Sharon Lowe, vice president for marketing for the Electronic Toys Company, is about to begin a
project to design an advertising campaign for a new line of toys. She wants the project
completed within 57 weeks in time to launch the advertising campaign at the beginning of the
Christmas season.
Sharon has identified the six activities (labeled A, B, . . . , F) needed to execute this project.
Considering the order in which these activities need to occur, she also has constructed the
following project network table.
Immediate Mean
Activity Predesessors Duration
A --
B --
C A
D B
E C
F E
Using the PERT three-estimate approach, Sharon has obtained the following estimates of the
duration of each activity.
Now, Sharon Lowe is concerned that there is a significant chance that the vitally important
deadline of 57 weeks will not be met. Therefore, to make it virtually certain that the deadline will
be met, she has decided to crash the project, using the CPM method of time-cost tradeoffs to
determine how to do this in the most economical way.
Sharon now has gathered the data needed to apply this method, as given below.
The mean critical path gives an estimate that the project will finish in 51 weeks. However, Sharon
knows from the earlier analysis that some of the pessimistic estimates are far larger than the
means, so the project duration might be considerably longer than 51 weeks. Therefore, to better
ensure that the project will finish within 57 weeks, she has decided to require that the estimated
project duration based on means (as used throughout the CPM analysis) must not exceed
47 weeks.
g) Consider both paths through the project network. Use marginal cost analysis to determine the
most economical way of reducing the length of paths to 47 weeks.
h) Repeat part (b) by using MSC/Project or POM QM for Windows to show a Gantt Chart and
Predecessors Diagram when considering Calendar weeks and Working weeks.