Documente Academic
Documente Profesional
Documente Cultură
LEARNING GUIDE #1
Unit of Competence: Prepare Job Estimation and Costing
Module Title: Preparing Job Estimation and Costing
LG Code: CON BCM4 03 0211
TTLM Code: CON BCM4 07 1014
This learning guide is developed to provide you the necessary information regarding the
following content coverage and topics –
Reading project plans and specifications
Measurements and quantities
Labor unit cost projections
Logistic support contracts, supply agreements or equivalent
Details of proposed warehousing and physical distribution systems and related cost
factors
Converting Information to usable form and store ready for retrieval and application
This guide will also assist you to attain the learning outcome stated in the cover page.
Specifically, upon completion of this Learning Guide, you will be able to –
Read and Understand Appropriate project plans and specifications
Make Measurements and identify quantities from plans and specifications and which
conforms to standards industry practice
Obtain and agree Labor unit cost projections
obtain and analyze Logistic support contracts, supply agreements or equivalent
Obtain Details of proposed warehousing and physical distribution systems and related
cost factors
convert Information to usable form and store ready for retrieval and application
Learning Activities
1. Read the specific objectives of this Learning Guide.
Cost estimate
Estimates of base (civil works) cost must be calculated using unit rates judged to be applicable
for the region of the project site and major quantities of each item shall be calculated from the
drawings in just sufficient detail to serve the needs of proper estimating. Building costs should be
estimated on plinth area. Earthwork costs are based as far as possible on a balance between
cutting and filling. Estimates of cost are given for electricity supply, engineering (design of
detailed plan and supervision of construction), equipment, land procurement and physical
contingencies. Lastly, the operational costs and the production cost are provided under separate
heads.
Before approving a project, the cost of work required must be thoroughly investigated. It is
necessary to prepare the cost estimate, for the intended work from the plans and specifications.
Thus, an estimate for construction work can be defined as the process of calculating the
quantities and costs of the various items needed in connection with the work (Chakraborti, 1922).
This is a complete estimate of the quantities of materials or items that may be required to
accomplish the project concerned. The quantity estimate is one of the most important ones in
order to arrive at an accurate cost estimate for the detailed plan.
Detailed Estimate
Based on the results of the quantity estimate, this includes the cost estimate of everything
required for satisfactory completion of work, and should be the best and most reliable estimate
that can be made.
Complete Estimate
This is an estimated cost of all items, i.e. cost of main contract or material, labour and
supervision, cost of land, engineering fees, miscellaneous, viz. removal costs of owner,
contingency percentage, etc., which are related to the work in addition to the detailed estimate.
Based on the methods used for the preparation of detailed estimates in different countries, in
general the principal parts of the detailed estimates consist of the following:
This includes the name of the project, the date of preparation and the cost of different main sub-
headings, including engineering cost of civil works, cost of equipment and land, etc. as well as
contingencies. The detailed cost of each sub-heading is not shown in the general abstract of cost.
Abstract of cost
The estimated cost of each and every individual item of work is calculated by multiplying the
quantity by the specified rate in tabular form known as "Abstract form' as shown below, then
adding all together to get the actual estimated cost of work. A percentage (1.5 to 2.5 percent) of
the above estimate is usually added for a work charge along with an amount (usually 0.5 percent)
for tools and plant, to calculate the grand total of the estimated cost.
(c) Concrete work - this includes plain and reinforced concrete works, prefabricated concrete
works, formwork for concrete structures, etc.
(d) Brickwork - this includes brickwork in foundation and plinth, brickwork in superstructures,
etc.
(e) Stonework - this includes stone work for bed or wave protection and in structures, etc.
(f) Woodwork
(g) Steelwork
(h) Roofing
(j) Miscellaneous
(k) Finishing
The abstract of cost should contain the different sub-headings shown separately and added
together to show the cost to complete the project.
Analysis of rates
In order to provide a correct and reasonable rate per unit for a particular item, a detailed surveyed
called an "Analysis of rate" should be conducted on costs of materials, labour and equipment as
required for the unit following its specification. The rate per unit of an item consists of the
following:
Wherever possible, the cost of equipment should be allocated to a specific item of rate, i.e. the
cost of operating a concrete mixer should be spread over those items for which it is used. For
certain tools and plant it is difficult to allocate their use to an individual item of rate, and it is
therefore suggested that this expenditure be included in overheads, i.e. establishment charges.
These include such items as office rent and depreciation of equipment, salaries of office staff,
postage, lighting, travel, telephone charges, plans and specifications, etc. They are usually 2 /2%
of the net cost of a unit of rate, and may increase to 5 percent.
(e) Profit
In general, a profit of 10 percent is calculated for ordinary contracts after allocating all charges
for equipment, establishment, etc. For small jobs 15 percent profit and for large jobs 8 percent
profit should be considered as common figures.
For such items of work for which it is difficult to prepare an analysis of rate, a lump sum (L.S.)
rate should be provided in the estimate.
To facilitate the preparation of estimates and to enable them to be prepared in a uniform manner,
a schedule of rates or data for costing each kind of work commonly executed is provided by
different departments in each country. These usually include general conditions, general
specifications, items of different works, data for transportation, materials and labour, method of
rate analysis, plant rate analysis and basic unit rate analysis.
Quantity estimates
Calculating formulas
(1) Sectional area having no transverse slope for diking or cutting with same side slopes
A = B×d +s×d2, m2
where
(2) Sectional area having no transverse slope for diking or cutting with different side slopes
m2
where
b = base width of dike, m
Simpson's rule: divide the sectional area into an even number (n) of parallel strips by means of (n
+ 1) ordinates, spaced equal distances, d
In this formula, the mean depth or height should be calculated first by averaging the depths of
two consecutive sections. From the mean depth the area of mid section should be calculated and
volume of earthwork computed by multiplying the area of mid section by the distance between
the two original sections. To estimate the quantity of earthwork for a dike or a channel whose
level sections are taken at a distance, D, which may be varied depending on the ground level in
the longitudinal section of the dike or the channel, a tabular form can be used as shown below:
This method is based on the assumption that the mid area of a pyramid is half the average area of
the ends and the end sections are in parallel planes. If A 1 and A2 are areas of the ends the volume
of the prismoid is given by
If the volume of earth between two successive cross-sections is considered a prismoid, then a
more precise formula, the prismoidal formula, may be used. It is generally considered that end
sections are in parallel planes.
There are a number of alternative ways in which the prismoidal formula may be used. For
instance, it can be used to calculate the volume of excavation in a smaller nursery pond applying
the prismoidal formula for a single strip
, m3
where
D = depth of excavation, m
A1 = top area of excavation, m2
A2 = bottom area of excavation, m2
Am = mid area of excavation, m2
This method may be conveniently used where accurate contours are available. The contour
interval will determine the distance D in the trapezoidal or prismoidal formula, and for accuracy
this should be as small as possible, preferably 0.1 to 0.5 m. The areas enclosed by individual
contour lines are best taken off the map by means of a planimeter. In computing the volumes, the
areas enclosed by two successive contour lines are used in the trapezoidal formula, whence:
where
V = volume of earth between contour lines A1 and A2
D = vertical interval
This method can also be used to calculate the volume of water contained in a reservoir,
corresponding to a given height. This is done by calculating the total volume contained below
successive contours and then plotting volume against height to give a curve from which the
volume at intermediate levels may be read.
This is a method by means of which the earthwork for pond bottom, borrow pits, etc. and similar
works with vertical sides may be calculated. Using this method, the area marked out on the
contour map should be divided up into squares or rectangles. Elevations are taken at each of the
corner points and by subtracting these from the corresponding formation levels, a series of
heights is obtained from which the mean height of a series of vertical truncated prisms of earth
can be found. The volume of each prism is given by the plan area multiplied by the mean height
of the prism. The prisms may, of course, be considered as either rectangles or triangles.
TENDER DOCUMENTS
Draft Contract
Types of contracts
Unit-price contract
For unit-price contracts. Contractors are required to quote rates for various items of work on the
basis of the corresponding unit price.
(i) This form of contract ensures a more detailed analysis of cost by the Contractor. The authority
concerned with accepting the tender can easily control the rates with reference to its own
calculations and decide which of the tenders is favourable.
(ii) Since the Contractors are to write rates of individual items in figures as well as in words, it is
not easy to form a ring during submission of tender and allot work to one of the Contractors
without competition.
(iii) The Contractors work out the unit prices of all items of the Bill of Quantities in order to put
them in the bid. Thus, an unworkable rated tender may be avoided, which leads to smooth
progress and timely completion of the work.
Lump-sum contract
In this form of contract the Contractor is required to quote a fixed sum for execution of the work
completed in all respects. For such a contract, it is very important that the drawings and
specifications be comprehensive and show in complete detail all features and requirements of the
work.
(i) The employer knows exactly what the work will cost.
(ii) Detailed measurements of the work executed are not required to be recorded except in
respect of additions and alterations.
In this form of contract the Contractor is required to quote partly a fixed sum for execution of an
entire structure completely detailed on the drawings, and partly unit prices which may be
required for features of variable quantities such as excavation of drains for ponds.
Negotiated contract
When work is awarded on contract by mutual negotiation between the parties without call of
tenders, it is said to be a negotiated contract. It may be in any of the forms mentioned above.
Advantages of this contract are that it brings some economy in expenditure. The parties selected
being always reliable and financially sound, ensure interrupted work with less chance of dispute.
Draft contracts consist of general provisions or general conditions and special provisions or
special conditions. The general provisions set forth the rights and responsibilities of the parties to
the construction contract and the surety, the requirements governing their business and legal
relationships. Particular requirements of the project are separately inserted in the special
provisions.
Governments have their own standard general conditions of contract provided on the printed
tender form. The conditions specify mainly the following articles:
The general provisions used by FAO in the contract for an aquaculture project specify the
following articles:
Statements of work and services contain the scope of the work including description of the site
for work, soil characteristics determined by the reconnaissance soil survey carried out at the site,
meteorological features needed for the construction works and the operation of the project,
description of the project in detail including the construction works and services required.
The technical specifications contain detailed descriptions of all workmanship, services and
materials as well as testing methods which are required to complete a project in accordance with
the drawings and specifications.
1) Specification of work is required to describe the quality and different materials needed for a
construction work and is one of the essential contract documents. In this manner the Contractor
can prepare a programme to procure the materials required for a project as well as enabling the
Owner's representative (the Engineer) to check the quality of materials, confirming the
specifications and thereby avoiding any dispute with the Contractor.
2) This also specifies the scope of work and services provided by the Contractor to the Engineer
as well as the workmanship, including the method of performing the work. Thus specification of
a work serves as a guide both to the Contractor and the Engineer in order to execute the work to
their satisfaction.
3) As the rate of work is based on a specification, the Contractor can calculate the rates of
various items of works in a tender with his procurement rates of materials and labour. Thus
tender documents without specifications of works are baseless;
4) The necessity of specification is to test the quality of materials for the work involved in a
project.
5) Specification is an essential contract document and is required for Arbitration or court cases.
Types of specifications
Standard specifications
The governmental departments and other public agencies sponsoring public works publish
"standard specifications", ensuring a uniformity of administrative procedure and of quality of
constructed facilities, as evidenced by specific requirements of materials and workmanship
(Merritt, 1968).
Master specifications
In order that the specifications for a particular contract may be completely adaptable to the work
of a contract, the standard specifications almost always require modifications and additions.
Therefore, master specifications are prepared by design organizations. A master specification
covers a particular item of construction, such as excavation of drains, dikes and concrete
structures of ponds, etc. It contains requirements for all possible conditions and construction that
can be anticipated for that particular item.
Specification writing
Specifications usually are written in the traditional style of composition. They should be
prepared with as much detail as necessary to convey that which is required and hence agreed to.
Ambiguity and verbosity should be avoided. A good specification is clear, concise and easily
understood. The courts have traditionally interpreted ambiguous requirements against the party
who prepared them. Since specifications supplement the drawings, the special provisions and
standard specifications together should not leave any doubt as to the quality of the required work.
Bill of Quantities
A bill of quantities or schedule of quantities consists of a complete list of all various items of
works for a project, giving the item number and description of items with unit and quantity of
work against each, thus enabling an estimated calculation of price of work. The bill of quantities
is prepared from drawings and specifications and is arranged in a tabular form without
completing columns of rate and amount. The work of a project is usually divided into separate
elements for payment purposes with respect to the kind of work involved, each element as a
separate bill designated as a payment item. The total price of a bid is obtained by summation of
the amounts for all items scheduled in the tender, arrived at by multiplying the estimated number
of units for each item by the corresponding unit-price bid. A sample summary used for bill of
quantities and contract cost is shown in Annex 6.
Schedule of Execution
The Contractor shall complete the work and services of the project to be executed under the
contract in accordance with the schedule of execution.
Schedules may be performed in either tabular or graphical form, although the graphical form is
generally used because of ease in visualization.
The most widely used graphical presentation of schedule of execution is the rectangular bar chart
(Figure 9). It shows starting and completion dates for each item of work. It indicates the items on
which work must proceed concurrently, items that overlap others and by how much, and the
items that must be completed before work on others can begin. It is a convenient way to advise
the Contractor of necessary material delivery dates.
For comparing performance of work with that scheduled, a bar is usually placed above the
schedule bar showing actual start and completion dates. The chart in Figure 9 indicates that
clearing and preparing of site started on the date programmed and was completed ahead of time
whereas construction of outlets began late. At the close of August, construction of outlets was
75% complete. This method has the advantage of being simple. It can be used for a small-scale
project, however a more detailed schedule of execution is required for a large-scale project. In
this case bar charts have to be separately prepared for performance of work items and others
showing materials and different machinery needed for all items of works.
The bidding schedule is a very important document on which the contractor summarises his bid
including the total price of bid, the load bearing capacity of the soil at the site on which the bid is
calculated and confirms as well as signs the terms and conditions of the contract. There are
various forms of a bidding schedule.
One set of approved drawings prepared for the project should be provided with the tender, on
which the bidders will be able to control the tender's bill of quantities and calculate their bids.
The following drawings have been generally enclosed with the tender documents:
Further drawings may be issued from time to time at the discretion of the Engineer, as need
arises.
Schedule Control
In addition to cost control, project managers must also give considerable attention to monitoring
schedules. Construction typically involves a deadline for work completion, so contractual
agreements will force attention to schedules. More generally, delays in construction represent
additional costs due to late facility occupancy or other factors. Just as costs incurred are
compared to budgeted costs, actual activity durations may be compared to expected durations. In
this process, forecasting the time to complete particular activities may be required.
The methods used for forecasting completion times of activities are directly analogous to those
used for cost forecasting. For example, a typical estimating formula might be:
where Df is the forecast duration, W is the amount of work, and h t is the observed productivity to
time t. As with cost control, it is important to devise efficient and cost effective methods for
gathering information on actual project accomplishments. Generally, observations of work
completed are made by inspectors and project managers and then work completed is estimated as
described above. Once estimates of work complete and time expended on particular activities is
available, deviations from the original duration estimate can be estimated. The calculations for
making duration estimates are quite similar to those used in making cost estimatesabove.
For example, Figure 1 shows the originally scheduled project progress versus the actual progress
on a project. This figure is constructed by summing up the percentage of each activity which is
complete at different points in time; this summation can be weighted by the magnitude of effort
associated with each activity. In Figure 1, the project was ahead of the original schedule for a
period including point A, but is now late at point B by an amount equal to the horizontal distance
between the planned progress and the actual progress observed to date.
Schedule adherence and the current status of a project can also be represented on geometric
models of a facility. For example, an animation of the construction sequence can be shown on a
computer screen, with different colors or other coding scheme indicating the type of activity
underway on each component of the facility. Deviations from the planned schedule can also be
portrayed by color coding. The result is a mechanism to both indicate work in progress and
schedule adherence specific to individual components in the facility.
In evaluating schedule progress, it is important to bear in mind that some activities possess float
or scheduling leeway, whereas delays in activities on the critical path will cause project delays.
In particular, the delay in planned progress at time t may be soaked up in activities' float (thereby
causing no overall delay in the project completion) or may cause a project delay. As a result of
this ambiguity, it is preferable to update the project schedule to devise an accurate protrayal of
the schedule adherence. After applying a scheduling algorithm, a new project schedule can be
obtained. For cash flow planning purposes, a graph or report similar to that shown in Figure 2can
be constructed to compare actual expenditures to planned expenditures at any time. This process
of re-scheduling to indicate the schedule adherence is only one of many instances in which
schedule and budget updating may be appropriate, as discussed in the next section.
As an example of the type of changes that might be required, consider the nine activity project
described aboe and appearing in Figure 3. Also, suppose that the project is four days underway,
with the current activity schedule and progress as shown in Figure 4. A few problems or changes
that might be encountered include the following:
1. An underground waterline that was previously unknown was ruptured during the
fifth day of the project. An extra day was required to replace the ruptured section,
and another day will be required for clean-up. What is the impact on the project
duration?
o To analyze this change with the critical path scheduling procedure, the
manager has the options of (1) changing the expected duration of activity
C, General Excavation, to the new expected duration of 10 days or (2)
splitting activity C into two tasks (corresponding to the work done prior to
the waterline break and that to be done after) and adding a new activity
representing repair and clean-up from the waterline break. The second
approach has the advantage that any delays to other activities (such as
activities D and E) could also be indicated by precedence constraints.
o Assuming that no other activities are affected, the manager decides to
increase the expected duration of activity C to 10 days. Since activity C is
on the critical path, the project duration also increases by 2 days. Applying
the critical path scheduling procedure would confirm this change and also
give a new set of earliest and latest starting times for the various activities.
2. After 8 days on the project, the owner asks that a new drain be installed in
addition to the sewer line scheduled for activity G. The project manager
determines that a new activity could be added to install the drain in parallel with
Activity G and requiring 2 days. What is the effect on the schedule?
o Inserting a new activity in the project network between nodes 3 and 4
violates the activity-on-branch convention that only one activity can be
defined between any two nodes. Hence, a new node and a dummy activity
must be inserted in addition to the drain installation activity. As a result,
the nodes must be re-numbered and the critical path schedule developed
again. Performing these operations reveals that no change in the project
duration would occur and the new activity has a total float of 1 day.
o To avoid the labor associated with modifying the network and re-
numbering nodes, suppose that the project manager simply re-defined
activity G as installation of sewer and drain lines requiring 4 days. In this
case, activity G would appear on the critical path and the project duration
would increase. Adding an additional crew so that the two installations
could proceed in parallel might reduce the duration of activity G back to 2
days and thereby avoid the increase in the project duration.
3. At day 12 of the project, the excavated trenches collapse during Activity E. An
additional 5 days will be required for this activity. What is the effect on the
project schedule? What changes should be made to insure meeting the completion
deadline?
o Activity E has a total float of only 1 day. With the change in this activity's
duration, it will lie on the critical path and the project duration will
increase.
o Analysis of possible time savings in subsequent activities is now required,
using the procedures described above.
LEARNING GUIDE #2
Unit of Competence: Prepare Job Estimation and Costing
Module Title: Preparing Job Estimation and Costing
LG Code: CON BCM4 03 0211
TTLM Code: CON BCM4 07 1014
This learning guide is developed to provide you the necessary information regarding the
following content coverage and topics –
The types on-site personnel
The labor hours for non-contract elements
Time requirements for work activities and other lead times
The costs or rates for required on-site work.
This guide will also assist you to attain the learning outcome stated in the cover page.
Specifically, upon completion of this Learning Guide, you will be able to –
Identify the types and numbers of appropriate on-site personnel and estimate the time
required .
calculate the labor hours for non-contract elements of on-site work .
estimate time requirements for work activities and other lead times
calculate the costs or rates for required on-site work.
Learning Activities
1.Read the specific objectives of this Learning Guide.
2.Read the information written in the “Information Sheet”
3.Accomplish the “Self-check”.
4.If you earned a satisfactory evaluation proceed to the next “Information
Sheet ”. However, if your rating is unsatisfactory, see your teacher for
further instructions or go back to Learning Activity.
5.Submit your accomplished Self-check . This will form part of your
training portfolio.
6.Read and Practice “Operation Sheets”.
7.If you think you are ready proceed to “Lap test ”.
8.Request you teacher to observe your demonstration of the exercises and
give you feedback.
INFORMATIO The types on-site personnel
N SHEET # 1 The labor hours for non-contract elements
Time requirements for work activities and other lead times
The costs or rates for required on-site work.
Before starting any construction one has to have a thorough knowledge about the type of the
work and the probable cost that may be required for the completion of the project. Otherwise, the
construction will be stopped before its completion due to shortage of money or materials.
There are two types of estimates, Approximate/Rough estimate: To get an idea for the probable
expenditure in a short timeand also to prepare a preliminary estimate before drawing up a
detailed estimate for a project,and this is made after knowing the costs of similar projects. The
second one is detailed estimate: This is the best method and includes the quantities and cost of
everything required for the work. It requires Drawings and Specification Therefore, quantity
surveying may be defined as the process of calculating the quantities and cost of various works
required in connection with the project.quantity surveying have many purposes such, To know
the amount of money required, To know the quantities of materials required, To know the
different workers to be employed, To draw up the construction schedule and program etc. Our
project is focused on detail estimation.
Understanding how the building design influences constructioncosts is a challenging task for
estimators. Estimatorsmust identify the design conditions that are important i.e., incur a cost and
adjust the activities, resources, and resourceproductivity rates that form the basis of a
costestimate for a particular design. The primary product 3-D model exchangestandard for the
architecture, engineering, and constructionindustry.Models by extracting dimensional
information forquantity takeoff calculations However, in addition to dimensional information,
other types of design conditions impact the cost ofconstructing building components, such as
openings, penetrations,and component similarity. Estimators have differentpreferences for
describing these different design
conditions and the impact they have on a specific component’sconstruction cost. To provide
product models that
are useful for cost estimating, estimators need a vocabulary for describing the different types of
design conditionsthat affect construction costs and a framework to capturethis knowledge from
estimators so that it can be reusedfrom project to project in feature-based cost analysis.
Labour cost
This includes the number of labourers, skilled and unskilled, and their respective wages
multiplied by the hours required to complete per unit.
• The types and numbers of appropriate personnel are identified and the time required is
estimated.
• Time requirements for work activities and other lead times are estimated
Labor costs :are generally divided into direct and indirect costs.
• The direct labor cost is for labor directly involved in manufacturing the part ( productive
labor).
• This cost includes all labor from the time ,materials are first handled to the time the
product is finished.
The direct labor cost is calculated by multiplying the labor rate ( hourly wage , including
benefits) by the time that the worker spends producing the part.The time required for producing a
part depends not only on required part size , shape and dimensional accuracy , but also on the
work piece material.
Step 1
Determine which workers are considered direct laborers. Direct laborers are workers who
directly perform work on the product being produced. For example, in an automotive factory,
the person puts the wheels on the car is a direct laborer, but the person who sweeps the
floors is not.
Step 2
Add up the total hours that all direct laborer work in the period in question. If you had four
direct laborers, who worked 400, 300, 200 and 500 hours, you would add these hours up to get
1,400 hours.
Step 3
Multiply the number of hours by the labor rate. This will give you the total direct
manufacturing costs. Assuming that the wage rate was $10 per hour, you would multiply it by
1,400 -- the number of hours in this example -- to get total direct manufacturing costs of $14,000.
Self Check #
2 Written test
2. Describe time requirements for work activities and other lead times.
MARS ENGINEERING COLLEGE
LEARNING GUIDE #3
Unit of Competence: Prepare Job Estimation and Costing
Module Title: Preparing Job Estimation and Costing
LG Code: CON BCM4 03 0211
TTLM Code: CON BCM4 07 1014
This learning guide is developed to provide you the necessary information regarding the
following content coverage and topics –
Physical resource requirements
Lists of materials and quantities
Quantities against project or standard construction contracts
Supplier prices for materials and consumables
Plant or equipment requirements
This guide will also assist you to attain the learning outcome stated in the cover page.
Specifically, upon completion of this Learning Guide, you will be able to –
Identify physical resource requirements .
Calculate lists of materials and produce quantities.
Establish quantities against project or standard construction contracts.
Obtain supplier prices for materials and consumables .
Identify and cost Plant or equipment requirements.
Learning Activities
1.Read the specific objectives of this Learning Guide.
2.Read the information written in the “Information Sheet”
3.Accomplish the “Self-check”.
4.If you earned a satisfactory evaluation proceed to the next “Information
Sheet ”. However, if your rating is unsatisfactory, see your teacher for
further instructions or go back to Learning Activity.
5.Submit your accomplished Self-check . This will form part of your
training portfolio.
6.Read and Practice “Operation Sheets”.
7.If you think you are ready proceed to “Lap test ”.
8.Request you teacher to observe your demonstration of the exercises and
give you feedback.
Physical resource requirements
INFORMATIO Lists of materials and quantities
N SHEET # 1 Quantities against project or standard construction contracts
Supplier prices for materials and consumables
Plant or equipment requirements
• A resource is anything (e.g., people, material, money, capital asset) that help to achieve a
purpose. It includes knowledge, technology, power, material, people, time , information
and finance.
• ACQUISITION: procuring the right resources from the right sources at the right time
• ALLOCATION: Involves decisions about how resources are developed within a set of
time or period
• UTILIZATION: Putting the resources plan into operation. It involves activities such as
setting, timetabling, ordering supplies, maintenance and development.
• EVALUATION: evaluation of the past use of resources with a view to informing future
decision – making
• Inventory records
• Refers to stored information on the status of each item by time period, called time
buckets. It includes
• gross requirements,
Self Check #
3 Written test
LEARNING GUIDE #4
Unit of Competence: Prepare Job Estimation and Costing
Module Title: Preparing Job Estimation and Costing
LG Code: CON BCM4 03 0211
TTLM Code: CON BCM4 07 1014
LO #4: Develop estimated project costs
This learning guide is developed to provide you the necessary information regarding the
following content coverage and topics –
selecting and applying appropriate labor rates and material costs
Estimates of unit costs
Costs to the project of work cover
Company overhead recovery and margins
project costs for inclusion in a tender or bill
This guide will also assist you to attain the learning outcome stated in the cover page.
Specifically, upon completion of this Learning Guide, you will be able to –
select and apply appropriate labor rates and material costs.
determine and apply estimates of unit costs, as appropriate.
identify and apply costs to the project of work cover, environmental protection agency
requirements, seeking approvals, waste management site fees and other statutory or
additional costs.
Apply company overhead recovery and margins.
calculate completed estimated project costs for inclusion in a tender or bill.
Learning Activities
1.Read the specific objectives of this Learning Guide.
2.Read the information written in the “Information Sheet”
3.Accomplish the “Self-check”.
4.If you earned a satisfactory evaluation proceed to the next “Information
Sheet ”. However, if your rating is unsatisfactory, see your teacher for
further instructions or go back to Learning Activity.
5.Submit your accomplished Self-check . This will form part of your
training portfolio.
6.Read and Practice “Operation Sheets”.
7.If you think you are ready proceed to “Lap test ”.
8.Request you teacher to observe your demonstration of the exercises and
give you feedback.
Unit costs may include but are not limited to the cost of:
tiling per square meter
painting per square meter
masonry walls per meter square
construction cost per square meter
installation of sanitary ware per unit
laying of foundation per meter
laying of slabs per meter square
installation of pipes per meter laying of steel tray roofing per meter square
Project __________________________________
Item T D S Description
A. SUB STRUCTURE WORK
1. EXCAVATION & EARTH WORK
18.50 1.1 Clear and remove top soil to an average depth of 200mm
16.50 18.50 * 16.50 = 305.2 m2
305.2 m2
1.2 Bulk excavation in ordinary soil to 400mm depth from RGL to
18.50 remove expansive soil material.
16.50 18.50 * 16.50 * 0.40 = 122.1 m3
0.40
122.1 m3
1.3 Pit excavation in ordinary soil to a depth not exceeding 1800mm
1.80 from reduced ground Level.
1.70 1.80 * 1.70 * 1.70 =78.03 m3
1.70
78.03 m3
1.4 Trench excavation for masonry foundation to 900mm depth
starting from reduced ground level
70.12 10.2+11.94+9.11+12.5+5.58+0.45+4.92+2.19+3.75+580+358
0.9 = 70.12
0.8 Trench excavation a depth of 900mm from GL
50.48 m3 70.12 * 0.9 * 0.8 = 50.48 m3
1.5 Back fill around foundation with selected material from site and
compact in layers not exceeding 200mm thick.
Project __________________________________
Page ____________________________________ Date ____________________
Item T D S Description
1. 6.Cart away
Load and cart away all excavated material to an appropriate tip
Site clear and Top soil + bulk excavation
= 305.2*0.20
61.04 = 61.04
78.03 = 61.04 + 78.03 m3
139.07 m3 =139.07 m3
1. 7.Hard core
250mm thick basaltic stone hardcore well rolled, consolidated and blinded
with crushed stone.
3.05
4.47
13.63 m2 Area -1
2.55
3.62
9.23 m2 Area -2
3.60
2.55
9.18 m2 Area -3
5.45
4.47
24.36 m2 Area - 4
3.58
5.45
17.72 m2
2.08 Area – 5& 5’
4.55
9.46 m2 Area - 6
3.90
0.80
3.12 m2 Area - 7
4.10
1.50
6.15 m2 Area - 8
3.90
1.80
7.02 m2 Area - 9
Project __________________________________
Page ____________________________________ Date ____________________
Item T D S Description
2. CONCRETE WORK
2.1. lean concrete
50 mm lean concrete quality C-5, with minimum cement content of 150 kg
/m3, of concrete:
15/ 1.70 a) Under Footings
1.70
43.35 m2 43.35x0.05=2.16
b) Under Masonry
60.64
0.6 36.39x0.05=1.81
36.39 m2
4.55
5.26 c) Under parking
2
23.93 m
23.93x0.05=1.19
103.67 m2 Total area of lean concrete
b) In grade beams
14.75
3/ 0.50
0.30
6.63 m3 On axis D,C & A
11.85
2/ 0.50
0.30
3.55 m3 On axis 1 & 2
10.04
2/ 0.50
0.30
3.01 m3 On axis 3 & 4
Project __________________________________
Page ____________________________________ Date ____________________
Item T D S Description
4.55
0.50
0.30
0.68 m3 On axis 7
7.36
0.50
0.30
1.10 m3 On axis 8
5.52
0.50
0.30 On axis 9
0.82 m3
6.03
0.50
0.30
0.90 m3 On axis 10
2.3.form work
Provide, cut and fix in position sawn zigba wood or steel formwork which
ever is appropriate.
a) To footing.
15/ 4.88
0.30
21.96 m2
(2*1.24)+(2*1.2)= 4.88
Project __________________________________
Page ____________________________________ Date ____________________
Item T D S
for footing column form work
15/ 3.00
0.58
26.10 m2
15/ 3.00
0.50 (1.5*2) = 3.00
22.50 m2 (2*.29) = 0.58
(2*.25) = 0.50
48.60 m2 Total area of form work for footing column and for footing pad
24.90
0.30
7.47 m2 Grade beam on Axis C
15.96
0.30
4.77 m2 Grade beam on Axis B
15.80
0.30
4.74 m2 Grade beam on Axis A
18.62
0.30
5.60 m2 Grade beam on Axis 4
16.50
0.30
4.95 m2 Grade beam on Axis 3
18.42
0.30
5.52 m2 Grade beam on Axis 2
Project __________________________________
Page ____________________________________ Date ____________________
Item T D S Description
20.42
0.30
6.126 m2 Grade beam on Axis 1
3. MASONRY WORK
500mm thick hard trachytic roughly dressed stone masonry foundation wall
below ground level bedded in cement mortar (1:3)
foundation wall
70.12*0.5*0.9
=31.55 m3
31.55 m3
Project __________________________________
Item T D S Description
B-SUPER STRUCTURE
9.37
0.30
0.35 0.98 m3 volume of concrete for upper beam On axis B
4.37
0.30
0.35 0.45 m3 volume of concrete for top tie beam on axis B
Project __________________________________
Item T D S Description
d. Lintel beam (concrete work)
2.75
0.20
0.20
0.11 m3 Volume of concrete for lintel beam for W1
3.72
3/ 0.20
0.20
0.45 m3 Volume of concrete for lintel beam for or FD1
2.75
3/ 0.20
0.20
0.33 m3 Volume of concrete for lintel beam for W5
2.00
2/ 0.20
0.20
0.12 m3 Volume of concrete for lintel beam for D1 (external)
2.75
3/ 0.20
0.20
0.33 m3 Volume of concrete for lintel beam for W4
4.20
2/ 0.20
0.20
0.336 m3 Volume of concrete for lintel beam for W2
1.50
2/ 0.20
0.20
0.12 m3 Volume of concrete for lintel beam for W6
2.30
2/ 0.20
0.20
0.18 m3 Volume of concrete for lintel beam for W7
2.74
9/ 0.20
0.20
0.986 m3 Volume of concrete for lintel beam D1(internal)
2.74
4/ 0.20
0.20
0.438 m3 Volume of concrete for lintel beam D2
Project __________________________________
Item T D S Description
5.20
6.35
0.20
6.60 m3 Volume of concrete for first floor slab for A10
7.97
0.20
1.59 m3 Volume of concrete for first floor slab for A5 & 5’
3.90
1.80
0.20
1.40 m3 Volume of concrete for first floor slab for A9
Project __________________________________
Item T D S Description
3.90
1.80
0.202
1.40 m3 Volume of concrete for second floor slab for A9
Project __________________________________
Item T D S Description
0.18
0.30
1.20
1.20
2/ 2.50
0.15
0.90 m3 Total volume of concrete for landing
1.62m
2.7m
C2 = a2+b2
= (2.7)2+(1.62)2
3.14 c = 3.14 m
4/ 1.20
0.15
2.26 m3 Total volume of concrete for stair slab.
Project __________________________________
Item T D S Description
a.1.In elevation columns for ground floor (form work)
2.75
15/2 0.29
23.92 m2
15/2 2.75
0.25
20.62 m2
8/2 2.75
0.29
12.76 m2
23.76 m2
13.55
0.30
Total area of form work for second floor.
4.06 m2
b.1. In upper beams (form work)
28.30
Upper beam form work for axis D.
0.35
9.90 m2
axis D form work bottom
L= external + internal
= 14.75+13.55 = 28.3
Project __________________________________
Item T D S Description
Upper beam form work for axis C.
13.55
0.30
4.06 m2 Axis C form work bottom.
13.55
0.35
4.065 m2 Axis A form work bottom.
4/ 18.88
0.35
26.40 m2 Axis 1 form work side.
8.84
4/ 0.30
10.65 m2 Axis 1 form work bottom.
Project __________________________________
Item T D S Description
3/ 18.88 Top tie beam form work for axis 2,3, & 4.
0.35
19.82 m2 Axis 2, 3, & 4.form work side.
3/ 8.65
0.30
7.78 m2 Axis C, D & A form work bottom.
Project __________________________________
Item T D S Description
3/3 2.75
0.20
4.95 m2 area of form work for W5
2.00
6/3 0.20
7.20 m2 area of form work for W3
1.52
2/3 0.20
1.82 m2 area of form work for D1 (External)
2.75
5/3 0.20
4.95 m2 area of form work for W4
4.20
2/3 0.20
5.04 m2 area of form work for W2
1.50
2/3 0.20
1.80 m2 area of form work for W6
2/3 2.30
0.20
2.76 m2 area of form work for W7
9/3 2.74
0.20
14.79 m2 area of form work for D1-(internal)
4/3 2.74
0.20
6.51 m2 area of form work for D2
Project __________________________________
Item T D S Description
3.60
2.55
9.18 m2 area of form work for A3
3.00
3.70
11.1 m2 area of form work for A6’
2.55
3.62
9.23 m2 area of form work for A2
5.20
6.35
33.02 m2 area of form work for A10
7.97
94.27m2 Total area of form work from the first floor slab.
f.1. slab for Second floor (form work)
5.00
3.70
18.50 m2 area of form work for A1
3.62
2.55
9.23 m2 area of form work for A2
3.90
0.80 3.12 m2 area of form work for A7
5.45
4.47 24.36 m2 area of form work for A4
Project __________________________________
Item T D S Description
3.40
6.30
21.42 m2 area of form work for A12
7.97
7.97 m2 area of form work for A5 & 5’
3.90
1.80
7.02 m2 area of form work for A9
Perimeter = 2(2.5)+2(1.2)
= 7.40m
7.40
0.15
1.11 m2 Side panel(board) for landing
2/ 1.20
2.50
6.00 m2 Bottom panel(board) for landing
3.14m
C2 = a2+b2
= (2.7)2+(1.62)21.62m
c = 3.14 m
3.14 2.7m
4/ 1.20
15.07 m2 Bottom panel(board) for flight
3.14
4/2 0.15
Side panel(board) for flight
3.768m2
25.945m2
Total form work area for stair case
Take off Sheet
Project __________________________________
Item T D S Description
2. BLOCK WORK
2.1. 200mm thick class C HCB wall with the designed compressive strength
capacity, bedded in cement mortar (1:3) and both sides left for
61.33 plastering.
3.05
187.05m2 Block work for Ground floor
65.09
3.05
198.53m2 Block work for Upper floor
45.37
3.05
138.53m2 Block work for Second floor
2.15
2.45
-5.26 m2 Deduction for W1
3/ 3.12
2.45
-22.93 m2 Ditto but for FD1
3/ 2.15
0.91
-5.86 m2 Ditto but for W5
6/ 1.40
1.30
-10.92 Ditto but for W3
2/ 0.92
2.35
-4.32 Ditto but for D1
4/ 2.15
1.45
-12.47 Ditto but for W4
Project __________________________________
Item T D S Description
2/ 3.60
2.45
-17.60 Ditto but for W2
2/ 0.90
0.91
-1.63 Ditto but for W6
2/ 0.90
0.91
-8.50 Ditto but for W7
434.46 m2 The net total area of block work for external wall (200 mm HCB)
2.2. 150mm thick class HCB wall with the designed compressive strength
capacity, bedded in cement mortar (1:3) and both sides left for
24.35 plastering.
3.05
74.26 m2 Block work for Ground floor
29.02
3.05
88.60 m2 Block work for upper floor
23.45
3.05
71.52 m2 Block work for second floor
4/ 2.14
0.70
-9.26 ditto but for D2
207.25 m2 the net total area of HCB for internal wall(150 mm HCB)
Project __________________________________
Item T D S Description
2.3. 150mm thick HCB parapet wall
A = ½*5.4*2.25
2/ 6.10 = 6.1 m2
8.52 A = 8.52*2.25
2.25 = 19.17 m2
19.17 m2 Area of block work for rectangular parapet wall.
A = ½*1.2*1.7
2/ 1.02m2 = 1.02 m2
A = ½*1.2*1.5
= 0.9 m2
2/ 0.90
1.80 Area of block work for triangular parapet wall.
Project __________________________________
A1 A2
A = (A1+A2)
=2(1/2*1.2*1.95)
=2.34 m2
2/ 2.34
4.68 m2 Area of block work for triangular parapet wall.
770.22m2 The net total area of HCB including external, internal, & parapet walls
3. ROOFING
Roof cover in Decra roof tile that should be fixed to 70x50mm zigba purlins
of c/c 370mm spacing, to be fixed to structural eucalyptus truss members. The
decra tile shall be fixed according to the local agent's instruction. (Roof cover
is measured in horizontal projection and purlins measured separately).
3.1.Roof cover
For A1
5.48 X =√52+2.252
8.50 =5.48m
46.58 m2 Area of roof for A1
For A2
x
A2
2 2
X =√4.35 +1.86
4.73 =4.73m
4.15
19.62 m
Area of roof for A2
Take off Sheet
Project __________________________________
Item T D S Description
For A2’ &A3’
x
A2'
X= 3.83m
2/ ½ 3.83 A=2(1/2*3.55*3.83)
3.55 =13.6 m2
13.60 m2 Area of roof for A2’& A3’
For A3
x
A3
X=√3.352+1.862
3.83 =3.83m
4.15
15.90 m2 Area of roof for A3
For A4
x
A4
2/½ 3.35
3.83 X =3.83m
12.80 m2 A=2(1/2*3.35*3.83)
= 12.8m2
Area of roof for A4
For A5 & A5’
A5 A5'
x x
2.92 X =√1.22+1.952
2/ 2.28 = 2.28m
13.31 m2
Area of roof for A5 & A5’
Project __________________________________
Item T D S Description
For A6
x
A6
X=√2.62+1.52
X= 3m
A= 2(1/2*2.75*3)
2/ ½ 2.75 = 8.25 m2
3.0
8.25 m2 Area of roof for A6
For A7
x
A7
X=√2.752+1.52
X=3.13m
A= 2(1/2*2.6*3.13)
2/ ½ 2.60 = 8.13 m2
3.13
8.13 m2 Area of roof for A7
For A8 & A8’
A8 A8'
x x
X=√2.752+1.52
X=3.13m
A= 2(4.2*3.13)
2/ 4.20 = 26.29m2
3.13
26.29 m2 Area of roof for A8 & A8’
x
A9
x
A10
X=√1.72+12
X=1.97m
4.00 A= 4*1.97
1.97 = 7.88m2
7.88 m2 Area of roof for A10
x
A11
X=√1.72+12
X=1.97m
1.97 A= 4.75*1.97
4.75 = 9.35m2
9.35 m2 Area of roof cover for A11
56.51
0.20
0.08
0.904 m3 Volume of concrete for gutter bed slab.
56.51
0.40
0.08
1.808 m3 Volume of concrete for gutter face(side)
Project __________________________________
Item T D S Description
4pcs
4 ∑vertical .member = 0.6m+1.1m+1.61m+2.13m= 5.44m
∑rafter = 5.3m
Width = 5.3m
c/c = 0.3m
Space = 5.3/0.3 = 17
No of purlin = 17+1 = 18
Length of roof = 8.5m
Project __________________________________
Item T D S Description
For Area -2
4 pcs truss
∑rafter = 4.73m
Width = 4.73m
c/c = 0.3m
Space = 4.73/0.3 = 16
No of purlin = 16+1 = 17
Length of roof = 4.35m
Project __________________________________
Item T D S Description
For Area -3
4
4 pcs of truss
∑vertical .member = 0.53+1.2+1.86=3.58m
∑rafter = 3.83m
Total length for A-3 = 14m
4.35m/1.1m = 4 , 4+1=5
Total length of truss for A-3 =14*5=70m
Purlin for A-3
Width = 3.83m
c/c = 0.3m
Space = 3.83/0.3 = 13
No of purlin = 13+1 = 14
Length of roof = 4.35m
Total length of A-3 purlin = 4.35*14=61m
= 2*61=122m
Take off Sheet
Project __________________________________
Item T D S Description
∑rafter = 3.83m
Total length for A-4 = 14m
3.7m/1.1m = 3 , 3+1=4
length of truss for A-3’ =14*4=56m
Total length of truss for A-3’& A4 =56m *4parts
=224m
Width = 3.83m
c/c = 0.3m
Space = 3.83/0.3 =13
No of purlin = 13+1 = 14
Length of roof = 4.35m
length of A-3 purlin =3.70 *4=14.8m
Total length of A-3’ & A4 purlin = 14.8m*4parts
= 59.2m
Project __________________________________
Item T D S Description
Width = 3.13m
c/c = 0.3m
Space = 3.13/0.3 =10
No of purlin = 10+1 = 11
Length of roof = 2.93m
length of A-7 purlin =2.93m*11 =32.23m
Total length of A-6& A7 purlin = 32.23m*4parts
= 128.92m
Take off Sheet
Project __________________________________
Item T D S Description
For Area 8
∑rafter = 3.47m
Purlin for A8
Width = 3.47m
c/c = 0.3m
Space = 3.47/0.3 =12
No of purlin = 12+1 = 13
Length of roof = 4.06m
length of A-8 purlin =4.06m*13 = 52.78m
Total length of A8 purlin = 52.78m*2parts
= 105.56m
Project __________________________________
Item T D S Description
For Area A9
∑rafter = 2.01m
Width = 2.01m
c/c = 0.3m
Space = 2.01/0.3 =7
No of purlin = 7+1 = 8
Length of roof = 4.16m
Total length of A-9 purlin =4.16m*8 = 33.28m
Project __________________________________
Item T D S Description
For Area 10
∑rafter = 1.97m
Width = 1.97m
c/c = 0.3m
Space = 1.97/0.3 =7
No of purlin = 7+1 = 8
Length of roof = 4m
Total length of A-10 purlin =4m*8 = 32m
Project __________________________________
Item T D S Description
∑rafter = 1.97m
Total length for A-11 = 6.2m
5.81m /1.1 =5, 5+1= 6
Total length of truss for A11 =6.2*6=37.2m
Width = 1.97m
c/c = 0.3m
Space = 1.97/0.3 =7
No of purlin = 7+1 = 8
Length of roof = 5.81m
Total length of A-11 purlin =5.81m*8 = 46.5m
Project __________________________________
Item T D S Description
Total = 28.54m
Project __________________________________
Page ____________________________________ Date ____________________
38.89 m2 Parapet wall two face plastering area
Project __________________________________
Page ____________________________________ Date ____________________
Item T D S Description
2/ 207.25 m2
414.5 m2 Internal (partition) wall two face area
Project __________________________________
Item T D S Description
3.05 b) To concrete ceiling
4.47 First floor concrete ceiling
13.63 m2 For A1
3.90
0.80
3.12 m2 For A7
3.60
2.55
9.18 m2 For A3
3.00
3.70
11.10 m2 For A6’
2.55
3.62
9.23 m2 For A2
5.20
6.35
Project __________________________________
Item T D S Description
3.62
2.55
9.23 m2 For A2
3.90
0.80
3.12 m2 For A7
5.45
4.47
24.36 m2 For A4
3.40
6.30
5.95
3.85
22.91 m2 For A5 & 5’
3.90
1.80
7,02 m2 For A9
Project __________________________________
Item T D S Description
Windows and Doors manufactured from 28x1.5mm LTZ profile all as per the
Engineers approval and window door schedule. Price includes one coat of
antirust and two coats of synthetic enamel paint, door stopper, best quality
cylinder lock with handle and al
1 Doors Qty
Type FD1 size:300X314cm 2
D1 size:214 *94 cm (internal) 9
D2size:214 *70cm 4
D1 size:235 *92cm 2
2 WINDOWS
Type W4 size:215X145cm 4
Type W5;1 size: 216x100cm 1
Floor Finishing
2mm thick PVC tile flooring laid with best quality adhesive glue;
10.93
5.10
55.74 m2 Living and dining room ceramic tile 30*30cm-(A1,A4, & A10)
1.70
4.15
7.05 m2 Living and dining room ceramic tile 30*30cm-(A8)
3.90
4.70 Kitchen room ceramic tile 30*30-(A2)
18.33 m2
5.20
3.55 Maids bed room, ceramic tile 30*30-(A3)
18.46 m2
3.00
3.70 11.10 m2 For toilet, ceramic tile 30*30-(A6’)
1.80
3.50 7.02 m2 For entrance porch, ceramic tile 30*30-(A9)
2.60
1.20 Stair
3.12 m2 For landing area, ceramic tile 30*30
32/ 1.20
0.30
11.52 m2 For stair trade, ceramic tile 30*30
36/ 1.20
0.17
7.34m2 For stair riser, ceramic tile
Project __________________________________
Item T D S Description
Upper floor
5.0
3.7
18.5 m2 For bed room, ceramic tile 30*30-(A1)
6.35
5.20
33.02 m2 For master bed room, ceramic tile 30*30-(A10)
5.18
3.55
18.38
For bed room, ceramic tile 30*30-(A3)
3.60
2.95
10.62 m2 For bath room, ceramic tile 30*30-(A6’)
3.20
3.90
12.48 m2 For bath room, ceramic tile 30*30-(A2)
7.97
7.97 m2 For stair area, ceramic tile 30*30-(A5 & A5’)
100.97m2
Total area for upper floor tile work
Project __________________________________
3.20
3.90
12.48 m2 For bath room ceramic tile 30*30-(A2 & A7)
7.97
7.97 m2 For around stair ceramic tile 30*30 -(A5 & A5’)
3.40
6.50
22.10 m2 For study room ceramic tile 30*30-(A12)
1.20
0.30
5.70 m2 For stair trade ceramic tile 30*30
2.60
1.20
3.12 m2 For landing ceramic tile 30*30
2.85
5.00
14.25 m2 For terrace ceramic tile 30*30
5.10
3.95
20.14 m2 For family room ceramic tile 30*30-(A4
window sill
marble window sill with 3mm thickness & 230mm width
Project __________________________________
Item T D S Description
Skirting work
Project __________________________________
Item T D S Description
13.38 m For family room
Ceiling work
8mm thick chip wood ceiling or equivalent fixed on 40x50mm zigba batten at
c/c 600mm both ways to all bath rooms. Price shall include batten and
decorative angular corner list.
6.35
5.20
33.02m2 Master bed room A10( on first Floor)
5.00
3.70
18.50 m2 For bed room -(A1)
3.20
3.90
12.48 m2 For bath room
3.40
6.50
22.10 m2 For study room
3.90
7.45
29.05m2 For (A5 & A5’)
5.10
4.25
21.67m2 For family room
Project __________________________________
Date ____________________
Item T D S Description
Glazing
Sanitary installation
Ground floor
Trap(S) ½ 2
FD DIA. 80 1
valve ½ 1
Trap(S) ½ 1
valve ½ 1
WC With full
accessesary
FD DIA. 80 with cover 1
Toilet paper 1
holder
T- 1
2 From toilet to 15.38 Elbow(900) 5
kitchen
T- 1
First floor
valve ½ 1
Trap(S) ½ 1
Bath foceto 1
Elbow (900) 2
WC With accessories 1
Toilet paper 1
holder
Water heater 50 lit. 1
valve ½ 1
Trap(S) ½ 1
WC With accessories 1
Bath foceto 1
Elbow (900) 2
Second floor
valve ½ 1
Trap(S) ½ 1
WC With accessories 1
Bath foceto 1
Elbow (900) 2
Toilet paper 1
holder
T- union 1
Project __________________________________
Project __________________________________
Item T D S Description
For first floor
Project __________________________________
Project __________________________________
Item T D S Description
0 Fence work
1.Excavation and earth work
72.25
1.00 1.1Trench excavation: withboth direction allowance 0.25cmarea given
0.60 43.5m3 L)=72.5m w) = o.90m d)=0.60m
72.5
0.50
0.60 1.2Stone masonry work for foundation trench on fence
21.75m3 Undressed and mix with 1:4 cement rtion
72.5
2.0
0.40 1.3stone masonry work for wall
rough dressed un coursed with the cement mortar 1:3
58m3
72.5
2.00
145m2 1.4Pointingon dressed masonry only for external face
72.5
2.00 145m2
1.5plastering :only for internal wall with mix ratio 1:3
72.5
0.50 2.Concert work
0.20 36.05m2 2.1Grade beam for fences C-25 mix ratio 1:2;3
2.50 2.2colmun for fences c -25 grade concert with mix ratio 1:2:3
8 0.40
3 form work
0.40
3.20m3 L=72.5 H=0.20 for two side =2x (72.5x0.20)=29
For side cover = 2x(0.20x0.20)=0.8
72.5
2 0.20 29m2
Total area of fence form work= 29.08m2
2 0.20
0.8
0.20
Concert copping With mass concert mix ratio 1:2:4
29.08
72.5m
Project __________________________________
Item T S Description
1.Septic tank
Construction septic tank of masonry wall and cover with
Reinforcement concert slab of 150mm thickenss
d)=6m w)= 1.5 l)=1.5
A. SUB-STRUCTURE
Eth. Birr
1. Excavation and earth work 17711.60
B. SUPER-STRUCTURE
568972.40
Description Unit Qty Rate Amount
Item
A. Substructure
1.7 M2
25 cm thick basaltic or equivalent stone
hard core well rolled, consolidated and 307 33 10131.00
blinded with crushed stone.
2. Concrete work
2.1 5 cm thick lean concrete in c-5 with M3
minimum cement content of 150 M3
kg/m3under M3
M2
Provide, cut and fix in position sawn M2
M2
zigba wood form work
2.6 33 75 2475.00
Kg
2.7 72 75 5400.00
For footings
Kg
2.8 101 75 7575.00
To foundation column
Kg
To grade beams
B. Superstructure
1. Concrete work
M2
In elevation columns M2
1.3 In top tie beam 98 75 7350.00
Kg
1.4 Provide, cut and fix sawn zigba wood 190.3 75 14272500
form work Kg
To elevation column
M2
1.5 Steel reinforcement according to 2505 7.50 18787.50
structural drawing. Price shall include M2
1.6 cutting, bending placing position and 1558 7.50 11658.00
M2
tying wire.
8 mm deformed bars
62960.00
16 mm deformed bars
2.1 179 75 13425.00
Total carried to summary
2. Masonry work
2.2 196.6 65 12779.00
20 cm thick hollow block wall bedded in
2.3 cement sand mortar mix ratio (1:3) both 65.8 60 9948.00
sides left for plastering
36152.00
Ditto but 15 m thick
3. Roofing
3.1 M2 332 85 28220.00
Roof cover in G-28 (t = 0.6mm) fixed to
of lock 19239.00
Type Size
D1 90x275cm
W2 90x250cm
6.1 6. Finishing
M2 920 26 23920.00
Finishing work shall include all surfaces M2
6.2 per cleaning preparation, chiseling M2 300 31 9300.00
application of finishing, polishing and M2
6.3 cleaning at the end of finishing work. 175 19 3325.00
2
M
Apply three coats of plaster in cement Ml
6.4 mortar (1:3) to internal wall surface 332 110 36520.00
9. Sanitary Installation
I Internal Installation
9.8
Supply and install soil, waste and vent pipe
cement mortar.
50 mm
100mm
150 mm
200mm Ml 33 25 825.00
Ml 4.5 35 157.00