REMAINING WORK CIVIL FIELD (UTILITY AREA)

No. ITEM PEKERJAAN Qty Status KETERANGAN


A Pipe Rack D Boiler to STG
1 Pilecap 5 Outstanding
2 Pedestal 14 Outstanding
3 Fabrication structure Finished
4 Erection Structure Outstanding
B Pipe Rack E Boiler to STG
1 Pilecap 1 Outstanding
2 Pedestal 2 Outstanding
3 Fabrication structure Finished
4 Erection Structure Outstanding
C Pipe Rack H
1 Erection Structure 2 Outstanding
D STG Building
1 Brick masonry (hebel) On going - Sisi utara ruang panel kurang ±1 m
-
Sisi selatan ruang panel belum
dikerjakan
-
Di atas pintu sisi utara belum bisa
dikerjakan
- Sisi timur sebagian harus dibongkar,
menyesuaikan drawing terbaru
2 Plastering Outstanding
3 Ceiling + Frame Outstanding
4 Finishing Floor Outstanding
5 Painting Outstanding
6 Door + Frame 4 Holded - Frame sudah terpasang sebagian
- Pintu sudah difabrikasi
- Kendala keluar-masuk equipment
7 Ventilation (kawat ayam) Outstanding
8 Platform and support STG Outstanding - Menunggu STG equipment terinstall
Pilecap cooling tower to STG - Menunggu STG equipment terinstall
9 4 Holded
pipe support
Pedestal cooling tower to STG - Menunggu STG equipment terinstall
10 8 Holded
pipe support
11 Cable Trench STG Holded - Menunggu STG equipment terinstall
Excavation underground pipe - Menunggu STG equipment terinstall
12 Holded
13
Outstanding
Excavation Atmospheric Tank
E Compressor STG Shelter
1 Brick masonry (hebel) On going
2 Plastering Outstanding
3 Painting Outstanding
4 Ventilation (kawat ayam) Outstanding
5 Install BRC Outstanding
6 Roof Outstanding
F Spray Pond Pump Shelter
1 Foundation Outstanding
2 Stucture Outstanding
G Spray pond
1 Platform On going
2 Biotray 350 On going
3 Drainase existing Holded
H Pipe Support Cooling Tower to STG
1 Pilecap 2 Outstanding
2 Pedestal 6 Outstanding
3 Fabrication structure Outstanding
4 Erection Structure Outstanding
5 Pipe Sleeper 4 Outstanding
I P807 A/B and P808 A/B Pump Shelter
1 Foundation Outstanding
2 Structure Outstanding
J P805 A/B and P806 A/B Pump Shelter
1 Foundation 6 Finished
2 Structure Outstanding
K P809 A/B Pump Shelter
1 Foundation Outstanding
2 Structure Outstanding
L P804 A/B Pump Shelter
1 Foundation Outstanding
2 Structure Outstanding
M P801 A/B Pump Shelter
1 Foundation Outstanding
2 Structure Outstanding
N P810 A/B Pump Shelter + P6 Pump
1 Foundation Outstanding
2 Structure Outstanding
3 P6 pump foundation Outstanding
O Pit Netralisasi (WTP)
1 Slab Finished
2 Wall Finished
3 Drainase from WTP area to Pit
Outstanding
Netralisasi
P DEG Shelter
1 Stucture Outstanding
Q Control Room Boiler
1 Plestering On going
2 Ceiling + Frame ?
3 Painting Outstanding
4 Finishing Floor Outstanding
5 Window Outstanding
R Compressor Boiler Shelter
1 Painting On going
S WWTP
1 Install pipe sleeper aeration
On going
tank
2 Blower existing foundation ?

4 Handrail and stairway/ladder Outstanding

3 Aeration existing walk way Outstanding


T Baggase Supply Structure
U Baggase Return Structure