SB Construction DAILY WORK REPORT

SB Construction Corporation -Site SB Construction Corporation -Office


Prepared Reviewed Approved Checked Reviewed Approved
Drydocking SB-G-1

Michelle Anne Labbao Joseph Panganiban Capt. Woo Sang Yoon

Weather: Rainy As of : October-15-2018 Shift : Day Work

1. Daily Manpower
Scope Classification Unit Previous Today Cumulative
Indirect Manpower
Korean Manager Man - Days 1 1
Admin Staff Man - Days 1 1
Mechanic Man - Days 3 3
Light Vehicle Driver Man - Days 1 1
Sub Total 0 6 6
SB Direct Manpower
CONSTRUCTIO Supervisor Man - Days 1 1
N Rigger Man - Days 3 3
CORPORATION Electrician Man - Days 1 1
Deckhand Man - Days 1 1
Heavy Equipment Operator Man - Days 2 2
Heavy Equipment Driver Man - Days 1 1
Welder Man - Days 2 2
Sub Total 421 -410 11
Total 421 -404 17

2. Daily Construction Machinery


Machinery
Scope Previous Today Cumulative
Equipment Grade Unit
Welding Machine ea 164 4 168
Total 164 4 168

3. Daily Work Activity Contents


Area Today Work Tomorrow Work Remarks
Repair Clamshell Repair Clamshell
Chipping and Brushing Main Deck of the Barge Cleaning Barge
SB-G-1 7:00 AM - 6:00 PM
Sandblasting Sandblasting
Painting Painting
4. Daily Photo Progress

SANDB;ASTING OD THE SIDE WALL PAINTING AT BOTH SIDE WALL

REMARKS:
AS OF THE TODAY, 80% WERE ALREADY FINISH SANDBLASTING AND PRIME PAINTING,
AS PER SEAFRONT IF THE WEATHER CONDITION IS GOOD, SANDBLASTING AND PAINTING WILL BE DONE IN SEVEN DAYS, BUT AS OF THE MOMENT WE ARE EXPERIENCING
CONTINUOUSLY RAINING AND COLD TEMPERATURE WHICH IS CONTRAST IN PAINTING ACTIVITY. THE SEVEN DAYS COMPLETION PERIOD IS BASED ON NORMAL AND SUNNY
WEATHER CONDITION.

Page 1 of 2
SEAFRONT ACTIVITY
Date Sandblasting Painting Weather Remarks
1-Jul
2-Jul
3-Jul
4-Jul
5-Jul
6-Jul ü Sunny Start
7-Jul ü x Cloudy
8-Jul ü ü Sunny
9-Jul x ü Sunny
10-Jul x x Rainy
11-Jul x x Rainy
12-Jul x x Rainy
13-Jul x x Rainy
14-Jul x x Rainy
15-Jul x x Rainy
16-Jul x x Rainy