Sunteți pe pagina 1din 7

BIDFORM

DEVELOPER : PHIRST PARK HOMES INC.


LOCATION : BRGY. PALO-ALTO, CALAMBA, LAGUNA
PROJECT : PHIRST PARK HOMES CALAMBA- BASIC LAND DEV'T
SUBJECT : GENERAL REQUIREMENTS
DATE : April 2, 2020
CONTRACTOR : VERZONTAL BUILDERS,INC.

ITEM SCOPE OF WORK UNIT QUANTITY UNIT COST AMOUNT TOTAL COST REMARKS

1.1.0 Mobilization/Demobilization lot 1.00

1.2.0 Temporary Facilities lot 1.00

1.3.0 Materials and Quality Assurance Test lot 1.00

1.4.0 Bonds and Insurance lot 1.00

Sub-total :

NOTE TO BIDDER:

1. Contractor shall provide their own barracks and other temporary facilities.

2. All testing including Field Density Test (FDT), Concrete Compressive Strength Test (ASTM C 39), and other testing required by the Developer, shall already be included in the Bid Cost.

3. Field Density Test (FDT) shall be provided by the contractor before road pavement.

BIDFORM

SUBDIVISION : PHIRST PARK HOMES INC.


LOCATION : BRGY. PALO-ALTO, CALAMBA, LAGUNA
PROJECT : PHIRST PARK HOMES CALAMBA- BASIC LAND DEV'T
SUBJECT : EARTHWORKS & SITE GRADING
DATE : April 2, 2020
CONTRACTOR : VERZONTAL BUILDERS,INC.

UNIT COST AMOUNT


ITEM SCOPE OF WORK UNIT QUANTITY TOTAL COST REMARKS
MATERIALS LABOR EQUIPMENT MATERIAL LABOR & EQUIPMENT

2.1.0 Clearing and Grubbing (-0.30m) sqm

2.2.0 Cut and Road Excavation cu.m

2.3.0 Engineered Fill (Local) cu.m

2.4.0 Engineered Fill (Borrow) cu.m

2.5.0 Disposal of Unsuitable soil cu.m

2.6.0 Disposal of Excess soil cu.m

Sub-total :

NOTE TO BIDDER:

1. Clearing of Project Area shall be deducted by the Showvillage Earthworks Area.

2. The cost of transferring the excavated materials to the local fill areas shall already be included in the Bid Cost.

3. All Bid Cost and Items for payment shall have already included swell and shrinkage factors applicable.

4. Excluded area shall be omitted in Land Development Construction unless otherwise specified.

5. All Bid Cost for the compaction of earthfill materials shall already be included in the Bid Cost.

6. Hauling out and cost of transferring of unsuitable materials shall already be included in the Bid Cost.

7. Mark-up shall already be included in the Bids.

8. Mark-up shall cover for all profits, taxes (including VAT), overheads and all other charges.

9. All incidental works necessary for the completion of the project shall be borne by the contractor.

BIDFORM

SUBDIVISION : PHIRST PARK HOMES INC.


LOCATION : BRGY. PALO-ALTO, CALAMBA, LAGUNA
PROJECT : PHIRST PARK HOMES CALAMBA- BASIC LAND DEV'T
SUBJECT : ROAD PREPARATION
DATE : April 2, 2020
CONTRACTOR : VERZONTAL BUILDERS,INC.

UNIT COST AMOUNT


ITEM SCOPE OF WORK UNIT QUANTITY TOTAL COST REMARKS
MATERIALS LABOR EQUIPMENT MATERIAL LABOR & EQUIPMENT

3.1.0 Road Tracing sqm 17,890.00

3.2.0 Subgrade Preparation sqm 17,890.00

3.3.0 Base Course cu.m 1,789.00

3.4.0 PCC Pavement Preparation sqm 15,199.00

3.5.0 Curb and Gutter Preparation lm 4,810.00

3.6.0 Sidewalk Preparation sqm 2,691.00

3.7.0 Bituminous Joint Sealant cu.m 1.00

Sub-total :

NOTE TO BIDDER:

1. The limits of subgrade preparation shall be the entire R.O.W. with at least 95% Compaction

2. Limits of base course preparation shall be the carriageway which is measured outer to outer of opposite curbs and gutter.

3. Thickness of roadbase course shall be 100 mm for all roads unless otherwise specified at road section details

4. Volume for Ready-Mixed-Concrete should be separated. (See Bidform for Ready Mix Concrete)

5. Mark-up shall already be included in the Bids.

6. Mark-up shall cover for all profits, taxes (including VAT), overheads and all other charges.

7. All incidental works necessary for the completion of the project shall be borne by the contractor.

BIDFORM

SUBDIVISION : PHIRST PARK HOMES INC.


LOCATION : BRGY. PALO-ALTO, CALAMBA, LAGUNA
PROJECT : PHIRST PARK HOMES CALAMBA- BASIC LAND DEV'T
SUBJECT : READY MIX - CONCRETE
DATE : April 2, 2020
CONTRACTOR : VERZONTAL BUILDERS,INC.

UNIT COST AMOUNT


ITEM SCOPE OF WORK UNIT QUANTITY TOTAL COST REMARKS
MATERIALS LABOR EQUIPMENT MATERIAL LABOR & EQUIPMENT

4.1.0 3000 PSI (G-1, 28 days) cu.m 2,280.00

4.2.0 2500 PSI (G-1, 28 days) cu.m 253.00

4.3.0 1600 PSI (G-3/4 28 days) cu.m 270.00

Sub-total :

NOTE TO BIDDER:

1.Thickness of pavement shall be 150 mm for all roads unless otherwise specified at road section details

2. Thickness of sidewalk shall be 100 mm for all roads unless otherwise specified at road section details

3. All concrete works shall be done using Ready-Mixed-Concrete unless otherwise instructed by Project Site Engineer.

4. Mark-up shall already be included in the Bids.

5. Mark-up shall cover for all profits, taxes (including VAT), overheads and all other charges.

6. All incidental works necessary for the completion of the project shall be borne by the contractor.
BIDFORM

SUBDIVISION : PHIRST PARK HOMES INC.


LOCATION : BRGY. PALO-ALTO, CALAMBA, LAGUNA
PROJECT : PHIRST PARK HOMES CALAMBA- BASIC LAND DEV'T
SUBJECT : STORM DRAINAGE SYSTEM
DATE : April 2, 2020
CONTRACTOR : VERZONTAL BUILDERS,INC.

UNIT COST AMOUNT


ITEM SCOPE OF WORK UNIT QUANTITY TOTAL COST REMARKS
MATERIALS LABOR EQUIPMENT MATERIAL LABOR & EQUIPMENT

5.1.0 RCP, Ordinary RCP, Including trenching, bedding, backfill, disposal, etc.

5.1.1 RCP 300 mm dia ln.m. 2,780.00

5.1.2 RCP 375 mm dia ln.m. 162.00

5.1.3 RCP 450 mm dia ln.m. 22.00

5.1.4 RCP 600 mm dia ln.m. 198.00

5.1.5 RCP 750 mm dia ln.m. 0.00 included in show village

5.1.6 RCP 900 mm dia ln.m. 0.00 NOT ON PLAN

5.1.7 RCP 1050 mm dia ln.m. 0.00 NOT ON PLAN

5.1.8 RCP 1200 mm dia ln.m. 0.00 NOT ON PLAN

5.1.9 RCP 1500 mm dia ln.m. 0.00 NOT ON PLAN

5.2.0 Curb Inlet Manhole, including earthworks, concreting works, etc.

5.2.1 Curb Inlet manhole , 300mm sets 367.00

5.2.2 Curb Inlet manhole , 375mm sets 15.00

5.2.3 Curb Inlet manhole , 450mm sets 2.00

5.2.4 Curb Inlet manhole , 600mm sets 27.00

5.2.5 Curb Inlet manhole , 750mm sets 0.00 included in show village

5.2.6 Curb Inlet manhole , 900mm sets 0.00 NOT ON PLAN

5.2.7 Curb Inlet manhole , 1050mm sets 0.00 NOT ON PLAN

5.2.8 Curb Inlet manhole , 1200mm sets 0.00 NOT ON PLAN

5.2.9 Curb Inlet manhole , 1500mm sets 0.00 NOT ON PLAN

5.3.0 Outfall, (Conrete Headwall and Scouring Protection)

5.3.1 Outfall , 300mm RCP sets 1.00

5.3.2 Outfall , 375mm RCP sets 0.00 NOT ON PLAN

5.3.3 Outfall , 450mm RCP sets 4.00

5.3.4 Outfall , 600mm RCP sets 0.00 NOT ON PLAN

5.3.5 Outfall , 750mm RCP sets 0.00 included in show village

5.3.6 Outfall , 900mm RCP sets 0.00 NOT ON PLAN

5.3.7 Outfall , 1050mm RCP sets 0.00 NOT ON PLAN

5.3.8 Outfall , 1200mm RCP sets 0.00 NOT ON PLAN

5.3.9 Outfall , 1500mm RCP sets 0.00 OUTFALL #7

Sub-total :

NOTE TO BIDDER:

1. All labor, materials, and tools necessary for the completion of works shall be provided by the Contractor.

2. No additional compensation shall be given on the basis of the nature of the earth encountered during

excavation. It is the responsibility of the contractor to make a general perception of the type of soil he will encounter.

3. Drainage Service Connection for each household is not included on the Bid

4. Manhole Size 900mm and below are CHB, and 1050 above are Reinforce Concrete, as indicated at the plans.

5. Mark-up shall already be included in the Bids.

6. Mark-up shall cover for all profits, taxes (including VAT), overheads and all other charges.

7. Reinforced Concrete Pipeline must be at least 3/4 fully collared and shall not encroach the Planting Strip/sidewalk as indicated at the plans.

It is the responsibility of the contractor to repair or reworks any damage lines due to incompliance as indicated at the plans.

BIDFORM

SUBDIVISION : PHIRST PARK HOMES INC.


LOCATION : BRGY. PALO-ALTO, CALAMBA, LAGUNA
PROJECT : PHIRST PARK HOMES CALAMBA- BASIC LAND DEV'T
SUBJECT : WATER DISTRIBUTION SYSTEM
DATE : April 2, 2020
CONTRACTOR : VERZONTAL BUILDERS,INC.

UNIT COST AMOUNT


ITEM SCOPE OF WORK UNIT QUANTITY TOTAL COST REMARKS
MATERIALS LABOR EQUIPMENT MATERIAL LABOR & EQUIPMENT

6.1.0 PVC Pipe, includes trenching, bedding, backfill, disposal, etc.

6.1.1 200 mm PVC l.m. 45.00

6.1.2 150 mm PVC l.m. 290.00

6.1.3 100 mm PVC l.m. 377.00

6.1.4 75 mm PVC l.m. 300.00

6.1.5 50 mm PVC l.m. 1,500.00

6.2.0 PVC Fittings for Distribution Lines including Trenching and Backfilling

6.2.1 Tee

6.2.1.1 Tee - 50mm sets 15.00

6.2.1.2 Tee - 75mm sets 2.00

6.2.1.3 Tee - 100mm sets 0.00 NOT ON THE PLAN

6.2.1.4 Tee - 150mm sets 1.00

6.2.1.5 Tee - 200mm sets 0.00 NOT ON THE PLAN

6.2.2 Reducer

6.2.2.1 Reducer - 75 x 50 sets 3.00

6.2.2.2 Reducer - 100 x 50 sets 0.00 NOT ON THE PLAN

6.2.2.3 Reducer - 100 x 75 sets 2.00

6.2.2.4 Reducer - 150 x 50 sets 1.00

6.2.2.5 Reducer - 150 x 75 sets 0.00 NOT ON THE PLAN

6.2.2.6 Reducer - 150 x 100 sets 1.00

6.2.2.7 Reducer - 200 x 50 sets 0.00 NOT ON THE PLAN

6.2.2.8 Reducer - 200 x 75 sets 0.00 NOT ON THE PLAN

6.2.2.9 Reducer - 200 x 100 sets 0.00 NOT ON THE PLAN

6.2.2.10 Reducer - 200 x 150 sets 2.00

6.2.3 Reducer Tee

6.2.3.1 Reducer Tee - 75 x 50 sets 3.00

6.2.3.2 Reducer Tee - 100 x 50 sets 1.00

6.2.3.3 Reducer Tee - 100 x 75 sets 4.00

6.2.3.4 Reducer Tee - 150 x 50 sets 2.00

6.2.3.5 Reducer Tee - 150 x 75 sets 1.00

6.2.3.6 Reducer Tee - 150 x 100 sets 1.00

6.2.3.7 Reducer Tee - 200 x 50 sets 0.00 NOT ON THE PLAN


6.2.3.8 Reducer Tee - 200 x 75 sets 0.00 NOT ON THE PLAN

6.2.3.9 Reducer Tee - 200 x 100 sets 1.00

6.2.3.10 Reducer Tee - 200 x 150 sets 0.00 NOT ON THE PLAN

6.2.4 Cross Tee

6.2.4.1 Cross Tee - 50mm sets 1.00

6.2.4.2 Cross Tee - 75mm sets 0.00 NOT ON THE PLAN

6.2.4.3 Cross Tee - 100mm sets 1.00

6.2.4.4 Cross Tee - 150mm sets 0.00 NOT ON THE PLAN

6.2.4.5 Cross Tee - 200mm sets 0.00 NOT ON THE PLAN

6.2.5 Bend - 45 degrees

6.2.5.1 Bend - 50mm sets 10.00

6.2.5.2 Bend - 75mm sets 3.00

6.2.5.3 Bend - 100mm sets 2.00

6.2.5.4 Bend - 150mm sets 5.00

6.2.5.5 Bend - 200mm sets 0.00 NOT ON THE PLAN

6.2.6 Bend - 90 degrees (Elbow)

6.2.6.1 Elbow - 50mm sets 3.00

6.2.6.2 Elbow - 75mm sets 0.00 NOT ON THE PLAN

6.2.6.3 Elbow - 100mm sets 0.00 NOT ON THE PLAN

6.2.6.4 Elbow - 150mm sets 0.00 NOT ON THE PLAN

6.2.6.5 Elbow - 200mm sets 1.00

6.2.7 Gate Valve

6.2.7.1 Gate Valve - 50mm sets 5.00

6.2.7.2 Gate Valve - 75mm sets 3.00

6.2.7.3 Gate Valve - 100mm sets 1.00

6.2.7.4 Gate Valve - 150mm sets 2.00

6.2.7.5 Gate Valve - 200mm sets 2.00

6.2.8 End Cap

6.2.8.1 End Cap - 50mm sets 10.00

6.2.8.2 End Cap - 75mm sets 0.00 NOT ON THE PLAN

6.2.8.3 End Cap - 100mm sets 0.00 NOT ON THE PLAN

6.2.8.4 End Cap - 150mm sets 0.00 NOT ON THE PLAN

6.2.8.5 End Cap - 200mm sets 0.00 NOT ON THE PLAN

Fire Hydrant, Angle Valve Type Hydrants with 100mm dia inlet (include
6.2.9 sets 3.00
valves, barricades etc.

6.3.0 Service Connection, including Riser and End Cap


6.3.1 Dual Service Connection, 32 mm dia. (short)

6.3.1.1 Connection - 200mm PVC sets 0.00 NOT ON THE PLAN

6.3.1.2 Connection - 150mm PVC sets 0.00 NOT ON THE PLAN

6.3.1.3 Connection - 100mm PVC sets 25.00

6.3.1.4 Connection - 75mm PVC sets 21.00

6.3.1.5 Connection - 50mm PVC sets 76.00

6.3.2 Dual Service Connection, 32 mm dia. (long)

6.3.2.1 Connection - 200mm PVC sets 4.00

6.3.2.2 Connection - 150mm PVC sets 27.00

6.3.2.3 Connection - 100mm PVC sets 39.00

6.3.2.4 Connection - 75mm PVC sets 23.00

6.3.2.5 Connection - 50mm PVC sets 102.00

6.3.3 Single Service Connection, 25 mm dia. (short)

6.3.3.1 Connection - 200mm PVC sets 0.00 NOT ON THE PLAN

6.3.3.2 Connection - 150mm PVC sets 0.00 NOT ON THE PLAN

6.3.3.3 Connection - 100mm PVC sets 2.00

6.3.3.4 Connection - 75mm PVC sets 6.00

6.3.3.5 Connection - 50mm PVC sets 30.00

6.3.4 Single Service Connection, 25 mm dia. (long)

6.3.4.1 Connection - 200mm PVC sets 0.00 NOT ON THE PLAN

6.3.4.2 Connection - 150mm PVC sets 4.00

6.3.4.3 Connection - 100mm PVC sets 2.00

6.3.4.4 Connection - 75mm PVC sets 5.00

6.3.4.5 Connection - 50mm PVC sets 34.00

6.4.0 Thrust Blocks & Concrete Encasement sets 450.00

6.5.0 Final Testing lots 1.00

Sub-total :

NOTE TO BIDDER:

1. All labor, materials, and tools necessary for the completion of works shall be provided by the Contractor.

2. No additional compensation shall be given on the basis of the nature of the earth encountered during excavation.

3. PVC (Polyvinyl Chloride ) pipes shall be pressure Class 150, unless otherwise specified

4. All fittings shall be cast iron (C.I. 150)

5. C.I. Valve Box shall be of LWUA standard.

6. C.I. Fire Hydrant assembly shall be MWSS Standard Residential Type for 100 and MWSS Standard Commercial Type for 150.

7. Mark-up shall already be included in the Bids.

8. Mark-up shall cover for all profits, taxes (including VAT), overheads and all other charges.

9. No substitute product shall be used in the work until written approval has been received from the owner.

10. Labor for water distibution system shall include excavation, sand bedding and envelope, backfilling and compaction, installation

of valves and fittings, construction of thrust blocks for fittings, chlorinated flushing and hydroststic testing.
BIDFORM

SUBDIVISION : PHIRST PARK HOMES INC.


LOCATION : BRGY. PALO-ALTO, CALAMBA, LAGUNA
PROJECT : PHIRST PARK HOMES CALAMBA- BASIC LAND DEV'T
SUBJECT : OTHERS
DATE : April 2, 2020
CONTRACTOR : VERZONTAL BUILDERS,INC.

UNIT COST AMOUNT


ITEM SCOPE OF WORK UNIT QUANTITY TOTAL COST REMARKS
MATERIALS LABOR EQUIPMENT MATERIAL LABOR & EQUIPMENT

8.1.0 Special Drainage

8.1.1 Backfilling cu.m. 0.00 not applicable

8.1.2 RCP 1500 mm dia (Class III) ln.m. 147.90

8.1.3 Special Manhole 1500mm set 2.00

8.1.4 Special Catch Basin 1500mm set 1.00

8.1.5 Outfall #7 set 1.00

OTHERS

8.2.0 Catch Basin

8.2.1 Catch Basin,300mm dia set 26.00

8.2.2 Catch Basin,375mm dia set 2.00

8.2.3 Catch Basin,600mm dia set 2.00

8.30 GENERAL REQUIREMENTS

8.3.1 lot 1.00

8.3.2 lot 1.00

8.3.3 lot 1.00

8.3.4 lot 1.00

8.3.5 lot 1.00

8.3.6 lot 1.00

Sub-total :

BID SUMMARY
SUBDIVISION : PHIRST PARK HOMES INC.

LOCATION : BRGY. PALO-ALTO, CALAMBA, LAGUNA

PROJECT : PHIRST PARK HOMES CALAMBA- BASIC LAND DEV'T

SUBJECT : COST PROPOSAL SUMMARY

AREA (SQ.M.) : 0

DATE : April 2, 2020

CONTRACTOR : VERZONTAL BUILDERS,INC.

AMOUNT
ITEM SCOPE OF WORK UNIT SUBTOTAL REMARKS
MATERIAL LABOR & EQUIPMENT

I. GENERAL REQUIREMENTS LOT

II. EARTHWORKS LOT

III. ROAD PREPARATION LOT

IV. READY MIX CONCRETE LOT

V. STORM DRAINAGE SYSTEM LOT

VI. WATER DISTRIBUTION SYSTEM LOT

VIII. OTHERS LOT

PROJECT TOTAL COST: 0.00

COST PER SQM: #DIV/0!

NOTE TO BIDDER:

1. Mark-up shall already be included in the Bids.

2. Mark-up shall cover for all profits, taxes (including VAT), overheads and all other charges.

3. All incidental works necessary for the completion of the project shall be borne by the contractor.

Prepared by: VERZONTAL BUILDERS,INC.

Date: OCTOBER 15, 2019


BIDFORM

DEVELOPER : PHIRST PARK HOMES INC


LOCATION : BRGY. PALO-ALTO, CALAMBA, LAGUNA
PROJECT : PHIRST PARK HOMES CALAMBA - PROJECT IMPROVEMENTS
SUBJECT : GENERAL REQUIREMENTS
DATE : April 2, 2020
CONTRACTOR : VERZONTAL BUILDERS,INC.

ITEM SCOPE OF WORK UNIT QUANTITY UNIT COST AMOUNT TOTAL COST REMARKS

1.1.0 Mobilization/Demobilization lot 0.00 0.00 0.00 0.00

1.2.0 Temporary Facilities lot 0.00 0.00 0.00 0.00

1.3.0 Materials and Quality Assurance Test lot 0.00 0.00 0.00 0.00

1.4.0 Bonds and Insurances lot 0.00 0.00 0.00 0.00

Sub-total : 0.00 0.00

NOTE TO BIDDER:

1. Contractor shall provide their own barracks and other temporary facilities.

2. Concrete Compressive Strength Test (ASTM C 39), and other testing required by the Developer, shall already be included in the Bid Cost.

BIDFORM

SUBDIVISION : PHIRST PARK HOMES INC


LOCATION : BRGY. PALO-ALTO, CALAMBA, LAGUNA
PROJECT : PHIRST PARK HOMES CALAMBA - PROJECT IMPROVEMENTS
SUBJECT : RETAINING WALL
DATE : April 2, 2020
CONTRACTOR : VERZONTAL BUILDERS,INC.

ITEM SCOPE OF WORK UNIT QUANTITY UNIT COST AMOUNT TOTAL COST REMARKS

MATERIALS LABOR EQUIPMENT MATERIAL LABOR & EQUIPMENT

2.1.0 1.00m Reinforced Concrete Retaining Wall

2.1.1 Excavation cu.m 99.63

2.1.2 Concreting cu.m 22.55

2.1.3 Rebars kg 2,144.90

2.1.4 Formworks sqm 114.80

2.1.5 PVC Drain Pipe ln.m. 41.00

2.2.0 2.00m Reinforced Concrete Retaining Wall

2.2.1 Excavation cu.m 419.25

2.2.2 Concreting cu.m 87.75

2.2.3 Rebars kg 6,067.08

2.2.4 Formworks sqm 325.00

2.2.5 PVC Drain Pipe ln.m. 65.00

2.3.0 3.00m Reinforced Concrete Retaining Wall

2.3.1 Excavation cu.m 111.30

2.3.2 Concreting cu.m 21.00

2.3.3 Rebars kg 1,238.47

2.3.4 Formworks sqm 72.00

2.3.5 PVC Drain Pipe ln.m. 65.00

2.4.0 1.00m CHB Retaining Wall

2.4.1 Excavation cu.m 60.80

2.4.2 Concreting cu.m 1.96

2.4.3 Formworks sqm 30.80

2.4.4 6" CHB Load Bearing pc 67.00

2.4.5 Masonry Cement bags 4.86

2.4.6 Sand cu.m 1.22

2.4.7 Rebars kg 1,587.73

2.4.8 PVC Drain Pipe ln.m. 38.00

Sub-total :

NOTE TO BIDDER:

1. Reinforced Concrete Retaining Walls shall be done using Ready-Mixed Concrete with gravel size of G-3/4.

2. CHB Retaining Wall shall be composed Load Bearing Concrete Hollow Blocks with a minimum strength of 750 psi

3. All Bid Cost and Items for payment shall have already included swell and shrinkage factors applicable.

4. Mark-up shall already be included in the Bids.

5. Mark-up shall cover for all profits, taxes (including VAT), overheads and all other charges.

6. All incidental works necessary for the completion of the project shall be borne by the contractor.

7. All labor, materials, and tools necessary for the completion of works shall be provided by the Contractor.

8. Cost of Geotextile Blanket and Gravel Filter shall be included on PVC Drain Pipe
BIDFORM

SUBDIVISION : PHIRST PARK HOMES INC


LOCATION : BRGY. PALO-ALTO, CALAMBA, LAGUNA
PROJECT : PHIRST PARK HOMES CALAMBA - PROJECT IMPROVEMENTS
SUBJECT : STONE MASONRY
DATE : April 2, 2020
CONTRACTOR : VERZONTAL BUILDERS,INC.

ITEM SCOPE OF WORK UNIT QUANTITY REMARKS

3.1.0 1.00m Exposed Height Gravity Wall

3.1.1 Excavation cu.m 28.21

3.1.2 Boulders cu.m 28.21

3.1.3 Cement bags 8.46

3.1.4 Sand sqm 8.46

3.1.5 PVC Drain Pipe ln.m. 6.00

3.2.0 2.00m Exposed Height Gravity Wall

3.2.1 Excavation cu.m 487.92

3.2.2 Boulders cu.m 487.92

3.2.3 Cement bags 146.38

3.2.4 Sand sqm 146.38

3.2.5 PVC Drain Pipe ln.m. 202.30

3.3.0 3.00m Exposed Height Gravity Wall

3.3.1 Excavation cu.m 657.93

3.3.2 Boulders cu.m 657.93

3.3.3 Cement bags 197.38

3.3.4 Sand sqm 197.38

3.3.5 PVC Drain Pipe ln.m. 162.59

3.4.0 4.00m Exposed Height Gravity Wall

3.4.1 Excavation cu.m 130.68

3.4.2 Boulders cu.m 130.68

3.4.3 Cement bags 39.20

3.4.4 Sand sqm 39.20

3.4.5 PVC Drain Pipe ln.m. 70.60

3.5.0 5.00m Exposed Height Gravity Wall

3.5.1 Excavation cu.m 359.37

3.5.2 Boulders cu.m 359.37

3.5.3 Cement bags 107.81

3.5.4 Sand sqm 107.81

3.5.5 PVC Drain Pipe ln.m. 70.60

Sub-total :

NOTE TO BIDDER:

1. All labor, materials, and tools necessary for the completion of works shall be provided by the Contractor.

2. Mark-up shall already be included in the Bids.

3. Mark-up shall cover for all profits, taxes (including VAT), overheads and all other charges.

4. All incidental works necessary for the completion of the project shall be borne by the contractor.

5. Cost of Geotextile Blanket and Gravel Filter shall be included on PVC Drain Pipe

BIDFORM

SUBDIVISION : PHIRST PARK HOMES INC


LOCATION : BRGY. PALO-ALTO, CALAMBA, LAGUNA
PROJECT : PHIRST PARK HOMES CALAMBA - PROJECT IMPROVEMENTS
SUBJECT : PERIMETER FENCE
DATE : April 2, 2020
CONTRACTOR : VERZONTAL BUILDERS,INC.

ITEM SCOPE OF WORK UNIT QUANTITY REMARKS

5.1.0 Standard CHB Perimeter Fence

5.1.1 Earthworks cu.m. 594.00

5.1.2 Cement bags 2,270.60

5.1.3 Sand cu.m. 118.37

5.1.4 Gravel cu.m. 104.11

5.1.5 Ordinary CHB 6" pc 10,764.00

5.1.6 Formworks sq.m. 417.17

5.1.7 Rebars kg 6,395.28

5.2.0 Cyclone Perimeter Fence

5.2.1 Earthworks cu.m. 305.28

5.2.2 Cement bags 1,022.40

5.2.3 Sand cu.m. 35.96

5.2.4 Gravel cu.m. 71.92

5.2.5 Ordinary CHB 6" pc 5,751.00

5.2.6 Formworks sq.m. 186.65

5.2.7 Rebars kg 4,292.22

5.2.8 Cycone Wire sqm 339.20

5.2.9 GI Pipe ln.m. 707.00

5.2.10 Welds ln.m. 22.46

Sub-total :

NOTE TO BIDDER:

1. All labor, materials, and tools necessary for the completion of works shall be provided by the Contractor.

2. Mark-up shall already be included in the Bids.

3. All incidental works necessary for the completion of the project shall be borne by the contractor.

4. Mark-up shall cover for all profits, taxes (including VAT), overheads and all other charges.
BIDFORM

SUBDIVISION : PHIRST PARK HOMES INC


LOCATION : BRGY. PALO-ALTO, CALAMBA, LAGUNA
PROJECT : PHIRST PARK HOMES CALAMBA - PROJECT IMPROVEMENTS
SUBJECT : OTHERS
DATE : April 2, 2020
CONTRACTOR : VERZONTAL BUILDERS,INC.

ITEM SCOPE OF WORK UNIT QUANTITY REMARKS

8.1.0 (Others - Uprooting of Trees) lot 1.00

8.20 GENERAL REQUIREMENTS

8.2.1 0 lot 0.00

8.2.2 0 lot 0.00

8.2.3 0 lot 0.00

8.2.4 0 lot 0.00

8.2.5 0 lot 0.00

8.2.6 0 lot 0.00

8.3 1.40m Exposed Height Gravity Wall

Excavation cu.m 132.68

Boulders cu.m 132.68

Cement bags 39.80

Sand cu.m 39.80

PVC Drain Pipe lm 202.30

Graded Gravel lm 62.00

8.40 Cyclone Perimeter Fence

Tension Wire lm 426.00

Sub-total :

BID SUMMARY
SUBDIVISION : PHIRST PARK HOMES INC

LOCATION : BRGY. PALO-ALTO, CALAMBA, LAGUNA

PROJECT : PHIRST PARK HOMES CALAMBA - PROJECT IMPROVEMENTS

SUBJECT : COST PROPOSAL SUMMARY

AREA (SQ.M.) : 0

DATE : April 2, 2020

CONTRACTOR : VERZONTAL BUILDERS,INC.

ITEM SCOPE OF WORK UNIT AMOUNT SUBTOTAL REMARKS

MATERIAL LABOR & EQUIPMENT

I. GENERAL REQUIREMENTS LOT 0.00 0.00

II. RETAINING WALL LOT 0.00 0.00 0.00

III. STONE MASONRY LOT 0.00 0.00 0.00

IV. PERIMETER FENCE LOT 0.00 0.00 0.00

V. OTHERS LOT 0.00 0.00 0.00

PROJECT TOTAL COST: 0.00

COST PER SQM: #DIV/0!

NOTE TO BIDDER:

1. Mark-up shall already be included in the Bids.

2. Mark-up shall cover for all profits, taxes (including VAT), overheads and all other charges.

3. All incidental works necessary for the completion of the project shall be borne by the contractor.

Prepared by: VERZONTAL BUILDERS,INC.

Date: OCTOBER 15, 2019

S-ar putea să vă placă și