Project Owner : Azure Power Forty Private Ltd

EPC : Sure Energy Private Limited

PROJECT : 15 MW Solar PV Power Plant Project , Assam, Region 3

DOCUMENT DETAILS:

Drawing/Document Title AZR3_MDL_64 - AC HT CABLE SCHEDULE

Revision No REV 01
AC HT CABLE SCHEDULE

AC
Cable
Cable Total cable Full Load AC Resistance Reactance Total AC
Rating Power Factor Size Total No. Total Cable Rated Cable Voltage drop % Voltage Power Loss
Sr No. Source Destination Length length with 5% Currrent of cable at 90 ° of cable at Resistance %Power Loss
(kW) ( Cos Ф) sin Ф selected( of runs length (Mtr) Volatge(Volts) Derate (V) drop (W)
(Mtr) extra (Mtr) (Amps) C (ohm/km) 50 Hz ( Ohm)
Sq mm )
(mho/km)

1 ICR 01 IDT ICOG ( ICR 01 ) 7500 1 0 300 25 1 25 26.25 33000 131.2 0.13 0.111 0.960 0.003 0.74 0.002% 174.87 0.002%
2 ICR 02 IDT HT PANEL ( ICR 02 ) 7500 1 0 300 25 1 25 26.25 33000 131.2 0.13 0.111 0.960 0.003 0.74 0.002% 174.87 0.002%
3 ICOG ( ICR 01 ) HT PANEL ( ICR 02 ) 7500 1 0 300 250 1 250 262.5 33000 131.2 0.13 0.111 0.960 0.034 7.39 0.022% 1748.67 0.023%
4 HT PANEL ( ICR 02 ) Metering Yard 15000 1 0 300 290 1 290 304.5 33000 262.4 0.13 0.111 0.960 0.039 17.14 0.052% 8113.81 0.054%

Total AC Power cable length of 3C x 300 Sq.mm, 33 kV(E) 619.5 Meter


FRLS XLPE Arm AL Cable

Note : Lenghts Given in schedule are indicative only. Actual Cable length shall be as per site conditions.

LE NGTH CONSIDER IN THE CALCULATION SHALL BE FOR CALACULAATION PURPOSE ONLY.


VENDOR SHALL ENSURE THE COMPLETE CABLE LENGTH AS PER SITE REQUIEMENT.
CABLE SHALL BE LAID SINGLE CABLE IN UNDERGORUND DIRECT BURRIED TRENCHES AS PER CIVIL DRAWING.