Documente Academic
Documente Profesional
Documente Cultură
: 3729/GC13107800
CONTRACT TITLE: -
DOCUMENT TITLE :
CONTRACTOR:
REV. APPD.
DATE NO. REASON FOR REVISION PREPARED CHECKED APPD. Q.P.
Table of Contents
1.0 PURPOSE 3
9.0 DOCUMENTATION 9
9.1 PROJECT DRAWINGS
Method Statement for HVAC WORKS
12.0 PLANNING 10
12.1 PLANNING TASKS
12.2 COMMISSIONING DURATION TIME
12.3 VENDOR ASSISTANCE
12.4 CLIENT ASSISTANCE
20.0 ABBREVIATIONS 10
1. PURPOSE
• The purpose of this Document is to describe the methodology for the commissioning of
HVAC System under Project GC09107200.
2. PRE-COMMISSIONING REQUISITES
Commissioning activities are to be carried out under direct supervision of manufacturer’s representative
and QP Personal.
2.1 General
• Gather and ensure that the relevant information and documentation required for Pre
commissioning at the latest version .
• AFC copies are available.
• Mechanical completion certificate for the system/ subsystem shall be a prerequisite for
proceeding to Pre-Commissioning activities.
• Personnel present for pre-commissioning are wearing the appropriate PPE.
Before commencing any work on site confirm that a valid permit to Work (Hot I Cold Work
Permit as Applicable) is Available for the task to be undertaken and all pre-job Safety Talks
(Toolbox) have been Completed .
2.4 Consumables
3. PRE-COMMISSIONING
3.1 Summary
The purpose of the Pre Commissioning procedure is to ensure that the specific HVAC systems of
EPIC FOR RLC PORTABLE WATER STORAGE TANKS AND PUMPS are properly installed
according to the approved project specifications, construction drawings and materials.
Further this procedure ensures to confirm and comply with QP standards for pre-
commissioning.
3.3 Description
Method Statement for HVAC WORKS
• Scaffolding.
• Self-supporting ladders.
• Temporary barriers I Warning Sign Boards ETC, (if Required)
Client assistance
• To witness the testing.
5. SAFETY RESPONSIBILITIES
5.1 General
• Safety Representatives I Worksite Supervisor to shall ensure that the work permit for pre
commissioning or commissioning I Testing Process for HVAC Works is in line with the
scope of work I Approved by the HSE Plan.
• Check the Installation Conformity to the design Drawings and Specifications prior to pre-
commissioning or Commissioning.
• All Necessary approved PPE Shall be provided and worn at all times.
Method Statement for HVAC WORKS
6. PRE-COMMISSIONING STEP-BY-STEP
• Check and ensure I confirm the alignment and orientation of volume control damper.
• Check and ensure I confirm the free movement of blades I control linkages and extent
of closure of damper.
• Check and ensure I confmn that damper and access doors are provided with adequate
access/platform and space for operation and maintenance.
• Check and ensure I confirm that Damper and access doors are provided with proper
labeling/name/description/ tags as per standards.
• Check and ensure I confirm the operation of the lockable quadrant handle.
• Check and ensure I confirm the handle rotating direction label is fixed
• Check and ensure I confirm the identification tags has been installed
Method Statement for HVAC WORKS
• Check and ensure I confirm the Access doors have been provided for maintenance.
• Check and ensure I confirm the alignment and orientation of control damper.
• Check and ensure I confirm the rotation of the Actuator is in right direction.
• Check and ensure I confirm the Actuator is properly aligned with the shaft of the Damper.
• Check and ensure I confirm the rotation direction tag has been fixed.
• Check and ensure I confirm that Damper and access doors are provided with proper
labeling/name/description/ tags as per standards.
• Check and ensure I confirm that damper and access doors are provided with adequate
access/platform and space for operation and maintenance.
• Check and ensure I confirm the alignment and orientation of Fire damper.
• Check and ensure I confirm the free movement of blades I control linkages and extent of
closure of damper.
• Check and ensure I confirm the operation of the lockable quadrant handle.
• Check and ensure I confirm the rotation direction tag has been fixed.
• Check and ensure I confirm that Damper and access doors are provided with proper
labeling/Name/description/ tags as per standards.
• Check and ensure I confirm that damper and access doors are provided with adequate
access/platform and space for operation and maintenance.
• Check and ensure I confirm the Limit Switches are provided with adequate
access/platform and space for operation and maintenance.
• All Extract fans are installed as per the HVAC layout specifications.
• Check and ensure I confirm the free rotation and direction of the extract fans.
• Check and ensure I confirm the identification tags have been fixed properly.
• Check and ensure I confirm all the Power and Control cables connected with the
System s h o u l d carry out the insulation resistance test and all the values to be recorded
in the check list provided.
• Check and ensure I confirm that all the Power and Control cables are suitably tagged for
identification.
• The incoming power cables to the unit isolators and to the control panel are properly
tightened and are within the specified torque values.
• Check and ensure I confirm that all the cables are routed through the proper cable trays and
trunks.
• Check and ensure I confirm that all the Cable trays and trunks are suitably grounded.
• Check and ensure I confirm that the cables are suitably glanded, and the glands have been
grounded with their check nuts.
• All the Units, Exhaust fans, Control panel , Motorized Control Damper and Isolators
should be properly grounded.
• All the Instruments (Provided if any) Such as Temperature transmitters, humidity
transmitters , pressure transmitters, Differential pressure transmitters and other
instruments, should be provided with the instrument earthing and the signal cables
should be a shielded.
• Check and ensure I confirm if temperature sensor/transmitters (if provided) in the ducts are
properly fixed and suitably glanded inside the ducts.
• Wiring free from abrasion, kinks and sharp corners.
• All the Differential pressure switches to monitor the filters are installed and the
respective hoses are suitably fixed to the unit filters.
• Air flow switches are installed at the correct position to identify the airflow.
• All the Motorized actuators are properly terminated and tagged.
• The Package A/C units wiring and cabling has been carried out with respect to the
drawings provided by the Manufacturer.
• All the Compressors, Solenoid valves, Condenser fans, Supply fan, Blower are
properly tagged and Terminated to the local control station of the Units.
• All the Motors should be grounded properly.
• The HVAC Control Panel has been provided to overall control & Monitor the HVAC system.
• Check and ensure I confirm that panels provided are in compliance with the required
Protection ratings I certifications.
• Check and ensure I confirm that panels are provided with the "As Built I As
Manufactured" drawings I wiring diagrams (fixed inside the panel).
• Check and ensure I confirm that the control panel is properly installed and free from damages.
• Ensure that the Panel General Arrangement is as per the Approved Drawings or as per the
Q.P Specifications.
• Check and ensure I confirm that panel is FAT/ TPI approved (if Applicable).
• Check and ensure I confirm that the internal loop test has been carried out and is up to
the mark.
• Check and ensure I confirm that the IP protection of the panel is as per specifications.
• Control panel internal arrangement is as per the Approved panel drawings.
• Relays, Contactors, and other switchgear items inside the panel are suitably tagged,
ease for maintenance.
• B.O. Q of the Control panel is as per the Drawings.
• PLC/DDC Controllers are mounted in the panel ensure the wiring is carried out as per
the specifications of the manufacturer.
Method Statement for HVAC WORKS
• All the Feed backs from the field are properly terminated with the Loop test carried out
earlier and is reported.
• All the outputs are at the proper voltage levels and are terminated at the designated
points.
• Sensors/Transmitters are properly terminated and are shielded.
• Check and ensure I confirm that AC/DC power is properly tagged and identified.
7.1 Protection:
• Ensure electrical equipments are protected against rain and water ingress, especially
those items located externally and not normally exposed to the ambient conditions.
• Ensure no mechanical damage due to other activities on site.
• Ensure that the equipment are protected properly from dust ingress.
• Ensure that all ,hot works" that are carried out in the vicinity of any HVAC equipment ,
should have the necessary protection in place to ensure that no damage to the equipment
or paint finish.
8. POST CONDITIONS
Equipment released for next phase of testing (Commissioning)
9. DOCUMENTATION
FORM: GENERAL
TASK LOCATION
ESTIMATED TIME(MH) :
Subsystem
ITEM CHECKLIST
1 1 Check and ensure I confirm that all relevant Engineering &
Vendor drawings are listed and submitted as per table
10.1 of this procedure and all these drawings are of
latest revisions. (Status as a minimum shall be AFC).
2 Check and ensure I confirm that the location,
elevation Orientation and that the equipment is
correct aligned.
Method Statement for HVAC WORKS
REMARKS:
TPI
QP
REMARKS:
TPI
QP
Method Statement for HVAC WORKS
REMARKS:
Subcontractor/Vendor
TASK LOCATION NOT NOT
Accepted by
REMARKS:
Subsystem
TPI
ITEM CHECKLIST
QP
Pretest Condition
1 Check and ensure I confirm
compliance with all relevant
drawings.
2 Check and ensure I confirm that
installation protocol is
available and the equipment is
cleared for Pre-Commissioning.
Visual Inspection-
Observation- Adjustment
1 Nameplate details are complete
and correct.
2 Check and ensure I confirm that
installation protocol is available
and the equipment is cleared for
Pre-Commissioning.
3 Check and ensure I confirm that
the equipment is as per the
project specifications the
construction drawings.
4 Check and ensure I confirm
the location, elevation,
orientation and that the
equipment is correctly aligned .
Method Statement for HVAC WORKS
REMARKS:
Subcontractor/Vendor
Accepted by
TPI
QP
REMARKS:
TPI
QP
TASK LOCATION
ESTIMATED TIME(MH) : OK NOT NOT REMARKS
Subsystem OK APPLICABLE
ITEM CHECKLIST
Pretest Condition
1 Check and ensure I confirm
compliance with all relevant
Drawings.
2 Check and ensure I confirm that
installation
protocol is available and
the equipment is cleared
for
Pre-Commissioning
Visual .
Inspection-Observation-
Adjustment
1 Nameplate details are
complete and correct.
2 Check and ensure I confirm
that
3 the
Check,Tagthat
No" the
is correct.
equipment is
as per the vendors' drawings
and project specifications.
4 Check and ensure I confirm the
location, elevation, orientation
and that the equipment is
correctly aligned.
5 Check and ensure I confirm for
any apparent signs of
shipping I rigging damage.
(If applicable record details).
Method Statement for HVAC WORKS
REMARKS:
TPI
QP
Method Statement for HVAC WORKS
11.1 Summary
The purpose of the Commissioning procedure is to ensure that the specific HVAC
systems of EPIC FOR RLC POTABLE WATER STORAGE TANKS AND
PUMPS are properly installed and Operational according to the approved project
specifications, Construction drawings, Cause and effect and Operational Philosophy. All
required action for the punch list items generated in the previous stages shall have been
completed prior to proceeding to the next stage of commissioning. List of updated and
consolidated punch list shall be submitted.
Further this procedure ensures to confirm and comply with QP standards
11.3 Description
• Scaffolding.
• Self-supporting ladders.
• Temporary barriers I Warning Sign Boards, Etc.
11.6 Pre-requisites
11.6.1 General:
• Gather and ensure that the relevant information and document ation required for
Commissioning is at the latest version.
• AFC Copies are available.
• Portable Fire Extinguishers are in place
• Power Supply is available
• Barriers have been erected
• Personnel attending the commissioning are wearing the appropriate PPE
Method Statement for HVAC WORKS
• HVAC Pre-Commissioning checks and Punch lists (if any) completed (in
conjunction with QA/QC).
• Electrical Pre-Commissioning checks and Punch list (if any) are completed
• Instrumentation Pre-commissioning checks and Punch list (if any) are
completed.
• Mechanical Commissioning checks and Punch list (if any) are completed.
• PSSA of Dedicated subsystem issued (All punch list ,A" Cleared)
• RFC of Dedicated Subsystem already signed (No Punch list ,A" remaining)
11.6.5 Consumables:
11.6.6 Utilities:
• Availability of fire extinguishers suitable for electrical fires.
12. PLANNING
13.1 Verification
Check that all associated Elect I Instrument commissioning check sheets associated
with the HVAC equipment has been completed, witnessed and signed off by all have
parties .
Check all the items on the compiled punch list have been agreed to, witnessed and
signed off by all parties.
All HVAC equipment and Control panel is provided with the Incoming Supply,
Cables are Merged and the properly terminated.
Earthing is completed.
Space around the Control Panel or the PAC units is clean and free from any kind
of temporary electrical arrangements. Power
Supply is Available.
Power supply from LVDB is available.
Check and ensure I confirm the Correctness of the power from the isolator top
unit.
Check and ensure I confirm the equal phase representation in each power wiring conduit.
Check and ensure I confirm the wiring to the starter free size, Voltage and correct
phase rotation.
Check and ensure I confirm if the Direction of the rotation of the supply fan is
adequate.
Disconnect all temporary power cords, replace all fuses, connect motor leads, and make
final electrical inspection.
Power up the HVAC Control Panel.
If any temporary power supply is installed ensure that an emergency push button is
available to stop in case of any emergency.
In case of using temporary power for pre-commissioning I commissioning,
contractor shall provide UPS Systems and ensure the power quality so that the
equipment installed under these project are safeguarded without any premature failures
or any internal damage to the equipment
Ensure all doors and windows have been installed and correctly installed,
providing wind and water tight conditions within, with no obvious open paths
directly to atmosphere.
Ensure all false ceiling and floors, and internal partitions have been correctly
installed.
Ensure the area(s) of concern are clean from dust and debris. Install
barriers and warning signs around the test area.
Personnel access should be limited to minimize interruption during air balancing.
15.1Method
Method Statement for HVAC WORKS
Before commencing any work on site confirm that a valid, Permit to Work" (Hot I Cold
Work permit as applicable) is available for the task to be undertaken and that all pre-job
safety talks (Toolbox) have been completed.
Ensure that, Warning" notices have been posted.
Check and ensure I confirm the, OPEN/CLOSED “position by energizing the power if
control panel is available, if not it will be simulated.
Check and ensure I confirm the free movement of blades I control linkages and extent of
closure of control damper.
Check and ensure I confirm limit switch operation if control panel is available, if not it will
be simulated.
Check and ensure I confirm sequence of operation as per HVAC Cause and Effect
Diagram.
Method Statement for HVAC WORKS
16.1 Protection
Ensure electrical equipments are protected against rain and water ingress, especially
those items located externally and not normally exposed to the ambient condition s.
Ensure no mechanical damage due to other activities on site.
Ensure that all,hot works" that are carried out in the vicinity of any HVAC equipment
, should have the necessary protection in place to ensure that no damage to the
equipment or paint finish.
Ensure that the equipment are protected properly from dust ingress.
Check and ensure I confirm that Equipment provided is in compliance with the
required Protection ratings/ certifications.
Method Statement for HVAC WORKS
REMARKS:
TPI
QP
STARTER
Qty:
Type:
Manufacturer: Made in:
REMARKS:
DATE
REMARKS:
TPI
QP
Instrument used :
Equipment: Condenser Fan Motor-
Motor -
Type:
Manufacturer: Made in:
MfgNo :
Condenser Fan Motor #
Power supply : Condenser Fan Motor #
Measured power supply: RY = YB= RB=
RB=
Rated amps :
Measured Amps:
Condenser Fan Motor # Ll= L2= L3=
Condenser Fan Motor # Ll= L2= L3=
STARTER
Type:
Overload setting:
Overload range:
Coil volt:
Manufacturer: Made in
REMARKS:
TPI
QP
Type:
Manufacturer: Made in:
Mfg No:
Motor - No's
Type:
Manufacturer : Made in:
Mfg No: Condenser Fan Motor #1 :
Power supply:
Measured power supply: RY = YB= RB=
Rated amps:
Measured Amps
Blower Fan Motor #1 Ll= L2= L3=
STARTER
.Type:
Overload setting:
Overload range :
Coil volt:
Manufacturer: Made in:
REMARKS:
TPI
QP
Instrument used:
Equipment:
Manufacturer: Model no :
Volt: Phase: Cycle:
REMARKS:
TPI
QP
Comments
REMARKS:
TPI
QP
SUPPLY AIR:
Room Tag Type Size Design Air Initial Air Final Air Percentage Remarks
Reference No. Flow(LPS) Flow(LPS) Flow(LPS) of Design
TOTAL
Method Statement for HVAC WORKS
RETURN AIR:
Room Tag Type Size Design Air Initial Air Final Air Percentage Remarks
Referenc No. Flow(LPS) Flow(LPS) Flow(LPS) of Design
e
TOTAL
REMARKS:
TPI
QP
SUPPLY(m/s):
1 2 3 4 5 6 7 8 9
A
B
c
Method Statement for HVAC WORKS
D
TOTAL
RETURN AIR(m/s):
A
B
c
D
TOTAL
FRESH AIR (m/s):
A
B
c
D
TOTAL
EXHAUST AIR(m/s):
A
B
c
D
TOTAL
(m/s)
DUCT AREA (Sq.m)
TOTAL AIR QUANTITY
(m/s)
REMARKS:
TPI
by
QP
REMARKS:
TPI
QP
TYPE FANSHAFTDIA NA mm
DRIVE BELT SIZE MOTOR PULLEY NA mm
DIA
Method Statement for HVAC WORKS
VOLTAGE
CURRENT
SPEED
REMARKS:
TPI
QP
• Attached
20. ABBREVATIONS
o ASBRAE- American Society of Heating Refrigeration and Air conditioning Engineers
o VA- Volt- Ampere
o VT -Voltage Transformer
o CT - Current Transformer
Method Statement for HVAC WORKS