PERENCANAAN PEKERJAAN
INSTRUMENTASI TANKI STORAGE
CPO DI PERAK
TABLE OF CONTENT
TABLE OF CONTENT............................................................................................................. 3
1. INTRODUCTION.................................................................................................................. 5
1.1 Project Overview..................................................................................................................5
1.2 Scope................................................................................................................................... 5
2. DEFINITION......................................................................................................................... 5
3. CODE, STANDARD & REFERENCE...................................................................................6
4. PROCESS CONTROL AND SAFETY SYSTEM GENERAL DESIGN..................................7
3.1 System Recovery................................................................................................................. 8
3.2 Maintainability....................................................................................................................... 8
3.3 Modularity and Standardization..............................................................................................8
3.4 Electrical Transients, Electro Magnetical Interferece, and Radio Frequency Interference
9
3.5 System Control Panel........................................................................................................... 9
4. PROCESS CONTROL SYSTEM........................................................................................10
4.1 PCS Functional Requirement.............................................................................................10
4.2 PCS Hardware Requirement..............................................................................................11
4.2.1 Power Supply Module.......................................................................................................11
4.2.2 PCS Controller Unit........................................................................................................... 11
4.2.3 I/O Modules....................................................................................................................... 12
4.3 PCS Software Requirement.................................................................................................13
5. SAFETY SYSTEM.............................................................................................................. 14
5.1 Functional Requirement.....................................................................................................15
5.2 Safety System Hardware Requirement................................................................................17
5.2.1 Power Supply Modules.....................................................................................................18
5.2.2 Processor Modules........................................................................................................... 18
5.2.3 I/O Modules....................................................................................................................... 19
6. SYSTEM INTEGRATION...................................................................................................20
6.1 Communication System......................................................................................................20
JASA KONSULTASI
PERENCANAAN PEKERJAAN
INSTRUMENTASI TANKI STORAGE
CPO DI PERAK
1. INTRODUCTION
1.1 Project Overview
Currently PT. Pelindo III (Persero) is managing development of CPO Storage Tank in
Nilam Tengah Terminal at Tanjung Perak Port, Surabaya.
This project is expected to fulfill goals and objectives, which is to serve CPO supply.
The CPO come from Floating Storage or tanker at Tanjung Perak Port which will be
streamed through CPO pipeline transmission to fulfill the need of Crude Palm Oil at
Nilam Tengah Terminal.
1.2 Scope
This specification defines the Process Control System Specification to be used for
“Jasa Konsultasi Perencanaan Pekerjaan Instrumentasi Tanki Storage CPO di
Perak”.
2. DEFINITION
PROJECT Jasa Konsultasi Perencanaan Pekerjaan Instrumentasi
Tanki Storage CPO di Perak.
COMPANY PT Pelindo III (Persero) as an owner of the PROJECT
CONSULTANT PT Ostrada Indonesia appointed by COMPANY as their
Engineering Consultant.
CONTRACTOR PT Weltes Energi Nusantara
VENDOR/SUPPLIER A company providing specific materials or services
required for the construction of the Facility
JASA KONSULTASI
PERENCANAAN PEKERJAAN
INSTRUMENTASI TANKI STORAGE
CPO DI PERAK
VENDOR shall provide a complete system and guarantee that, once installed, it shall
be able to perform all functions as described in the specification.
The system shall be provided with all necessary associated modular devices
(processor modules, power supply units, termination modules, cards, terminals,
cabinet wiring, maintenance diagnostic equipment, etc) installed in cabinets and
completely wired, and ready to connect incoming cables.
The hardware, software and auxiliary components of the control systems provided by
VENDOR shall be suitable for industrial environmental use.
Compatibility of software and hardware releases for all equipment shall be ensured
by VENDOR.
Software shall be from the latest release. The effect of failures shall be minimized as
much as possible by using redundancy and "fail safe" design. The process control
and safety system shall allow for on-line expansion without interruption and/or
interference to current plant operation.
Time shall be synchronized throughout the Control Systems including the Safety
Shutdown System.
The proposed equipments, including the operator station shall restart automatically
JASA KONSULTASI
PERENCANAAN PEKERJAAN
INSTRUMENTASI TANKI STORAGE
CPO DI PERAK
after a power supply restoration without the assistance of highly qualified system
maintenance technician.
3.2 Maintainability
System fault diagnostics shall have the capability to identify faults of individual
modules.
Failure and subsequent replacement of any module shall not affect the working of
other components or cause a system failure. System modules shall be provided with
LED'S for normal and fault indication.
The process control and safety system shall be designed and standardized to
minimize the amount of spare parts and the operators and maintenance technicians
training requirements for operator and maintenance personnel.
The hardware, software, and auxiliary components of the process control and safety
system proposed by VENDOR shall be "standard type" from the selected
manufacturer and shall be available as "off the shelf' standard product.
VENDOR shall detail all software used for the system. Special software, if required,
shall be highlighted.
JASA KONSULTASI
PERENCANAAN PEKERJAAN
INSTRUMENTASI TANKI STORAGE
CPO DI PERAK
The process control and safety system shall be supplied with provisions for
protection against system errors and hardware damage resulting from electrical
transients on power or signal wiring. These transients include those generated by
switching large electrical loads, by power line faults, and due to lightning strikes and
lightning induced surged on power or signal cables. The system shall also exhibit a
high degree of immunity to RFI.
Complete system and marshalling cabinet shall be supplied for Process Control and
Safety System. The cabinet typically standard size of 800mm(W) x 800mm(D) x
2100mm(H), with 4 mm thickness, including 100 mm plinth, with front and rear
access. The cabinet shall meet the standard of IP 21, and equipped with ventilation,
fan, and lighting. Lifting eyes shall be provided on the top of the cabinets.
Field side and system side termination and cross wiring between the field side and
system side terminals shall be provided. All equipments, terminals, MCBs, cables,
and wires shall be clearly tagged for ease of identification and maintenance. Cables
and wires shall be routed within cable wire ducts with sufficient spare space within
the ducts for future modification. Grounding bars shall be provided.
The powered terminal for input and powered output loops shall be of the fused type
and the return terminal shall be of the disconnect/knife type, volt free contact outputs
shall have disconnect type terminal,
All cabinets supplied by VENDOR shall be fully equipped, wired and ready to be
installed on site. VENDOR shall take into account the spare capacity/expandability.
The Process Control system shall perform all process control functions indicated on
the applicable project P&ID's and related process control narrative documents. The
process control system shall be designed and manufactured to perform the main
following process operation tasks :
a. Controlling MOV
b. Pumps control Monitoring
c. and control of product flow
d. Monitoring and control of product transaction and transfer
e. Tank Management System
f. Alerting system
g. Data acquisition storage and file management
h. Data trend and historic storage display and reporting
i. Alarm, event, change log and status display and reporting
j. Communication with other systems
k. Automatic diagnostic
The Process Control System (PCS) shall be configured with redundant, parallel
processors. Design of system must be such to maximize reliability of PCS. Failure of
oneprocessor shall result in take-over of the control by the other processor without
processupset or loss of control / data archiving functions.
The process control system shall be able to implement PID control, ratio control, and
cascade control.
During operation, change over from auto to manual output mode or change over from
local to remote set point shall be bump less.
The process control system shall be able to handle a digital inputs and outputs to
operate valves and pumps. This will require the use of pre-configured digital "blocks"
including several inputs and several outputs to implement :
a. Auto/manual processing
b. On/off control, discrepancy alarming
c. Interlocking
d. Duty/stand-by selection and change over
The PCS shall operate with redundant power supply. Each power supply shall be
individually capable of supporting the full power load of all modules. The power
supply modules shall be fitted with status and diagnostic LED'S (as a minimum,
module status, and fault). The power supply module shall be replaceable without
affecting the working of any other modules in the PCS. Power supply modules shall
receive 230 V AC, 50 Hz, from UPS.
Microprocessors shall have non-volatile memory and be able to perform their control
functions without access to the operator interface or communication network.
Operator interface or network failure shall not disturb the process.
Loss of the active CPU shall cause system outputs to freeze at their last position or
to go to predefined fail safe conditions.
JASA KONSULTASI
PERENCANAAN PEKERJAAN
INSTRUMENTASI TANKI STORAGE
CPO DI PERAK
The PCS shall be provided with individual battery back-up to maintain the integrity of
the memory for six (6) months in case of a power failure. Battery low voltage
detection shall be included as part of the diagnostic alarm.
VENDOR shall provide the complete reference and data-sheet of proposed I/O
modules.
The supplied I/O modules shall include 20% installed spares of each type of I/Os for
future modification provision.
a. Analog Input
Analogue input module can use either active or passive circuit. Analogue input
circuit shall be powered by 24 VDC from the PCS through galvanic isolator.
Circuit type for field inputs shall be 4-20 mA DC 2 wires.
b. Analogue Output
The Analogue output shall be 4-20 mA DC 2 wires. The field converters shall be
powered with 24 VDC directly from the PCS through galvanic isolator.
c. Digital input
All input shall be powered by system 24 VDC and shall have optical isolation.
Normal status of digital inputs shall be either normally open or close. Digital
input modules shall be configurable and shall include facilities to ensure that any
JASA KONSULTASI
PERENCANAAN PEKERJAAN
INSTRUMENTASI TANKI STORAGE
CPO DI PERAK
"chatter" or "bounce" occurring during contact closure does not initiate spurious
alarm.
d. Digital Output
24 V DC powered outputs
Volt free output rated 2A @ 24 VDC powered by other system.
All the software and hardware engineering tools necessary to build and maintain the
configuration of operator control stations, PCS controller units, and computer
interfaces shall be provided by VENDOR. VENDOR shall clearly identify and
describe these tools, at bid stage and provide them in sufficient quantity for normal
operation. These engineering tools shall be available in an Engineering Workstation
installed in control room.
Ladder Logic,
Timer Functions,
Arithmetic Functions,
Counter Functions,
Logic Instructions,
Comparison Instructions,
PID Instructions,
Computing Instructions,
Functional Block,
Block Transfer Instructions,
Sequencer Instructions,
Diagnostic Instructions,
File Management, and
File Arithmetic and Logic
Vendor of DCS or PLC and ESD shall provide the flow chart for every step in the
whole system will be executed by controller, supervision, and data acquisition from
start system until shutdown system in according with their system
5. SAFETY SYSTEM
Process control system shall be integrated with Safety Instrumented System (SIS) to
measure risk and prevent accident due to fault system on process condition.
Safety Integrity Level is a way to indicate the tolerable failure rate of a particular
safety function (Based on IEC 61508). Standards require the assignment of atarget
SIL for any new or retrofitted SIF within the SIS. The assignment of the target SIL is
adecision requiring the extension of the Hazards Analysis. The SIL assignment is
based on the amount of risk reduction that is necessary to maintain the risk at
JASA KONSULTASI
PERENCANAAN PEKERJAAN
INSTRUMENTASI TANKI STORAGE
CPO DI PERAK
Vendor shall be provides architecture of SIS that certified withsafety level SIL 3. The
Vendor shall state any restrictions and/or exceptions to meeting this integrity level.
Protection of personnel
Protection of environment
Protection of plant and equipment
The logic shall act as in accordance with the Cause and Effect matrix to:
The ESD, PSD, and F&G system shall be combined into one common safety system
with segregation on 110 modules level.
JASA KONSULTASI
PERENCANAAN PEKERJAAN
INSTRUMENTASI TANKI STORAGE
CPO DI PERAK
The Safety System shall be designed on a fail safe basis so that its failure shall place
the plant process in safe shutdown conditions. However, some circuits shall be
energized to trip such as extinguishing system or deluge valve opening command.
Such circuits shall be line monitored by the system.
Shutdown Initiation
a. Automatic initiation
b. Manual initiation
Inhibit Function
Activation of start-up inhibits shall be carried out manually by operator via operator
control station display during a start-up sequence. It will only inhibit the shutdown
JASA KONSULTASI
PERENCANAAN PEKERJAAN
INSTRUMENTASI TANKI STORAGE
CPO DI PERAK
action; input status monitoring will remain operable. Each start- up inhibit function
shall be reset automatically either by the sensor signal returning to the normal or
healthy state, after a dedicated step of the equipment start-up sequence or after a
predetermined time delay.
Individual inhibit status indication shall also be provided with alarm at the operator
control station so that inhibited function can not be left engaged.
All inhibit functions shall be protected by password to prevent the unauthorized use
of these facilities.
Flame detectors and related action devices shall be directly controlled and monitored
by the Fire Detection System (FDS), which is integrated within the Safety system.
Refer to Datasheet for Flame detectors for detail of the FDS sensors.
All modules shall be replaceable on line without causing further system damage. Re-
initialization of replacement module shall be automatic.
Primary to back up controller change over shall be fully transparent to the operator
and to the plant operations. Fail-over of any controller unit shall cause an alarm to be
generated on the operator control stations and logged. Loss of both the active and
redundant CPU shall cause system outputs to freeze at their last position or to go to
predefined fail safe conditions. Scan time of the Safety Shutdown System shall not
exceed 250 msec.
modules. The supplied I/O modules shall include 20% installed spares of each type
of 110s for future modification provision.
a. Analog Input
Analogue input module can use either active or passive circuit. Analogue input
circuit shall be powered by 24 VDC supply from the SIS through galvanic
isolator. Circuit type for field inputs shall support 4-20 mA DC 2 wires for
transmitters, 0-20mA DC three (3) wires for F&G detectors, and active/four
wires 4-20 mAdevices, such as open path gas detectors (if applicable).
b. Digital Input
Digital input modules shall be configurable and shall include facilities to ensure
that any "chatter" or "bounce" occurring during contact closure does not initiate
spurious alarm. Normal status of digital inputs shall be either normally open or
close. All input shall be powered by system 24 VDC, and shall have optical
isolation. Line monitored digital input shall be provided for non fail safe signals.
c. Analog Output
The Analogue output shall be 4-20 mA DC 2 wires. The field converters shall
be powered with 24 VDC directly from the SCS through galvanic isolator.
d. Digital Output
JASA KONSULTASI
PERENCANAAN PEKERJAAN
INSTRUMENTASI TANKI STORAGE
CPO DI PERAK
24 V DC powered outputs
24 VDC Line Monitored outputs
Volt free output rated 2A@24 VDC powered by other system.
Line monitored digital output shall be provided for non failsafe signals.
6. SYSTEM INTEGRATION
The PCS VENDOR shall be responsible for integration of the Terminal Automation
System (TAS). The PCS VENDOR together with CONTRACTOR and respective
subsystem Vendor shall make sure the compatibility of the subsystem with the PCS.
Preliminary communication test might be conducted when necessary.
The communication system shall provide high speed, reliable, secure and error-free
communications between all devices resident on the network.
VENDOR shall provide the calculated load on the data communication network,
which shall be less than 65 %, including load generated by devices of future network
expansion.
JASA KONSULTASI
PERENCANAAN PEKERJAAN
INSTRUMENTASI TANKI STORAGE
CPO DI PERAK
The main communication network shall consist of redundant Ethernet network. The
redundant Ethernet network shall connect the process control system and safety
system to the operator control stations and servers. This redundant network
capability shall be a standard feature of the control systems.
Servers and Operator stations connected to the network shall be utilized with dual
NIC. Redundant network switches shall also be supplied.
internal operations, and inform operations personnel of the status of the diagnostics.
The main target is to reduce the downtime by clearly locating the faults, which in
turn, permits quickly replacing the defective module. Any failures, faults predicted
failure conditions shall be annunciated to the operator. Examples of faults include:
Processor fault
Communication Link Faults
Module Faults
Input/Output Signal Faults
Internal Memory Failures, etc.
Cabinet Common Alarm
Power Supply Faults.
Over temperature monitoring
The faulty units shall be highlight edon LED’s located on each module and the fault
logged via the Sequence of Event lists through the communication link to the PLC.
Additional diagnostics of the input/output circuits by line monitoring shall also be
signaled by different colour LEDs. The alarms shall only be cleared after the faults
have been rectified. Transient (line monitoring, power supply, diagnosis, redundant
module, etc.) faults shall also be recorded and logged. Once the number of transient
faults has exceeded preset limit, the device shall be marked as faulty (if applicable).
In the event of failure of a redundant component, the faulty unit shall be marked as
‘failed’ and annunciated on the operator workstations. In the event that there is no
built-in redundancy, the fault shall be alarmed.
The system diagnostics shall support fault is location to a specific module or channel
or sub-system device, which can be subsequently removed and replaced.
The system diagnostics shall include both hardware and software diagnostics
routines which upon detecting an abnormal conditions, reports this information on
standard diagnostics displays and printers.
JASA KONSULTASI
PERENCANAAN PEKERJAAN
INSTRUMENTASI TANKI STORAGE
CPO DI PERAK
Once a diagnostic test has detected a failure, a descriptive alarm shall be generated
and bumpless transfer to control to a redundant component shall be triggered
wherever specified.
Serial interface shall be as much as possible utilized for monitoring purpose only.
Command through serial interface might be permitted for non-critical command only.
Local manual back-up shall be available for commands sent through serial interface.
Loss of serial communication shall not disturb normal operation of the plant.
Some subsystem might require redundant serial communication system. The PCS
shall have a standard feature to handle this redundant serial communication. Critical
command from or to packaged control system to safety system shall be through
hardwired interface.
The Operator Control Station shall be the primary operating center of the Terminal
Automation System (TAS). The OCS shall consolidate all information, provide status
and process control / safety system information, and information from serial interface
hub system (such as Automatic Tank Gauging, metering system, and batch
controller), sort and display data in a standardized format and enable operators to
execute control actions.
1 unit of Supervisory Station (Engineering Work Station) with 21” LED Display.
JASA KONSULTASI
PERENCANAAN PEKERJAAN
INSTRUMENTASI TANKI STORAGE
CPO DI PERAK
Additional engineering station/laptop shall be supplied when necessary for the safety
system. Each server and stations shall be completed with 19" TFT color display,
keyboards, and pointing device/mouse. Necessary back-up/storage facility such as
DVD R/W drive shall be provided in the engineering stations and servers. The
system shall be able to do the following main function :
Various access level shall be provided on the operator control station such as view
only, operator access, supervisor access, engineering access, and system
administrator access.
JASA KONSULTASI
PERENCANAAN PEKERJAAN
INSTRUMENTASI TANKI STORAGE
CPO DI PERAK
Operator graphics shall be provided to display data in a user friendly and structured
format The display principles (windowing, special displays, etc.) shall be fully
described by VENDOR. These displays shall enable the operator to select and view
process variables, alarms, trends, status and graphic information. Displays
assignment for Operator Control Stations shall be defined and agreed during system
development by COMPANY and CONTRACTOR.
The control system shall be able to generate periodically or on demand shift reports,
transaction reports and maintenance reports. These reports shall be made from
current and archived data on a separate PC through MICROSOFT EXCEL files. The
required reports shall be easily formatted and configured using standard software
packages and shall not require any additional specialized programming.
The workstation shall have interface capabilities to a printer or plotter via an RS 232
C or parallel port. The workstation shall have the capability for documenting software
programs, configuration, data bases, etc.
The workstation shall include, but shall not be limited to, the following minimum
hardware and software requirements:
Video-card 16 GB minimum
CD-RW/DVD-RW drive
Real time clock
Minimum 25" LED color monitor
QWERTY keyboard
Mouse and Touch-pad
Serial port
Parallel port
Ethernet port
Power
Voltage Input : Auto-ranging, 90 to 263 Volts @47-63 Hz
Accessories : Surge Arrester
USB ports, minimum
Operating System: Microsoft Windows 7
Anti-virus software
An easy-to-use cursor device like mouse or trackball
Latest anti-virus for Windows operating system
All operating software shall be compatible with the main operator / engineer console
software. It shall be possible to develop control strategies in an offline, separate
control
file and download them to the relevant PCS microprocessor module for
implementation,
Access to this unit should be restricted by key lock for use by authorized personnel
only.
All process data parameter shall save in operator work station by SQL server
historian software. The SQL server historian shall provide data for reporting
software at work station and engineering Station.
Dynamic graphics displays (interface shall support ON/OFF status and digitally
coded analogue values)
Continuous updating of data (data transfer from PLC to display shall not exceed
1 second)
Alarm management (display and acknowledgement) for system application
software's being able to identify different alarm levels (eight levels as minimum),
The system shall handle all the process and system alarms. The system alarms
shall covers hardware and software alarms of all connected sub-system. There
shall be no effect on control function even during large number of incoming
alarms.
Screen builder to generate graphic screens (process symbol, bar and line graph,
and associated attributes (colour, discrepancy)
Display of SER (Sequence Event Recorder) data, control loops, first fault,
Data logging and trend data functions,
Time clock and calendar,
Self-diagnostics feature,
Note: Password access shall be provided for different using levels (configurations,
programming, operation and maintenance.
The HMI shall be provided with memory (screens, program) and its complete
software package (operating system, anti-virus, etc.) and all necessary cables.
The associated communication link with PLC system shall be carefully designed.
The protocol used between PLC and Operator Interface Console shall be
Ethernet/Modbus or dedicated interface operating network. CONTRACTOR shall
indicate his capability for such protocol.
Dialogue between PLC and HMI should restart automatically after a power supply
restoration.The HMI shall provide specific display for each location.
7.3 Server
Minimum specification for Server shall be follow or better :
8. ALARM MANAGEMENT
The system shall sequence the alarm according to ISA standard code S18.1
"Annunciator sequences and Specifications".
Alarm shall be detected by the system and processed to notify the operator through
operator station display and audible tone.
An alarm summary display shall be provided to show the operator a listing of alarms
status. Alarm shall be time stamped and shall appear in chronological order. Alarm
summary shall indicate the tag number and the description of each abnormal
condition in addition to "acknowledged / or not" status field.
An alarm log shall be stored and shall record the alarms in a chronological order. The
first-idfirst-out log sequence may be used for off line failure analysis. The Control
System shall be capable of storing at least a minimum of 1000 active alarms.
Employer, at its option and with prior notification, shall be permitted free access to
Vendor's facilities during all phases of the work for performing visual inspections and
for routine monitoring and checking of documentation and work progress.
JASA KONSULTASI
PERENCANAAN PEKERJAAN
INSTRUMENTASI TANKI STORAGE
CPO DI PERAK
Equipment tests, including heat soak test, shall be carried out as specified on the
Inspection and Testing Requirement Sheets, which will be attached to the PCS and
SCS requisition, and in accordance with the applicable sections of the referenced
specification and standards. Criteria for acceptance of tests shall be as established in
the attached or referenced specifications and standards.
Following the System Readiness Review, the system shall be prepared for the heat
soak test, and the Factory Acceptance Test (FAT) at the Vendor's (System
Integrator) staging facility.
The Vendor shall perform a heat soak test for the PCS/SCS System. The Vendor
shall raise the temperature surrounding each system to 120 °F (105 °F for work
station) at 80% humidity and maintain the temperature for 72 hours.
During the heat soak, the Vendor shall utilize the keyboard to call up displays, status
tables, summary tables, etc., on a regular basis. Selected input/outputs shall be
simulated and recorded by the Vendor.
A proposed test procedure shall be submitted by Vendor for approval one (1) month
prior to the Factory Acceptance Test (FAT). Vendor shall prepare a detailed Factory
Acceptance Test procedure for approval by CLIENT. This document shall include
Vendor's and sub-system vendor's key personnel to be involved in the Factory
Acceptance Test and the testing responsibilities assigned to each party. Upon
approval by CLIENT or an authorized representative, this document shall establish
the basis for conducting the Factory Acceptance Test and shall include, but not be
JASA KONSULTASI
PERENCANAAN PEKERJAAN
INSTRUMENTASI TANKI STORAGE
CPO DI PERAK
limited to, the tests described in this section. The FAT procedure list shall have one
column for Vendor's pre-FAT responsible staff signature. The pre-FAT must be
completed before notification to Employer for FAT witness.
The purpose of this testing shall be to witness Vendor performance of FAT and verify
the operation of hardware, the validity of programs, operator interface, guaranteed
accuracy and the proper functioning of components as a System, in accordance with
this specification prior to system shipment. Employer or its authorized representative
will take an active role in the Factory Acceptance Test. "Hands On" (with Vendor's
observation and advice) shall be permitted in the Factory Acceptance Test by
Employer or its authorized representatives. Sufficient time shall be allocated to
complete the Factory Acceptance Test, correct the errors detected, and retest the
system without jeopardizing the scheduled shipment dates.
Factory floor space, telephone, fax machine, test equipment, 100% simulation panel
(with lights and switches), man-hours, and any support required for successful
completion of the factory acceptance tests shall be provided by Vendor as part of the
Purchase Order price. The test equipment shall include a "purpose builts" simulation
test panel, one switch per discrete input, one potential meter per analogue input, one
LED per discrete output, and one millimeter output wired to the marshalling panel
and terminal panels for use during the pre-FAT and FAT test.
A pre-FAT test must be conducted by Vendor's test crew. The pre-FAT shall be
properly signed, item-by-item, in one column of the FAT procedure list.
Vendor shall keep accurate records of the hardware and software deficiencies,
errors, and action items encountered during each test, which shall be provided to
Employer or its authorized representatives. These deficiencies / errors / action items
shall be reviewed with Employer or its authorized representatives at the end of each
day to discuss the proposed procedures and schedule for correcting these items.
Employer or authorized representative may require the suspension of the FAT until
any such discrepancy has been corrected. After the discrepancy has been corrected,
JASA KONSULTASI
PERENCANAAN PEKERJAAN
INSTRUMENTASI TANKI STORAGE
CPO DI PERAK
Vendor shall repeat the procedure or perform any other testing required to verify
correct operation of the system and that the discrepancy has been corrected.
10. DOCUMENTATION
Minimum documentation must include for all hardware, some major software and
user manual should be provided for final approval by the Contractor/Employer less
than 30 (thirty) days prior to the FAT.
Vendor should be provided a manual for the PLC system that includes all the
essential documentation for the installation, operation, facilities for maintenance and
functions of the system. This manual also should include the following aspects:
1. Description of the philosophy of all the hardware and software with configuration
of the system and drawing. It should be include all the main philosophies such as
redundancy, grouping system, bypass philosophy, configuration base, security
levels, etc. It also should include detail description of the specific strategies
complex systems which used.
2. General instructions and procedures start-up for the system which supply.
Theory of operation.
All major schematic.
Maintenance instructions for troubleshooting, routine adjustment, preventive
maintenance procedures, assembly and disassembly instructions, testing
procedures online and offline, and all the information needed for the
JASA KONSULTASI
PERENCANAAN PEKERJAAN
INSTRUMENTASI TANKI STORAGE
CPO DI PERAK
CD–ROM Program
Listing Program
Vendor shall prepare all “as built” drawings Vendor after SAT.
Two sets of CD-ROMs and software must be provided for the final drawing.
11. TRAINING
11.1 Scope
Contractor should be ensure that the Vendor provides for the training of Employer
personnel in all aspects of control systems including theory of operation, system
architectural, implementation of system configuration, maintenance and daily
operation of equipment. Three different levels of training classes must be done to
meet the levels of operations personnel and engineering.
JASA KONSULTASI
PERENCANAAN PEKERJAAN
INSTRUMENTASI TANKI STORAGE
CPO DI PERAK
Vendor shall be responsible for providing all equipment, computer station and
equipment used in a professional learning environment.
11.2 OperatorTraining
Operator training classes to be held at the site, at the time of plant commissioning
activities will be carried out, to familiarize personnel with all aspects of the
operational plant control system.
Training should be done a minimum of three (3) days for field personnel.
Technician training class must be implemented at the site, at the time of plant
commissioning activities will be carried out, to train technician personnel in all
aspects of the theory, operation and configuration of the system and logic
implementation. Performed at a high environmental engineering from the course at
least 50 % of the time this course configuration work to be done by the instructor,
demonstrations, tutorials and troubleshooting. This course must be run for at least
five (5) days.
Engineer and supervisor training class should be implemented in the Vendor place to
provide an overview of all aspects of the theory, operation and configuration of the
system and logic implementation. Time course of configuration work to be done by
the instructor demonstrations tutorials and troubleshooting. This course must be run
for at least five (5) days.
PCS and SCS shall be cleaned and inspected prior to packing for shipment in order
to remove accumulated water, dust and manufacturing debris. The system shall be
JASA KONSULTASI
PERENCANAAN PEKERJAAN
INSTRUMENTASI TANKI STORAGE
CPO DI PERAK
packed in moisture proof containers and shall be able to withstand storage conditions
of a temperature range of 0 to 140°F and a relative humidity of 5 to 95% non-
condensing for up to five (5) years.
PCS and SCS shall not be released for shipment until all test data is approved by
Employer.
PCS and SCS equipment shall be packed in accordance with the best industrial
practice for electronic equipment to avoid damage due to rough handling. The
following are the basic requirements, but are not limited to:
a. Vendor shall identify desiccants and inhibitors used and the required
replacement frequency.
c. Keys, disks, cartridges, special tools shall be individually packaged and clearly
identified on the outside of the package.
f. The outermost covering shall be clearly marked with the complete Vendor
identification and shall include the weight. Employer's or an authorized
representative's equipment numbers shall also be marked.
g. Written instructions covering the location and stacking limits of the crates or
boxes on the transport vehicle shall be specified. These shall be marked on the
container.
h. Cabinet shall be self-supporting. The centre of gravity and lifting points for large
and heavy equipment shall also be identified.
JASA KONSULTASI
PERENCANAAN PEKERJAAN
INSTRUMENTASI TANKI STORAGE
CPO DI PERAK
A packing list shall be placed both on the inside and outside of each individual
package or container. Packing lists itemizing contents of each box crate shall be
placed inside each shipping unit. A second copy, together with any special
instructions, must be sealed in a waterproof envelope and securely fastened to the
outside of each shipping unit. Packing lists shall state purchase order number, item
number and full description of contents.
Vendor shall be responsible for load out, tie down and securing for shipment of the
completed assemblies on Vendor-furnished transport. Vendor shall be responsible
for supplying any required equipment or frames and required rigging for the load-out
at Vendor's facility.
13.1 General
Vendor shall submit project Quality Plans to the Employer after award of purchase
order. This Quality Plan shall incorporate specific quality requirements of the
Employer. Along with this document, Vendor shall also submit an established and
JASA KONSULTASI
PERENCANAAN PEKERJAAN
INSTRUMENTASI TANKI STORAGE
CPO DI PERAK
Vendor shall maintain they Quality Assurance system throughout the Purchase Order
period.
The full extent of these requirements shall be applied to the sub-Vendor's who get
subcontracts the whole or main parts of the work or materials. Surveillance/audit of
Vendor shall be performed by the Vendor as necessary.
Control of sub-Vendor shall encompass measures to verify that progress and quality
of works meet all the requirements.
a. General
Employer may conduct quality audits, technical reviews, test witnesses and
inspections at source in order to verify compliance with the Purchase Order
requirement.
Vendor shall provide free access to the Employer or its delegated inspector and
cooperate with the Employer or its delegated inspector in the performance of all
testing, witnessing and audits.
b. Audits/Reviews
The Employer reserves the right to audit at source at any time during the duration
of the Purchase Order and will give two (2) week’s notice. Vendor shall undertake
to close out any findings raised as part of such an audit.
Vendor shall co-operate in the provision of information and the supply of all
necessary Vendor/sub-Vendor's personnel to allow the Employer or delegated
inspector to perform a meaning audit/review.
JASA KONSULTASI
PERENCANAAN PEKERJAAN
INSTRUMENTASI TANKI STORAGE
CPO DI PERAK
14. WARRANTY/GUARANTEE
The Vendor shall design the equipment for twenty (20) years design life cycle and
warrant the availability of spares and service for all parts for a minimum of two (2)
years.
Vendor shall repair or replace all defective items during the guarantee period at no
cost to Employer.