IFI SUMMARY SHEET

JUPC EO/EG III PROJECT REMARKS

RFI DATE (Schedule Date /Time) Inspection Point


WORK
SL.NO RFI NO CATEGORY TYPE OF INSPECTION Drawing No
Issue DATE INSPECTION DATE/TIME Subcont. Contractor Company

Cross Hole Ultrasonic test for Test Pile TP1, TP-2 &
1 RFI-CL-BWL-0008 28-Jun-18 30-Jun-18 4:00 PM Pile Test I H H 60-CD-1006-01, REV 0
TP-3
REQUEST FOR INSPECTION

United EO/EG III Project (SC 6122)

RFI No. 60-CON-TCC-RFI-P-AG-0001 Issue Date 19/12/2018

Discipline PIPING Subcontractor TCC

ITP No. 60-CON-TCC-ITP-P-0001 REV.B DWG No.


Originator (TCC) QC Name: Confirm (SSA) QC Name -
Inspection Date 20/12/2018
Aale Ahmad
Point of Inspection
Serial No. Time Area / Place ITP Code Inspection Activity Item Description
Subcon. Contractor Company

Physical Examination
TCC/WORK Marking and Cutting
1 13:00 2.1 and / Performance I S S
SHOP 2 of Pipes
Evidence Review

Material Verification..
Dimensions. Long Seam
TCC/WORK Edge Preparation & Fit Staggering, Root
2 14:30 2.2 I W1 S
SHOP 2 Up Inspection Gap,Root Face,Land
Zone Incl. Angle.Socket
Weld GasBack Purge

Visual Inspection of Surface defects, weld


TCC/WORK
3 15:00 2.5 Completed Spool profile. Identification of I W1 S
SHOP 2
Welds weld and welders .

Comments:

Acknowledgement (see comments, if any) Results

Description Subcontractor Contractor Company Approved

Name
Approved with
Comments
Signature

Date Not Approved

Samsung Engineering Co., Ltd