Roof deck Vertical Sec. 1 (External) 0.85(20)a(300)=845.

25(275)
Span A @ Support a=45.58mm
a=ßc
fc’=20MPa 44.51=0.85c
fy =275Mpa c=53.62mm
25mmØ
Mu=86.76kN/m3 Єt = 0.003
d-c c
Depth=base-steel covering-stirrupsØ-radius of =0.003(437.5-53.62)
steelbar 53.62
=500-40-10-12.5 Єt=0.02148•TC
Depth=437.5mm
Єt=fs/Es
Mu=ɸbd2ρfy(1-ρfy/1.7fc’) fs=0.02148(200,000)
Assume Tension Controlled fs=4295.56MPa
fs>fy •Steel Yields
86.76x106=0.9(300)(437.5)2ρ(275)[1-275ρ/1.7(20)]
ρ =0.00644 Spacing=b-2(cover)-Øbars(N)-stirrups(2)
N-1
ρmax = 0.85fc’ß1(3) =300-2(40)-25(2)-10(2)
Fy(7) 2-1
Spacing=150mm
20MPa<28MPa
ß=0.85

ρmax =0.85(20)(0.85)(3)
275(7)
ρmax =0.02252

ρmax>ρ •SRB
ρmin =√fc’ =√20
4fy 4(275)
ρmin =0.00407
ρmin =1.4 = 1.4
fy 275
ρmin =0.00509

ρ>ρmin •Use ρ

As= ρbd
=(0.00644)(300)(437.5)
As=845.25mm2

No. Of Bars=As/(π/4)Ø2
= 845.25
π/4 (25)2
N=1.68≈ 2 bars
Roof deck Vertical Sec. 1 (External)
Span A @ Midspan

fc’=20MPa
C1=T1 fy =275Mpa
25mmØ Єt = 0.003
Mu=44.34kN/m3 d-c c
=0.003(437.5-42.38)
Depth=base-steel covering-stirrupsØ-radius of 42.38
steelbar Єt=0.02797 •TC
=500-40-10-12.5
Depth=437.5mm Єt=fs/Es
fs=0.02797(200,000)
Mu=ɸbd2ρfy(1-ρfy/1.7fc’) fs=5593.96MPa
Assume Tension Controlled fs>fy •Steel Yields

44.34x106=0.9(300)(437.5)2ρ(275)[1-275ρ/1.7(20)] Spacing=b-2(cover)-Øbars(N)-stirrups(2)
ρ =0.0032 N-1
=300-2(40)-25(2)-10(2)
ρmax = 0.85fc’ß1(3) 2-1
Fy(7) Spacing=150mm

20MPa<28MPa
ß=0.85

ρmax =0.85(20)(0.85)(3)
275(7)
ρmax =0.02252

ρmax>ρ •SRB
ρmin =√fc’ =√20
4fy 4(275)
ρmin =0.00407
ρmin =1.4 = 1.4
fy 275
ρmin =0.00509

ρ<ρmin •Use ρmin

As= ρmin bd
=(0.00509)(300)(437.5)
As=668.063mm2

No. Of Bars=As/(π/4)Ø2
= 668.063
π/4 (25)2
N=1.36≈ 2 bars
Roof deck Vertical Sec. 1 (External)
Span B @ Support

fc’=20MPa
C1=T1 fy =275Mpa
0.85(20)a(300)=668.063(275) 25mmØ
a=36.02mm Mu=45.67kN/m3
a=ßc
36.02=0.85c Depth=base-steel covering-stirrupsØ-radius of
c=42.38mm steelbar
=500-40-10-12.5
Depth=437.5mm Єt=fs/Es
fs=0.02797(200,000)
Mu=ɸbd2ρfy(1-ρfy/1.7fc’) fs=5593.96MPa
Assume Tension Controlled fs>fy •Steel Yields

45.67x106=0.9(300)(437.5)2ρ(275)[1-275ρ/1.7(20)] Spacing=b-2(cover)-Øbars(N)-stirrups(2)
ρ =0.0033 N-1
=300-2(40)-25(2)-10(2)
ρmax = 0.85fc’ß1(3) 2-1
Fy(7) Spacing=150mm

20MPa<28MPa
ß=0.85

ρmax =0.85(20)(0.85)(3)
275(7)
ρmax =0.02252

ρmax>ρ •SRB
ρmin =√fc’ =√20
4fy 4(275)
ρmin =0.00407
ρmin =1.4 = 1.4
fy 275
ρmin =0.00509

ρ<ρmin •Use ρmin

As= ρmin bd
=(0.00509)(300)(437.5)
As=668.063mm2

No. Of Bars=As/(π/4)Ø2
= 668.063
π/4 (25)2
N=1.36≈ 2 bars Roof deck Vertical Sec. 1 (External)
Span B @ Midspan

fc’=20MPa
fy =275Mpa
C1=T1 25mmØ
0.85(20)a(300)=668.063(275) Mu=11.41kN/m3
a=36.02mm
a=ßc Depth=base-steel covering-stirrupsØ-radius of
36.02=0.85c steelbar
c=42.38mm =500-40-10-12.5
Depth=437.5mm
Єt = 0.003
d-c c Mu=ɸbd2ρfy(1-ρfy/1.7fc’)
=0.003(437.5-42.38) Assume Tension Controlled
42.38
Єt=0.02797 •TC
11.41x106=0.9(300)(437.5)2ρ(275)[1-275ρ/1.7(20)] Spacing=b-2(cover)-Øbars(N)-stirrups(2)
ρ =0.00081 N-1
=300-2(40)-25(2)-10(2)
ρmax = 0.85fc’ß1(3) 2-1
Fy(7) Spacing=150mm

20MPa<28MPa
ß=0.85

ρmax =0.85(20)(0.85)(3)
275(7)
ρmax =0.02252

ρmax>ρ •SRB
ρmin =√fc’ =√20
4fy 4(275)
ρmin =0.00407
ρmin =1.4 = 1.4
fy 275
ρmin =0.00509

ρ<ρmin •Use ρmin

As= ρmin bd
=(0.00509)(300)(437.5)
As=668.063mm2

No. Of Bars=As/(π/4)Ø2
= 668.063
π/4 (25)2 Roof deck Vertical Sec. 1 (External)
N=1.36≈ 2 bars Span C @ Support

fc’=20MPa
fy =275Mpa
25mmØ
C1=T1 Mu=45.67N/m3
0.85(20)a(300)=668.063(275)
a=36.02mm Depth=base-steel covering-stirrupsØ-radius of
a=ßc steelbar
36.02=0.85c =500-40-10-12.5
c=42.38mm Depth=437.5mm

Єt = 0.003 Mu=ɸbd2ρfy(1-ρfy/1.7fc’)
d-c c Assume Tension Controlled
=0.003(437.5-42.38)
42.38 45.67x106=0.9(300)(437.5)2ρ(275)[1-275ρ/1.7(20)]
Єt=0.02797 •TC ρ =0.0033

Єt=fs/Es ρmax = 0.85fc’ß1(3)


fs=0.02797(200,000) Fy(7)
fs=5593.96MPa
fs>fy •Steel Yields 20MPa<28MPa
ß=0.85
=0.003(437.5-42.38)
ρmax =0.85(20)(0.85)(3) 42.38
275(7) Єt=0.02797 •TC
ρmax =0.02252
Єt=fs/Es
ρmax>ρ •SRB fs=0.02797(200,000)
ρmin =√fc’ =√20 fs=5593.96MPa
4fy 4(275) fs>fy •Steel Yields
ρmin =0.00407
ρmin =1.4 = 1.4 Spacing=b-2(cover)-Øbars(N)-stirrups(2)
fy 275 N-1
ρmin =0.00509 =300-2(40)-25(2)-10(2)
2-1
ρ<ρmin •Use ρmin Spacing=150mm

As= ρmin bd
=(0.00509)(300)(437.5)
As=668.063mm2

No. Of Bars=As/(π/4)Ø2
= 668.063 Roof deck Vertical Sec. 1 (External)
π/4 (25)2 Span C @ Midspan
N=1.36≈ 2 bars
fc’=20MPa
fy =275Mpa
25mmØ
Mu=44.34kN/m3
C1=T1
0.85(20)a(300)=668.063(275) Depth=base-steel covering-stirrupsØ-radius of
a=36.02mm steelbar
a=ßc =500-40-10-12.5
36.02=0.85c Depth=437.5mm
c=42.38mm
Mu=ɸbd2ρfy(1-ρfy/1.7fc’)
Єt = 0.003 Assume Tension Controlled
d-c c
44.34x106=0.9(300)(437.5)2ρ(275)[1-275ρ/1.7(20)]
ρ =0.0032

ρmax = 0.85fc’ß1(3)
Fy(7)

20MPa<28MPa
ß=0.85

ρmax =0.85(20)(0.85)(3)
275(7)
ρmax =0.02252

ρmax>ρ •SRB
ρmin =√fc’ =√20
4fy 4(275)
ρmin =0.00407
ρmin =1.4 = 1.4
fy 275
ρmin =0.00509

ρ<ρmin •Use ρmin

As= ρmin bd
=(0.00509)(300)(437.5)
As=668.063mm2

No. Of Bars=As/(π/4)Ø2
= 668.063
π/4 (25)2
N=1.36≈ 2 bars
Roof deck Vertical Sec. 1 (External)
Span C @ End Support

fc’=20MPa
C1=T1 fy =275Mpa
0.85(20)a(300)=668.063(275) 25mmØ
a=36.02mm Mu=86.76kN/m3
a=ßc
36.02=0.85c Depth=base-steel covering-stirrupsØ-radius of
c=42.38mm steelbar
=500-40-10-12.5
Єt = 0.003 Depth=437.5mm
d-c c
=0.003(437.5-42.38) Mu=ɸbd2ρfy(1-ρfy/1.7fc’)
42.38 Assume Tension Controlled
Єt=0.02797 •TC
86.76x106=0.9(300)(437.5)2ρ(275)[1-275ρ/1.7(20)]
Єt=fs/Es ρ =0.00644
fs=0.02797(200,000)
fs=5593.96MPa ρmax = 0.85fc’ß1(3)
fs>fy •Steel Yields Fy(7)

Spacing=b-2(cover)-Øbars(N)-stirrups(2) 20MPa<28MPa
N-1 ß=0.85
=300-2(40)-25(2)-10(2)
2-1 ρmax =0.85(20)(0.85)(3)
Spacing=150mm 275(7)
ρmax =0.02252
ρmax>ρ •SRB fs=0.02148(200,000)
ρmin =√fc’ =√20 fs=4295.56MPa
4fy 4(275) fs>fy •Steel Yields
ρmin =0.00407
ρmin =1.4 = 1.4 Spacing=b-2(cover)-Øbars(N)-stirrups(2)
fy 275 N-1
ρmin =0.00509 =300-2(40)-25(2)-10(2)
2-1
ρ>ρmin •Use ρ Spacing=150mm

As= ρbd
=(0.00644)(300)(437.5)
As=845.25mm2

No. Of Bars=As/(π/4)Ø2
= 845.25
π/4 (25)2
N=1.68≈ 2 bars

C1=T1
0.85(20)a(300)=845.25(275)
a=45.58mm
a=ßc
44.51=0.85c
c=53.62mm

Єt = 0.003
d-c c
=0.003(437.5-53.62)
53.62
Єt=0.02148•TC

Єt=fs/Es