Topics 1. Overheating 2. Gas Detection 3. Pressure Indicator and Relief Valve 4. Overcurrent 5. Differential Relaying
Engineering Simply the Best !!!
Topics Rating of transformer is based on the temperature rise above an assumed maximum ambient temperature; Under this condition no sustained overload is usually permissible. Normal maximum working temp = 95°C; 8-10° rise will halve the life of the transformer Protective Instruments Liquid Temperature Indicator Thermal Relays
Engineering Simply the Best !!!
Overheating
Engineering Simply the Best !!!
Overheating
Engineering Simply the Best !!!
Gas Detection
Engineering Simply the Best !!!
Gas Detection
Engineering Simply the Best !!!
Pressure Indicator & Relief Valve
Engineering Simply the Best !!!
Overcurrent Fuses for Small Distribution Transformer Overcurrent Relaying for Large Power Transformer Characteristics Must be below the damage curve Must be above cold starting and magnetizing inrush
Engineering Simply the Best !!!
Differential Relaying
Engineering Simply the Best !!!
Differential Relaying
Engineering Simply the Best !!!
Differential Relaying DIFFERENTIAL RELAY SETTING (GENERAL PROCEDURE) 1. FLC Primary and Secondary 2. Select CT Ratios 3. Determine Currents at the secondary of the CTs 4. Determine Tap @ primary and secondary 5. Determine Currents at the relays (given the Tap settings in P & S) 6. Determine CT Ratio Mismatch 7. Determine Transformer Tap Changing Mismatch 8. Determine CT Errors [Example: 10CXXX 10% error] 9. Add Margin [e.g., 5%] 10. Add: CT Ratio Mismatch + Transformer Tap Changing Mismatch + CT Error + Margin to Determine Differential Relay Slope
Engineering Simply the Best !!!
Differential Relaying
Engineering Simply the Best !!!
Differential Relaying
Engineering Simply the Best !!!
Differential Relaying Step 1: Full Load Current on Primary & Secondary
Engineering Simply the Best !!!
Differential Relaying Step 2: Select CT Ratios to be used
Engineering Simply the Best !!!
Differential Relaying Step 2: Select CT Ratios to be used
Engineering Simply the Best !!!
Differential Relaying Step 3: Determine the Tap at Primary and Secondary
Engineering Simply the Best !!!
Differential Relaying Step 4: Determine the CT Ratio Mis-match
Engineering Simply the Best !!!
Differential Relaying Step 5: Determine Tap Changing Mis-match
Engineering Simply the Best !!!
Differential Relaying Step 5: Determine Tap Changing Mis-match
Engineering Simply the Best !!!
Differential Relaying Step 5: Determine Tap Changing Mis-match
Engineering Simply the Best !!!
Differential Relaying Step 5: Determine Tap Changing Mis-match
Engineering Simply the Best !!!
Differential Relaying Step 5: Determine Tap Changing Mis-match
Engineering Simply the Best !!!
Differential Relaying Step 6: Determine the CT error Assume the CT error to be 10% Common error for protection CTs)
Step 7: Add margin of Error
Add margin of error of 5%
Engineering Simply the Best !!!
Differential Relaying Step 8: Differential Relay Slope Slope=CT Ratio mis-match + Transformer Tap Changing mis-match + CT error + Margin Slope = 1.11% + 13.24% + 10% + 5% Slope = 29.35% ; so set the slope to be at 30%. This will serve as the boundary of the restrained and operation region of the differential relay. If the difference measured by the relay exceeds this slope will cause the relay to operate and trip.