Documente Academic
Documente Profesional
Documente Cultură
O LTE
ISOLATOR & EARTH SWITCH
R O U
V P
DOC. No. : VEPL/T&CF/IES/007 / Rev : 0
VOLTECH ENGINEERS PVT. LTD.
Excellent Electrical Service JOB REF NO : VEPL/TR/ /
DATE : Page No.
CLIENT : M/s.
PROJECT : Sheet No 1 of 6
2. Equipment Details :
LOA No :
Make :
Type :
Sl. No. : R ph : Y ph : B ph :
Mfg Year :
3. Feeder Name :
1 Check the erection of equipment is carried out as per the approved drawings & the
earth switch is provided as per the SLD / Layout
2 The Isolator & Earth switch main contacts are aligned for simultaneous operation
of three poles & proper engagement during closing.
3 Check for free movement of arms of main contacts during closing & opening of
isolator & Earth Switch
4 Main contacts are cleaned and greased
5 Check earth connections from isolator structure to Earth mat
6 Check Earth switch is connected properly
7 Check the insulators are cleaned and free from dust/dirt etc.
8 Marshalling Box of Isolator & Earth Switch
a. Wiring is completed as per the drawing & terminals are tightened
b. All the fuses provided are of the rating as shown in drawing
c. The unused holes in the gland plate are sealed properly
d. The cable tags, ferrules for all cores are provided
e. Cables are properly dressed and clamped
9 Check the Clearance for the following :
a. Phase to Phase _______________
b. Phase to Earth ________________
10 Check the phase sequence of power supply of motor
11 Check the current drawn by motor is not more than the rated full load current & O/L
relay is set for full load current given on motor nameplate
13 All moving parts of drive mechanism are lubricated
14 Check for Changeover of Aux. Contacts during open & close operation
O LTE
ISOLATOR & EARTH SWITCH
R O U
V P
DOC. No. : VEPL/T&CF/IES/007 / Rev : 0
VOLTECH ENGINEERS PVT. LTD.
Excellent Electrical Service JOB REF NO : VEPL/TR/ /
DATE : Page No.
CLIENT : M/s.
PROJECT : Sheet No 2 of 6
7. Motor Details :
Between R ph Y ph B ph
Winding to Earth
O LTE
ISOLATOR & EARTH SWITCH
R O U
V P
DOC. No. : VEPL/T&CF/IES/007 / Rev : 0
VOLTECH ENGINEERS PVT. LTD.
Excellent Electrical Service JOB REF NO : VEPL/TR/ /
DATE : Page No.
CLIENT : M/s.
PROJECT : Sheet No 3 of 6
Isolator Phase
Operation R ph Y ph B ph
Open
Close
Between R ph Y ph B ph
Male Side to Ground
Female Side to Ground
Between R ph Y ph B ph
Male Side to Ground
Female Side to Ground
Male Side to Female Side
Across R ph Y ph B ph
Connector Male Side
Connector Female Side
Main Contact Male & Female
11.2. Isolator Open Condition & Ground Switch Close : (Values in Micro Ohms)
Test Performed by Witnessed by Witnessed by
Name : Name Name
Designation : Designation Designation
Signature & Signature & Signature &
Date Date Date
CH G TEST REPORT FOR
O LTE
ISOLATOR & EARTH SWITCH
R O U
V P
DOC. No. : VEPL/T&CF/IES/007 / Rev : 0
VOLTECH ENGINEERS PVT. LTD.
Excellent Electrical Service JOB REF NO : VEPL/TR/ /
DATE : Page No.
CLIENT : M/s.
PROJECT : Sheet No 4 of 6
Across R ph Y ph B ph
Main Contact (Male & Female)
Ground Switch
O LTE
ISOLATOR & EARTH SWITCH
R O U
V P
DOC. No. : VEPL/T&CF/IES/007 / Rev : 0
VOLTECH ENGINEERS PVT. LTD.
Excellent Electrical Service JOB REF NO : VEPL/TR/ /
DATE : Page No.
CLIENT : M/s.
PROJECT : Sheet No 5 of 6
O LTE
ISOLATOR & EARTH SWITCH
R O U
V P
DOC. No. : VEPL/T&CF/IES/007 / Rev : 0
VOLTECH ENGINEERS PVT. LTD.
Excellent Electrical Service JOB REF NO : VEPL/TR/ /
DATE : Page No.
CLIENT : M/s.
PROJECT : Sheet No 6 of 6
a. Before Commissioning Tan Delta Test Link & switch Should be Earthed :
b. CVT Secondary Spare Terminal Should be Earthed :
c. CVT Secondary All Terminals Tightness Should be Checked :
11. Remarks :