Main Contractor: The Subcontractor :

G.E.T
Reporting Date: 1-Dec-19 Report Serial Number : 272

Contractual Commencement Date : 17-Jan-19 Days Elapsed 318


Contractual Completion Date : 16-Jan-20 Days Left for Completion : 46

Weather :Mostly Sunny Temperature :21C 0 Max: 27C


Humidity : 71%
Subcontractor's Manpower Subcontractor's Equipment
Trade (Indirect) No. Trade (Direct) No. Eqipment/Type Descriptions Fleet/Plate No. Working / day
Project Manager 1 9 Power Generator
QA/QC Engineer 1 2 Air Compressor
Planning Engineer 1 2 Concrete Mixer
62025, 55813,
1
Site Engineer 1 3 Bobcat 21936
Surveyor 2 9 Vibrator
Surveyor Assistant 1 4 Tower Light
General Foreman 2 1 Mobile Crane 7129
Foreman 7 Back-Hoe Loader
Supervisor 3
Lifting Supervisor 1
Carpenter Chargehand 3 Nissan X-Trail
Steel Fixer Chargehand 4 Urvan
Scaffolding Inspector 4 Nissan Tida
Mason Gangleader 2
Structural Autocad Operator 0 Roller
Document Controller 0 Wheel loader
Admin 1 Skid Loader
HSE Supervisor 6 Skid Loader
HSE Jr.Supervisor 1 GPS 1
Office boy 1 Boom Truck 5 ton 1
Timekeeper 1 4 pickup Duble cabin 1
Store Keeper 2 2 pickup 1 ton 1
Assistant Store Keeper 1 1 Steel Bending Machine
Heavy Duty Driver 1 Steel Cutting Machine
Light Duty Driver Water Tank with pump 1
Technican/Electrican 3 Plat Compactor
Driver 8 1 Steel Bending Machine
Operator 5 9 Rotary Drill
Rigger 4 3 Drill Machine
Plumber 2 5 Helicopter Machine
EARTH WORKS 3 Total Station Surveyor Equipment 1
SKILLED Level Machine Surveyor Equipment 1
UNSKILLED 1 Power Floating machine 1
CIVIL/STRUCTURAL 5 Tata Bus 65 Seats
Mason Bus 28 Seats
SKILLED 33 1 BUS 14 Seats
UNSKILLED 4 10 Circular SAW
Steel fixer 6 Jack Hammer
SKILLED 101 3 Air blower
UNSKILLED 6 3 Vacuum
Shuttering Carpenter
SKILLED 162
UNSKILLED 8
Scaffolder Materials Delivered to Site
Item
Unit Qty Delivery Note No. Remarks
SKILLED /Descriptions

FIRST-AID
Nurse
Total Manpower 381

Today's Activities

S.No Building / No. Percentage Activity

42.1.1 - MAIN SPORTS Assemble, tieing up, placement of reinforcemnt for Wall from Basement to ground floor around
1 82%
COMPLEX swimming pool area (Internal)

42.1.1 - MAIN SPORTS Assemble, tieing up, placement of reinforcemnt for columns from ground floor to Mezzanine
2 100%
COMPLEX floor(Part 2)

42.1.1 - MAIN SPORTS


3 64% Layout & Formwork of Blinding under SOG - Part-4
COMPLEX

42.1.1 - MAIN SPORTS


4 52% placement tieing up of reinforcemnt for Slab on Grade (Part-4)
COMPLEX

42.1.1 - MAIN SPORTS


5 96% placement tieing up of reinforcemnt for Slab on Grade (Part-2)
COMPLEX

42.1.1 - MAIN SPORTS


6 31% Formwork for Mezzanine floor slab(Part 2)
COMPLEX

6 42.1.1 - MAIN SPORTS 50% placement tieing up of reinforcemnt for Slab on Grade (Part-1)
COMPLEX

7 42.1.1 - MAIN SPORTS 51% Formwork for Ground Floor Slab(part 5&6)
COMPLEX

8 28.3 - MAIN MASJID Curing of Roof Floor Slab and beam(ssl level 12.650m-part 1)

9 28.3 - MAIN MASJID 85% placement & tieing up of reinforcemnt for Minerat Column

10 28.3 - MAIN MASJID 99% Formwork for Roof Floor Slab(ssl level 13.400m - part1)

11 28.3 - MAIN MASJID 90% placement & tieing up of reinforcemnt for Column(Roof floor to Upper Roof floor)

28.3 - MAIN MASJID 42% Formwork for Column(Roof floor to Upper roof floor)

29.1 - BASE
12 100% placement & tieing up of reinforcemnt for staircases no 01 and 02(Ground floor to First floor)
ADMINISTRATION

29.1 - BASE
13 100% Formwork for Staircases no 2 and Staircases no 01(Ground floor to First floor)
ADMINISTRATION

16.2 - FLOTILLA COMMAND


14 100% placement tieing up of reinforcemnt for Slab on Grade
BUILDING

16.2 - FLOTILLA COMMAND


15 22% Formwork for Upper roof Floor Slab and Beam
BUILDING

16.2 - FLOTILLA COMMAND


16 72% Formwork for Column(Roof floor to Upper roof floor)
BUILDING

16.2 - FLOTILLA COMMAND


17 100% Parapet Wall Casted
BUILDING

16.2 - FLOTILLA COMMAND


18 100% Formwork for parapet wall
BUILDING

16.2 - FLOTILLA COMMAND


19 100% Formwork for Staircases no 02(First floor to Second floor)
BUILDING

20 18.1 - FIRE - STATAION 12% Formwork for Trench wall

21 18.1 - FIRE - STATAION 15% Assemble, tieing up, placement of reinforcemnt for First Floor Slab and Beam(part 2)

22 18.1 - FIRE - STATAION 40% Formwork for First Floor Slab and Beam (part 2)

23 18.1 - FIRE - STATAION 100% Formwork for Ground Floor beams(part 2)

24 18.1 - FIRE - STATAION 100% Ground Floor beams casted(part 2)

25 18.1 - FIRE - STATAION 100% Assemble, tieing up, placement of reinforcemnt for Ground Floor columns(part 2)

26 18.1 - FIRE - STATAION 89% Assemble, tieing up, placement of reinforcemnt for First Floor Column(part 1)

26 18.1 - FIRE - STATAION 20% Formwork for First Floor Columns(part 1)

27 18.1 - FIRE - STATAION 100% Formwork for Ground Floor Columns(part 2)

28 18.1 - FIRE - STATAION 100% Ground Floor column casted(part 1)

29 12.1- NORTH GATE 100% Assemble, tieing up, placement of reinforcemnt for Column Neck

4.4 - MECHANICAL
30 41% Formwork for Trench wall(Part 2)
WORKSHOP

4.4 - MECHANICAL
31 99% Assemble, tieing up, placement of reinforcemnt for Ground Floor columns(part 3)
WORKSHOP

4.4 - MECHANICAL
32 95% Assemble, tieing up, placement of reinforcemnt for Ground Floor beams(Part 3)
WORKSHOP

4.4 - MECHANICAL
94% placement,tieing up of reinforcemnt for Slab on Grade (Part-3)
WORKSHOP

4.4 - MECHANICAL
33 91% Formwork for Ground Floor Columns(part 3)
WORKSHOP
Main Contractor: The Subcontractor :

G.E.T
Reporting Date: 1-Dec-19 Report Serial Number : 272

Contractual Commencement Date : 17-Jan-19 Days Elapsed 318


Contractual Completion Date : 16-Jan-20 Days Left for Completion : 46

Weather :Mostly Sunny Temperature :21C 0 Max: 27C


Humidity : 71%

4.4 - MECHANICAL
34 80% Formwork for Ground Floor beams(part 3)
WORKSHOP

4.4 - MECHANICAL
35 70% Assemble, tieing up, placement of reinforcemnt for Trench wall(Part 2)
WORKSHOP

4.5 - ELECTRONICS
36 80% Layout & Formwork of Blinding under Ground Beam
WORKSHOP

4.5 - ELECTRONICS
37 99% Surface preparation of blinding
WORKSHOP

4.6 - COASTAL DEFENSE


38 94% placement,tieing up of reinforcemnt for Slab on Grade
MASJID

4.6 - COASTAL DEFENSE


39 100% Formwork for Parapet wall (Level 8.850 and 10.25)
MASJID

4.7- Vehicle Wash Stand


40 100% Assemble, tieing up, placement of reinforcemnt for Ground Floor columns
Area

4.1 - COSTAL DEFENCE


41 100% Assemble, tieing up, placement of reinforcemnt for 1st Floor columns
HEADQUARTER

4.1 - COSTAL DEFENCE


42 100% Assemble, tieing up, placement of reinforcemnt for Staircases 2
HEADQUARTER

4.1 - COSTAL DEFENCE


43 100% Formwork for Staircases NO 02
HEADQUARTER
4.1 - COSTAL DEFENCE
44 42% Formwork for Roof Floor Slab and Beam(ssl level 12.700m)
HEADQUARTER
4.1 - COSTAL DEFENCE
45 22% Assemble, tieing up, placement of reinforcemnt for Roof Floor Slab and Beam
HEADQUARTER
4.1 - COSTAL DEFENCE
46 100% Formwork for first Floor Column
HEADQUARTER

47 4.2.2-Battery Shed

16.2 - FLOTILLA COMMAND


48
BUILDING

49 42.1.1 - MAIN SPORTS


COMPLEX
50 28.3 - MAIN MASJID
Houskeeping
29.1 - BASE
51
ADMINISTRATION
4.1 - COSTAL DEFENCE
52
HEADQUARTER

53 18.1 - FIRE - STATAION

concrete
First floor
TIE Beam(Part
Column(Part SOG(part 1)/42.1.1
6)/42.1.1
1)/18.1

8m3 43m3 4m3

AL SAAD Construction Manager : Signature Date

Mohamed Sulaiman
Signature
GET Construction Manager: Date

Dimitris Kordalis
Signature
GET Project Manager: Date