on sandy bed bring out that
the scour changes with time. The depth of flow depends on the
adjustment of bed and silt carrying capacity of the water current a t
different sections. As the scour hole increases in size, its rate of for-
mation decreases. the maximum depth of scour takes place before the
first mass of sediment settles in thLscour depression tb induce condi-
tion of eauilibrium. Coming to this condi:ion of eauilibrium though
takes tinie, will not last h e t o the discharge i n the stream being
rarely constant for a su5ciently long period. This is illustrated by
the scour depth-time relationship curve given in Fig. 3.2.
----
Pig. 3.2
3.3. The s o u r pattern around piers set a t different angles t o the
direction of flow are indicated in Fig. 3.3 which shows the effect of
the angle of flow o r attack on scour depth With the increase in the
angle of flow, a greater length of the pier obstructs the flow causing
wider and deeper scour. In every case, scour is deepest on the
downstream side of the pier.
lo* so* 30'
The value of d,
- for various values of p can also be picked from
Y
Fig. 3.4.
T'
%
Y
I *'
1 n
nsnu or SCOUI AROUND PIEIS
Fig. 3.4
An example to illustrate the effect of reduction of waterway in
lowering the bed level of the stream is given below :
ExampIe 1 :
The cross section of stream with 10 feet depth of flow from
H.F.L.is reduced by 20 per cent due to approaches and the pler
blocking the effective waterway as shown in Fig. 3.5. It is required
to Bod the general increase in bed deepening :
ROAD LEVEL
Fig. 3.5
y-I0 feet
830.20
From graph in Fig. 3.4. for p-0.20,
.- ,
.. d, = 0 . 2 5 ~10=2.5say 3 feet :
i.e., total depth of flow will increase from 10 feet to 13 feet.
3.5. The scour below bed level for a rectangular pier, obtained
from the experiments carried out by the Iowa Research Laboratory
for a zero angle of attack and plotted non-dimensionally as equili-
brium depth of scour against depth of flow with the width of pier at
bed level used as the common variable, is given in Fig. 3.6 which
may be used for determining the scour around a pier.
Fig. 3.6
3.6. If the pier is at an angle t o the flow of the currept, the
normal scour depth obtained from Fig. 3.6 has to be multipl~ed by
a factor K (based on
*'
L
0
55
z
-
0
z
t
2
E 3
2I
1
I
1.20 10. A M 75 PO
ANGLE OF ATTACK IN DEGREES
Dmign factor for piers not aligned in the d~rectinnof ROW
Fig. 3.7
.While designing the bridge piers, it is always desirable to assume
the direction cf flow at 20 degrees even in those cases where the
angle of flow is less than 20 degrees to the direct~onof the pler to
provide for a possible variation of flow in the river.
3.7. Scour depths in excess of equilibrium depth of the scour
can occur. This is associated with unsteady flow condition and is
DBSlGN AND S I ~ I NOF
G WBLL FOUNDATIONSPOR BRIDGES 11
given in Fig.. 3.2. The predicted depth of scour in such cases should
be increased to account for flash floods by a t least fifty per cent for
rivers with catchments subjected to sudden downpour like cyclonic
storms. An example illustrating the use of these curves is given
blow :
Example 2 :
A cross section of the bridge pier which collapsed due to scour
(Photo 1) is given in Fig. 3.8. The width of pier at the bed levd of
the stream is 6.5 feet and depth of flow 17.88 feet. With an observed
scour of 18.5 feet below the bed level, the pier was undermined.
The probable scour depth that could be anticipated below the bed
level is given below :
".I., ,I*
.... -
.I
.
: i
2-!
Fig. 3.8
Depth of flow, y 17.88 ft 17.88 ft
Dep!h of flowlbreadth of pier, 17.8816.5 2.70
Y
d~/b,from Fig. 3.6 f o r 7 =2.7 - 2.10
Angle of attack of flow, a 20 dfg .
I
Ratio, -b
32/65 5
I
K, from Fig. 3.7 for--5 and a =20°. about 2
b
da. scour below bed level 2.1 x 6.5 x 2 27.3 feet, say 28 ft
This indicates that the scour could be expected to extend upto
28 ft below bed level. If the foundation had been taken 28 ft below the
bed, the failure would not have occurred. The actual scour of 18.5 ft
observed or measured below the bed level occurred in over 25 years
and is due to the resistance offered by hard clay strata in which the
pier was founded.
This shows that the total depth of scour in clay will be reached
after a time whm the resistance to r o u r by cohesion of clay is
overcome.
3.8. The effect of velocity and cohesion on the scour is not
included in the experiments referred to in the preceding sections
Rivers with bed consistine of large sized shingle usually have high
velocity during floods. Water with such high velocity will acqnire
higher load carrying capacity flowing past a pier causing scour in the
same manner.
If V. is the velocity in the stream and r. the radius of a circular
pier and V. the velocity on the sides of a pier a t a distance x from
the centre of the pier, then the velocity a t the side of the pier
will be :
Fig. 3.9
Average velocity of
stream in feet per
second
1/28 117
2
518
3
If
4 ..1 -- 5
21 3t
~-
7
I
1 / 1 0
14
- --
From To
1. Granite 2.500 38.W
2. Sandstone 1.200 25.000
3. Limestone 3,'30'3 30,000
4. Marble 11,000 25.W
5. Trap 10.000 24.000
6. Slate 14,000 U),ooO
4.3. In the case of rock bed like the one shown in Fig. 4.1 it is
extremely difficult to determine the safe bearing strength.
Fig. 4.1
4.4. In the case of one bridge, the rock at bed level consisted of
hard and soft rock laminations. Plate bearing test conducted with
12 in. x 12 in. x I? in. plate under 22 ton load applied by hydraulic
14 BALWANT RAO & MIJTI~WAMY
ON
The same test was repeated under 24 ton load on the bed two
feet away from the first site. The results of the second test are
given in Table 4.3.
TABLE4.3
1. 5.00 0.0573
2. 7.50 0.0873
3. 10.00 0.1140
4. 12.50 0.1455
5. 15.00 0.1925
6. 17.50 0.2435
7. 20.00 0.3075
8. 22.00 0.3410
9. 24.0 0.3675
From Table 4.2 it is seen that the settlement under 15 ton load
waa 0.5 in. and under 22 tons 1.32 in. while in Table 4.3, the
settlement under 15 ton was 0.1925 inch, under 22 tons 0.3410 inch
and even under 24 ton load it did not exceed 0.37 inch.
4.5. Tbtrc being no dcfinitc yield point and total settlement not
exceeding half an inch in the second test, tbe load of 15 tons in
Di!SlON AND SINKING OF FOR BRIDGES 15
WELL FOUNDAT~ONS
the first test causing half inch settlement may be taken as the failure
load. In the type of cases discussed, safe permissible load is usually
taken as half the load causing 4 in, settlement, as such 7f tons per
sq. ft. appears to be the safe load for this foundation.
In similar test on granite bed in case of another bridge, only
0.015 in. settlement was observed under 12 ton per sq. ft. load, which
shows that the whole rock without any laniinations can support a
very much greater load.
4.6. The wells resting on rock, due to difficulties in cutting
into the rock, need not be taken deep into it. Cutting 6 in. to 9 in.
into the rock or stepping would he adequate. Wells founded on rock
are invariably anchored into it with mild steel dowels. Test on
one in. diameter dowel bars with 3 ft length inserted in a 1& in.
diameter hole and grouted with cement sand mortar has shown that
the anchor bar developed bond strength exceeding 75 lb per sq. in.
These, when embedded 3 ft in rock, can be relied upon to develop
sufficient bond to resist the pull. As the concrete in plug is compara-
tively more porous for developing full bond, the length of bond rods
in the plug should be at least six feet.
4.7. The number of anchor bars t o be provided depends on the
nature of the rock profiles and the base pressure. If there is tension
devdoping over any portion of the base, anchor rods should be pro-
vided to take the full tension. If the rock is sloping. the base should
be stepped and anchor rods provided at every step to prevent slipping.
In any case, a mioimum spacing of 3 ft along the internal periphery
of the well is desirable, vide Fig. 4.2.
Fig. 4.2
fig. 4.3
i '*F
:tl
2 0 1 / 1 1 1
Typ of clay
Safe bearing capacity
itoo ner sa. ft.1
Angular grains
(4 in degrees well graded
i (4 in degrees!
1. Loose 28.5
2. Dense 35.0
Typical mechanical proporties of clay
TABLB4.8
o . I I I m . x Y
(-11 1.1010" I* L. Pl" ss n
Fig. 4.5
4.18. It could, therefore, be concluded that for the wells in
sandy soils the skin friction can be taken to vary from 100 Ib per
sq. ft. to 300 lb per sq. ft. depending on the depth.
For wells in clayey strata, it is desirable that no allowance
should be made for skin friction while calculating maximum bearing
pressure but it should be taken into account for calculating the
minimum pressure.
4.19. "Bentonite" solution injected on the external surface of
the well considerably reduces its skin friction.
DESIGN FOUNDATIONS FOR BRIWES 21
AND SINKINGOF WELL
5. WELL SHAPES
.-, ,a
Fig. 5.1
5.7. If the well is to sink under its own weight overcoming the
skin friction, i t must have sufficiently thick steining. Taking the
limiting condition when weight of steining is equal to skin friction, for
a circular well, the following relationship can be obtained :
7
4 D * - ( D - Z ~ ) ¶ ] w = n Df
-
or Dwf- wt2=Df
TABLE5.2
Steining thickness t o overcome friction
( w=140 l b per cu. ft.)
Value of 'f' in lb
per sq. ft.
- -
Steining
thickness
0.75 1.70 3.00 5.00 - -
10 ft ex- (ft)
tcrnal
din. wells Size of E.50 6.60 4.00 0.00 -
20 fl ex- (ft)
tcrnal
din. wells Sin of 18.60 16.80 15 20 13.20 10.40 7.40
dredge
hole (it)
Sfeining 0.75 0 2.25 3.15 4.20 5.10
thickness
30 it ex- (It)
ternal
din. wells Size of 28.50 27.00 25.50 23.70 21.60 19.80
dredge
hole :ft)
Note : Buoyancy not considered.
It would be seen from Table 5.2 that the weight of a 10-ft exter-
nal diameterwell with 1.70 ft thick steining will balance the total skin
friction caused at the rate of 200 ib per sq. ft. and it will need some
additional kentledge for sinking the well. Similarly, in case of a 20 ft
external diameter well with 4.6 ft thick steining in soils with skin
friction of 500 lb per sq. ft. will need some additional kcntledge for
sinking.
However, for economic and other considerations, the minimum
thicknesr of the steining may be 118 of the external diameter of the
well with a minimum of I + ft for masonry wells. For cement con-
crete wells the thickness of the well steining is kept 1/10 of the
external diameter with minimum thickness of 12 inches. This thick-
ness for the whole length of the masonry wells should, however, be
Detro~AND SINKING
OF WELL FOUNDA~ONS
POR BRIWES 25
increased by 4 inches after 10 ft for every 10 ft depth thereafter.
In case of ckment concrete wells, this increase shall be 6 in. after
20 ft depth and for every additional 20 ft depth thereafter.
6.6. Total dead and live load upto the maximum scour level
of the bridge pair being known, the self-weight of the portion of the
well below the maximum scour level after allowing for buoyancy is
added to get the total direct load coming over the foundation. This
will give the uniform normal pressure on the soil. Knowing the safe
bearing capacity of the soil below the foundation, the additional
N SINKINGOF WELL
D ~ I GAND FOVNDA~OM
FOR BRIWPS 27
pressure that the soil can take to withstand effects of the resultant
overturning moment can be worked out. The following expressions
give the maximum pressure that the soil at the base of well has t o
bear without exceeding its safe bearing capacity (see Fig. 6.1).
-. I. l* I..".
,., I
.,
".
.-
Fig. 6.1
or, M B = ( P ~ - ~ ~ ) Z E
where p,=safe bearing capacity of the foundation soil
assumed or known.
I.--=IY
A
-- normal intensity of pressure
IY,+Wz,
A
W=(W,+ W;), net direct load coming on the well
base,
W,=total weight of the well less buoyancy for the
portion above maximum scour level,
W,=self weight of well less buoyancy below the
maximum scour level,
A=arca of well base,
h=s,
ZB
bending stress
ME =maximum moment at the base that can be safely
carried by the soil within its bearing capacity
without developing tension, and
ZE =section modulus of the well at its base.
If M R = M E , then the base pressures are within the limits a s
in Fig. 6.1 (a) and (b) and the base pressures exceed the limits
when MR >ME as in Fig. 6.1 (c), whrre.f ', =-? MR. The pattern
-8
of pressure distribution under a well is not exactly trapezoidal hut
it will be in the shape of a bulb. The slight variation in pressure
due to the tilt of the well will neither materially affect nor increase
the bearing pressure. The distribution of pressure indicated in
Fig. 6.1 (b) is acceptable in practice.
6.7. The well subjected to the horizontal forces presses against
the soil in front compressing it and causing cleavage between the well
and soil on the opposite side. The cleavage or gap may get closed if
the well is surrounded by an ideal non-cohesive soil. If the surround-
ing soil is cohesive then the gap, once formed, may remain and get
filled with water and silt or sand and thus destroy any relief by way
of adhesion that a clayey soil could be capable of. It is very likely
that on the removal of the horizontal force, the well of its own wiU
not completely regain its normal position.
where A = -%
L '
and considzring tilt of the well about its base
A. will be given [Vide Fig. (6.3)] as :
(6.3b)
D
For various ratios of --,
L
the value of A. can be determined
D
for a given A. Assuming that -= 1.00 will produce full resistance
L
D
with afactor of safety of 2.0, the values of A, and f for different -
ratios for A - 1.0 and P = f, are given in Table 6.1. Similarly
Table 6.2 gives the value of A , and f for A = 1.0 and P = 0.
L
-
Fig.6.3
6.12. Due to the size of wells being large the shape factor
included in the expression developed in this chapter may not have
greater influence on the extent of passive pressure mobilized.
6.13. The quantum of passive earth resistance offered to the
well will be given by the expressions :
qmaa = mD. (D-2D1) (6.4)
in which 2 D, = 3 HI fJ9 HIY--2D(3H,-~D) (as)
where,
q,,, = the equivalent maximum earth resistance acting a tH ft
above the maximum scour level,
H = height in feet, above the maximum scour level, of the
point of application of resultant horizontal force due
to applied forces and moments,
D = depth, in feet, of well below the maximum scour level,
Hi = (H+D).
32 BALWANTRAO& MUTHUSWAMY
ON
.,<
. . ...". ~. ,.
,. ,.
m... "-a,.
. ,, .
Fig. 6.4
Fig. 6.5
. # #
m*..IO*
*I
I*TO*'
" n.
.I"I.,
,.
Pig. 6.6
6.16. Duriog sinking of wells, the clay next to the well will get
disturbed and get remoulded by the squeezing out of some of the
water.
6.17. The re.sult of a test and l l ~ evariation with depth of the
value of c ' for both the undisturbed and remoulded clay is given
in Fig. 6.6. I t shows that though the rate of increase of cohesion
with depth is [here, it is not very substantial. The value of ' c '
cannot be taken i~nifnrmthroughout the depth; the law governing
its variation is not known ; therefore, an average rectangle has been
considered for the purpose of design. The value of ' c ' ior the
purpose of evaluating the passive resktance should be from a sample
taken from about ll3rd depth of embcd~nentof well below maximum
scour level and shall be an average between its remoulded value and
its experimental value ou an undisturbed sample.
Photo 1 Photo 2
Failure of a bridge pier Foundation of a bridge showing
due to scour variations in rock characteristic
;'.
,:, "t:
.:.<L--;:.,.., Photo 4
Helmet and the fittings in the
Photo 3 foreground. The skip box fixed in
Diver with helmet on before position ready for concreting
entering the well bottom plug
Photo 6 Photo 7
Skip box open at top. Skip box showing the
Note : Canvass cover release mechanism
Photo 8
Load test of a well
HIR BRIDGES
OF WELLFOUNDATIONS
AND SINKING
DESIGN 39
6.18. When the well is resting in and on clayey soil mixed
with little sand, the bulk head formulae could be used with suitable
modifications ; the base frirction being absent will not restrict its
rotation about the base. Tho assumption here, as already argued,
is that the average resistance of e in clay per foot depth is consrant
because it is independent of the magnitude of the tilt of the well.
The expressions (6.11) can, therefore, be written as given heldw :
nr
Knowing the value of Da, the value of q,.,. and the moments
at any point can be worked out.
6.19. The maximum quivalent horizonal force, q,.. . due to
the pasrive resistance of the soil having been calculated, the
unbalanced force acting at H feet abovr the maximum scour level
that is contributing to the resultant overturning moment at the base
will be :
Q x =(Q-qmse) (6.16)
and M R -(Q-~ma=). ( H + D )
='R (H+ D). (6.17)
In order to keep the bearing pressure of the soil at the base within
the permissible limits, At,, iq equation (6.17) must be less than or
equal to h f ~in equation (6.2). that is, <M, .
If M n 7 M B , then it should be corrected either by altering the
dimensions of the section of the well or its deplh of embedment by
trial and error On arriving at the factors that make MR = M R . the
actual foundation pressure, ' p b ' cdn be checked from the following
expressions :
Fig. 6.8
or, .* = (%)A
and, M,,,,,,. - (f)-
h a - 2 1 3 Qo 2 Q 4
nl
6.25. The metbods for istimating the lateral earth support for
well foundations and calculating the maximum moment in the
steining of well foundations are explained in the following numerical
examples.
Example I :
A well foundation of a bridge in a non-seismic zone is assumed
to be embedded 46 ft below the maximum scour level, for considera-
tions of foundation soil. The data collected for designing the well
foundation are given below :
External diameter of the well 20.00 ft
Steining thickness 3.00 ft
Area of well base. A 3 15 sq. ft.
Section modulus, Za- of well b a ~ e 785 ft3
Total moment a t the maximum scour
level, M, 13,800 kips. ft
Resultant force at the maximum scour
level, Q. 166.0 kips
Soil surrounding the well Sand
Allowable bearing pressure of soil, pb 6.0 tons per sq. R.
Total weight on the base, W 3,230 kips
Weight of submerged soil, w 60.0 ib per cu. ft.
Angle of internal friction of soil, $ 30' (submergtd)
Ratio of the depth of embedment to the
height of bearings above the maxi-
mum scour level, A 0.33
(i) Lateral Pressure :
Using equation (6.5),
2D1 - 3Hr f J ~ H ,-=2 0 HI - D)
-
From expression (6.4),
qmR,. ) X 2.7 X 46 (46.0 - 4 2 . 8 )
= 198.5 kips.
-
For the ratio of the depth of embedment to the bearing height
equal to 4, the reduction factor f 0.454. Then (for the design
purposes),
q ,,,,,, = 0.454 x 198.5 = 90.0 kips for one well.
or q,.,,,, =3 x 90.0 =; 270.0 kips for two wells
= 15,620 ft kips.
Example 2 :
Same data as in Example I . Assume that the well tilts about
its base.
Using expression (6.7).
= 340.0 kips
with A =? 4, reduction factor f = 0.50
Then q,,,,,. = 0.50 x 340.0 = 170.0 kips
> 166.0 kips.
The pas~iveearth pressure that is expected to be mobilized is
sufficient to relieve the applied resultant horizontal forces.
Example 3 :
Consider in Example I that the soil surrounding the well is clay
mixed with little sand. Assume that the unit average coheslon
c = 750 lb per sq. ft and the angle of internal friction of the soil;
4 = 5". All other data remnin the same as in Example :.
li) Loferal Pres.vtrre r
,It. = 0.3~3
= 0.90
-
In expression (6.15),
55.0 x
kips!sq. ft.
m r 20 tan*(rr
4)
nlr = 2 x 0.333 x 750 :< 20 x tall (45' +
Then, D2*+ 151 E,z + 4350 DI - 316200 = 0
Solving the cubic equation,
Dz = 31.48 ft
Using expression (6.13)
q,,,.. . = (0.90 x 31.48" )+ (2 x 15.70 x 31.48) -
(4 x 0.90 x 46a + 15.70 x 46)
=. 1885 - 1675 = 210 kips.
The passive earth pressure that is expected to be mobilized is
sufficient to relieve the applied resultnut horizontal forces.
14,944 ft kips.
r f mf--
kentledge.
Solving h = - 0 t w] ~ - 3 - P (7.la)
This equation indicates that the skin friction and unit weight of the
well have a bearing on determining the steining reinforcement. The
process is simil;lr to drawing the well thlough an earth mass.
For example, for given depth, H = 100 ft./= 1000 lb/sq. ft.
D = 30ft,r = 3 f t , a n d w = 120lbpercu.ft.;
h = 66 ft, when P = 0.
Steel required to fuily carry this weight will be 113 sq. in., i,e.
nearly I50 lb per 100 cu. ft. of concrete. I t will be noticed that for
the value of skin friction assumed, the steel required to carry this
weight will be co!isiderable.
Fig. 7.2
For steel caisson to be Roated to site. the cutting edge must also
serve as a part of the girder or truss of a deep curb which acts as a
barge.
50 BALWANTRAO& MUTHUSWAMY
ON
Fig. 8.1.
-
curb, ustl;~llydefined by tan = tan 20' = 0.364,
P force in tons per foot run of curb acting uormally to
the bevel surface,
Q = farce in tons per foot length of curb acting tangen-
t~allyto the bevel surface, and
H = horizontal resultant force in tons per foot of curb.
Then.
Sin S - li Cos 6
H pn foot run = N ( ~ ~ - - = ! , )
(!
and total hoop tension, FI = I r . A . , =a,!, 5.~2
- $, (8.3)
where, K
D ~ N
AND SINKINGOF WELL FOUNDATIONS FOR BRIWES 51
While sinking, the external compression or active earth pressure
of the soil may not be fully developed at the curb due t o unsettled
conditions.
8.4. Sometimes, during sinking operations in case of a deep
dredge hole the well may suddenly descend. This can be caused by
sand blows, springs etc. I t is, therefore, desirable to make provision
for increased stresses due to such exigencies by increasing the hoop
tension reinforcements by 50 per cent and by providing vertical bond
rods. The tension in the curb will be (see Fig. 8.1).
H - 0.75 N K ~ (8.4)
8.5. Cnrb Resting on the Bottom Plug
When the cutting edge is prevented from moving down iythe
reactions developed a t the interface of the curb and the bottom
plug, the reaction. neglecting cumulative effect of skin friction. could
be resolved into horizontal and vertical component3 by assuming
formation of a two-hinged parabolic arch within the thickness of the
bottom plug. The weight of the material filled in the well and the
bottom plug will be transmitted to the bed directly.
8.6. For the condition assumed in para 8.5 under the action of
a load uniformly distributed along the horizontal span of the concrete
plug, the following expression for H can be obtained:
Fig. 8.2
where. p = f kw Dl,
-
p' = f kw ( D a)',
w = submerged weight of soil,
= angle of internal friction, and
1 - Sin 4
k=
1 + Sin 4
and the net boop tension will be :
HI = ( H - C)
--
Net weight on the soil = 1500 - 20G = 1300 tons
-q 8.45 tons per sq. ft.
r 4.125 feet
Then,
Hoop tension, H - 8.45 x 12'
16~4.125
(b) Relief due to earth pressure :
(Assuming the bed material to be sand)
&v = 69 1b per cu. ft.
4 = 30'
D = 40 ft
b = 2.75 ft
p = 8.2 tons per foot run
p' = 7 tons per foot run
q d"
Axial thrust per running foot H = -
8 rr
(8.12)
r * I D BEAM
PLAN
!='I1 'a!d
9.4. The square or rectangular well caps supported o n all four
sides are usually designed as flat plates. The formulae for deter-
mining stress and strain in a well cap can be taken from any
standard book. The formulae for flat plates are based on the
assumption that the thickness of well cap is not more than about
one-quarter of the least transverse dimension. The Poisson's ratio
t o be assumed for converting these formulae for a concrete well
cap is0.15.
Brick m ~ u o r y
(i) in lime mortar Nil
(iil in cement sand mortar
1:3 Nil
Stone masoon
(i) in lime mortar I : 2 Nil
(ii) in cement sand mortar
1:3 Nil
Plum concrete with cement
concrete 1 : 3 : 6 Nil
Prcpackt concrete Nil
Cement concrete 1 :3 : 6,
Cemmt concrete 1 : 2 :4 Nil
R.C.C. 1 :2 :4 75
For the steining, the design stresses should not exceed 80 per
cent of the above to allow for any overstress caused by tilts. and
shifts during their rectification. The minimum thickness of stelning
is given in paras 5.7 and 7.5.
10.6. In the cage of brick masonry provided with mild steel
bars as bond bars. as these bars ate not bonded in the same sense as
bars embeded in cement concrete for proper composite action, i! is
not desirable to take the transformed sectional area of these bars ~ n t o
account.
10.7. In seismic areas to keen the oressure on foundation and
the centre of gravity low, sometimes hsnd illinp in the foundation wells
is done only i ~ to
p the maximum scour level. This adds to the general
stability of the bridge and reduces the dead load moment. In all such
cases, it is good practice to lay about 3 ft thick concrete plug on top
of the sand filling.
0.'" r,Olro
Fig. 11.1
,
DESIGN OF W ~ L FOUNDATIONS
AND SINKING L FOR BRIDGES 61
DETAILS OF GRAB
Height I Width
j
I'
Capacily Main Side Of
Opsn Closed open Closed urn
I
)O CU. ff. V.0' 6'-9" 5'-3" 1
5'-10" 20'-3" 14-7" 4'43.
35 ,, 10'43' 8'-0" 5.4" &2" 18'-2" 11'.6" S.0'
Two major bridges located very near each other. with fpunda-
tions taken deeper than 100 ft through clay and sandy strata with
very similar characteristic variations and having wells of very nearly
equal sizes and of steining areas, presented an interesting study of the
relative merits of the two methods of sinking adopted. One contrac-
tor did the sinking of wells with divers while the other made use of
grabs. Both had organised the works efliciently.
The relative merits were examined with the following conside-
rations for selecting the most effective methqd for any particular
aituation :
(I) Cost of sinking, excluding overheads but including
plant depreciation and running expenses, kentl~dge,etc.,
( 2 ) Initial cost of the equipment t o be used,
(3) Speed of sinking of wells for quick completion of
work, and
(4) Safety during sinking.
Fig. 11.2
:4) Safety
In case of grabs, there is no danger of men losing their life due
t o a sudden sand blow or due to water preccure at sreat depths of
sinking. Whereas in cilse of divers usins steel helmets and compress-
ed air. the divers are always in danger of failure of equipment. ?and
blows and working at great depths
11.5. The method adopted for correctly placing the curb
depends on local configuration.
(I) Ifthe bed of the river is high. the bed is excavated upto
within say 6 in. above the subtoil water level The curb
is then laid there and after it has sufficien!ly hardened,
say after 5 days. steining is built over it [Fig. 11.3 (all.
..-t -. .-
Fig. 11.3 ( a )
w
. -""..
Fig. 11.3 (b)
The sand island method has been very sucassfully used upto
I5 ft depth of water. The sides of the sand island must be at least
three times the diametcr of the well.
COFFER o m
Fig. 11.4
11.6. If the depth of standing water and the variation in the
water.level at the site of the well make the formation of sand island
uneconomical, sometimes steel caissons with cutting edges are
floated to the site and sunk into position. The curb and the
strakes are hollow and made of mild steel plates f in. and in. thick
suitably braced with angle irons depending on the size of the well
and the depth of standing water. The operation consists of towing
to the site and potitioning a manageahlc height of the strake by
tugs and adding concrete gradually iu the annular-span as the
caisson sinks to its position adding further strakes when required.
A description of the method adopted for sinking the steel caissons
for the Brahmaputra Railway Bridge near Pandu will be of
interest (see Photo 5).
The r t n l caissons used were of the Double D shape with
overall dimension of 53 ft 6 in. by 32 ft the thickness of steining
was 9 ft and that of the central diaphragm 7 ft 6 in. The well
curb was 15 ft high and was made of f in. thick steel plates
properly braced inside. The strakes above the curb were 7 ft high
and all joints were made watertight. A cast iron seating ring was
attached to the first strake for fixing the adapter for the airlock,
should sinking under pneumatic pressure be necessary.
Each well curb weighing 121 tons was assembled on level
ground and one strake was assembled on it. A small quantity of
concrete was placed in the curb to make the cutting edge water-
tight. With the rise ia flood level, the well curb floated up and the
sinking srts were taken to the well curb which was moved to the
D ~ amNSINKINGOR WRLLFOUNDATIONS
FOR BRIW 65
site. A draft of about 4 ft was maintained and for this purpose the
water inside the caisson was removed by compressed air.
The sinking sets consisted of'two barges with trestles 46 ft high
and cross beams on top. The barges were 36 feet apart. The cross-
beams on the top were designed to take a load of over 10 tons.
After placing the sinking sets roughly in position, strakes
were added and small quantities of concrete poured into- the
annular apace sufficient to lower the caisson leaving adequate free-
board or further addition of strakes. The total height of each
caisson depended upon the depth of water at the time of grounding
and the critical grip required. Before grounding, however, the
caisson was positioned accurately with cutting edge just about a
foot or so above the river bed. Each caisson was held by six
pully blocks when grouaded on river bed, concrete was poured in
the annular space sufficient to give an initial grip of 6 ft or so.
Grabbing and concreting were repeated and when the critical grip of
about 20 ft was obtained the whole annular space was filled with
concrete. Thereafter, building of steel caisson was discontinued and
ordinary cement concrete steining built. Until the critical grip is
obtained, it is necessary to ensure that the weight of the caisson plus
the concrete in the annular space slightly exceeds the buoyancy to
avoid the caisson tiltin~. Any uneven sdf-sinking or scour will result
in aggravation of the tilt.
After the erection of strakes a t nearly the c0rrec.t position,
deep scouring on the upstream side was observed. To prevent the
scour, sand bagging was done on the upstream side.
While erecting the caissons, heavy tilting caused by rapid
current in deep waters was observed and this tilting increased with
the increase.of a~bmergence. This was rectified by tying a wire rope-
round the well at 8 ft to 10 ft from tile bottom and pulling it from
the upstream side bv means of a hand-winch fixed on properly
anchored boats.
11.7. Dredging, Jetting md Sinking
The removal of material by dredging the wells is usually
accomplished by clamshell buckets. For dredging through hard
material the heaviest and largest bucket that can operate in the
dredge hole should be used.
When the caisson approaches very hard strata, special rock-
cutting teeth should be added to the grab or very often heavy chisel-
ling resorted to for breaking such strata. The chisels may consist of
long steel beams with tempered chisel points or a set of rails with
cutting edge clamped or bolted together. These cao be operated by
raising and dropping manually or mechanically.
11.8. In those cases where due to the depth water and
peculiarities of the soils, sinking by the use of grabs, etc., cannot be
done, pneumatic sinking or in some cases sinking by divers with the
use of steel helmet and compressed air is resorted to. Both these
methods are very expensive and slow.
11.9. In the case of divers using steel heirnets, continuous
supply of compressed air is required.
In one of the bridge works, compressors with a capacity of 250
cu. ft. per minute and 110 cu. ft. per minute were used for supply of
air to the divers using steel diving helmets. For a depth up t o 40
ft, compressors with a capacity of 110 cu. ft. at 45 lb per sq. in.
pressure were found suitable. Beyond that depth compressors with
a capacity of 250 cu. ft. at 150 lb per sq. in. pressure were used.
Compressors worked with electricity were not used because conti-
nuous supply of energy could not be ensured.
Upto 40 ft depth, a 250 cu. ft. per minute at 50 10 per sq. in.
supply can feed air required by 8 to 10 divers. Beyond this depth
and upto a depth of 60 ft it can supply air to 6 divers and beyond
60 ft only to two divers. Each diver required on the average 1+ cu.
ft. of air per minute. Beyond 50 ft depth below water the operation
becomes very slow and hencc uneconomical.
11.10. As a safety measure, it is essential that, either there
should be two compressors with their compressed air supply suitably
connected together working simultaneously on each well, each com-
pressor capable of giving the full required supply, or one compressor
on each adjacent well with inter-connected compressed air supply
arrangements and a pressure tank be provided. In this case, each
compressor should be of the capacity to meet tbe full requirements
of both the wells.
lI.11. The rate of sinking of a well is a function of the rate
at which the bed material is removed from the well bottom. Sand
from upper layers was removed at the rate of 120 to 160 cu. ft. per
hour by four divers. Digging in clay is more difficult and the out-
put is reduced by about 50 per cent. This rate wds maintained upto
a depth of about 40 feet. As the depth increased, the number of
divers put on the job was reduced and the output decreased consider-
ably and, as a consequence, rate of sinking went down. The rate of
sinking in top sandy layers was 1 ft Gin. per day and in middle clay
layer it dropped to 7 in. due to difficulty of digging in clay and again
increased to 9 in. in saudy strata. The reduced progress in the sandy
strata at r'nese depths i\ mainly due to !he smaller number cf divers
working a t those depths. These ratcs o r sinking may go down consi-
deiably if obi~ructions like tree trunks or boulieri, arc met.
DIBIGNAND SINKINO mu
OF WBLLFOUNDATIONS B R I W ~ 67
It is important t o note that the quantity of earth removed for
sinkiig a well varies, and depends on the curb area or the outer
dimensions of the well. The quantity of sandy bed removed may be
as much as 2 to 2.5 times the calculated quantity based on the area of
the well, due to sand flowing in from sides during grabbing operations.
In a clayey soil, the,quantity of bed material removed will be compar-
ably less. For work~ngout diver hours, output per diver may be taken
as 10 cu. ft. per hour in clay and I5 cu. ft. per hour for sand. Working
day for divers is given in Table 11.1. The observed endurance of
divers to remain under water at different depths and the wages
demanded on one of the bridge works in 1961 are also given in Table
11.1.
TABLE11.1
- - ~ ~~
Depth
--
0 to 50 it
I
Duration of shift per day
in hours at a stretch
Wages in r-s per
diver per shift in 1961
5010 60ft
60 to 70 ft
Beyond 70 ft
~ ~ ~ ~ - ~ p ~
11.16. Tilting also takes place when the well enters a harder
layer from a comparatively softer layer. This would be self-
explanatory by a reference to Fig. 11.5.
Tilting usually does not take place suddenly. Actually when thq
well is one or two feet above the level of comparatively harder
strata l h t movement of the well may be noticed as sand o r softer
strata starts flowing in the well along the slope or #he harder strata.
That is the time for taking effective measures t o prevent or set right
tilt, if any had taken place.
11.17. A well sinks by its own weight when the soil below its
cutting edge is removed. I f the side friction is so great as t o
retard the sinking under its own weight, additional weight o r kent-
ledge will have to be added. When the addition of kentledge does
nor make the. wdl sink, it is best t o suspend the work for sometime
dad allow the water in the well to reach its normal level, than lower
the water level by say 13 to 20 ft by pumping. The diflerential
head causes increased flow in the well. This Row reduces surface
friction and helps the well in sinking. In such cases, sometimes
the well sinks rather rapidly. However, care should be exercised
not to depress the water too much and thus avoid sand blowing and
consequences thereof.
In this connection a very instructive experience in sinking one
of the wells of a bridge is worth recounting. The well with 76 ft
long steining was being sunk through clay strata and was held up.
Grabbing to depth of 15 ft below cutting edge did not make the
well sink. Addition of 160 tons of kentledge proved ineffective.
70 BALWANTRAO& MUTHUSWAMY
ON
Dewatering of the well was resorted t o and when the water surface
was depressed by about 24 ft, the well suddenly went down 15 feet.
Investigations proved that there was still two feet depth of clay strata
below the cutting edge but the differential head o i water caused the
piercing of this clay seal causing considerable sar:d blowing which
made the well travel down 15 ft in one go.
Another interesting sand blow that occurred in a well of one of
the major bridges gives a n indication of the nature of the pheno-
menon. The clay layer was of poor qualify. The earth right from
the surface, within a radius equal t o the depth at which the blow
occurred, caved in and blow u p in the well. This caused cracks
and depression in the surrounding earth surface in concentric circles
as shown in Fig. 11.6. 'This flow caused n o movement of the well
as there was practically n o draw off of the soil from below the bed
o f the curbs.
F i g . 1 1.6
Fig. 11.7
If the well is to be brought hack plumb, the shift 'e' suffered by
:he well can be expressed by the equation :
e=SD, (11.3)
where, S is the slope of the tilt equal to t a ? tl
In equation (1 1.3), D,is the height from thc bottom about
which the well will rotate while being brought back to vertical posi-
tion by a force applied a t a height H ft above the bed level. The
value of D, in case of non-cohesive s o ~ l sand the value of Dsin case
of cohesive soils are given respectively ih equations (6.5) and (6.15).
From the ioregoing it may be secn that the point of rotation
depends on the height above the bed level at which the force is
applied and the depth by which the well has already sunk and not
on the magnitude of the correcting force. This will enable the shirt
to be calculated in advance by a;ljusting ihc point of application of
the force. In case of a bridg? most wells rectified were found to
rotate about 1/3rd depth of embedment from the base.
11.20. It is usual to restrict the shifts and tilts to certain
limits. Shifts of one foot and t i l t of l in 60 to l in 100 depending
upon the depth of wells are the mnsimum permissible limits. These
limits should be taken only as a y:~ideand every shift or tilt of n well
be dealt with in each individual case.
11.21. The shifts changc span lengths and thereby induce
eccentric loads on the well steining and the foundations while the
tilts cause uneven pressure on foundations. The magnitude of the
ill effects depends upon the size of the well and depth to which
it is sunk. These are illustrated in Fig. 11.8 which shows that the
effect of a cant on wells of same size differs at different depths. This
also indicates the necessity for rectifying the cants immediately lbey
are noticed.
72 BALWANTRAO& MMUTHUSWAMY
ON
Fig. 11.8
a*.,
If a simple tilt occurs at a certaindepth and the sinking conti-
nued till designed foundation depth is reached, theshift at the bottom
could be ereater than at the top a s shown in Fig. 11.9.
4 .e--
",...
. %"-
-
-.- , !
Fig. 11.9
These shif!s and tilts may take place in any cornbization as
shown in Fig. 11.9. The total shirt at the base will then be lhc sum
of the two shifts. The development ol'tilts and shifts actually obser-
ved in a well of a bridge will illustrate t h i ~poin!, vide Fig. 11.10.
DESIGN
AND SINKINGOF WELL FOUNDATIONS
FOR BRIDGES 73
Fig. 11.11
Fig. 11.12
5 ft long lived with steel piate at top are inserted at four or five
places underneath the cuttins edge on the lower side and sinking
operation is continued on the higher, side. After the cants are
rect~fied, these blocks are removed. By this method cants as high
as I in 24 are known to have been rectified. If in. spite of the best
Fig. 11.13
efforts, the tilts arc not rectified lo a desirable degree. the effect of
eccentricity on bearing prescurrs could be minimised by projecting
the concrete caps so as to keep the resultant reaction within
permissible limits.
11.23. Bottom Plugging
(I) Bottom plug of a well usually consists of (I : 2 : 4) cement
concrete laid by means of tremic or skip boxes. Plugging done with
"prepackt concrete" is also considered satisfactory. It has been
noticed that the concrete laid for the bottom plug takes longer time
to set and considerable proportion of cement gets washed resulting
in weak c h c r e t e and, therefore. 10 per cent extra quantity of cement
should be added in the concrete.
(2) Bottom plupging should always be done in one conti-
nuous operation when the water in the well is at its normal level.
If there are two or more dredge holes, plugging should be done
simultaneously and to equal heights in all the dredge holes.
(3) Before plugging the bottom of a well, sounding should be
taken to check that there is no sand lying above the cutting edge
of the curb and t o ascertain the depth at various points in the
dredge hole for getting a fair idea of the profile of the bottom and
its cubic contents. For the required quantity of concrete in the
plug, quantity of aggregate to be used should be 89 cu. ft. for every
100 cu. ft. of calculated quantity.
(4) Founding wells on uneven rocky bed is always difficult.
Careful observations of boriogs are required specially if pinnacles
arc observed from the base rock. The rock may have to be blasted
all the way down or underpinning may have to be resorted to, to
support the steining of the well.
" I.
7.
3
5 '*
c I*
;24
.
.d
ior
u
.a
0 I I. I, 1D g
m,.**n*OF 111. LOIDlD
Fig. 12.1
Fig. 12.2
applied per sq. ft. over the steining of thickness It' aAd 'd' the depth
at which the curb will come to rest during a test under that load, vide
Fig. 12.2, then the factor of safety '7' with respect to 'n,' for the well
without plug is given by :
(12.1)
+
0.00 12 (0
Dt
t)'
1
and 11 ,. - [ 1 - 0.004 ( D t t ):
(12.2)
78 BALWAMRAO & MUTHUSWAMY
ON
-,
z
0 2
?
I
0
., .,
"""".#
.,
0"",.WE,
Fig. 12.3
836 tons giving an intensity of load of 2.82 tons per sq. ft. Fig. 12.3
shows that under a total load (superimposed load.plus weight of the
well) of 540 tons the well did not move, tllereby ~ndicatingthat total
skin friction and buoyancy is nearly 540 tons. In this case, skin
friction was approximately 440 lb per sq. ft.
~ I G AND
N SINKING FOUNDATIONS
OF WELL FOR BRIDGES 79
12.10. The load increment and the corresponding settlements
recorded are shown on the same graph. It will be seen that for an
increase in the intensity of 0.75 ton per sq. ft. (2.00 to 2.75 tons per
sq. ft.) the settlement was0.6 inch. For a settlement of 2 in., consi-
dering the large size of well, the safe bearing capacity will work out
to 2.5 tons per sq. ft. This appears to be reasonable for medium
yellow sand.
12.1 1. During the removal and after removing the test load
the well cannot be expected to recover the settlement by elastic
rebounding unless the load added over and above that requ~redto
overcome skin friction and buoyancy is greater than the skin friction
that will act in the opposite direction. Thus once the load overcomes
the skin friction that part of the load gets locked up and keeps the
soil stressed permanently. This phenomenon was noted in the-actual
load test described in para 12.9. Thus it can be concluded that,
once the reaction due to live load gets transferred to the base of
the foundation well, it remains locked there if the skin friction
developrd below the maximum scour level is greater than the live load
reaction. Thus the foundation pressure under a bridge becomes set
after some time.
12.12. The arrangement for a plate bearing test (Fig. 12.4)
consists of a stiffened 24 in. square or ;I suitable sized steel plate
which supports a stanchion of' fabricated steel and angle irons. The
stanchion should rest on a roller assembly to transmit the load verti-
cally. The stanchion projects outside the well and supports a loading
platform. A lever device resting on a knife edge independent of the
stanchion can m a ~ n i f ythe settlement 10 to 15 times dependingon the
ratio of lever arms itlid measure settlenlents accurately upto 0.001 inch.
The reliability of result of this test depends upon the size of the
plate but this again is restricted by the capacity of the loading
platform. In order to produce the erect of surcharge, the plate
should be covered with sand to a height in the ratio of the model to
prototype dimensions.
If the dimensions of the prototype are D and B a n d that of
the model d and b as shown in Fig. 12.4, then
BID = bld (12.3)
nn I* "OVn'
-0 01 .l*1 o* Y m l Y l U I
Fig. 12.5
Fig. 12.6
13. CONCLUSIONS
Scienlific design of well foundations is still an open subject.
The Authors have attempted to bring together in one place the
experiences of field engineers facing the complex problems connected
with the practical sinking of wells. Considerable amount o f factual
material has been drawn from many sources which might have not
been fully acknowledged eycept where direct mention is made. The
Authors are very much indebted to various engineers who have
added to the knowledge of well sinking by recording their experience
and discussions.
82 BALWANTRAD & MVTHUSWAMY
ON D e s l ~AND
~ SINKING OF
WELLFOUNDATIONS
FOR BRIDGES
ACKNOWLEDGEMENT
REFERENCES
There was the other question of the extent to which the well
would get relief in the form of the passive resistance o f thc surroud-
ing soil. This had got to bc assessed for the depth below the scour
level. This problem was also under active consideration of an I.R.C.
Sub-committee. With heavier vehicles forming the bulk of the present
day traffic. large transverse forces are a reality and this aspect had
become important for the purposes of keeping the sub-structure of
the bridge true and vertical within tolerable limits. For deriving the
relief from clay soils, active pressure which takes tiwe to mate-
rialise w3s omitted from consideration. The side, friction in non-
cohesive soils has also been omitted. Its coming Into action was
doubtful due to vibration that might be present in the well due to
water flow and the movement of traffic.
Althabgh the Authors had quoted the data given by Gale in his
Paper, they were not very explicit about the relatiohships between
the skin friction and the depth of embedment of well foundations in
granular soils.
If, however, any yield of the ground occurs during the process
of sinking the well foundation, the horizontal stress would be reduced
and, in the limit, wou!d approach a value of K. y' d, where K, was
the co-efficient of actlve earth pressure.
-
4
120 -
1+0 -
160 -
This chart was valid for shallow foundations above water table.
As settlement decreased with increase in lateral confining pressure,
it was true that the value of allow~hlesoil pressure obtained from
the above chart should be multiplied by a factor of 2 for deep
foundations. Again, if the water table was within a distance equal
to the width of the footings, the value obta~ned from the chart
would need reduction. The term "normal bearing capecity" used
in the expression was not correct. It should be "allowable soil
pressure" based on settlement consideration as given in Terzaghi
-
and Peck's chart. The factor submerged
- weight., which was a cons-
?
dry we~ght
tant for a particular sample, also needed modification as the factor
varied depending on the position of the water table and would be
submerged weight
equal to - - only when the water table was a t the
drv weight
foundation level o r acove it.
O 5
la I-
2
lo;$
J0 !3$
@ 23
u1Q
50 n 8
e
60 $5
70 2
4
!
il
For 4=O (consequently N,= 1) and D,= 15 ft, say. the expres-
+
sions y D,N,would be equal to 300 ib per sq. ft. which is not
negligible. Therefore, it would not be correct to neglect the depth of
surcharge in all cases as mentioned in para 4.13.
The appropriata term for 'Type of clay' used in Table 4.4 should
be consistency.
FOUNDATIONS
W~LL FOR BRIDGBPIERS 11
The Authors should furnish complete details o f the results of
the load test represented by Fig. 4.3 which did not wnvey any-
thing to,a reader. The direct use of the result of such plate bearing
test, as suggested by the Authors, to ascertain the allowable soil
presaure might prove to be dangerous. Mere mention of grain size
like coarse, medium or fine would not convey any idea about the load
bearing capacity of the sand strata. Even coarse sand. if loose,
would have poor load bearing capacity. Therefore, relative density
must be indicated for such purpose. Wherever any material had
been borrowed from other publication it would be desirable to give a
reference to the publication in order to give the readers an oppor-
tunity to refer to the original for clarification whenever required.
Regarding para 6 which dealt with evaluation of earth prmsure
it might be mentioned that resultant earth pressure had two
components, one active earth pressure and the other psssive
resistance. An impreceptible movement of the well would
reduce the earth pressure a t rest to a value equal to Rankine's
active earth pressure. But as the horizontal deformation increased,
passive resistance would go on increasing and reach the maximum
value at "Rankine's state of plastic equilibrium." The Authors
had also'brought out the same idea about passive resistance but had
mentioned 'elasto.plastic limit' instead of a 'State of plastic
equilibrium'. He was not a w a ~ ewhether the term used by the
Authors was used in any standard publication. Moreover the word
'plastic limit' had go! quite a different meaning and was not at all
knnected with thk is<ue of earth pressure. he expression should,
therefore, be corrected.
The Authors had also mentioned that in the case.of a heavily
loaded well under a bridge, the horizontal movement of the well
would depend on the maximum movement of the pier s t bearing
level and as that movement in itself was small, the movement of
the well at scour level would be still smaller. They had, therefore,
suggested that the passive resistana should be reduced arbitrarily
to half the value. They had, however, applied the same reduction
to the active earth pressure also. As active pressure indicated the
minimum pressure that would be exerled by the surrounding
soil mass. this value must not be reduced further under any
circumstances.
Regarding passive resistance, Shri Sen stated that the resistance
depended on uncertain deformation factor viz., a co-efficiency of sub-
grade reaction which was neither based on any theoretical analysis
nor on information from wide range of experiments. Moreover as it
was a restoring force it would be better to adopt only the value of
earth pressure a t rest. That would mean erring on the safe side.
But if a higher value was to be adopted, it was necessary to
determine first how much the well could move a t the scour level and
then estimate the resistance offered by the soil mass by using co-
efficient of horizontal subgrade reaction values recommended by
Terzaghi in his Paper entitled "Evaluation of Co-efficient of Subgrade
Reaction", published in 'Geotechnique', December 1955.
In the case of cohesionless sand, value of this resmtancc would
be given by the equation :
B (ft) -earth
width of surface of contact
nh (tons/fta) = a factor indicated by the following table
given in Terzaghi's Paper :
Volue of nn in tons/cu. ft.
for a pile I ft wide
Relofive density Dry or moist mnd Submerged sond
Loose 7 4
Medium 21 14
Dense 56 34
In the case of clay, the resistance would be given by the following
relationship :
In para < o n pages 21 & 22, it had been said that the choice of
the shape depended on a) the cost and ease of sinking ; (b) the extent
\
of control of tilts : (c) t i e loads to be,carried; and (d) the magnitude
of the horizontal forces. Although thls was so, the observation and
the selection of the well shape for the particular example dealt with
in sub-para 5.3 made one feel that the choice mainly depended on the
sinking effort and also only on the modulus of section in the bridge
direction. This was incorrect and it might be said that the shape of
the well was actually in addition, mainly governed by the relative
maximum horizontal forces and moments that were likely to come in
the bridge as well as in the flow direction. Thus for bridges in a
seismic area where these were equal, a single circular well might be
more suitable whereas the same might not he the case in other areas.
Fig. 2
In what way the weight of kentledge affects the lateral rein-
forcement (i.e., horizontal rings) para 7.4, was not understood. This
should be clarified by an illustrative example. In para 8.5 according
to Authors, the plug should be considered to act as an inverted arch.
etc. This approach did not seem to be quite rational, as far as the
design of the kerb was concerned. A force of N lb per running foot
of the kerb, acting vertically downwards was being transmitted t o the
plug through the medium of the bevelled surfaces. The active or the
disturbing force on the surface was the load N brought by the steiding
or kerb, and a reaction 'P'had to be developed betaecn the surfans.
such that its component in the direction of the disturbing force had
to be equal and opposlte to it. This force 'P'might be accompanied
by a force pP tangential to the surface of contact, depending upon the
absence or presence of friction between the two surfaces. Using the
notation of article, 8.3,
d
which reduces to R N tan 8.-
2
, w h m p=O.
The force P between the bevelled surfaces was thus induced by
the force brought in by the steining and it had to be dependent upon
the force N. Expression ( 8 . 9 was misleading as the terms q and r in
it were not independent functions. They were derivatives of H, which
was dependent on N. p and 9.
The plug would be subjected to the forces P and p P along its
periphery and the thrusts on the bevelled surface would be so ad-
justed that they were equal and opposite to the resultant of P and FP.
The directions of the peripherial thrusts and the horizontal plane
tangential to the bottom surface of the pl-.g, situated in its centre,
practically decided the rquation of the paraboloid or circular dome,
the bottom plug might be assrmed to act as.
The criterion given by equation 8.8 for the designing of the junc-
tion of the kerb and the steining was equally misleading. The thrust
P accompanied by the fric!ional force pP on the bevelled surface
would create a horizontal force H' which would be resisted mainly by
the hoop tension in the kerb. Very little portion of it would create
any hending moment i n the kerb as contemplated by the Authors.
24 D~scussro~
ON
Fig. I.
The statement made in para 4.18 regarding the skin friction was
contradictory t o that made in para 4.17. The values suggested here
were very low as compared with para 4.17.
The minimum diameter suggested in para 5.7 was 5 ft which
in his opinion was too small for use with grabs. The normal
minimum diameter was about 8 ft.
In the example w was taken as 120 lb per cu. ft. It was not
correct because they were considering the submerged weight of the
well and it should be about 60 per cu. ft.
The design of well curb had only been done for the hoop
s m s e s that might develop during and after sinking. On the other
hand, the curb would be highly stressed when resting on an obstruc-
tion. say, a trunk which would give a two-point support.
In para 8.13.the thickness of bottom plug had been worked.out
by assuming it to be an arch. In his opinlot~it was not just~fied
because in general, the rise was not certain or in other words there
might be no sump below the cutting edge. The normal practice was
t o assume it as a simply supported plate. One such solution had
been given by Anderson (1966) page 235.
The purpose of sand filling had not been properly realised in
para 8.14. There was no doubt about the fact that the sand filling
would transmit absolutely no load from the well cap to the bottom
plug because of its being relatively very compressible and secondly
some settlement would always take place after filling and it would
not be incorrect to presume that there was no connection between
the well cap and filling. The filling was done only to provide stabi-
lity to the foundation.
It was suggested by the Authors that a well might be filled
completely as to transmit the load to the bottom plug. This would
not help in transmitting the load from the steining to the bottom
plug. Instead i f shear keys were provided in the curb and also the
stelning ns shown in Fig. 3, a better solution would be obtained.
nOTlOM PLUG
C U I I W EDGE
Pig. 3
It might also be mentioned that at times, the bottom plug (seal) had
also been reinforced (Mears and Pool 1957).
8.
The provision of flat bars 4 in.x in, or 4 in. x f in. etc.
seemed to be quite a common practice an this was. also' advocated by
the Authors in para 10.2. One was at a loss to appreciate the. pro-
vision of this because they did not at all add to the strength of the
well. It would be better if the lateral reinforcement was provided in
the form of continuous bars as shown in Fig. 4.
I t was suggested in para 11.2 that in the initial stages, small
grab should be used instead of pig grab, this would afford good
control on sinking in the early stages
It appeared from para 11.12 that normal precautions for
depressurisations were not taken which resulted in casualties.
This happened because the I.R.C. did not have a code of practice
WELL FOVNDA~ONS
FUR BRIDGE PIERS 29
HORIZONTAL REINFORCEMEMI
UEtNFOUCEMENl
for pneumatic sinking. I t was suggested that the IRC Bridge Code
should include a chapter on work under compressed air. A reference
might, however, be made to Lee (1961) for details.
The writer does not agree with the statement made by the
Authors in para 11.17 that dewatering reduced skin friction. The
effect of dewatering was two-fold ;
COS 8
sin (++ 8) sin (+-p)
sin (a- 8) sill ( a + p ) 1'
P R = f x 166x46s
129x6x46s---166=1230 kips.
The surface of contact between the plug and the soil being
rather rough, the co-efficient of friction would be very high. Even
when this force was overcome and the point of rotation moved up,
this force had still to be considered in stability computations.
The Authors had not. considered the restoring moment due to
thevertical component of pressures. In case of broad wells. this
would be a substantial force and taking these into account for a well
with base rotation, the final value for 'q' could be written as (for full
plastic failure):
-- -
@
PRCSSURL AT RLST - PRESSURE AT REST TO CH4NGt
TO CUANOL IMTO A .- b TO ACTIVE STATE
P4bSIVL WATC
q= .V(bml D+2d m3
6 -. -- . .. -
H+ D
where PIr, = . ~ . K RW.
.
f = coefficient of friction between soil and well.
KR = coefficient of earth pressure at rest n$ & m, as
before.
For KR, Terzaghi had suggested values from 0.5 to 0.8 for sands
naturally deposited, with the recommendation that these could ba
increased where artificially compacted. In the case of bridge piers,
the sinking of the well shaft compressed the soil around to a large
extent. Further, for an attempted movement or rotation, the state
of stress in the soil on the sides would change into a passive state
thereby increasing KI(values while it might not be correct to assume
full passive values, it appeared reasonable to adopt KR values from
1.0 to 1.5. This would perhaps be still increased for very coarse
sands. In the example g i v ~ nby the Authors, the resistance to the
entire force by the side friction would be assumed:
Then nt, and m, = 0
Adopting the same values adopted by the Authors for y' & w,
The required KR value was 1.61 and this was quite possihk
The well might not rotate or move a t all. It was suggested that in
all the computations for the stability of wells this factor be wnsi-
dered and the KP & Kd values were to be further reduced as the
object was to reduce the probable rotation. For a reduction factor
of 0.5 and less, for KP & Kd values, the equations based on full
plastic failure might not be strictly correct but could be used as the
error was negligible. The correct equation could be written as (for
no plastic flow) :
Para 8.3: The most severe stresses in the curb. would be caused
onits striking buried boulders, o r logs in the process of sinking. The
condition assumed by the Authors would occur when the curb was a t
rest, i.e., after it had sunk into the soil and for this condition, it might
not be correct t o assume the Q force between the curb and soil, as the
curb was not a free body sliding down the plane. Equating the forces
required for stability, the toral horizontal force would be N. sin 8.
it was doubtful whether this force would be localised on the curb
alone, as thesteining was continuous with thecurb. As suggested by
the Authors, the steel in the curb would have to be fairly heavy, t o
withstand the forces in the curb, during sinking, particularly in soils
with boulders and rock where these forces are not determinable.
fB)
, , Effect of F at tov would be such as to disturb the
foundation pressure C G . O Fkr..
distribution.
If a condition is impo- FOQC~S.
sed that at the limit-
ing point of n o tension
only the foundation
starts yielding, then
maximum resisting
moment amounts to
B
MRI=(Dw+D S ) ; ~ +c
Fig. 2.
(Nore :Surcharge effect not considered)
9.3. The shear resistance between the water and of the bottom
well being practically zero, it is not necessary for the water in partially
filled well to oscillate with the well.
11.2. Shri Balwant Rao stated that it was not correct to say
that criteria given by the equation 8.8 for the design of the junction
of the kerb with the steining was misleading. If for any reason the
kerb is damaged, the reinforcement suggested in the Paper will be
required to keep the kerb in position and prevent it from spreading.
12.2. He agreed with Shri Sikka's remark that the skin friction
should not be taken into account for calculating the passive
resistance. I t is not possible to work out or predict the exact
quantum of skin friction ; because, effects of factors like, the kind of
strata, the size of the we!l, the material of the well, the depth of
sinking, local condition and depth to size ratio of the well were
dificult to assess.
The values of skin friction given in the Paper are a fair indi-
cation of the values that could be expected. The Authors are grateful
for the data given by Shri Sikka which will be most useful.
12.3. It was pointed out by Shri Sikka that the sand filling
may not be flush with the bottom of the well cap. This can be true,
in which case, whole of the load will be carried down to the foun-
dations through the steining. In the Paper, it was meant that in case
of the failure of the bottom plug, the well may settle down and the
sand filling will then come into play. The sand filling will under such
circumstances function as a medium for transmitting the load to
the base.
12.4. Authors agree that the reasons for the reduction of the
skin friction during de-watering may not be only due to the down-
ward movement cf the water on the outer face of the well.
14.2. The reason for adopting the factor 0.5 for calculating the
passive resistance is to obtain a resultant passive resistance diagram
WELLFOUNDATIONS
FOR B n m e hms 49
well within the so-called elastic limits of the soil. The saturated
condition of the soil will cause a reduction in the vertical subgrade
reaction and is not, therefore, connected with its submerged weight
which has been taken into account in deriving the formula for passive
resistance.