Documente Academic
Documente Profesional
Documente Cultură
03&*/$*%&/545)"5
%&'*/&130$&444"'&5:
.03&*/$*%&/545)"5
%&'*/&130$&444"'&5:
$&/5&3'03$)&.*$"-130$&444"'&5:
PGUIF
".&3*$"/*/45*565&0'$)&.*$"-&/(*/&&34
/FX:PSL
/:
This edition first published 2020
© 2020 the American Institute of Chemical Engineers
A Joint Publication of the American Institute of Chemical Engineers and John Wiley & Sons, Inc.
All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or
transmitted, in any form or by any means, electronic, mechanical, photocopying, recording or
otherwise, except as permitted by law. Advice on how to obtain permission to reuse material from
this title is available at http://www.wiley.com/go/permissions.
The rights of CCPS to be identified as the author of the editorial material in this work have been
asserted in accordance with law.
Registered Office
John Wiley & Sons, Inc., 111 River Street, Hoboken, NJ 07030, USA
Editorial Office
111 River Street, Hoboken, NJ 07030, USA
For details of our global editorial offices, customer services, and more information about Wiley
products visit us at www.wiley.com.
Wiley also publishes its books in a variety of electronic formats and by print-on-demand. Some
content that appears in standard print versions of this book may not be available in other formats.
Limit of Liability/Disclaimer of Warranty
While the publisher and authors have used their best efforts in preparing this work, they make no
representations or warranties with respect to the accuracy or completeness of the contents of this
work and specifically disclaim all warranties, including without limitation any implied warranties
of merchantability or fitness for a particular purpose. No warranty may be created or extended by
sales representatives, written sales materials or promotional statements for this work. The fact that
an organization, website, or product is referred to in this work as a citation and/or potential source
PGGVSUIFSJOGPSNBUJPOEPFTOPUNFBOUIBUUIFpublisher and authors endorse the information or
TFSWJDFTUIFPSHBOJ[BUJPO
XFCTJUF
PSQSPEVDUNBZQSPWJEFor recommendations it may make. This
XPSLJTTPMEXJUIUIFVOEFSTUBOEJOHUIBUUIFQVCMJTIFSJTOPUFOHBHFEin rendering professional
TFSWJDFT5IFBEWJDFBOETUSBUFHJFTDPOUBJOFEIFSFJONBZOPUCFTVJUBCMFGPSZPVSsituation. You
TIPVMEDPOTVMUXJUIBTQFDJBMJTUXIFSFBQQSPQSJBUF'VSUIFS
SFBEFSTTIPVMECFBXBSFUIBUwebsites
MJTUFEJOUIJTXPSLNBZIBWFDIBOHFEPSEJTBQQFBSFECFUXFFOXIFOUIJTXPSLXBTXSJUUFOBOE
XIFOJUJTSFBE/FJUIFSUIFQVCMJTIFSOPSBVUIPSTTIBMMCFMJBCMFGPSBOZMPTTPGQSPGJUPSBOZPUIFS
DPNNFSDJBMEBNBHFT
JODMVEJOHCVUOPUMJNJUFEUPTQFDJBM
JODJEFOUBM
DPOTFRVFOUJBM
PSPUIFS
EBNBHFT
$PWFS%FTJHO8JMFZ
Printed in the United States of America
10 9 8 7 6 5 4 3 2 1
More Incidents that Define Process
Safety
Table of Contents
1 ........................................................................................................... 41
Introduction ....................................................................................... 41
1.1 WHY A SECOND VOLUME? ..................................................... 41
1.2 CCPS RISK BASED PROCESS SAFETY ELEMENTS.................. 42
1.3 HUMAN PERFORMANCE......................................................... 48
1.4 ORGANIZATION OF THIS BOOK............................................. 48
1.5 Engineering Design ................................................................. 49
1.6 How To Use The Book ............................................................ 50
1.7 Final Note ................................................................................. 50
2 ........................................................................................................... 52
Reactive Chemical Incidents ............................................................ 52
2.1 Introduction ............................................................................. 52
2.2 T2 Laboratories Runaway Reaction and Explosion, Florida,
US, 2007 .......................................................................................... 53
2.3 HOECHST GRIESHEIM RUNAWAY REACTION, GERMANY,
1993 ................................................................................................. 60
2.4 ARCO CHANNELVIEW EXPLOSION, TEXAS, US, 1990 .......... 64
2.5 AMMONIUM NITRATE INCIDENTS ........................................ 68
2.6 WEST FERTILIZER COMPANY AN EXPLOSION, TEXAS, US,
2013..................................................................................................69
2.7 RUI HAI INTERNATIONAL LOGISTICS AN EXPLOSION,
TIANJIN, CHINA, 2015 .................................................................... 78
2.8 PORT NEAL AMMONIUM NITRATE EXPLOSION, IOWA, US,
1994................................................................................................. 81
2.9 HICKSON & WELCH JET FLAME, UK, 1992 ............................ 86
2.10 OTHER INCIDENTS ................................................................ 92
2.11 ADDITIONAL RESOURCES .................................................... 93
.PSF*ODJEFOUTUIBU%FGJOF1SPDFTT4BGFUZ 3
3 ........................................................................................................... 96
Fire Incidents ..................................................................................... 96
3.1 INTRODUCTION....................................................................... 96
3.2 HOEGANAES METAL DUST FIRES, TENNESSEE, US, 2011... 97
3.3 CHEVRON RICHMOND REFINERY FIRE, CALIFORNIA, US,
2012 .............................................................................................. 105
3.4 VALERO-MCKEE LPG REFINERY FIRE, TEXAS, US, 2007 ..... 115
3.5 BLSR DEFLAGRATION AND FIRE, TEXAS, US, 2003 ............ 121
3.6 SIMILAR INCIDENTS .............................................................. 127
3.7 ADDITIONAL RESOURCES .................................................... 128
4 ......................................................................................................... 131
Explosion Incidents ......................................................................... 131
4.1 INTRODUCTION..................................................................... 131
4.2 BUNCEFIELD STORAGE TANK OVERFLOW AND EXPLOSION,
UK, 2005 ....................................................................................... 135
4.3 PETROLEUM OIL LUBRICANTS EXPLOSION, JAIPUR, INDIA
2009 .............................................................................................. 145
4.4 CELANESE PAMPA EXPLOSION, TEXAS, US, 1987 ............. 151
4.5 WILLIAMS OLEFINS HEAT EXCHANGER RUPTURE,
LOUISIANA, US, 2013 .................................................................. 158
4.6 IMPERIAL SUGAR DUST EXPLOSION, GEORGIA, US, 2008165
4.7 HAYES LEMMERZ DUST EXPLOSION, INDIANA, US, 2003 173
4.8 VARANUS ISLAND PIPELINE EXPLOSION, AUSTRALIA, 2008
....................................................................................................... 182
4.9 NATURAL GAS PURGING EXPLOSIONS .............................. 189
4.10 OIL STORAGE TANK EXPLOSION, ITALY, 2006 ................. 194
4.11 NDK CRYSTAL VESSEL RUPTURE, ILLINOIS, 2009.............199
4.12 SIMILAR INCIDENTS ............................................................ 205
4 More Incidents that Define Process Safety
List of Figures
AN Ammonium Nitrate
CP Cathodic Protection
DDT Dichlorodiphenyltrichloroethane
DNT Dinitrotoluene
EU European Union
FMG FM Global
HF Hydrofluoric Acid
MCHM Methylcychohexanemethanol
.PSF*ODJEFOUTUIBU%FGJOF1SPDFTT4BGFUZ 17
MCPD methylcyclopentadiene
MI Mechanical Integrity
MNT Mononitrotoluene
PA Public Address
PTFE Polytetrafluoroethylene
QA Quality Assurance
TNT Trinitrotoluene
UK United Kingdom
US United States
GLOSSARY
Many of these terms and definitions are taken from the CCPS
Glossary, which is continually updated. Please check the glossary
at www.aiche.org/ccps/resources/glossary for the most current
definition.
ACKNOWLEDGMENTS
Tracy Whipple BP
.PSF*ODJEFOUTUIBU%FGJOF1SPDFTT4BGFUZ 35
Peer Reviewers:
Dave Fargie BP
PREFACE
The Center for Chemical Process Safety (CCPS) was created by the
AIChE in 1985 after the chemical disasters in Mexico City, Mexico,
and Bhopal, India. The CCPS is chartered to develop and
disseminate technical information for use in the prevention of
major chemical accidents. The Center is supported by more than
180 chemical process industry sponsors who provide the
necessary funding and professional guidance to its technical
committees. The major product of CCPS activities has been a
series of guidelines to assist those implementing various
elements of a process safety and risk management system. This
book is part of that series.
The AIChE has been closely involved with process safety and
loss control issues in the chemical and allied industries for more
than five decades. Through its strong ties with process designers,
constructors, operators, safety professionals, and members of
academia, AIChE has enhanced communications and fostered
continuous improvement of the industry’s high safety standards.
AIChE publications and symposia have become information
resources for those devoted to process safety and environmental
protection.
The integration of process safety into the engineering
curricula is an ongoing goal of the CCPS. To this end, CCPS created
the Safety and Chemical Engineering Education committee, which
develops training modules for process safety. One textbook
covering the technical aspects of process safety for students
already exists; however, there is no textbook covering the
concepts of process safety management and the need for process
safety for students. The CCPS Technical Steering Committee
.PSF*ODJEFOUTUIBU%FGJOF1SPDFTT4BGFUZ 37
Foreword
Center for Chemical Process Safety, and all the case histories,
process safety incidents continue to occur. I wish I could say I have
an easy answer.
Introduction
.PSF*ODJEFOUTUIBU%FGJOF1SPDFTT4BGFUZ
By $$14
¥5IF"NFSJDBO*OTUJUVUFPG$IFNJDBM&OHJOFFST
42 More Incidents that Define Process Safety
2.1 INTRODUCTION
“Safely conducting chemical reactions is a core competency of the
chemical industry” (CSB 2002) states the executive summary of a
US Chemical Safety Board (CSB) study of reactive chemical
incidents. Yet, reactive chemical incidents continue to occur. This
study reviewed 167 incidents in the US over a twenty-one-year
period. A few statistics:
Forty-eight (29%) resulted in a total of 108 fatalities.
37% resulted in toxic gas emissions.
30% of the incidents affected the public.
Over 50% involved chemicals not covered by U.S. OSHA or
EPA regulations.
36% were due to chemical incompatibilities.
35% were due to runaway reactions.
10% were due to thermally sensitive or impact-sensitive
materials.
70% occurred in the chemical industry, 30% occurred in
other industries.
More than 65% occurred in storage or other process
equipment.
25% occurred in chemical reactors.
More than 90% involved reactive hazards that were
documented in publicly available literature.
This chapter describes four incidents involving reactors, two
involving bulk storage, and one in a wastewater tank. Resources
for managing chemical reactivity hazards are provided at the end
of the chapter.
.PSF*ODJEFOUTUIBU%FGJOF1SPDFTT4BGFUZ
By $$14
¥5IF"NFSJDBO*OTUJUVUFPG$IFNJDBM&OHJOFFST
Chapter 2 Reactive Chemical Incidents 53
2.2.1 Summary
A runaway reaction during the production of
methylcyclopentadienyl manganese tricarbonyl (MCMT) at T2
Laboratories, Inc. resulted in the rupture of the reactor on
December 19, 2007. The resulting explosion caused four T2
employee fatalities and injured thirty-two people: four T2
employees and twenty-eight people at nearby businesses. Pieces
of the reactor were found one mile away. Thirty-two structures
were damaged. Figure 2.2-1 shows a section of the reactor,
weighing approximately 907 kg (2,000 lb) that damaged a building
121 m (400 ft.) away from the reactor. The explosion was heard,
and the overpressure felt 24 km (15 mi.) away in downtown
Jacksonville, Florida. (see Figure 2.2-2).
Key Points
Process Safety Competency – Ensure someone on the job
understands process safety. We work with many intelligent
people, but that does not mean that they understand process
safety. Without someone on the site to ask the right questions,
process safety may be lacking.
Chapter 2 Reactive Chemical Incidents 55
2.2.2 Description
Background. T2 Laboratories Inc. opened in 1996 as a solvent-
blending business. It was founded by a chemical engineer and a
chemist. One of their products was a blend of purchased MCMT,
a gasoline additive. In 2004, T2 began producing MCMT, which
became their primary product by 2007.
Process. The runaway reaction occurred during the first step of the
MCMT process. This was a reaction between
methylcyclopentadiene (MCPD) dimer and sodium in diethylene
glycol dimethyl ether (diglyme).
MCPD and diglyme were charged to a 9.3 m3 (2,450 gal.)
reactor. Sodium metal was then added manually through a valve
at the top of the reactor (see Figure 2.2-3). The heat was applied
to the reactor using hot oil at 182°C (360°F) to melt the sodium
and initiate the reaction to make methylcyclopentene. Hydrogen
was a by-product, vented through a pressure control valve. At
99°C (210°F), the agitator was started (by this time the sodium
should have melted). At 149°C (300°F), the heat was turned off.
Since the reaction was known to be exothermic, cooling was
applied at 182°C (360°F).
What Happened. After eliminating other possible causes, the CSB
concluded that loss of cooling was the immediate cause of the
runaway reaction. The reactor was cooled by adding water to the
jacket and allowing it to boil off (see Figure 2.2-3).
56 More Incidents that Define Process Safety
2.3.1 Summary
On February 22, 1993, a runaway reaction occurred at the
Hoechst plant in Griesheim, Germany. The reactor’s pressure
safety valve (PSV) opened and about 9 metric tons (10 tons) of the
reaction mixture were released, covering 30 hectares (74 acres)
around the plant with a yellow deposit.
As a result of this incident, Germany’s Technical Committee
on Plant Safety was created to determine the minimum
knowledge required to run a chemical process. Their report,
Leitfaden Erkennen und Beherrschen exothermer chemischer
Reaktionen (Guidelines recognizing and mastering exothermic
reactions” (TAABMU 1994), influenced chemical industry
regulation in Germany (Gustin 2001). Media coverage of this event
may have been a factor in Hoechst’s withdrawal from chemical
manufacturing (Kepplinger and Hartung 1995).
Key Points
Process Safety Competency – Consider what might go wrong
and design against it. If there is an important operational
sequence, design out the potential for inadvertent mis-
operation. If it is not possible to design it out, then design in
controls.
Conduct of Operations – COO is not just for operators, but also
applies to the work conducted by managers, engineers, and
other employees who design, implement, and oversee process
operations. Ensure all involved conduct their work diligently.
The design work could have easily included interlocks to
prevent the operating errors that occurred in this incident.
2.3.2 Description
Background. The chemical reaction involved was one between 1-
chloro-2-nitrobenzene (also called 2-chloronitrobenzene) and
methanolic caustic soda to produce ortho nitroanisole (Figure 2.3-
1).
Process. The process was conducted in a 36 m3 (9510 gal.) reactor
at 80°C (176°F) and 10 bar-a (145 psia). Methanol and 2-
chloronitrobenzene were added to the reactor with the agitator
running. Following the chemical addition, the agitator was turned
off and the level in the reactor checked through an open manhole
cover. The cover was replaced, and the agitator was restarted. The
mixture was heated to 80°C (176°F), and nitrogen was applied to
raise the reactor pressure to 3 bar (43.5 psi). This reduced the
oxygen concentration in the headspace to 8 vol%; some oxygen
was required to prevent unwanted secondary reactions. The
methanol and the caustic solution were then added, and cooling
was applied manually as necessary to control the reactor
temperature at 80°C (176°F).
What Happened. During the batch in question, operators had to
apply heating to the reactor to maintain a temperature of 80°C
(176°F) instead of applying cooling, as was normal at this point in
62 More Incidents that Define Process Safety
the batch. When the methanol and caustic addition was complete,
the batch was sampled for conversion. At this time, operators
discovered that the agitator was turned off, so they proceeded to
start it. As soon as mixing was started, a runaway reaction
occurred, raising the temperature to about 160°C (320°F) and the
pressure to 16 barg (232 psig). The reactor had a PSV set at 16
barg (232 psig), which opened, leading to the release of the
reactor contents as described in the summary.
Why it Happened. The investigation found that the agitator was not
restarted after the level check. This led to a buildup of unmixed
and unreacted material in the reactor. A sample that had been
taken for conversion showed only 45% conversion of 2-
chloronitrobenzene. Therefore, more than half of the charge was
available to react. When the agitator was restarted, the rapid
mixing caused the entire mixture to react immediately. This
exothermic reaction was further driven by the heat which had
previously been manually applied.
Compounding the problem, the high temperature triggered a
secondary decomposition reaction that had a heat of reaction of
390 kJ/mole (93 kcal/mole), further accelerating the exotherm and
buildup of pressure in the reactor.
2.4.1 Summary
A wastewater tank containing process wastewater with
hydrocarbons and peroxides exploded during the restart of an
off-gas compressor. The normal nitrogen purge had been
reduced during the maintenance period, and a temporary oxygen
analyzer failed to detect excessive oxygen in the tank vapor space.
When the compressor was restarted, a flammable mixture of
hydrocarbons and oxygen was pulled in and ignited. The
flashback of the flame into the headspace of the tank ignited the
confined vapors and an explosion occurred. The explosion caused
seventeen fatalities. ARCO spent $20 million replacing the unit
and installing safety enhancements (ARCO 1991), and also paid
about $3.5 million in penalties (OGJ 1991).
This incident was one of those cited in the Background section
of the U.S. OSHA PSM rule as justification for the need for the PSM
rule (OSHA 1992).
Chapter 2 Reactive Chemical Incidents 65
Key Points
Process Safety Competency – What is safe? Conducting
operations safely depends on designing, documenting and
following the planned response when safe operating
parameters are exceeded. Ensure all involved are competent to
conduct their work with process safety in mind.
Asset Integrity and Reliability – Make sure equipment will work
when it is needed. Critical equipment must be designed, tested,
and maintained to ensure that it will function as intended to
prevent a process safety incident.
2.4.2 Description
Background. ARCO acquired the Channelview complex in 1980.
The plant produced propylene oxide, methyl tertiary butyl ether,
and styrene monomer.
Process. The 3,407 m3 (900,000 gal) wastewater tank contained
process wastewater from propylene oxide and styrene processes.
Peroxide and caustic byproducts from these processes traveled
through thousands of feet of piping to the tank where they mid.
There was normally a layer of hydrocarbons on the surface of the
water. Also, oxygen was formed in the tank due to decomposition
of the hydrocarbon peroxides in the tank. A nitrogen purge was
used to keep the vapor space inert, and an off-gas compressor
drew the hydrocarbon vapors off before the waste layer was
disposed of in a deep well. Figure 2.4-1 shows the process
scheme.
What Happened. The tank was taken out of service to repair the
nitrogen blanket compressor. However, even though flow into the
tank had ceased, it had not been emptied and oxygen was still
forming due to the decomposition of peroxides in the tank. A
temporary oxygen analyzer was installed between two roof
beams and provisions were made to add a nitrogen purge if a high
oxygen level was detected. During this time, the oxygen analyzer
failed, giving incorrect low readings and the normal flow of
66 More Incidents that Define Process Safety
2.6.1 Summary
On April 17, 2013, a fire occurred at the West Fertilizer Company
in West, Texas, which triggered an explosion of about 27 metric
tons (30 tons) FGAN at 7:51 p.m. The explosion registered as a 2.1
on the Richter scale. There were fifteen fatalities—twelve were
emergency responders; three were members of the public. One
of the public fatalities was in a nursing home (from a stress-
induced heart attack) and the other two were in an apartment
complex. The overpressure from the blast damaged 150 buildings
off-site, including four schools, a nursing home (later
demolished), an apartment complex, and 350 private residences
(142 beyond repair) (CSB 2016).
This was a significant incident in the US, due to the extensive
public impact, and the prevalence of FGAN storage and handling
facilities in the US. The CSB identified over 1,300 facilities handling
AN within close proximity to a community. The United States
president issued Executive Order EO-13650. This established a
working group consisting of the U.S. Department of Homeland
Security (DHS), the U.S. Environmental Protection Agency (EPA),
and the U.S. Departments of Labor (under which the U.S. OSHA is
located), Justice, Agriculture, and Transportation. The purpose of
the working group was to improve the identification and response
to the risks of chemical facilities (EO 2013).
70 More Incidents that Define Process Safety
Key Points
Process Safety Culture – Ensure all involved value process safety.
A poor safety culture will have consequences. It could be any-
thing from a loss of insurance coverage to a tremendous loss
of life, both of which occurred at West Fertilizer.
Stakeholder Involvement – Work together to prevent incidents.
It is important that local planners understand the hazards of
facilities and that enforcement agencies identify shortfalls in
neighboring compliance. Stakeholders communicating with
each other can create a mutual understanding on managing
risks.
Emergency Management – Ensure emergency responders
understand the hazards. Inform your local emergency
responders of the risks at your site so that when they respond
to help you, and they are not put in harm’s way.
2.6.2 Description
Background. West Fertilizer Company (WFC) stored and handled
AN in a fertilizer building, along with several other fertilizers,
including diammonium phosphate, ammonium sulfate, and
potash. The fertilizer building was a wood-frame building. AN was
stored in two plywood bins. Figure 2.6-1 shows an overview of the
building layout, and Figure 2.6-2 provides an exterior view of the
building with the Primary AN bin superimposed on it.
In addition to receiving and storing the various fertilizers,
West Fertilizer also made fertilizer blends, delivered, and
sometimes applied the fertilizers. West Fertilizer also stored and
handled anhydrous ammonia in two pressurized storage tanks.
In 1962, when the facility was first built, it was surrounded by
open land. As the town grew over the years, WFC was surrounded
by residences and schools (Figure 2.6-3). This contributed to the
high impact of this incident.
Chapter 2 Reactive Chemical Incidents 71
2.7.1 Summary
An explosion occurred around 11:30 p.m. on August 12, 2015, at
the Rui Hai International Logistics (RHIL) storage facility in Tianjin,
China. The explosion registered as a 2.9 on the Richter scale. The
entire facility was destroyed. There were 170 fatalities (99
firefighters and 11 policemen), and about 800 people were
injured. The blast affected 17,000 households and 779 businesses
(Figure 2.7-1). The waterways and soil nearby were severely
polluted. An early estimate of losses was $1.5 billion (Huang &
Zhang 2015), (Hernandez 2016). Following the investigation, 123
people were arrested. This was one of the worst industrial
incidents in China, (Trembley 2016).
Key Points
Process Safety Culture – Apply process safety culture concepts
to all stakeholders. When an operating site has a poor safety
culture, and uses political influence to avoid regulatory
enforcement, there can be no confidence that the process is
safe.
Compliance with Standards – Follow the rules. Standards are
developed based on best practices and learnings. Deciding not
to comply with standards and regulations can be reckless. If
you think that a standard doesn’t work for your application,
then communicate with the standard’s authors to discuss the
situation.
Chapter 2 Reactive Chemical Incidents 79
2.7.2 Description
Background. RHIL was started by two men; one the son of a local
police chief and the other an executive at a chemical firm. Tianjin
was a rapidly growing area and the facility eventually grew to 4.5
hectares (11 acres) in size. The warehouses were known for
“shoddy construction” (Jacobs, Hernandez & Buckley 2015).
Process. The facility stored more than 40 hazardous chemicals
(Zeng 2015), including 800 tonnes (882 tons) of AN, 700 tonnes
(772 tons) of sodium cyanide, 200 tonnes (220 tons) of
nitrocellulose as well as various metal powders.
What Happened. A fire was observed in the facility at 10:50 p.m.
The first responders arrived by 11:06 p.m. and others arrived
2.8.1 Summary
On December 13, 1994, an explosion occurred in the AN portion
of a fertilizer plant in a process vessel known as a neutralizer. The
explosion occurred while the AN process was shut down with AN
solution remaining in several vessels. Multiple factors contributed
to the explosion, including strongly acidic conditions in the
neutralizer, the application of 13.79 barg (200 psig) steam to the
vessel, and a lack of monitoring of the AN plant when the process
was shut down with materials left in the process vessels. The
explosion resulted in four fatalities and eighteen people injured.
Serious damage in other parts of the plant resulted in the release
of nitric acid to the ground and anhydrous ammonia into the air
(EPA 1996).
Key Points
Hazard Identification and Risk Analysis – Identify process
hazards so that you can manage them. Without first identifying
the hazards, the hazard management controls and systems will
not be implemented, and the risk will not be managed.
82 More Incidents that Define Process Safety
2.8.2 Description
Background. The Port Neal, Iowa, plant produced nitric acid,
ammonia, ammonium nitrate, urea, and urea-ammonium nitrate.
In the neutralizer, ammonia from the urea plant off-gas or from
ammonia storage tanks was added through a bottom sparger and
55% nitric acid was added through a sparge ring in the middle of
the vessel. The product, 83% AN, was sent to a rundown tank via
an overflow line for transfer to storage. See Figure 2.8-1 for a
process flow diagram of the neutralizer and rundown tank. A pH
probe in the overflow line to the rundown tank was used to
control the nitric acid flow to the neutralizer in order to maintain
the pH at 5.5 - 6.5. The temperature in the neutralizer was
maintained at about 131°C (267°F) by the evaporation of water
and ammonia. Both vessels were vented to a scrubber, where the
vapors were absorbed by 55–65% nitric acid and makeup water
to make 50% AN. A stream of 50% AN was sent back to the
neutralizer.
What Happened. About two weeks prior to the event, the pH probe
was found to be defective, and the plant was controlled by
manually taking samples for pH.
Two days prior to the event, the pH was determined to be -1.5
(sic) and was not brought into the acceptable range until about
1:00 a.m. on December 12. The AN plant was shut down at about
3:00 p.m. on the afternoon of December 12, because the nitric
acid plant was out of service. At about 3:30 p.m., operators
purged the nitric acid feed line to the neutralizer with air. At
about 7:00 p.m., operators pumped scrubber solution to the
neutralizer. At about 8:30 p.m., 13.8 bar (200 psig) steam, which
is about 197°C (387°F), was applied through the nitric acid feed
line to the nitric acid sparger to prevent backflow of AN into the
nitric acid line. The explosion in the neutralizer occurred at
Chapter 2 Reactive Chemical Incidents 83
about 6:00 a.m. on the morning of the 13th. Figure 2.8-2 shows
the aftermath of the explosion.
8. Operating Procedures.
Operating procedures need to cover all phases of operation. This
event was directly tied to a lack of shutdown procedures and the
lack of equipment monitoring requirements during the
shutdown. Without this key information, operators performed
actions that first sensitized the AN solution to decomposition, and
then provided the energy needed to initiate the decomposition
reaction.
2.9.1 Summary
A fire occurred at the Hickson & Welch nitrotoluene plant in
Castleford, UK, in September 1992. When a vessel containing
residual dinitrotoluene (DNT) and nitrocresols from a batch still
was opened for cleaning, a jet flame was released that resulted in
five fatalities. The jet flame first destroyed a control room/office
building (Figure 2.9-1) and then impinged upon the main office
building in which there were sixty-three people. One of the five
fatalities was in this office building. H&W paid £500,000 ($638,203)
in fines and costs in 1993. This incident provides important
lessons on reactive chemical management, facility siting, the
potential effects of jet flames, and the hazards that can be posed
by abnormal operations.
Key Points
Operating Procedures – Ensure operating procedures address
all phases of an operation. There are hazards, sometimes
different ones, in various phases of start-up, operation,
shutdown, cleaning, catalyst change, and emergencies. In
documenting all phases, procedures can address the specific
hazards of each phase and how to control them.
Chapter 2 Reactive Chemical Incidents 87
2.9.2 Description
Background. Hickson & Welch was founded in 1931 and became
publicly held in 1951. In its history, it manufactured dyes,
dichlorodiphenyltrichloroethane (DDT), and timber preservatives.
Process. The Meissner plant made mononitrotoluene (MNT).
Isomers of MNT and the by-product dinitrotoluene (DNT) were
separated by a series of stripping steps. The final distillation left a
residue containing DNT and nitrocresols that were transferred to
a 45.5 m3 (12,021 gal) horizontal storage tank called the 60 still
base.
A final vacuum strip was done in the still base to recover the
last of the MNT. The 60 still base contained steam coils for
heating. The temperature was supposed to be controlled using
6.9 bar (100 psig) steam at 170°C (338°F). However, an existing
pressure regulator was not working properly, so the steam
Figure 2.9-1 Control room and office building after a jet flame
impact (courtesy HSE).
88 More Incidents that Define Process Safety
the HSE support the theory that heat from the steam heaters
could have initiated self-heating of the residue, causing a thermal
runaway that could have reached temperatures of 500°C (932°F),
well above the auto-ignition temperatures of MNT isomers and
the decomposition products.
The temperature probe in the vessel was not in the sludge
itself but above it. Therefore, the temperature being recorded was
that of the vessel atmosphere, not the sludge.
Most of the casualties occurred in the control room, which
was located only 13.4 m (44 ft.) away from the still base and was
directly in the line of fire. One lesson that can be learned here is
the need to examine the location of control rooms and other
occupied buildings with respect to potential hazards.
8. Operating Procedures.
Hickson and Welch had no written procedures for cleaning
vessels. Again, the lesson here is the need to have written
procedures for all phases of operation. Modern PSM programs
recognize this, but abnormal operations such as start-up,
shutdown, maintenance, and in this case, cleanout, warrant
emphasis because the risk during these modes can be much
higher than during normal operation. Applying PHA tools such as
a procedural HAZOP can uncover risks that may be overlooked in
a PHA done for normal operations and it can identify important
safeguards to safely manage these risks.
10. Asset Integrity and Reliability.
The malfunctioning steam regulator was known to be
malfunctioning but was not repaired. Instead the plant relied on
operators to control steam pressure manually. The operators
relied on seeing steam start to emerge from a PSV set at 6.9 bar
(100 psi) as their guide; however, this PSV was malfunctioning. It
should be noted that PSVs are not intended to be normal control
devices. Because the steam regulator and the PSV were critical,
they should have been included in a routine maintenance plan to
check and replace (or service) them periodically to maintain
reliability.
92 More Incidents that Define Process Safety
Fire Incidents
3.1 INTRODUCTION
Safe handling of flammable and combustible (ignitable) materials
is a core competency for the process industries and many others.
Flammable releases within congested areas, such as a refinery or
chemical complex, or in a building, can lead to explosions
(Chapter 4). This chapter will start with a description of a series of
metal dust fires at Hoeganaes Corporation because the lack of
understanding of the hazards of combustible dust hazards is a
frequently recurring problem. The other case studies involve
incidents from the oil production and refining industry. This is not
surprising given that this industry handles large amounts of
flammable materials in complex production operations and the
consequences of fires can be very significant. CSB has produced
videos that describe the incidents at Hoeganaes, Chevron, and
Valero. The videos are excellent learning and safety meeting tools.
A few topics appear in multiple incidents in this chapter and
are worth highlighting.
Emergency Isolation Valves (EIV). In three incidents, the
Valero-McKee, Shell, and CITGO refinery fires, fires lasted
for days because of the lack of EIVs. When compared with
the cost of potential damage, EIVs have high cost/benefit
ratio.
Compliance with Standards. Of the six incidents described,
lack of compliance with standards and regulations was a
factor in three: the Hoeganaes metal dust fires, the BLSR
Operating Ltd. deflagration, and the CITGO Refinery fire.
Auxiliary Operations. Two incidents, the BLSR deflagration
and the Shell Refinery fire, involved operations that are
not typical for a traditional chemical or petrochemical
plant. The Shell Refinery fire is an example of the need to
treat all operations with respect for process safety.
.PSF*ODJEFOUTUIBU%FGJOF1SPDFTT4BGFUZ
By $$14
¥5IF"NFSJDBO*OTUJUVUFPG$IFNJDBM&OHJOFFST
Chapter 3 Fire Incidents 97
3.2.1 Summary
In 2011, Hoeganaes suffered a series of dust flash fires and a
hydrogen explosion that led to a secondary dust flash fire that
together caused five fatalities and injured three others (CSB
2011b). The Hoeganaes facility located near Nashville, Tennessee,
receives scrap metal and converts it into metal powders after
melting and adding various materials to it.
Key Points
Process Safety Competency – Understand how process safety
underpins all the other elements of process safety. Without
understanding what might go wrong, there is no driver to put in
place the barriers to prevent such an incident.
Compliance with Standards – Build on the experience of others.
Standards, regulations, codes, and other guidance documents
are created from both the good and bad experiences of others.
Incident Investigation – Don’t just investigate. Learn! The
purpose of an incident investigation is to learn what happened so
that it can be prevented in the future. Choosing not to investigate,
or investigating and choosing not to take action, is choosing to
risk having an unfortunate repeat.
3.2.2 Description
Background. Hoeganaes Corporation melts scrap steel to produce
atomized steel and iron powders. The Gallatin, Tennessee, facility
has increased their production more than six-fold since beginning
operations in the 1980s.
Process. Hoeganaes’s main product is a powder that is 99% iron.
The process involves melting the iron, then cooling and milling it
98 More Incidents that Define Process Safety
What Happened.
Figure 3.2-5. Hole in 4-inch piping after the May 27, 2011
incident (courtesy CSB).
3.3.1 Summary
On August 6, 2012, a piping failure of a 20 cm (8 in.) line occurred
at the Chevron Richmond Refinery and subsequently ignited,
causing a large fire. The fire engulfed nineteen operators and
maintenance personnel, but fortunately all escaped.
The smoke plume was visible for miles (Figure 3.3-1). Chevron
initiated a Community Warning System Level 3 alert. At or around
the same time, a shelter-in-place warning for the cities of
Richmond, North Richmond, and San Pablo was issued. A number
of people sought treatment, with most cases involving minor
complaints of nose, throat, or eye irritation, or respiratory issues.
This incident led to a CSB recommendation that the American
Petroleum Institute (API) strengthen the language of API RP 939-
106 More Incidents that Define Process Safety
Key Points
Process Safety Culture – Embrace process safety culture from
the highest levels in the organization down, not from the
bottom up. Otherwise employees will not be sure if
management really believes process safety is important.
Asset Integrity and Reliability – Understand corrosion damage
mechanisms. Make sure that proper metallurgy and inspection
protocols are used to minimize the potential for corrosion.
Emergency Management – Stand clear! There have been
countless instances where people move in close to see the
situation, seemingly unaware of the hazards and risks. Crowd
control, and even positioning of responders, should be clearly
addressed in emergency response plans and drills.
3.3.2 Description
Background. Chevron is a large international company with their
headquarters in San Ramon, California. At the time, Chevron
operated seven refineries, five of which are in the United States.
Chapter 3 Fire Incidents 1 7
Figure 3.3-1. Vapor cloud and ignition seen from Marin County
(courtesy CSB).
Process. The crude oil separation process is the start of the oil-
refining process. Crude oil is heated and separated into several
fractions by distillation (see Figure 3.3-2 for a generic PFD of the
crude oil separation process). At the Richmond refinery, the light
gas oil fraction from the Crude Unit, called the Crude Unit #4
sidecut, was drawn off the column through a 51-centimeter (20-
in.) line, which was then split into a 30-centimeter (12 in.) line and
a 20-centimeter (8-in.) line. The Crude Unit #4 sidecut conditions
were 338°C (640°F) and 3.8 barg (55 psig).
What Happened. Figure 3.3-3, a timeline for the incident, provides
a brief, illustrated summary of the events leading to the release
and fire. The leak was discovered in the Crude Unit #4 sidecut at
3:50 PM (see Figure 3.3-4). The operator who discovered the leak
then notified the head operator and a shift leader. Shortly
afterward, the plant fire department was called to provide
assistance. Approximately 15 minutes after the discovery of the
leak, the fire department took command of the incident and set
up a hot zone of 6 m by 6 m (20 ft. by 20 ft.) around the leak. At
around the same time, the board operator began reducing the
feed rate in the Crude Unit #4 sidecut, per the refinery’s normal
shutdown procedure.
108 More Incidents that Define Process Safety
3.4.1 Summary
On February 16, 2007, an LPG release from cracked piping in the
propane deasphalting (PDA) unit of Valero’s McKee refinery
ignited. The resulting fire burned for about two days. There were
four serious injuries, the entire refinery had to be evacuated,
there was $50 million in property damage, and the refinery was
shut down for two months. This incident illustrates the concept of
“knock-on” effects, i.e., new incidents triggered by the initial
incident. This fire triggered two near-misses, whose
consequences could have been worse with slight changes in
conditions, such as wind direction. The heat from the fire
triggered a release of 1,134 kg (2,500 lb.) of chlorine from three
one-ton cylinders and blistered the paint on a nearby butane
storage sphere (CSB 2008a).
Key Points
Compliance with Standards – Use good practices to prevent
potential failures. When designing equipment to control a
hazard, consider the mechanism and likelihood that the
equipment could fail. If the consequences of failure are
significant, multiple or more robust controls could be warranted.
Hazard Identification and Risk Analysis – Do a good job on
hazard identification. Operator participation is essential, and
alternating revalidation with a complete redo is often a good
idea. If the team fails to consider topics such as facility siting and
dead legs, then those potential hazards will remain unidentified
and uncontrolled.
Management of Change – Understand how changes can impact
existing protection systems. Unmanaged change can introduce
new hazards and render existing protections ineffective. In this
case, an abandoned line from a piping modification was not
reviewed.
116 More Incidents that Define Process Safety
3.4.2 Description
Background. The Valero-McKee Refinery was originally built in
1933 and has been modified over the years. The refinery joined
Valero as part of the Ultramar Diamond Shamrock merger in
2001.
Process. The PDA unit removes paving-grade asphalt from heavy
bottoms from the oil fractionation unit. Liquid propane is the
extraction solvent. The unit operates at about 34.5 bar (500 psi).
The PFD in Figure 3.4-1 illustrates the steps in the process.
What Happened. On the morning of the incident, the temperature
dropped to -14°C (6°F), causing water in a dead-leg to freeze and
subsequently cracking the pipe (Figure 3.4-3). When the
temperature rose in the afternoon, the ice thawed, and the
release of propane vapor began. The estimated release rate was
2,041 kg (4,500 lb.) per hour.
The wind blew the propane vapor cloud toward a boiler, which
was the likely ignition source. The resulting jet fire impacted a
steel support column that had not been fireproofed, causing it to
collapse. This led to further piping failures and releases of
combustible petroleum products, which further fueled the fire.
High winds hindered emergency response efforts to fight the fire.
These factors led to the evacuation of the entire refinery 15
minutes after the fire started, which likely saved lives.
The fire heated three 907 kg (1 ton) chlorine cylinders, causing
the fusible plugs to melt and release about 2,268 kg (2.5 tons) of
chlorine. Chlorine was used as a biocide in cooling towers.
The paint on a nearby 1590 m3 (420,000 gal.) butane storage
sphere blistered due to fire. The heat prevented emergency
responders from accessing nearby fire monitors to protect the
sphere. Fortunately, the wind direction was away from the
sphere, keeping flames from affecting it even more. Figure 3.4-4
shows location of chlorine shed and butane storage tank with
respect to the PDA unit.
The main feeds and fuel gas supply to the refinery were shut
off. Eventually emergency response teams were able to enter the
Chapter 3 Fire Incidents 117
area and shut off other fuel sources, although chlorine and
sulfuric acid leaks hampered this effort. The fire burned for two
days.
Why it Happened. About 15 years before the incident, a process
modification occurred, and the original control station was
abandoned in place. (Figure 3.4-2) This created a dead-leg into
which water and propane could collect (the propane contained
small amounts of water). To compound the problem, a foreign
object had become lodged in the 25 cm (10 in.) gate valve,
preventing it from being fully closed.
3.5.1 Summary
During unloading of a vacuum truck (Figure 3.5-1) into an open
pit, hydrocarbons in basic sediment and water from oil
exploration and production ignited. Two trucks were destroyed,
and the unloading area was seriously damaged. This event is
notable for two things. First, the flammability hazard of the
wastewater was not widely recognized in the recovery business.
This is also not always recognized in the chemical process
industry. Second, auxiliary operations, such as vacuum truck
loading and unloading, can create hazards that need to undergo
a risk analysis like any other potentially hazardous operation.
122 More Incidents that Define Process Safety
Key Points
Compliance with Standards – Don’t forget the basics. Some
standards are very basic, but that does not mean that they are
not important. Workers have a right to know what materials
they are handling. They should have access to SDS’s and
instruction on how to safely handle hazardous materials.
Operating Procedures – Procedures are not just about the
process. Operating procedures should address all aspects that
could present a hazard. Controlling ignition sources is a
fundamental aspect of safe operations. Vehicles are an ignition
source that must be controlled where flammable materials
may be present.
Chapter 3 Fire Incidents 123
3.5.2 Description
Background. The BLSR facility has been in operation since the mid-
1980s. It is permitted by the Texas Railroad Commission to
operate waste injection wells.
Process. The gas stream from an exploration and production (E&P)
operation (Noble Energy in this case) contains solids, water, and
liquid hydrocarbons. This mixture goes through separators that
separate the water and hydrocarbons (as a condensate). The
condensate still contains water and is stored in tanks, where the
water is separated from the hydrocarbons, with the water being
the bottom layer, basic sediment and water (BS&W). The E&P
company sells the top layer to refineries. Two or three times a
week a vacuum truck operated by a waste hauler draws off the
BS&W layer for disposal at an approved site. The vacuum truck
operator conducts the entire operation: identifying the tank,
connecting the truck, drawing off the BS&W layer, and
disconnecting the truck. In this case, T&L Environmental Services
was the truck operator, and BLSR operated the disposal site.
At the BLSR facility, there were separate tanks for collecting
what was considered by the truck driver to be clean fresh water,
saltwater, and condensate. There was also an open
disposal/washout pad. BS&W was usually unloaded at the
disposal/washout pad. This pad (Figure 3.5-2) was a covered, 14.6
m by 19.8 m (48 ft. by 65 ft.) pit with pumps and equipment for
handling drilling mud and viscous materials from E&P and
pipeline operations (Figure 3.5-3). Drivers were supposed to
unload “dirty” water (containing solids such as drilling mud) at the
disposal and washout pad.
What Happened. On the afternoon of January 13, 2003, two
vacuum trucks collected BS&W from the tanks at Noble Energy.
The amount of BS&W was recorded by the operator at Noble
Energy as 7.3 m3 (46 barrels). The vacuum truck driver reported
that 7.9 m3 (50 barrels) were removed.
The trucks backed up to the disposal pit, informed the BLSR
operators the trucks were ready for unloading, and went to a shed
124 More Incidents that Define Process Safety
for drivers, leaving the truck engines running. At the time, the
drilling mud in the pit was being diluted with water using the
hydraulic pumps to recirculate the pit contents. The valves on the
trucks were opened to drain the BS&W. After three to five
minutes, eyewitnesses said that one of the truck engines began
to violently race and that black smoke was blowing from the
exhaust. Backfiring was heard, prompting the truck drivers to
leave the shed and begin running toward the trucks. The second
truck engine also began to race. At that point, ignition occurred,
and there was a deflagration.
There were three fatalities resulting from burns from the
incident (two BLSR employees and a truck driver; one after forty-
six days). Three BLSR employees were also seriously burned.
Figure 3.5-4 shows the damaged trucks and disposal pit area.
Why it Happened. BS&W in the storage tanks always contains some
flammable hydrocarbons. The actual flashpoint of any given
truckload of BS&W depends on how much time the organic and
8. Operating Procedures.
Noble Energy did not have written procedures for loading waste
trucks. Consequently, trucks contained varying amounts of
flammable material, depending on how the waste tanks were
drained. BLSR did not have written procedures for determining
where a waste truck was unloaded, for truck unloading, or for
emergency response. As a result, not only was the truck unloaded
with the engine running but when the truck engine began to
overspeed (a sign that flammable vapors had entered the diesel
engine), employees ran toward the hazard rather than away from
it.
11. Contractor Management.
Noble Energy did not inform the waste hauler contractor of
hazards, nor did they provide them with hazard information in the
form of an SDS. Checking that contractors are qualified to do the
job is also a part of contractor management.
Explosion Incidents
4.1 INTRODUCTION
CCPS defines an explosion as “a release of energy that causes a
pressure discontinuity or blast wave,” NFPA defines it as “the
bursting or rupture of an enclosure or container due to the
development of internal pressure from a deflagration.” There are
two major kinds of explosions: physical and chemical (Figure
4.1.1).
Physical explosions are caused by the release of mechanical
energy. The term “physical explosion” includes vessel ruptures,
BLEVEs, and rapid phase transition. A vessel rupture occurs from
a material defect or from a pressurization that exceeds the
mechanical strength of the vessel. BLEVE is defined by CCPS as “a
type of rapid phase transition in which a liquid contained above
its atmospheric boiling point is rapidly depressurized, causing a
nearly instantaneous transition from liquid to vapor with a
corresponding energy release. A BLEVE of flammable material is
often accompanied by a large aerosol fireball, since an external
fire impinging on the vapor space of a pressure vessel is a
common cause. However, it is not necessary for the liquid to be
flammable in order to have a BLEVE occur”. A rapid phase
transition can occur when a material is exposed to a heat source.
This increases the material’s volume, which increases the
pressure in the container.
Chemical explosions are caused by chemical reactions and
can be uniform or propagating reactions. Uniform reactions occur
throughout the space of the reaction mass, such as a runaway
reaction in a reactor. A propagating reaction, e.g. combustion,
moves through the mass of the reactant, such as in a VCE. A
deflagration occurs when the speed of the reaction front is less
than the speed of sound. A detonation occurs when the speed of
the reaction front is equal to or greater than the speed of sound.
.PSF*ODJEFOUTUIBU%FGJOF1SPDFTT4BGFUZ
By $$14
¥5IF"NFSJDBO*OTUJUVUFPG$IFNJDBM&OHJOFFST
132 More Incidents that Define Process Safety
Propagating
reactions
4.2.1 Summary
A delivery of gasoline (petrol) from a pipeline into a storage tank
in the Buncefield depot began on Sunday morning, December 11,
2005. The level control and shutoff systems in place failed to
operate. The tank overflowed, and gasoline cascaded down the
side of the tank. The Major Incident Investigation Board (MIIB)
reported that up to 272 metric tons (300 tons) of gasoline had
escaped from the tank (MIIB 2008a). About forty-five minutes
after the release started, a series of explosions took place. The
main explosion appears to have been centered on car parking lots
just west of the depot. This explosion was massive and generated
overpressures higher than would have been expected in a normal
VCE. Some have speculated it was a deflagration to detonation
transition (DDT) event.
Forty-three people were injured and about 2,000 were
evacuated from the area. If the incident had happened on a
weekday, it could have resulted in more injuries and even
fatalities. The explosions caused the largest fire in peacetime
Europe, engulfing more than twenty large storage tanks over a
large part of the Buncefield depot. The fire burned for five days,
destroying most of the depot (Figure 4.2-1). In addition to
destroying large parts of the depot, there was widespread
damage to surrounding property and disruption to local
communities. Houses close to the depot were destroyed, and
others suffered severe structural damage. Buildings as far as 8 km
(5 miles) from the depot suffered damage such as broken
windows and damaged walls and ceilings. The MIIB estimated the
cost of the incident was £1 billion (about $1.35 billion as of mid-
2017).
136 More Incidents that Define Process Safety
Key Points
Process Safety Culture – Do not “live with” frequent instrument
failures. A good process safety culture investigates to find out
what is causing the failures and addresses the problem. Thus,
the barrier against a process safety incident remains healthy.
Chapter 4 Explosion Incidents 137
4.2.2 Description
Background. The Buncefield depot is a large tank farm near Hemel
Hempstead in Britain. The Buncefield depot was constructed in
1968. At the time of the incident, there were three sites at the
depot operated by Hertfordshire Oil Storage (a joint venture
between Total and Chevron), British Pipeline Agency (a joint
venture between Shell and BP), and BP.
Process. The Buncefield depot, or tank farm, was a large site that
stored gasoline, heating oil, and aviation fuel in over twenty-five
storage tanks (Figure 4.2-2). The fuels were received via two 0.25
m (10 in.) and one 0.36 m (14 in.) pipelines. Gasoline and heating
oil from the tanks were offloaded into trucks for delivery, and the
jet fuel was sent out by pipeline. The depot was about 4.8 km (3
mi) away from the center of the nearest town, Hemel Hempstead.
The storage tank involved was Tank 912. Tank 912 was a 6,000 m3
(1.6 million gal.) floating roof tank with an automatic tank gauging
(ATG) system that was monitored in the control room.
From the control room, operators could operate the
appropriate valves to shut off and/or divert flow from Tank 912 to
other tanks. The high and high-high level alarms could be
set/changed by the supervisors. Tank 912 also had an
independent high-level switch (IHLS) that would stop the incoming
flow at a high-high level by closing the inlet valves and provide an
audible and visual alarm in the control room.
What Happened. The tank started receiving gasoline containing
10% isobutene at a rate of about 550 m3/hr (145,294 gal/hr).
around 7:00 p.m. on Saturday evening. At 3:00 a.m. on Sunday,
138 More Incidents that Define Process Safety
the tank was about 2/3 full, but the level gauge stopped recording
any further increase in level despite filling continuing. The
independent high-level switch (IHLS) shutdown also failed to stop
flows to the tank. At about 5:20 a.m. the tank began to overflow
and flow into the tank continued, even increasing in rate to about
890 m3/hr. (235,113 gal/hr.).
As fuel continued to overflow from Tank 912, a vapor cloud up
to 2 m (6.6 ft.) tall, and covering an area of about 500 by 350 m
(1640 by 1148 ft.) formed, engulfing a large portion of the facility
(Figure 4.2-3) (HSE 2017). The first explosion occurred at 6:01 a.m.
Initially, the ignition source was hard to determine. Candidates
included a pump house, heaters in the emergency generator
building, and car engines (witnesses stated their cars began to run
erratically, (i.e. surging due to drawing in fugitive gasoline vapors).
Subsequent analysis (see below) has settled on the pump house
as the initial site of ignition. Further explosions occurred,
eventually engulfing the entire facility in fire.
Why it happened. The IHLS did not function because a test lever
for the switch had not been locked in the neutral position. The
lever enabled testing of the high-level and low-level function of
the IHLS. Failure to lock the lever in the middle position allowed it
to slip into the low-level test position, thereby disabling the high-
level function.
Experts were surprised by the severity of the damage
resulting from the explosion given the low level of congestion at
the site. The extent of the damage led experts to conclude that a
DDT occurred. This conclusion led to recommendations to
conduct further study of DDT mechanisms.
140 More Incidents that Define Process Safety
Figure 4.2-4. Breakup of liquid into drops spilling from tank top
(adapted from HSE).
Strong ignition source. The pump house was located near Tank 912
and was completely engulfed by the vapor cloud. The ignition
source in the pump house led to an explosion inside the pump
house. This explosion created a strong ignition source that also
created turbulence around the pump house, leading to a strong
external explosion and the DDT.
Congestion due to vegetation. There were hedgerows near the
pump house that served as obstruction and congestion in the
vapor cloud. Also, there was a tree-lined street next to the facility
that caused further acceleration of the flame front and led to
detonation. It came as a surprise to investigators that vegetation
could do this, in effect acting similarly to a pipe rack.
Note on detonations. The report, Review of vapour cloud explosion
incidents (HSE, 2017), has challenged the conclusion that the
Buncefield explosion, and several others, was a detonation, based
on the nature of some of the physical damage at the explosion
sites. It hypothesizes that there can be a mechanism in between
a VCE and a detonation, and the HSE has called for further
investigation of this phenomenon. Interested readers can obtain
and read the HSE report. For brevity, this book will continue to
refer to the Buncefield and Jaipur explosions as detonations. The
important thing to remember is that with these types of events,
the potential damage may be much worse than the commonly
used consequence models might indicate.
8. Operating Procedures.
The operating procedures were inadequate. They were not
detailed enough (e.g., no safe operating limits were included), and
the supervisors on each shift used the available level alarms
differently.
10. Asset Integrity and Reliability.
The IHLS failed to close the inlet valve because the test lever was
not secured. It is imperative that safety-critical devices such as this
switch be tested on a regular basis and also that they be placed
back into service properly. The staff did not have procedures for
putting the switch back into operation.
This incident led the HSE to issue an alert on how to test the
switch. The MIIB recommended that these storage sites improve
their maintenance systems and conduct regular proof testing.
13. Management of Change.
In 2002 there was a large increase in throughput to the facility
when an adjacent facility was shut down. There was no MOC done
to check if the control systems and staffing levels were adequate
to handle the increased throughput. The IHLS was installed in
2004. Its design allowed the failure to occur. The failure mode
could have been eliminated if an MOC review had been
performed when the switch was installed.
Key Points
Process Safety Culture – Make commercial plans with
operational safety in mind. The plant had a contractual
obligation to fill tanks according to a schedule determined by a
planning department. A good process safety culture ensures
that production needs do not compromise safety.
Asset Integrity and Reliability – Maintain the integrity of
equipment that serves in the prevention or mitigation of
process safety incidents. In this case, on-line monitoring was
unreliable because transmitters were frequently out of service.
Emergency Management – Plan and train with local emergency
responders. In this case, training of personnel to fight fires
involving multiple tanks was inadequate. Coordination with
local firefighters and emergency responders is essential to
ensure that both the plans and the execution of the plans are
sufficient for incidents.
Chapter 4 Explosion Incidents 145
4.3.1 Summary
On October 29, 2009, an explosion occurred at the Petroleum Oil
Lubricants Terminal at Sanganer in Jaipur, India. The explosion
was caused by an unabated release of mineral spirits (petrol) from
a valve which had continued for over an hour. There were eleven
fatalities, six on site and five off-site. The facility was destroyed as
the fire spread to every tank at the terminal. The fire burned for
eleven days because the decision was made to allow the fire to
burn itself out rather than to risk additional lives fighting it.
Damages were estimated at RS 280 crore ($44 million). Figures
4.3-1 and 4.3-2 show before and after pictures of the terminal,
and Figure 4.3-3 shows some of the burning storage tanks. There
is evidence (Johnson, 2012) that this explosion also transitioned
to a detonation, similar to the Buncefield explosion (Section 4.2).
The incident resulted in recommendations for legislation for land
use around hazardous installations and reviewing all major
146 More Incidents that Define Process Safety
Key Points
Conduct of Operations – Equipment should be designed to
prevent loss of containment (LOC) or adequate layers of
protection should be installed to reduce the likelihood of LOC.
Tank levels are continually changing, thus there are many
opportunities for the level to be exceeded if there are not
sufficient layers of protection in place.
4.3.2 Description
Background. The Indian Oil Company operated a large oil terminal
near Jaipur, India. The pipelines division was located in the
northwest corner of the site.
Process. The Indian Oil Corporation terminal received and
transferred petrochemicals. In this event, the intent was to
transfer gasoline from a storage tank in the terminal to another
facility.
What Happened. A pipeline from a gasoline storage tank was being
lined up for transfer to another site (Figure 4.3-4). The procedure
was to ensure the MOV and HOV were closed, reverse the position
of the Hamer blind valve, open the HOV, and open the MOV
gradually (to be sure there was no leakage from the Hamer blind
valve). It is believed the MOV was opened first, and then the
Hamer blind valve was opened. The leak began as soon as the
Hamer blind valve was opened.
The fumes from the leak overwhelmed the operator. A nearby
shift officer saw the incapacitated line operator and tried to help,
but he was also overcome by the fumes. A second operator came
over to help, and he was also overwhelmed by the fumes. Thus,
the leak was able to go on for about 75 minutes and released
about 1,000 metric tons (1102 tons)
a known hazard, i.e., a line being opened while not isolated from
the storage tank. Safeguards, such as a remote shutoff valve, an
interlock to prevent changing position unless the MOV and HOV
were closed, and LEL detectors, could be part of the design.
The immediate cause of this incident was not following the
standard operating procedures. Although operating discipline is
important, alternative designs that eliminate the leak point would
be inherently safer. In the hierarchy of controls, eliminating the
hazard through inherently safer design is most effective,
engineering controls are next, and finally, administrative controls.
Chapter 4 Explosion Incidents 151
4.4.1 Summary
An explosion occurred in a reactor at the Celanese Pampa, Texas,
plant on November 14, 1987 that led to a release and vapor cloud
explosion. There were three fatalities and thirty-nine injuries.
Extensive property damage occurred in the immediate area, and
severe damage occurred throughout the plant. The firehouse that
contained the fire trucks was damaged so the trucks could not be
driven out. Fid firefighting equipment was also damaged, making
it more difficult to control the fires. Figures 4.4-1 and 4.4-2 show
the extent of the damage caused by the explosions (J. Forest,
personal communication, July 2016).
As a result of the learnings from this incident, Celanese
implemented a comprehensive twenty-one-element process
safety program similar to the twenty elements of the CCPS RBPS
program.
152 More Incidents that Define Process Safety
Key Points
Process Safety Competency – Humans are an important part of
the system. Understand human factors. Designing operations
to help a human succeed can help to avoid process safety
incidents.
Hazard Identification and Risk Analysis – Hazard identification
methods should include human failures just as they do
equipment failures. When a single human action may cause
significant undesired consequences, there is a risk that
warrants management.
4.4.2 Description
Background. The Celanese plant was built in 1952 and produced
acetic acid.
Process. The unit involved was a liquid phase oxidation (LPO)
reactor in which butane was oxidized in the presence of air and a
catalyst to make acetic acid and byproducts. This was an
exothermic reaction. The reactor product was sent to several
downstream units in the Pampa plant to make products that
included acetic acid, acetic anhydride, and methyl ethyl ketone.
The reactor operated at a relatively high temperature and
pressure. Figure 4.4-3 is a schematic of the reactor.
154 More Incidents that Define Process Safety
the reactor with inert gas. Shutting off the air and purging with
inert gas were essential to ensure the reactor atmosphere was
not flammable and to prevent backflow of the reaction mixture
into the air line. There were three ways to shut down the reactor:
A shutdown system designed to automatically shut down
if safe limits were exceeded;
A manual button that activated the shutdown system;
Three manual buttons: one button to activate the double
block, another to activate the bleed, and a third to activate
the purge.
On the day of the incident, the operator chose to shut down
the reactor using the three manual buttons on the control panel.
The activation of these three buttons was equivalent to the
activation of the manual shutdown button or the automatic
shutdown. The first step was to close the process air valves to the
reactor. The second step was to open the air bleed after the air to
the reactor was blocked in. The third step was to activate the
timed nitrogen purge.
The operator pushed the first two buttons but mistakenly did
not push the inert gas purge button. The standard operating
procedure for this critical step was not followed by the operator.
Failure to initiate the inert gas purge allowed the contents of the
reactors, including the catalyst, to enter the air sparger system.
Personnel did not realize that the chemicals were in the air
sparger pipe. Some of the reactor contents remained in the pipe
for about a day.
As the reactor was started upon November 14th and
approached start-up temperature, an explosion occurred in the
air sparger inside the reactor. Oxygen was available because the
reactor had not been purged, fuel was available from the reactor
contents, and the ignition source was probably the catalyst that
was plated on the inside of the air sparger.
156 More Incidents that Define Process Safety
4.5.1 Summary
On June 13, 2013, a reboiler on a fractionation tower in the
Williams Geismar Olefins plant ruptured due to the expansion of
liquid propane in the heat exchanger, which had been isolated
from its pressure relief valve. The released propane ignited,
resulting in a large fireball (Figure 4.4-1). There were two fatalities,
and 167 people were injured. The plant was down for eighteen
months (CSB 2013). The business interruption and repair costs
were $343M (insured) plus $73M (uninsured) (ICIS 2013). Williams
paid $34 million as a result of lawsuits from the incident.
(LexisNexis 2016).
Key Points
Management of Change – Conduct a safety review appropriate
to the hazards before a change is made.
Operating Procedures – Procedures need to be written for all
phases of an operation, including switching to a spare piece of
equipment.
Asset Integrity and Reliability - Fouling of reboilers is a
common occurrence. Establish a cleaning schedule for heat
exchangers so they can be cleaned at an appropriate time,
without disruption to the process.
4.5.2 Description
Background. The Williams Companies owns natural gas interests,
pipelines, and processing facilities in North America. The Geismar
Olefins plant was built in 1967. It was bought by Williams in 1999.
At the time the incident, it was operated by Williams Olefins and
jointly owned by Williams Olefins and Saudi Basic Industries
Corporation (SABIC).
Chapter 4 Explosion Incidents 159
The tower was driven by two external reboilers. Hot quench water
at 85°C (185°F) on the tube side of the heat exchanger vaporized
the propane mixture (95% propane, balance propylene, and C4s)
on the shell side. The original design intent was to operate with
both reboilers. In 2001, valves were installed to enable operation
with only one reboiler. The other reboiler was set up as a spare to
allow one reboiler to be cleaned without having to shut down the
unit (Figure 4.5-2).
What Happened. On the day of the incident, Reboiler A was in
operation and Reboiler B was the spare. Flow to Reboiler A
dropped, possibly due to fouling. Quench water was likely opened
to Reboiler B. Three minutes after the quench water was started
to Reboiler B, it exploded (Figure 4.5-3), ignited, and caused a
fireball.
8. Operating Procedures.
The plant did not have an operating procedure for putting the
reboiler into service, even though it would have been an expected
operation. Instead, the plant relied upon a generic SOP for
reboiler restart. A procedure specific to these reboilers could have
included a check on the position of the valves before restart and
the proper sequence to be followed in opening the process side
valves before introducing hot quench water. Note that the generic
reboiler procedure assumed the process to be on the tube side,
whereas these particular propylene reboilers had the process on
the shell side.
10. Asset Integrity and Reliability.
Fouling of the reboilers was a known issue, and it is a common
situation in industry that exchangers and reboilers require
maintenance at a higher frequency than the rest of the unit.
Where block valves are provided for safe isolation of equipment,
they should never isolate a pressure vessel from its pressure relief
device.
13. Management of Change.
The MOC review was done after the valves were installed. When
it was done, the hazard of isolating the reboilers from the PRV was
not identified, and a PHA of the change was not required.
15. Conduct of Operations.
There are several examples of poor conduct of operations.
Plant personnel used checklists to perform both the MOC
review and the pre-start-up safety review (PSSR). The checklists
contained questions about whether any valves needed to be car-
sealed open (Figure 4.5-4), if operating procedures needed to be
updated, or whether any operator training was needed. These
were answered “no”. There was a question that asked “PRVs lined
up and block valves car-sealed open? Pressure release systems in
Chapter 4 Explosion Incidents 163
4.6.1 Summary
A large primary dust explosion, followed by a series of secondary
dust explosions, occurred at the Imperial Sugar refinery in Port
Wentworth, Georgia in February 2008. The consequences
included fourteen fatalities and thirty-six injuries. The explosions
destroyed the facility (Figure 4.6-1). Imperial Sugar settled with
OSHA on a $6 million fine. This incident provides important
lessons in understanding the hazards created when combustible
dust is released outside of the process equipment into a building
or structure.
The explosions at Imperial Sugar turned national attention to
the hazards of combustible dust in the chemical and agricultural
industries. It also triggered the U.S. OSHA National Emphasis
Program (NEP) for solids-handling facilities. A NEP is a program by
166 More Incidents that Define Process Safety
Key Points
Process Safety Competency – Apply what you know. Knowledge
alone is not enough. You must apply what you know about safe
handling of material hazards.
4.6.2 Description
Background. Imperial Sugar Company purchased the Port
Wentworth facility in 1997. The facility refined raw sugar into
granulated sugar and sugar products.
Process. The sugar refinery was housed inside a four-story
building, with the silos extending from the ground to above the
top floor (Figure 4.6-2). In this process, raw cane sugar was
converted into granulated and powdered sugar. The refinery had
dozens of belt conveyors, screw conveyors, bucket elevators,
mills, as well as packaging equipment. Granulated sugar was
stored in three large 374 m3 (13,200 ft3) silos. From the silos,
granulated sugar was conveyed to the powdered sugar mills, to
packaging equipment, to specialty sugar production, or to the
bulk sugar building. At the powdered sugar process, belt
conveyors and bucket elevators conveyed the granulated sugar to
the powdered sugar mills. In 2007, steel panel enclosures were
installed on the horizontal belt conveyors to protect the sugar
from contamination.
What Happened. The first explosion likely occurred in a belt
conveyor located underneath the silos. The ignition source may
have been an overheated bearing or belt support. The belt
enclosure allowed the formation of dust clouds above the
Minimum Explosion Concentration (MEC) of the sugar dust in the
interior of the silo tunnel, providing fuel for the explosion.
The pressure wave from the initial explosion spread
throughout the building, dislodging sugar dust that had
accumulated in various parts of the building due to leaks from the
sugar processing equipment. The dislodged dust ignited and
created fireballs, resulting in several secondary explosions
throughout the building. These explosions were powerful enough
to buckle the concrete floors and create flying debris. The
explosions continued for fifteen minutes after the initial
explosion. The CSB report notes that secondary explosions
occurred on all four floors of the building. (See Figures 4.6-1 and
4.6-3)
Chapter 4 Explosion Incidents 169
Figure 4.6-4. Motor cooling fins and fan guard covered with
sugar dust; large piles of sugar cover the floor (courtesy CSB).
Chapter 4 Explosion Incidents 171
4.7.1 Summary
On October 29, 2003, a dust explosion occurred in a dust
collection system at an aluminum wheel manufacturing plant in
Huntingdon, Indiana (CSB 2005). The explosion propagated into
other equipment and into the manufacturing building. One
174 More Incidents that Define Process Safety
person, who was engulfed in flames, died from burns, and a total
of six people were injured, two critically. This was one of three
explosions that occurred in 2003. The other two, an explosion at
West Pharmaceuticals in North Carolina, and CTA Acoustics in
Kentucky were described in Incidents that Define Process Safety
(CCPS 2008). These explosions led the CSB to conduct a study of
the phenomenon of dust explosions. The resulting report,
Combustible Dust Hazard Study (CSB 2006) included
recommendations for the NFPA to create a combustible dust
standard and for U.S. OSHA to conduct a National Emphasis
Program (NEP) on combustible dust hazards. These
recommendations were implemented. The NFPA standard is
NFPA 652–Standard on the Fundamentals of Combustible Dust
(NFPA 2016).
Key Points
Process Knowledge Management–Understand your process, its
hazards, and how to manage them. Regardless of whether you
built or designed it, you cannot ignore this responsibility.
Incident Investigation–Maintain a chronic sense of unease.
Normalization of deviance is very dangerous. When near-
misses become part of normal operations, you have a problem.
Find out why these near-misses are happening and take action
to prevent a bigger incident.
4.7.2 Description
Background. Hayes Lemmerz International owns a number of
companies, including Hayes Lemmerz International–Huntington,
that manufacture cast aluminum alloy wheels.
Process. The plant manufactures aluminum automotive wheels.
Scrap aluminum from the machining of the wheels creates
aluminum chips. These chips are recovered using a process
designed by Premelt Systems Inc. who has built more than fifty
such systems.
Chapter 4 Explosion Incidents 175
The scrap aluminum is coated with oil and water from the
machining process. It is collected and chopped into chips about
6.4 mm (0.25 in.) long. The chips are centrifuged, dried to remove
the oil and water, collected in a hopper, and further dried in a
rotary kiln. The chips have some small particles attached by the
oil and water. Drying in the kiln detaches these particles and
creates more by breaking down some of the chips. From this point
on the process stream contains some amount of combustible
dust.
The chips and dust are air conveyed through a 15.2 cm (6 in.)
duct to a cyclone, where the solids drop to a reverberating
furnace. The air and fine dust stream go to a dust collection
system. Figure 4.7-1 shows the cyclone, furnace, and exhaust
stream. The aluminum chips are melted in the vortex box, where
a pump is used to create a vortex with the molten aluminum. This
provides better mixing of the chips into the molten aluminum. At
Hayes Lemmerz, this part of the system was located indoors.
The top outlet of the chip feed cyclone goes through a spark
box, then outside of the building into a drop box and a dust
collector (see Figure 4.7-2). Note the presence of a slide gate valve;
more will be said about that later. The spark box had a baffle plate
to remove large embers or heavy objects, the drop box provided
a place for heavy particles to drop out of the air stream, and the
dust collector trapped the fines. The dust collector had pleated
filter cartridges which were air-pulsed to dislodge accumulate
dust, and it was equipped with explosion vents. This system was
installed three years after the rest of the chip melt system. The
original design had the air stream discharged directly into the
building; however, dust accumulation from the chip cyclone
exhaust led the company to install the dust collection system. The
design and construction were handled by Premelt Systems Inc.
Other plants using the chip melt process apparently did not have
this problem (the CSB contacted one other plant that confirmed
this).
What Happened. On the day of the incident, operators noticed the
duct connecting the fume hood to the fume separator was
glowing red due to a fire inside it. They shut down the chip feed
176 More Incidents that Define Process Safety
system and allowed the fire to burn out; this was the usual
response to this event, which had happened before. After the fire
stopped, they cleaned the system, waited at least two hours, and
then restarted the feed system. About ten minutes later, an
employee noticed chips falling out of the spark box, indicating
that a crust had formed on the vortex and chips were overflowing
into the dust collection system duct. Immediately after this, a
fireball came out of the furnace, totally engulfing one employee.
As the fireball grew, a contractor on the building roof heard a
boom and was knocked down. As he fell, he witnessed the roof
panels being blown off. Another contractor, who had been
working inside a trailer near the drop box, was also knocked down
by the boom. When he looked out, he saw the dust collector was
on fire. He tried to exit the trailer by a rear door, but it was
blocked, so he exited out a side door. A plant alarm was sounded,
and the plant evacuated. The Huntington fire chief knew the plant
handled molten aluminum, and the responders thus used the
appropriate means, Class D fire extinguishers, to put out the fires.
Figure 4.7-3. Dust collector and drop box remains after the
explosion (courtesy CSB).
Why it Happened.
The chip melt and dust collection systems were not the main part
of the business. The engineers at Hayes Lemmerz admitted they
did not have the knowledge to understand the chip melt and dust
collection systems. Neither management nor employees knew of
the hazards of accumulated dust; the housekeeping program was
not adequate for the situation; housekeeping was frequently
done improperly, e.g. using compressed air to clean dust deposits
(a hazardous practice that creates a flammable dust cloud); and
the fugitive dust collection equipment was not properly
maintained.
8. Operating Procedures.
The procedures did not include proper response to upset or non-
routine situations. There were no written emergency procedures.
10. Asset Integrity and Reliability.
The dust collection system was inadequate and poorly
maintained. Dust accumulations resulted in the secondary
explosions that destroyed the entire building and led to the
fatality.
182 More Incidents that Define Process Safety
4.8.1 Summary
On June 3, 2008, a 0.3 m (12 in.) natural gas line ruptured due to
external corrosion. The released material exploded and caused
another 0.3 m (12 in.) gas line that was about a 0.3 m (1 ft) away
to rupture. About an hour later, a 41 cm (16 in.), a 15 cm (6 in.)
Chapter 4 Explosion Incidents 183
and two 10 cm (4 in.) gas lines ruptured (Figure 4.8-1). The result
was nearly A$60 million (about US$46 million) in plant damages.
Western Australia lost its gas supply for two months, causing an
A$3 billion (US $2.3 billion) loss to its economy. The plant took
more than one year to return to full production. The incident led
to the identification of weaknesses in the regulatory and
standards regimes.
Key Points
Process Safety Culture – The operating company believed this
event was unforeseeable. Just because it hasn’t happened in
your memory, does not mean it is inconceivable.
Process Safety Competency – The operating company relied on
contractors to supplement staffing in safety technical positions.
All tasks and skills, especially those managing the facility risks,
must be addressed, whether through a company or contracted
staff.
Asset Integrity and Reliability – Keep it in the pipe. Use good
practices and diligently conduct pipeline inspections.
4.8.2 Description
Background. Varanus Island was operated by a subsidiary of
Apache Corporation. Apache was also the majority shareholder.
Process. Hydrocarbons were piped to the Varanus Island gas
production facility, run by Apache Energy, from offshore facilities.
After separation and purification, natural gas was piped to
Western Australia in 0.3 m (12 in.) and 0.4 m (16 in.) undersea
sales gas pipelines (SGL). Crude oil was shipped out by tankers. A
total of six pipelines came into and out of the production facility
at a beach on the north-northeast side of the island.
What Happened. The 0.3 m (12 in.) SGL ruptured at a section
between low and high tide on the beach. The cause of the rupture
184 More Incidents that Define Process Safety
Figure 4.8-2. Ruptured 12” sales gas line (courtesy Bills and
Agostini).
4.9.1 Summary
Two natural gas explosions, at ConAgra Foods in North Carolina
and Kleen Energy in Connecticut, occurred within eight months of
each other, with ten fatalities and more than 100 injuries. One led
to the release of about 8,165 kg (18,000 lb) of ammonia to the
surrounding environment. Both caused extensive physical
damage to buildings. Both were caused when new gas lines
containing air used to pressure test the line were purged with
natural gas. The purge discharged into confined areas with no
monitoring, no control of ignition sources, and no access control
to minimize the number of people exposed to the hazard. During
their investigation of these incidents, the CSB found at least four
other similar incidents of this nature (CSB 2009c, CSB 2010).
Gas purging was a common practice in the industry. These
incidents led the International Code Council (ICC) and its
members to revise the International Fire Code (IFC) and the
International Fuel Gas Code (IFGC) to prohibit the practice of gas
purging and to comply with requirements of NFPA 56 – Standard
for Fire and Explosion Prevention During Cleaning and Purging of
Flammable Gas Piping Systems.
Key Points
Process Safety Competency – Do not accept a hazardous
practice as normal. A good understanding of process safety
would identify this hazard and seek safer alternatives.
Safe Work Practices – Give careful thought to potential hazards
when completing a work permit. Is the scale of the hazard
understood? Are the controls specified in the permit sufficient
to control the hazard? In this case, hot work permits were either
not used or inadequate for the scale of the predictable natural
gas release.
190 More Incidents that Define Process Safety
4.9.2 Description
What Happened.
4.10.1 Summary
An explosion occurred in a crude olive oil storage tank in Spoleto,
Italy, while workers were welding above the tank. Crude olive oil
contains up to 5% hexane from a solvent extraction process. The
explosion released the contents of the tank, which caught fire.
About an hour later, the fire caused explosions in two other crude
olive oil storage tanks. The resulting fire damaged the entire tank
farm (Figures 4.10-1 and 4.10-2) and the explosion propelled the
two tanks about 60–90 m (196–295 ft). There were four fatalities
(Marmo, et al. 2013).
Chapter 4 Explosion Incidents 195
Key Points
Process Safety Knowledge–Understand the hazards of the
materials you handle. They may not be as harmless as they
seem. The material involved (crude olive oil) in this case was not
considered to be flammable despite the presence of residual
hexane.
Hazard Identification and Risk Analysis—Identify hazards so
that you can then protect against them. Since the crude olive
oil material in this case was not considered flammable, there
was no HIRA conducted. This led to inadequate tank design,
inadequate SWP, and weak Emergency Management.
4.10.2 Description
Background. A number of oil refineries in this region of Italy
process olive oil.
Process. The refinery produced edible olive oil from crude pomace
olive oil. Pomace olive oil is obtained by extracting residual oil
from pressed olives using hexane (the oil obtained from the
pressing is virgin olive oil). The pomace olive oil was received from
multiple suppliers and contained varying amounts of hexane. At
the facility, hexane was removed by either chemical or physical
processes. Then it was deodorized by a low-pressure, high-
temperature stripping step. The facility also made soaps from
inedible oil.
Hexane is a flammable material with a flash point of -26°C (-
14.8°F). The flash point of mid isohexane isomers is -18°C (-0.4°F).
Crude olive oil can contain up to 5 wt.% hexane.
Various grades of olive oil were stored in atmospheric tanks
in a tank farm. Figure 4.10-3 is a schematic of the tank farm layout.
Tanks 93–107 were 645 m3 (170,390 gal) each and were located
Chapter 4 Explosion Incidents 197
outdoors. Tanks 77–88 were 365 m3 (96,423 gal) each and were
located indoors. The tanks contained various grades of olive oil:
Tanks 86, 93, 94, 95 and 103—pomace olive oil
Tanks 87. 89, 96 and 100—refined oil
Tanks 81-85, and 87—virgin oil
Tanks 101, 102, and 104–107—lampante oil (an inedible
grade of oil)
What Happened. On the day of the incident, Tank 95 was less than
10% full, Tank 93 was about 25% full, and Tank 94 was about 50%
full. Four contractors were welding supports to the top of Tank 95
for a footbridge to cover tanks 93–96. Ignition occurred in Tank
95, lifting the tank about 10 m (33 ft) into the air and killing the
four contractors. The tank fell back near its original position and
its contents were released and caught fire. The fire engulfed tanks
93 and 94, and their contents ignited after about an hour. The
explosion lifted these two tanks off their pads, and they landed
60–80 m (197–262 ft) away. Tank 93 landed on the roof of the
finished product warehouse and tank 94 landed near the
byproducts warehouse.
Why it Happened. Samples from Tank 95 were available from the
plant’s lab and had been tested for hexane level and flashpoint.
The tank contained about 1.5 wt.% hexane and had a flashpoint
of 29°C (84°F). Two mechanisms were identified for the tank
headspace to accumulate sufficient hexane to ignite: During the
day, the tank’s surfaces were heated above 30°C (86 °F) by the sun.
In addition, the tanks were purged with air in order to mix
different batches of oil. This likely entrained hexane into the vapor
space. During the night, hexane vapors condensed on the internal
surfaces of the headspace. The hot tank skin temperature and
purging with air enabled the headspace of the tanks to become
enriched with hexane. With a flammable mixture in the
headspace, welding provided a strong ignition source in Tank 95,
and the resultant external fire around Tanks 93 and 94 generated
temperatures high enough to ignite their headspaces.
198 More Incidents that Define Process Safety
4.11.1 Summary
On December 7, 2009, a 2,068 bar (30,000 psi) pressure vessel
ruptured during a crystal growing process, likely due to a
combination of stress corrosion cracking (SCC) and temper
embrittlement. SCC is the formation of cracks through the
200 More Incidents that Define Process Safety
Key Points
Process Safety Culture. Listen to the advice of others. Try to
understand their concerns. You might learn something and
prevent an incident. This company also chose to continue
operations after being warned by its insurer not to do so.
Compliance with Standards. Standards exist for a reason.
Comply with them. In this case, the original vessel did not
comply with the appropriate ASME standard. This company was
able to get a waiver but then did not comply with the
requirements of the waiver. They also violated the ASME
standard by welding cracks in one of the vessels. With a waiver
comes with the responsibility to comply with it.
Incident Investigation. Recommendations are a gift.
Understand their intent, take action, and verify that the
hazard was addressed. NDK management did not implement
the findings of an incident investigation, despite strong
recommendations from an outside consultant and its insurer.
Chapter 4 Explosion Incidents 201
4.11.2 Description
Background. Nihon Dempa Kogyo (NDK) Co. was founded in Japan
and produces synthetic crystal products. The Belvidere, Illinois,
facility began operation in 2003.
Process. NDK’s facility consisted of six large-pressure vessels. The
process was operated in vessels with walls that were 20.5 cm (8.1
in.) thick. The top was 46.3 cm (18.25 in.) thick and the bottom
41.3 cm (16.25 in.) (Figure 4.11-2). The vessels had an MAWP of
2,068 bar (30,000 psi) and maximum operating temperature of
399°C (750°F). The six vessels were supposed to be constructed to
meet the ASME Boiler and Pressure Vessel Code using SA-723
Grade 2 steel. However, the fabricator could not certify that the
202 More Incidents that Define Process Safety
first three vessels vessel were compliant with the ASME code for
the type of steel used. They were able to certify the next three.
NDK petitioned the Illinois Boiler and Pressure Vessel Safety
Division for permission to use the three uncertified vessels
because they were acceptable at the operating temperature of
371°C (700°F). After a review by an independent third party, the
state approved the vessels. The vessel designer recommended
that annual inspections be done after the approval was granted.
NDK relied on a protective coating created by the formation of an
acmite layer (sodium iron silicate) during the process to prevent
SCC.
The process itself was simple, akin to making dinner in a
pressure cooker. Mined quartz crystals were inserted into the
vessel, 3 m3 (800 gal) of 4% sodium hydroxide and a small amount
of lithium nitrate was added, and then a rack of seed crystals was
suspended at the top of the vessel. The vessel was sealed and
heated to 371°C (700°F) with electric heaters. The mined crystals
dissolved in the solution and pure quartz crystals formed on the
seeds. A typical batch processed for 120–150 days, at which point
the vessel was allowed to return to ambient temperature, the
pure crystals were removed, and the caustic solution transferred
to a holding tank.
What Happened. The vessel in question, Vessel 2, was operating at
2,000 bar (29,000 psi) and 120 days into the 150-day cycle when it
ruptured. The consequences are described in the Summary.
Why it Happened. Examination of vessel fragments revealed cracks
in the metal that were likely caused by SCC from exposure to
caustic. Traces of impurities from the mined quartz (silicon,
aluminum, titanium, sulfur and chloride) were found in the cracks.
Impact tests showed the fragments had up to 50% lower strength
than had been observed in the original tests. Investigators
concluded, that the acmite coating did not provide adequate
protection against SCC.
Chapter 4 Explosion Incidents 203
.PSF*ODJEFOUTUIBU%FGJOF1SPDFTT4BGFUZ
By $$14
¥5IF"NFSJDBO*OTUJUVUFPG$IFNJDBM&OHJOFFST
210 More Incidents that Define Process Safety
5.2.1 Summary
Most of the information in this section was published in a report
by the Bureau of Ocean Energy Management Regulation and
Enforcement (BOEMRE 2011), the BP report (BP 2010), the CSB
reports (CSB 2014a, b, c, and d), and the Transocean report (TO
2011).
At approximately 9:50 p.m. on the evening of April 20, 2010,
an undetected influx of hydrocarbons escalated to a blowout on
the Deepwater Horizon rig at the Macondo Well. A cement barrier
was set in the process of temporarily abandoning the well for
future production. Tests of the cement barrier integrity were
misinterpreted, and the cement barrier failed, allowing
hydrocarbons to flow up the wellbore, through the riser and onto
the rig, resulting in the blowout. Shortly after the blowout,
hydrocarbons that had flowed onto the rig floor through a mud-
gas vent line ignited. Flowing hydrocarbons fueled a fire on the rig
that continued to burn until the rig sank on April 22 (Figure 5.2-1).
Eleven people died, and seventeen were seriously injured.
Over the next 87 days, an estimated five million barrels of oil were
discharged from the Macondo Well into the Gulf of Mexico
(BOEMRE 2011). This was one of the worst environmental
incidents in US history. The aftermath of the incident was
devastating on the Gulf Coast region economy, and studies of the
environmental impact continue to this day. BP, Transocean, and
Chapter 5 Environmental and Toxic Release Incidents 211
MOEX Offshore LLC (10% owner of the well) agreed to pay the
following fines (DOJ, 2015):
$5.5 billion as a Clean Water Act penalty, 80% of which
goes to restoration efforts (BP)
$8.1 billion for natural resource damages (BP)
$600 million for other claims (BP)
$4 billion in criminal fines (BP)
$90 million for violations of the Clean Water Act (MOEX)
$400 million as a Clean Water Act penalty (Transocean
Deepwater Inc.)
At the time, Mineral Management Service (MMS) managed
both the revenue management and safety and environmental
protection. The incident prompted a reorganization for offshore
drilling regulations; the creation of the Office of Natural
Resources Revenues (ONRR), responsible for the revenue
function; the BOEMRE, responsible for resource planning and
leasing; and the Bureau of Safety and Environmental Enforcement
(BSEE), responsible for safety and environmental protection (CSB
2014).
Key Points
Process Safety Culture – The way we do things around here.
What is that ‘way’ and where is ‘here’? Understanding what the
culture actually is ‘on the shop floor’ and if it is consistent across
a company may identify opportunities for improvement.
Asset Integrity and Reliability – Is that last line of defense truly
a defense? The integrity of barriers that are critical to safety and
safe shutdown should be assured through systematic analysis
and maintenance.
Contractor Management - Have a clear interface. Many
workplaces involve multiple contractors and numerous
interfaces. Is there complete clarity on who is handling what?
Are communication paths defined and used so that all are
informed?
212 More Incidents that Define Process Safety
5.2.2 Description
Background. The Macondo Well was owned by BP (leaseholder
and operator). Transocean was the owner and operator of
Deepwater Horizon, the drilling rig. Halliburton was responsible
for the well monitoring and cementing operations. Cameron,
contracted by Transocean, was responsible for providing testing
and repairs for the blowout preventer (BOP), a key safety and
environmental protection layer. There were other subcontractors
involved as well, but those mentioned here were the main parties.
Process. At the time of the incident, the well was being temporarily
shut down, with the intention of being reopened for production
at a later date, a process known as temporary abandonment. The
production casing, a high-strength steel pipe set in a well to
ensure well integrity and allow future production, was installed on
April 18-19. The bottom of the well was in a laminated sand-shale
zone, an area that has an increased likelihood of cement
channeling, which can prevent a strong bond (BOEMRE 2011).
What Happened. On April 19, cementing began. The purpose of the
cement is to seal the well and prevent hydrocarbons from flowing
Chapter 5 Environmental and Toxic Release Incidents 213
(CSB 2014a, 26). During the drilling of the well, there had been
significant losses of drilling mud into the formation. BP engineers
and Halliburton studied how to do the cementing in a way that
would minimize additional losses. To do this they used a different
cement mixture than had been originally planned, a foamed
cement slurry that is injected with nitrogen bubbles. An MOC
review was not done on the change. After the blowout,
investigations showed the cement mixture was not stable. The
conclusion that the cement job was successful was based, in part,
on the use of the displacement procedure. This procedure
assumed a 96.1% volumetric efficiency for a pump stroke. Later
analysis showed the actual efficiency was 89-91%. This difference
resulted in less seawater being pumped than was thought which
left space in and below the BOP.
After the cementing was completed, a positive well integrity
test was run to see if there was outflow from the well to its
surroundings. This well passed the positive test. The positive well
test cannot test if the cement is sealing the well at the very
bottom. A negative pressure test was conducted, although it was
not called for in the abandonment plans and was not required by
regulations. The results of the negative pressure test showed that
drill pipe pressure was increasing; this was an indication the
cement barrier had failed, and material was flowing into it. The
test was repeated several times and eventually, the pressure did
stop increasing. Not believing the results, a member of the crew
of the rig put forward a theory (which became known as the
bladder effect) to explain the differences, and the well leaders
accepted it. A final test, a cement bond log, was cancelled on the
belief the cement barrier injection was successful. The BOEMRE
investigation states that the “central cause of the blowout was
failure of a cement barrier in the production casing string”
(BOEMRE 2011).
An extremely simplified explanation of this behavior is that,
based on the original monitoring of material in and out, and the
successful positive test, the crew believed the cement job was
successful, and any evidence to the contrary was rationalized
Chapter 5 Environmental and Toxic Release Incidents 215
8. Operating Procedures.
The Deepwater Horizon crew was not supplied with a procedure
for testing the cement barrier. The crew did not, therefore, have
a criterion for deciding if the test was positive or negative, or
actions to take following a negative test (CSB 2014a). The
abandonment procedure was written 24 hours in advance, partly
due to the fact that the nature of the strata at the bottom of the
well could not be known until the well was drilled. No MOC or
process hazard review was done for the procedure, with the
exception of an occupational safety review.
10. Asset Integrity and Reliability.
The BOP was not managed as safety critical equipment, though it
was the only equipment on the rig designed to be able to stop a
blowout. One of each pair of redundant solenoid systems was
inoperable at the time of the blowout. The BOP was overdue for
vendor-recommended preventive maintenance, and no effective
testing or monitoring process was in place to confirm the
availability of the redundant systems in the emergency automatic
mode function (AMF)/deadman system if called upon to function
(CSB 2014b).
11. Contractor Management.
An offshore drilling rig employs many contractors, hence
communications and management of the relationship between
owner and the various contractors is very important. The CSB
report (2014d, p. 168) states, referring to BP and Transocean, that
“while both companies had more rigorous corporate policies for
risk management, neither assumed effective responsibility for
ensuring their implementation at Macondo.”
One safeguard against a blowout was supposed to be the
monitoring of well conditions by the mudlogger. The mudlogger
was from a subcontractor. He was not included in the discussions
that occurred during the well testing, so was unaware there had
been issues with the negative pressure test, diminishing his
Chapter 5 Environmental and Toxic Release Incidents 219
were able to shut down the well. Transocean, the owner and
operator of the drilling rig, prepared a presentation on this event
and issued an operations advisory to its North Sea fleet. However,
the lessons from these events were not learned by the crew and
engineers running the Deepwater Horizon.
5.3.1 Summary
On January 9, 2014, Freedom Industries chemical storage and
distribution facility in Charleston, West Virginia, an aboveground
storage tank experienced a leak that flowed into the Elk River.
Upon arrival at the site, West Virginia Department of
Environmental Protection (WVDEP) inspectors discovered what
was later identified as methylcyclohexanemethanol (crude
MCHM) and polyglycol ethers (PPH, stripped) leaking from an
aboveground storage tank.
The chemicals flowed 2.4 km (1.5 mi) to the intake of the West
Virginia American Water (WVAW) water treatment facility and
contaminated the drinking water distribution system, prompting
a do-not-use order across portions of nine counties. Refer to
Figure 5.3-1. Over 350 emergency room visits were recorded in
the first few days of the incident. The do-not-use order also
resulted in closures of many businesses, schools, and public
offices.
This incident garnered national news coverage. CSB
recommendations were made to the local water works company
as well as the American Water Works Association. The tanks have
been removed from the Freedom Industries site and only the
office/warehouse, garage, and storage buildings remain.
Freedom Industries entered into a Voluntary Remediation
Program in late February 2015, and the land has since undergone
extensive remediation. Freedom Industries executives and
managers were convicted of criminal charges related to violating
the Clean Water Act, negligently discharging refuse matter in
violation of the Refuse Act and failing to have a pollution
prevention plan. (CSB 2017) Two were sentenced to federal prison
and the remaining four received three years of probation.
Chapter 5 Environmental and Toxic Release Incidents 223
Key Points
Compliance with Standards – Learn from industry standards.
They contain many hard-won learnings. Even if you are not
‘regulated’ to comply with a certain standard, it may still be a
great resource.
Asset Integrity and Reliability – Maintain equipment integrity.
Equipment will start degrading the day it is installed. Inspection
and maintenance of process and storage equipment (in this
case, tanks) as well as layers of protection (in this case, dikes)
are necessary to ensure the integrity of the system.
Emergency Management – Plan for the unlikely event, be
transparent about the possibilities, and involve the potential
stakeholders. Emergency plans should include information on
all chemicals involved, drills should include external emergency
responders that may be involved, and drill experiences should
be used to improve the emergency response plans.
5.3.2 Description
Background. Freedom Industries provided specialty chemicals for
the mining, steel, and cement industries. Freedom Industries had
ownership of the facility for only nine days prior to the incident,
having merged with the Etowah River Terminal, LLC (ERT). At the
site in Charleston, Freedom Industries stored and sold ShurFlot
944, a mixture containing methylcychohexanemethanol (crude
MCHM) and polyglycol ethers (PPH, stripped), in addition to
calcium chloride and glycerin.
224 More Incidents that Define Process Safety
5.4.1 Summary
On August 23, 2010, at the Millard Refrigerated Services facility in
Theodore, Alabama, hydraulic shock caused a roof-mounted 0.3
m (12 in.) suction pipe to catastrophically fail, leading to the
release of more than 14,515 kg (32,000 lb) of anhydrous
ammonia. The ammonia cloud traveled downwind, impacting
crew on the ships docked at Millard and, across the river,
impacting more than 800 contractors at a Deepwater Horizon oil
Chapter 5 Environmental and Toxic Release Incidents 229
Key Points
Process Knowledge Management – Consider abnormal
operations. Design and operation, including that of control
systems, should include consideration of both normal and
abnormal operations, such as utility failure or cycle
interruption. Changes to that design should be managed and
controlled.
Hazard Identification and Risk Analysis – How big is the risk?
The greater the volume in a single system, the greater the
potential release. Although it may be easier to group process
equipment or tankage under a single control system, if there is
a failure, the release may include the volume of the entire
system. This risk should be identified and analyzed.
Emergency Management – Use emergency shutdown systems
in emergencies! Manually operated emergency shutdown
systems should be used immediately. If there is a desire to first
verify the situation, then this time delay and its consequences
should be analyzed and clearly communicated in procedures
and training.
230 More Incidents that Define Process Safety
5.4.2 Description
Background. Millard Refrigerated Services operated as a marine
export facility that sent frozen meat abroad. The site is located on
the Theodore Industrial Canal in Theodore, Alabama. Refer to
Figure 5.4-1. Millard operated a 64,864 kg (143,000 lb) ammonia
refrigeration system that supplied five product storage freezers
and three blast freezers.
Anhydrous ammonia (NH3) is a colorless gas at normal
temperature and pressure, with a characteristic pungent odor.
The American Industrial Hygiene Association (AIHA) Emergency
Response Planning Guidelines Level 2 (ERPG) for ammonia is 150
Chapter 5 Environmental and Toxic Release Incidents 231
same pipe. The mixing caused the hot gas to rapidly condense to
a liquid, creating hydraulic shocks that ruptured both the
evaporator piping manifold and the low-temperature suction
piping on the roof.
Immediately upon discovering the release, two Millard
employees went to the roof to manually close the isolation valves.
They attempted to isolate the source of the leak, but all other
equipment connected to the low-temperature suction header was
still in operation.
One Millard employee and more than 152 off-site workers,
including nine crew members of a ship docked at the Millard
facility, sustained injuries as a result of ammonia exposure. Of the
153 reported exposures from this incident, a total of thirty-two
workers were admitted to the hospital, and four were placed in
intensive care.
Why it happened. The rapid opening of a valve between the high-
pressure and low-pressure areas caused shock to the ammonia
system. The coil rapidly depressurized, causing refrigerant liquid
and vapor to accelerate into the downstream suction piping. The
gas quickly condensed to a liquid, leading to shock when voids of
trapped gas built up pressure and then rapidly condensed,
creating a vacuum. The creation of the vacuum reduces the
volume, allowing fluid from other parts of the system to rush in at
high velocity. Then, when this fluid hits a corner or end of a pipe,
it stops suddenly, potentially damaging that piece of pipe. The
Millard failure was likely caused by a combination of the
condensation shock and the high velocity liquid impact.
A contributing factor in this incident was the configuration of
the blast freezer evaporators at the Millard facility. Specifically,
multiple evaporator units were connected to a single control valve
group. This allowed an excessively large volume of high-pressure
gas to be introduced to the suction line during restart.
Chapter 5 Environmental and Toxic Release Incidents 233
5.5.1 Summary
On November 15, 2014, a release of 10,886 kg (24,000 lb) of
methyl mercaptan from the third floor of the building that housed
DuPont’s LaPorte, TX, Lannate® process resulted in methyl
mercaptan concentrations that were above the level considered
“immediately dangerous to life and health” (IDLH) in the building.
Area personnel activated the building evacuation alarm and
requested rescue via the plant emergency communication
system. The Site Emergency Response Team responded to the
area for search and rescue. Site personnel placed calls to 911, and
external agencies also responded to the site. The Site Emergency
Response Team members stopped the release and isolated the
process.
The release resulted in four employee fatalities, three
personnel injuries, and three other personnel chemical
exposures. There were no off-site injuries or exposures. In 2016,
Chapter 5 Environmental and Toxic Release Incidents 235
DuPont announced that it will close the La Porte plant, which has
been shut down since the gas leak (CSB 2015d).
Key Points
Hazard Identification and Risk Analysis – Look beyond the
P&ID. Are there surrounding features such as a building or a
fence that could increase the risk or limit emergency response?
Is the “vent to safe location” really safe–or is it in an area that
operators may need to access?
Operating Procedures – Use operational discipline when using
operating procedures. Following procedures every time, such
as walking the line, can help to avoid likely errors such as
misalignment of valves.
Emergency Response – Put human nature aside for a moment.
It is human nature to respond to another person’s need for
help. However, in a toxic release situation, it is imperative for
the safety of the emergency responders, as well as that of the
victim, that the responders first assess the situation and
protect themselves. Otherwise, all may become victims.
5.5.2 Description
Background. At the La Porte plant, DuPont made insecticides,
herbicides, and other products. In the Lannate® unit, methyl
mercaptan was reacted with other chemicals to create the
insecticide Lannate®. Refer to Figure 5.5-1.
Process. The process of making Lannate® is not the key process
involved in this incident. Instead, it was the chemistry of slurries
and hydrates are key. The reaction between methyl mercaptan
and other chemicals can create a slurry. This slurry is typically
cleared by flushing the lines with hot water. Hydrates are an ice-
like, solid substance that can be created when a hydrocarbon and
water are mid below a certain temperature. Lines blocked with
hydrates can be challenging to clear.
236 More Incidents that Define Process Safety
8. Operating Procedures.
The operators created a strategy to resolve the hydrate blockage.
However, they did not consider the potential blockage of relief
paths in this strategy. Operating procedures should include
troubleshooting and other non-routine activities. The lead-up to
this incident, like so many others, took place over a number of
shifts. In this instance, the operators were not aware of the
positions of all of the valves. This reinforces the importance of
clear and complete shift turnover communications and also the
Chapter 5 Environmental and Toxic Release Incidents 241
5.6.1 Summary
On January 22 and 23, 2010, three separate incidents at the
DuPont plant in Belle, West Virginia triggered notification of
outside emergency response agencies. One involved the release
of methyl chloride, one the release of oleum, and one the release
of phosgene. The incident involving the release of phosgene gas
led to the fatal exposure of a worker performing routine duties in
an area where phosgene cylinders were stored and used.
The phosgene incident occurred when a hose used to transfer
phosgene from a 0.9 metric ton (1 ton) cylinder to a process
catastrophically failed and sprayed a worker in the face while he
was checking the weight of the cylinder. Coworkers immediately
responded to the worker’s call for help. Initially, the worker that
had been sprayed with phosgene showed no symptoms of
exposure. However, his condition deteriorated rapidly, and he
died the next night. Delayed onset of symptoms is consistent with
phosgene exposure.
In 1988, DuPont conducted risk assessments of the Belle
phosgene plant. Using internal company criteria, decisions were
made, and no potentially inherently safer approaches were
undertaken.
The CSB investigation also examined concerns raised by
emergency response organizations regarding the timeliness and
quality of information provided to response personnel (CSB
2011d).
Chapter 5 Environmental and Toxic Release Incidents 243
Key Points
Compliance with Standards – Listen to your colleagues.
Company standards often codify the learnings of many of your
colleagues over many years of operation. Follow their
guidance. If the guidance seems to not make sense or to be out
of date, then use a MOC or deviation process to ensure that all
aspects of this guidance are recognized and analyzed before a
change is made or the guidance is not used.
Asset Integrity and Reliability – Take care of the systems that
take care of you. Changes in a maintenance management
system, whether computerized or manual, should be managed
and potential unintended consequences should be considered.
These systems should have sufficient redundancy to ensure
tracking and timely scheduling of preventive maintenance for
safety-critical equipment.
Incident Investigation – Know when to escalate. Incident
reporting and investigation procedures are typically clear on
what and to whom information is to be communicated. It
sometimes takes hours or days to go through the process. But
occasionally the situation identified could have imminent
consequences. The procedures also need to be clear about how
and when to escalate the process to avoid potential imminent
consequences.
5.6.2 Description
Background. DuPont’s Crop Protection business area is
responsible for the development, manufacture, and sale of
fungicides, herbicides, insecticides, and seed treatments globally.
The DuPont Belle plant is located in Belle, West Virginia, about 13
km (8 mi) east of Charleston, the state capital. The plant occupies
about 293 hectares (723 acres) along the Kanawha River and sits
in an industrial, commercial, and residential use area.
Process. The process unit runs on a campaign basis and is divided
into a “front end” and “back end.” The front-end process makes
244 More Incidents that Define Process Safety
5.7.1 Summary
On the morning of August 14, 2002, a chlorine transfer hose
failed, releasing 21,772 kg (48,000 lb) of chlorine over a three-hour
period during a railroad tank car unloading operation at DPC
Enterprises, L.P., near Festus, Missouri. Refer to Figure 5.7-1. The
facility repackages bulk dry liquid chlorine into 0.9 metric ton (1
ton) containers and 68 kg (150 lb) cylinders for commercial,
industrial, and municipal use in the St. Louis metropolitan area.
250 More Incidents that Define Process Safety
Key Points
Asset Integrity and Reliability – Did you get what you paid for?
It is often difficult to simply visually determine if that pipe, hose,
or valve is what you thought you were purchasing. Positive
Material Identification (PMI) should be used to verify that
materials are delivered as specified, especially where the use of
an incorrect material may lead to failure.
Emergency Management – We are in it together. Recognize and
test the assets and limitations of the neighboring emergency
response capabilities in your emergency response plans and
drills.
Asset Integrity and Reliability – Will your ESD system work in
an emergency? ESD system design should consider the
operating and environmental conditions, including that of
upstream equipment that might impact the system. ESD
system testing should verify that the entire system works, from
a sensor or button to the closing of a valve.
Chapter 5 Environmental and Toxic Release Incidents 251
5.7.2 Description
Background. DPC Enterprises bought the Festus repackaging
facility in 1998 and added chlorine detectors and an ESD system
to the chlorine repackaging area. The facility is part of the DX
Distribution Group network of eighteen repackaging and
distribution companies.
DPC Festus is located on an 8-acre site in the Plattin Creek
Valley of Jefferson County, Missouri. The facility receives bulk dry
liquid chlorine in 82 metric ton (90 ton) tank cars and repackages
it into 68 kg (150 lb) cylinders and 0.9 metric ton (1 ton) containers.
DPC Festus employs twelve full-time personnel, including four
packaging operators (packagers), four truck drivers, two
252 More Incidents that Define Process Safety
5.8.1 Summary
On January 16, 2002, hydrogen sulfide (H2S) gas leaked from a
sewer manway at the Georgia-Pacific Naheola Mill in Pennington,
Alabama. Several people working near the manway were exposed
to the gas. There were two contractor fatalities, and seven people
were injured. Choctaw County paramedics who transported the
victims to the hospitals also reported symptoms of H2S exposure.
The CSB called on the Agency for Toxic Substances and
Disease Registry, the Pulp and Paper associations, and the
associated unions to consider and communicate the risks of
hydrogen sulfide exposure (CSB 2003c). This incident prompted
the CSB to release a Safety Bulletin that warns of the dangers of
sodium hydrosulfide and to recommend safe practices to prevent
accidents when handling the chemical. The CSB found forty-five
accidents associated with sodium hydrosulfide that have caused
thirty-two fatalities and 176 injuries since 1971.
258 More Incidents that Define Process Safety
Key Points
Hazard Identification and Risk Analysis – Be careful with what
you are mixing! The need to analyze chemical reactivity may be
more obvious in the process unit. However, the potential for
chemical reactions with potential hazardous results in utility
systems such as in drains and vents should not be overlooked.
Emergency Management – Right to know. Make sure all
involved (designers, operators, emergency responders, etc.)
know what materials are on site, where they are located, how
to handle them, and emergency procedures in case of
accidental release.
Management of Change – Little things add up. Over the years,
adding a little connection here or there may result in a
significant change. Changes, big or small, should be analyzed
so that hazards may be identified.
5.8.2 Description
Background. The Georgia-Pacific Naheola Mill is located in
Pennington, Alabama, approximately 201 km (125 mi) north of
Mobile and 241 km (150 mi) southwest of Birmingham. The mill
began operation in 1958, went through a series of mergers and
acquisitions, and now operates as Fort James Operating
Company, a fully owned subsidiary of Georgia-Pacific
Corporation. The Naheola Mill produces over 589,670 metric tons
(650,000 tons) of paper, paperboard, and pulp annually.
Approximately 1,475 employees work at the mill.
Process. The Naheola Mill uses the Kraft process to produce pulp.
In this process, wood chips are treated with a liquor of sodium
hydroxide and sodium sulfide that chemically breaks them down
into pulp. The liquor is recycled, and fresh chemicals are added,
including sodium hydrosulfide (NaSH). The pulp is sold as pulp
and, after processing, as tissue, towels, and paperboard.
Chapter 5 Environmental and Toxic Release Incidents 259
8. Operating Procedures.
Operating procedures for NaSH tank truck unloading and oil pit
operations did not warn of the hazard of mixing NaSH with acids
or the hazard of allowing NaSH to enter sewers. Companies
should ensure that operating procedures warn of the hazards of
the chemicals being handled, including the hazards of mixing
chemicals.
13. Management of Change.
Modifications to the acid sewer over a period of several years
included connections to the chlorine dioxide sewer, to the sewer
from the truck unloading area, and to the containment area
known as the oil pit. These changes were not managed with a
formal MOC process, and there was no hazard evaluation nor
consideration of the potential chemical reactions. The potential
for H2S evolution was not identified; therefore, no detectors or
alarms were placed in the oil pit area. Companies should apply
good engineering and process safety principles to all areas
handling toxic materials, including process sewer systems. This
should include hazard reviews and management of change (MOC)
analyses.
16. Emergency Management.
Since H2S was not identified as a hazard, there were no detectors
or alarms in the area to warn of a release. Personnel had only
their sense of smell to indicate the possible presence of H2S;
however, smell is not a reliable indicator for H2S because the gas
causes olfactory fatigue. Companies should identify areas where
toxic materials could be present or generated and provide
safeguards (including detectors and alarms) to minimize
exposure. Personnel should be trained to recognize the presence
of toxic materials and the appropriate emergency response
practices for conducting a rescue operation.
The victims were not decontaminated at the scene, because
this was not required in the local procedures. Company
262 More Incidents that Define Process Safety
5.9.1 SUMMARY
A fire in the alkylation unit at CITGO's Corpus Christi refinery led
to a release of hydrofluoric acid (HF). One worker was critically
burned. One other employee was treated for possible HF
exposure during emergency response activities.
The CSB investigation raised questions regarding the
adequacy of the water mitigation system supply (CSB).
Key Points
Emergency Management – Plan for the worst. Emergency
response plans and equipment should consider the worst-case
events. When an incident could continue for many hours or
days, backup systems may be required. These backup systems
should be tested and maintained to ensure they will function
when called into service.
Auditing – Consider audits as a gift. Audits enable the
identification of potential problems before an incident occurs.
Audit protocols often include learnings from across a company
or industry. The gift of audit findings should be welcomed, even
sought.
5.9.2 DESCRIPTION
Background. CITGO’s refineries in Corpus Christi, Texas, and
Lemont, Illinois, include HF alkylation units. Processes using 454
kg (1,000 lb) or more of HF must comply with the US Occupational
Safety and Health Administration (U.S. OSHA) Process Safety
Management Standard for Highly Hazardous Chemicals (29 CFR
1910.119) and the US Environmental Protection Agency (EPA)
Chapter 5 Environmental and Toxic Release Incidents 263
19. Auditing.
API RP 751, Safe Operation of Hydrofluoric Acid Alkylation Units,
recommends refineries audit the safety of HF alkylation
operations every three years. API 751 details elements to be
included as part of a comprehensive audit plan. CITGO had never
conducted an API RP 751 safety audit of HF alkylation operations.
Companies should take benefit from the learnings provided in
industry guidance documents. HF alkylation unit operations
should be audited using API RP 751 by a lead auditor with an
extensive knowledge of HF hazards, HF alkylation units, and API
RP 751.
Chapter 5 Environmental and Toxic Release Incidents 265
5.10.1 Summary
On September 27, 2012, eight metric tons (8.8 tons) of
hydrofluoric acid (HF) was released at the Hube Global plant in
Gumi, South Korea. The incident resulted in five fatalities,
eighteen injuries, three thousand residents seeking medical
treatment, 212 hectares (534 acres) of damaged crops, and more
than thirty-nine livestock being exposed and destroyed.
The incident prompted the Korean government to create a
“Comprehensive Plan for Chemical Safety” that introduced off-site
consequence analysis as well as other requirements. It also
prompted changes to promote cooperation between emergency
responders, including governmental agencies (Korea Institute of
Public Administration).
266 More Incidents that Define Process Safety
Key Points
Compliance with Standards – Having and using a safety
management system is fundamental. Regulatory entities and
companies both need to commit to process safety.
Emergency Management – Cooperate. Emergency response
often calls upon several different organizations that may not
work closely in their day-to-day work. Planning and conducting
drills will highlight areas where cooperation may be improved.
5.10.2 Description
Background. The Hube Global plant is located in Gumi, South
Korea, about 200 km (124 mi) from Seoul. The commercial area
was originally developed with the goal of attracting high-tech
firms but now includes other industries, primarily manufacturing.
Refer to Figure 5.10-1. In 2008, Hube Global, a South Korean-
Chinese joint venture headquartered in Seoul, opened the plant
to supply raw materials to the electronics, chemicals, cosmetics,
pharmaceuticals, and biotech sectors.
Process. Hydrofluoric acid is used to produce chemical precursors
for the pharmaceutical industry and also has other industrial
applications. HF is highly toxic, and exposure can be fatal or cause
serious damage to the skin, lungs, heart, bones, and nervous
system.
What Happened. Investigation reporting of this incident is limited.
The incident occurred during the unloading of an HF delivery
tanker when the delivering vessel was pressurized, pushing the
HF into the receiving vessel. A security video camera recorded two
workers on top of the receiving vessel. It appears that the
operator opened the valve before the connection was complete.
The HF release, which was estimated at eight tons, engulfed the
workers. The delivering vessel was reportedly not clearly marked,
leaving the emergency responders unaware of the toxic HF
contents, which resulted in further exposure to the responders
and broader community. Refer to Figure 5.10-2.
Chapter 5 Environmental and Toxic Release Incidents 267
Transportation Incidents
6.1 INTRODUCTION
Incidents that Define Process Safety (CCPS 2008) included a number
of transportation incidents in the marine and aviation sectors.
This chapter will focus primarily on train and pipeline incidents.
Unlike incidents that occur in a facility such as a refinery,
chemical plant, or offshore platform, transportation incidents
may occur anywhere along a vast pipeline route or transportation
corridor. These pass through open countryside, but also through
communities and densely populated cities where, if an incident
occurs, the consequences can be great.
The CCPS RPBS element of Stakeholder Outreach is very
important in transportation risk management. Many pipeline
incidents have occurred due to damage from mechanical digging
equipment, such as a backhoe, that was inflicted years before the
incident. Having open conversation and tools for people to
understand where pipelines are can greatly aid in preventing
accidental damage. Whether from damage or from aging,
understanding the integrity of a pipeline system that spans
thousands of miles is a challenge, especially since the original
construction data may no longer be available. Ensuring that
integrity management systems are robust and based on good
data has been the subject of regulation following incidents
described in this chapter.
Considering the expanse of pipeline networks, planning for
and managing an emergency can be daunting since a release can
occur anywhere along their route. This means that stakeholder
outreach and emergency response should work together to make
sure that the location of the incident can be pinpointed, that the
potentially impacted people can quickly be made aware of the
.PSF*ODJEFOUTUIBU%FGJOF1SPDFTT4BGFUZ
By $$14
¥5IF"NFSJDBO*OTUJUVUFPG$IFNJDBM&OHJOFFST
Chapter 6 Transportation Incidents 273
situation, and that plans are clear on how to verify the emergency
situation is rendered safe, and how to clean up the aftermath.
A few of the incidents highlight two important elements of the
conduct of operations: design expectations and what to do when
an operation doesn’t seem right. The key learning here is that if
there is an expectation for an operator to respond in a certain
way, then that information should be clearly stated, implemented
in design/training, and tested. Equally, if an operator is working
on a task and it just doesn’t seem right, then he should stop. Stop,
think, check it out, plan the appropriate next steps, and then
proceed.
6.2.1 Summary
In the early hours of July 6, 2013, an unattended Montreal, Maine
& Atlantic (MMA) Railway train rolled from its overnight parking
location and proceeded over seven miles into the town of Lac-
Megantic, where it derailed. The train was carrying crude oil and
the resulting fires and explosions fatally injured forty-seven
people and destroyed forty buildings and fifty-three vehicles.
Refer to Figure 6.2-1. Forty-seven counts of criminal negligence
were filed against three MMA employees, and the company
declared bankruptcy as a result of this incident (TSB 2013).
This incident prompted discussions on the safe rail
transportation of crude oil and the DOT final rule in May 2015 to
strengthen safe rail transportation of large volumes of flammable
liquids (NCSL, 2015).
274 More Incidents that Define Process Safety
Key Points
Compliance with Standards – Comply with industry and
company standards. Standards include the experience, hard
learnings, and even expert calculations of many others. Take
their advice and follow the standards.
Management of Change – Beware of creeping change. When
small changes happen slowly over time, it is easy to overlook
them. Eventually the small changes add up to a big change that
has not been realized or had the risk managed.
Emergency Management – Is it really “all clear?” It’s human
nature to want an emergency to be over—to declare it under
control. However, when that emergency involves operating
equipment, an expert in the control of that equipment should
be consulted to verify that the equipment status is truly safe.
6.2.2 Description
Background. The MMA-002 train was traveling from Farnham,
Quebec, to Brownville Junction, Maine. The train was made up of
seventy-two cars carrying 7.7 million liters (2 million gal) of crude
oil (UN1267). Just before midnight on July 5, 2013, the train was
parked in Nantes.
Process. The 1,433 m (4,700 ft) long train contained seventy-two
tank cars loaded with crude oil from the Bakken fields in North
Dakota (NTSB 2015). The cars were DOT-111 design. With the
fracked crude from primarily Texas and North Dakota, the US was
producing more crude oil than it had in thirty years.
Transportation of crude oil by rail had increased significantly to
move the crude to refineries for processing. Carloads carrying oil
in 2014 rose by more than 5,000% when compared with 2008
numbers (NCSL 2015).
The fracked crude oils from formations such as the Bakken
are of a lower density, flow freely at room temperature, and have
a higher proportion of light hydrocarbon fractions resulting in
higher API gravities (between 37° and 42°). A Sandia report stated
that “No single parameter defines the degree of flammability of a
fuel; rather, multiple parameters are relevant.” (Sandia 2015) The
attention following this incident is continuing to prompt
discussion on the safe transport of various classifications of crude
oils.
What Happened. The locomotive engineer stopped the train on a
downhill grade on the main track. He used the automatic brakes
and applied the brakes on the locomotive and the buffer car. He
then began to apply the hand brakes and shut down the trailing
locomotives. He tested the hand brake by releasing the
locomotive automatic brakes but did not release the locomotive
independent brakes.
He communicated with the rail traffic controller, noting
mechanical difficulties he had experienced, including excess
smoke and a loss of power in the lead engine. They decided to
address these issues in the morning. The locomotive engineer
went off-duty to stay in a Lac-Megantic hotel. The taxi driver noted
276 More Incidents that Define Process Safety
the smoke from the smokestack, along with oil droplets. The
locomotive engineer stated that he had informed the company of
the issue.
Just before midnight, a fire was reported on a train at Nantes.
A track foreman met with the fire department and was told that
the emergency fuel cut-off switch had been used to shut down the
lead locomotive. This stopped the fuel to the fire. The firefighters
also put the locomotive electrical breakers in the off position. The
track foreman and the fire department were in conversation with
the rail traffic controller. The locomotive engineer asked the rail
traffic controller if he needed to return to the train to start
another engine. He was told that the track manager had
dispatched a track foreman to the site. The train was left for the
night with no engines running.
Over the course of the next hour, air pressure bled from the
brake system, and the train began to roll downhill. It reached a
speed of over 105 kph (65 mph) and traveled the 11.6 km (7.2 mi)
to the town of Lac-Megantic, where sixty-three railcars derailed,
releasing approximately six million liters (1 million gal) of crude
oil. The spill flowed to the lake, ignited, and resulted in the forty-
seven fatalities.
Why It Happened. The MMA procedure for parking of unattended
trains required 9 hand brakes to be set for trains of this length
and additional hand brakes to be used if the train was parked on
a slope of the grade in Nantes. Canadian rail industry best practice
would have been to set 40% of the train hand brakes. Only seven
hand brakes were set on this train, and the engineer improperly
performed a brake test without releasing the locomotive’s air
brakes. When the firefighters responded to the train fire in
Nantes, they shut down the locomotive per the firefighting
procedure; however, they did not follow the procedure
addressing parking the train on the grade. Additionally, they did
not contact the locomotive engineer. With none of the other
locomotives running, the air in the brake system started to
deplete, and an hour later the train began to roll downhill. The
train reached 105 kph (65 mph). The track in the Lac-Megantic
switch area was rated for only 24 kph (15 mph).
Chapter 6 Transportation Incidents 277
At the time of the incident, the DOT-111 train car was the
standard car for flammable liquids. A number of changes
happened during the increased production of fracked crudes,
including the number of cars in a single train, the overall volume
of crude transported by train, and the properties of the fracked
crude itself. The DOT-111 car was not capable of withstanding the
impacts experienced in the Lac-Megantic derailment. A 2015 DOT
final rule addressed “high-hazard flammable trains” (HHFT) which
means “a continuous block of twenty or more tank cars loaded
with a flammable liquid or thirty-five or more tank cars loaded
with a flammable liquid dispersed through a train.” This rule
included provisions on enhanced breaking, enhanced standards
for new and existing tank cars, reduced operating speeds, more
accurate classification of unrefined petroleum-based products,
and rail-routing risk assessment (DOT 2015). The DOT-117 is the
new generation of rail car now used for transportation of HHFTs.
It includes thicker gauge jackets, head shields, and tank ends and
improved valve designs. Refer to Figure 6.2-2.
6.3.1 Summary
On January 6, 2005, a Norfolk Southern Railway freight train
collided with another parked Norfolk Southern train. The collision
derailed sixteen of the forty-two freight train cars. Among these
derailed cars were three tank cars containing chlorine, one of
which released chlorine gas. Nine people died from exposure to
the chlorine gas and 554 people sought treatment in hospitals.
Approximately 5,400 people near the derailment site were
evacuated for several days (NTSB,2005).
Key Points
Stakeholder Outreach – Speak to your stakeholders. Plan
together. Talking among yourselves will likely not provide the
best understanding and response. Working together in
advance, understanding who all may be involved, and planning
together will help support an effective response.
Conduct of Operations – Whatever control you are using, make
sure it works. If it is an engineered system – maintain it. If it is a
procedure – follow it. And if there is a safeguard – make sure
there is time for you to identify the issue, time for you to
respond, and sufficient time for the device to function properly
to prevent an incident.
Emergency Management – Be specific in communications.
Identify the best means of communication before an incident
occurs. Interpret the safety data sheet and plan appropriately.
Depending on the potential hazards, emergency
communications may require advising people to shelter in
place or to seek higher ground.
Chapter 6 Transportation Incidents 281
6.3.2 Description
Background. Graniteville is a rural community located in a valley
with approximately 5,400 people living within 1.6 km (1 mi) of the
accident site. The Norfolk Southern track in the area is not
equipped with automatic signals indicating rail switch positions.
There are a number of sidings, short sections of track distinct
from the main line, servicing the local industries.
Process. The process is that of moving train cars on various
industry sidings using both the sidings and some sections of main
line.
What Happened. On the day before the accident, train cars were
moved around the various sidings during the day. Shift change
occurred in the evening. At 2:39 a.m., a train traveling at 77 kph
(48 mph) was unexpectedly diverted onto an industry siding and
into a parked train. Refer to Figure 6.3-1. Several railcars ruptured.
Approximately 54 metric tons (60 tons) of liquefied chlorine gas
was released and rapidly vaporized.
The conductor and engineer survived the impact. They exited
the train, moved about 91 m (300 ft), traveled a bit further, and
laid on the ground. They saw white or gray smoke and smelled
chemicals.
Winds were light that night, and the chlorine cloud settled in
the valley along the track. There were numerous 911 calls as
people smelled the gas. The local fire departments responded,
sensed the gas, and stood back from the scene. At 2:49 a.m., the
fire department asked that the reverse 911 emergency
notification system be activated, advising residents to shelter
indoors. At 2:57 a.m., the fire department asked that road traffic
for a one-mile radius around the site be blocked and reiterated
the reverse 911 request. From 3:05 a.m. to 3:40 a.m., the fire
department set up an incident command center, moved that
center further away, accessed information on the materials in the
breached tank cars, and set up a second decontamination center.
At 3:50 a.m., firefighters began rescuing people from adjacent
industrial sites.
282 More Incidents that Define Process Safety
they left the site. Federal Railroad Administration data has shown
that a leading cause of train accidents is improperly lined switches
(NTSB 2005).
The NTSB concluded that there was not sufficient reaction
time for the train engineer to see the signal position banner, react,
and stop the train.
5. Stakeholder Outreach.
Railroads, like other transportation corridors, often traverse
populated areas, and the people in those areas may be impacted
by an incident on the traffic corridor at any time of the day or
night. This understanding and the details of what types of
chemicals might be involved, as well as what the appropriate
responses might be, should be communicated and understood by
local authorities. This requires cooperation between all the
stakeholders involved: the company that owns/produces the
chemical, the company transporting the chemical, the local
emergency responders, and the neighboring residents.
6.4.1 Summary
On October 23, 1995, a railroad tank car containing nitrogen
tetroxide and water began leaking at the Gaylord Chemical
Corporation plant in Bogalusa, Louisiana. Plant personnel and fire
responders used water to suppress the vapors. Approximately
3,000 people were evacuated. Of the 4,710 people that were
treated at local hospitals, eighty-one were admitted (NTSB 1998).
Key Points
Conduct of Operations – If it doesn’t seem right, stop and check!
When a measurement looks odd, or a gauge is at its maximum,
or a sample is not as expected–take this as a warning. Verify the
data before proceeding. In doing so, you may prevent an
accident before it happens.
Emergency Management – Make sure you clean up. This is
important to protect emergency responders, operators,
neighbors, and the environment. Many emergencies involve
the mishandling of materials that were involved in an incident
or that were generated in the emergency.
Chapter 6 Transportation Incidents 285
6.4.2 Description
Background. Vicksburg Chemical Company was the shipper of
nitrogen tetroxide to Gaylord Chemical Corporation in Bogalusa,
Louisiana.
Process. Nitrogen tetroxide is a liquefied poisonous gas and
oxidizer. When nitrogen tetroxide is mid with water, it reacts to
form nitric acid.
What Happened. On September 14, nitrogen tetroxide vapors
leaking from the tank car were suppressed with water. The Union
Tank Car Company replaced four valves and noticed that one
valve stem showed significant wear. On September 26, the tank
car was loaded with nitrogen tetroxide at the Vicksburg Chemical
Company. The tare weight of the car was 4,309 kg (9,500 lb) over
the maximum weight noted on the car, but operators saw the new
valves and assumed that the car had been rebuilt and that the
maximum weight had been increased. They did not verify this
assumption. On October 12, the nitrogen tetroxide was
transferred into a storage tank at Gaylord. At the same time,
material from the storage tanks was being transferred to the
plant. Process sensors detected water contamination in the
nitrogen tetroxide and triggered interlocks to shut down the
chemical reactor. Because of the water contamination, it was
decided to switch the rail car unloading into stainless-steel cargo
tank trailers. On October 13, a meter used to measure the
transfer indicated that the full quantity had been transferred. No
other verification of the remaining quantity was made.
Vapors started leaking from another cargo tank containing
the same material. On October 17 and 20, a number of valves and
gaskets on the tank car were replaced because they were
determined to be inappropriate for the nitrogen tetroxide and
fuming nitric acid. On October 19, Gaylord employees began
transferring the remaining material into a cargo tank. The meter
indicated over 23 m3 (6,000 gal) had transferred; post-accident
calculations determined actually only over 3 m3 (800 gal)
transferred. On October 23, a chemical analysis was done on the
286 More Incidents that Define Process Safety
8. Operating Procedures.
The NTSB indicated that the accident was caused by the lack of
adequate procedures on the parts of both the shipping and
receiving chemical companies (NTSB, 1998). The shortcomings in
these procedures enabled the contamination of the product and
the lack of detection of this contamination.
Operating procedures should address both normal and
abnormal situations. Providing clear direction on how to detect,
Chapter 6 Transportation Incidents 287
6.5.1 Summary
On September 9, 2010, a Pacific Gas and Electric (PG&E) Company
intrastate natural gas pipeline failed catastrophically in a
residential area of San Bruno, California. The release of an
estimated 1.3 million standard cubic meters (47.6 million
standard cubic feet) of gas resulted in a crater that was 22 m (72
ft) long and 8 m (26 ft) wide. A fire ensued, causing eight fatalities,
injuring many others, destroying thirty-eight homes, and
damaging seventy more. Refer to Figure 6.5-1.
The NTSB made recommendations to the US Secretary of
Transportation and multiple state agencies and industry
associations. The Pipeline Hazardous Materials SA issued an
Advisory Bulletin regarding the need to ensure the accuracy of
data supporting the maximum allowable operating pressure
calculations. Congress introduced several bills that strengthened
pipeline safety oversight (NTSB 2011).
Key Points
Process Knowledge Management – Make sure you have good
data. Garbage in, garbage out. It is imperative to have correct
data input to systems that control operations and
maintenance. Without correct data, poor decisions will result.
Asset Integrity and Reliability – Keep it in the pipe. Having a
good system to manage equipment inspection, testing, and
maintenance is required to maintain the integrity of the many
pieces of equipment.
Emergency Management – What’s happening? In an
emergency, operators may be swamped with many alarms,
work may be ongoing and other units may be impacted. Have
plans to promptly identify what the problem is, where it is
located, and how to isolate it to minimize the incident.
Chapter 6 Transportation Incidents 289
6.5.2 Description
Background. PG&E provides natural gas and electric service to
fifteen million people in northern and central California.
Process. The PG&E gas facilities include more than 67,592 km
(42,000 mi) of natural gas distribution pipelines and 10,300 km
(6,400 mi) of transmission pipelines. The pipeline involved in the
incident originates at the Milpitas Terminal and flows 74 km (46
mi) to the Martin Station. This PG&E system includes three
pipelines and six crossties that allow gas to flow between the
pipelines.
The supervisory control and data acquisition (SCADA) center
is located in PG&E’s San Francisco headquarters and manages the
operations of the system.
PG&E had experienced a 2008 explosion of a pipeline in
Rancho Cordova and a 1981 pipeline leak in San Francisco. The
NTSB noted similar factors between these incidents and the San
Bruno accident.
What Happened. About 3.5 hours before the rupture,
uninterrupted power supply work was initiated at the Milpitas
Terminal. The technician at the terminal was in contact with the
(SCADA) center. They confirmed that the valves on incoming lines
would close on loss of power, so they locked the valves open. As
the work progressed, the terminal technician and the SCADA
center were in contact at each step of the work. During the work,
a local control panel lost power. The workers began looking for an
alternate power source. Subsequent investigation showed that
erratic voltages from redundant power supplies during this work
caused erroneous pressure signals, prompting regulating valves
to open fully. Less than an hour before the incident, the SCADA
center displayed over sixty alarms in a few seconds. Through
troubleshooting, they realized that the SCADA center was not
receiving accurate data. They recognized that the entire system
was overpressured and began changing set points to lower the
pressure. High-high pressure alarms continued with pressures
290 More Incidents that Define Process Safety
above 27 bar (386 psig) until just after 6:11, when the rupture
occurred.
6.6.1 Summary
There have been numerous pipeline releases, in addition to the
PG&E San Bruno release described above, that have resulted in
human harm, damage to the environment, and destruction of
property. While pipelines are frequently thought of traversing
open countryside, they are also located in populated areas where
the consequence of incidents can be significant. The incidents
included below are representative, including toxic, flammable,
and explosive consequences.
Chapter 6 Transportation Incidents 295
Key Points
Stakeholder Outreach – “Know what’s below” (PHMSA, 2017).
You may own or operate a pipeline, but it likely runs under
areas where you have little control. Enabling stakeholders to
prevent damage can avoid a release.
Asset Integrity and Reliability – Is it still in good shape? There
are miles and miles of pipelines that are in service for many
years. Use a good integrity management system is imperative
to ensuring safe and reliable service.
Conduct of Operations – Where is it? Pipeline systems are vast.
Like all control systems, it is important to design the control
system to enable the operator to quickly understand and
respond.
6.6.2 Description
Three additional pipeline incidents are used to discuss the Key
Points in this Section.
Olympic Pipeline. On June 10, 1999, an Olympic Pipeline Company
pipeline ruptured and released 897 m3 (237,000 gal) of gasoline
into a creek in Bellingham, Washington. Over an hour later, the
gasoline ignited and burned 2.4 km (1.5 mi) along the creek,
causing three fatalities, injuring eight others, and damaging a
residence and the Bellingham water treatment plant. Refer to
Figure 6.6-1.
The pipeline was damaged during excavation works
associated with the 1994 water treatment plant modification. In-
line inspections indicated damage, but the pipeline was not
excavated for further inspection. The NTSB concluded that the
pipeline would have been able to withstand the internal pressure
at the time of the accident had it not been weakened by the
external damage.
Bayview Terminal was built and commissioned 6 months
before the accident. There were issues with the pressure relief
valves, resulting in operational issues that were reported but not
296 More Incidents that Define Process Safety
5. Stakeholder Outreach.
Pipelines, by their function, connect many stakeholders including
owners, operators, neighbors, regulators, and emergency
responders. Damage prevention systems such as the PHMSA 811
system— “Know what’s below. Call 811 before you dig.”—can help
reduce the likelihood of pipeline damage. As a PHMSA report
states, “Damage prevention is a shared responsibility.” (PHMSA,
2017) Sadly, as seen in the Nigerian incident, some damage is
intentional and then escalates to involve many other innocent
people.
6.7.1 Summary
Air France flight AF 447 was traveling from Rio de Janeiro to Paris
on 31 May 2009. Just over two hours into the flight, the plane
stalled and crashed into the Atlantic Ocean, resulting in 228
fatalities. The wreckage was found on April 2, 2011at a depth of
3,900 m (2.4 mi), about 12 km (6.5 nm) from the aircraft’s last
transmitted position (BEA 2012).
Key Points
Hazard Identification and Risk Analysis – Is now the best time?
There are some jobs, or elements within a job, that may pose
more risk than normal. Ensure that the right people are on the
job and that their mind is on their work at the critical points of
the job.
Conduct of Operations – Have realistic expectations. If you are
expecting specific behaviors to certain operational situations,
then make sure that situation can be easily detected and that
employees are trained and practiced in that response.
6.7.2 Description
Background. The captain had 6,258 flying hours, including sixteen
rotations in the South American sector in the preceding two years.
There were two co-pilots on the flight. The meteorology over the
Atlantic Ocean was normal, although there were some storms in
the early hours of the flight path.
Process. The plane was an Airbus A 330-203, manufactured in April
2005 with GE engines. The air speed is deduced from
measurements from three pitot probes and six static pressure
sensors. The probes were equipped with drains and an electrical
heating system to prevent icing. The speed of the plane is
calculated based on data from these probes and sensors used in
300 More Incidents that Define Process Safety
7
Non-Oil/Chemical Incidents
7.1 INTRODUCTION
Some people think that lessons are only learned from incidents in
industries that are the same as their own. This is a false and
limiting opinion. Lessons may be learned from industries,
locations, and cultures that are different from your own. In fact,
the differences may prompt deeper thinking in finding the root
cause that is common across the industries, and, by getting to that
root cause, potentially prevent a broader range of incidents in
your own situation.
It is interesting to note the impact of process safety culture in
the incidents in this chapter. These incidents occurred in
industries that were not familiar with process safety, but they did
have to manage hazards and risks. The culture to do this
effectively was lacking. In some cases, it was lacking in the
company, in the supporting companies, and in the regulator.
Without a strong culture to manage hazards and risks, the other
controls to support safe work start to degrade.
The other point that stands out in these incidents is that
emergency management is just as key as it is in the other
incidents described in this book. It is not just about having
emergency responders or knowing what number to call to get
them; it is about the planning. Identify the various emergency
scenarios, assess the resources required to handle the
emergency, and practice tabletop and field drills with in-house
and external emergency responders to verify the effectiveness of
the emergency plan.
.PSF*ODJEFOUTUIBU%FGJOF1SPDFTT4BGFUZ
By $$14
¥5IF"NFSJDBO*OTUJUVUFPG$IFNJDBM&OHJOFFST
Chapter 7 Non-Oil/Chemical Incidents 305
7.2.1 Summary
On March 11, 2011, one of the largest recorded earthquakes
occurred off the coast of Japan. This caused a tsunami that caused
more than 1,500 fatalities, injured more than 6,000, and many
more were missing. The tsunami waves flooded the Fukushima
Daiichi nuclear power plant, impacting all six units on site. In the
following days, the units overheated, and radioactive material was
released, exposing surrounding communities and the
environment (IAEA, 2015). People were evacuated within 20 km
(12.4 mi) of the site for years. No human fatalities were attributed
directly to the incident; however, since the accident, there has
been reporting of significant increases in thyroid cancer (NAIIC
2012).
The Fukushima Nuclear Accident Independent Investigation
Commission (NAIIC) called for reforms in both the electric power
industry and the related government and regulatory agencies.
Key Points
Stakeholder Outreach – Make sure companies and agencies
are working toward the same goal–safety. It is good to have a
positive working relationship with other stakeholders.
Remember, though, that just because someone says an action
is okay does not mean that it is safe.
Process Safety Competency – Make sure process safety
competency is strong as it underpins many elements in most
management systems. If process safety is strong, business
management will be also. If the understanding of process
safety is weak, then decisions over time will degrade overall risk
management.
306 More Incidents that Define Process Safety
7.2.2 Description
Background. Following the oil crisis of the 1970s, Japan moved to
diversify its power sources. By 2010, nuclear power generation
provided 29% of the total power generation in Japan. There are
five nuclear power plants located on the northeastern coast of
Japan. Fukushima Daiichi is operated by Tokyo Electric Power
Company (TEPCO).
Process. The Fukushima Daiichi design used boiling water
reactors. The reactors are a closed loop system. Water boils in the
reactor, producing steam that drives turbines to generate electric
power. The steam is condensed using cold water from the ocean
and then fed back to the reactor again. Refer to Figure 7.2-1.
What Happened. The Great East Japan Earthquake occurred at 4:46
p.m. It was a magnitude 9.0 and lasted more than two minutes,
causing damage to structures and power infrastructure. Units 1,
2, and 3 were running at the time and shut down automatically
due to the seismic motion. A tsunami was created by the
earthquake, with the waves arriving forty 40 minutes after the
initial shock. A wave of 14 to 15 m (46 to 49 ft) overwhelmed the
Daiichi seawalls and flooded the site, causing significant damage,
loss of power, loss of control, and eventual loss of reactor
containment.
Following the earthquake, TEPCO set up an emergency
response center in Tokyo and an on-site emergency response
center at the Daiichi site to manage the response. Evacuation and
shelter-in-place orders were issued over the next three days.
Why It Happened. After inserting the control rods (rods composed
of chemical elements used to control the nuclear fission) to stop
the reaction, heat continued to be generated. Cooling systems are
run and controlled by electrical power. The earthquake had
damaged the off-site power supply, resulting in a total loss of
power supply to the plant. This loss of power isolated the units
from their turbines, resulting in increased temperature and
pressure in the reactors. The operators followed appropriate
procedures for the earthquake and loss of power in shutting
down, isolating, and activating cooling systems.
The tsunami flooded the reactors and turbines, resulting in
loss of seawater intake for all units which in turn resulted in a loss
of cooling. It also damaged the electrical equipment, including the
diesel generators, power distribution, and switchgear, which
resulted in the loss of the emergency diesel generators to provide
cooling for all but one of the six units. DC power was provided as
an additional emergency backup, but the batteries were flooded,
and this power supply was lost to most of the units. With the loss
of power, the ability to monitor reactor pressure, water level, and
other aspects of core cooling was lost for three of the units.
308 More Incidents that Define Process Safety
7.3.1 Summary
On April 16, 2014, the Sewol ferry capsized and sank in the waters
off South Korea. Only 172 of the 476 passengers were rescued.
The Korea Maritime Safety Tribunal investigated the incident.
Over 150 people were jailed, some for murder, and government
structures were reorganized as a result of this accident and the
emergency response (Kwon 2016).
Key Points
Process Safety Culture – Work to make sure all stakeholders
have a good process safety culture. Process safety culture,
good or bad, can exist in companies you do business with, in
the regulator, and in auditors. Where it is good, it can
encourage all involved to continuously improve. Where it is
bad, it can fail to identify problems and enable the
normalization of deviance.
Chapter 7 Non-Oil/Chemical Incidents 313
7.3.2 Description
Background. The ferry was constructed in 1994 and operated for
18 years without incident. Chonghaejin Marine Company
purchased the ferry in 2012 and made extensive modifications,
adding cabins to the third, fourth, and fifth decks, increasing
weight by 239 metric tons (263 tons), decreasing cargo capacity by
half, and increasing the ballast water requirement by four times.
The Sewol traveled its 402 km (250 mi) journey in 13.5 hours three
times a week. It had made the journey 241 times before the
incident. The water temperature was approximately 15°C (59°F),
which can cause hypothermia in ninety minutes.
Process. The Sewol ferry was a car ferry or roll-on/roll-off (ro-ro)
ferry.
What Happened. On the day of the accident, the Sewol departed
over two hours late, carrying 476 passengers, 124 cars, 45 trucks,
and 1,157 metric tons (1,275 tons) of cargo. The third mate was
on the bridge. She had one year’s experience in steering ships and
had never steered the Sewol through the Maenggol Channel,
which is known for its strong underwater currents. The helmsman
had six months of experience on the ferry. Orders were given to
the helmsman to turn the ferry. He made a quick, sharp turn, and
the ferry lost balance, listing twenty degrees into the water. The
cargo containers fell to one side of the ferry. The ferry began
taking on water through the ro-ro doors at the bow and stern. The
Captain went to the bridge and ordered the engines be stopped.
314 More Incidents that Define Process Safety
7.4.1 Summary
On November 19, 2010, there was an explosion in the Pike River
Coal Mine. There were twenty-nine fatalities. There were three
additional explosions in the next nine days before the mine was
sealed. A royal commission was established to investigate the
incident. This was the twelfth such commission investigating fatal
coal mine incidents. The mine now has a new owner.
Recommendations have been made for a new regulator with a
focus on health and safety, changes to existing regulations and
conduct of joint emergency response drills (NZ Royal Commission
2012).
Key Points
Contractor Management – Manage your contractors, or you
may end up managing an incident. Contractors are often able
to cause, prevent, or mitigate an incident. Make sure they are
provided with the training, tools, and supervision to do a safe
job.
Operational Readiness – Are you ready, or just anxious, to start
up? A start up can be pushed for by management, can be
exciting after months of work, and can be demanding for the
workers. Determine what is required for a safe start up and to
verify those requirements are in place before the start up.
Management Review and Continuous Improvement – Is it really
that good? Management, like everyone, likes to hear good
news. But they should verify that they are getting accurate and
full data about operational safety and risk management so that
they can support improvements where needed.
Chapter 7 Non-Oil/Chemical Incidents 319
7.4.2 Description
Background. The Pike River Coal Mine is in the Paparoa Range on
the West Coast of New Zealand’s South Island near Greymouth.
Pike River Coal Ltd. operated the mine, and it was their only mine.
The mine was opened in 2008 with the first sales in 2010. The
company had overestimated the production forecasts,
underestimated the challenge of the geological conditions, and
was borrowing money to support operations.
Process. Methane gas is naturally occurring in coal. Large volumes
can be generated by mining the coal. The LEL and UEL for
methane in air are 5% and 15%, respectively. The methane level
is controlled through ventilation and atmospheric monitoring.
The original mine plan included two fans on the mountain. This
was changed to relocate a fan underground.
Hydro mining was seen as a way to significantly increase
production. It is not a common technique and uses a water jet
following a specific cutting sequence to avoid undue release of
methane.
What Happened. The investigation concluded that a large volume
of methane accumulated, potentially from a roof collapse due to
hydro mining or from operations in another part of the mine that
had reported high methane readings. The ignition sources could
have been the electrical system, diesel engines, the main fan, or
contraband (cigarettes, watches, and cameras). These were
prohibited, and preventive actions had been taken by Pike, but
the practices continued.
A search and rescue effort was undertaken but was hampered
due to lack of planning. Damage to the fans meant that the mine
could not be re-ventilated quickly. The emergency response was
managed by the police in Wellington. Many decisions were made
in Wellington instead of at the mine where the rescue experts
were gathered. The response included the police, mining
specialists, mine rescue services, and emergency responders. The
inability to understand the atmospheric conditions in the mine
prevented rescue attempts. Refer to Figure 7.4-1.
320 More Incidents that Define Process Safety
Why It Happened. Pike River Coal Ltd. had not completed the
ventilation and drainage systems to support management of the
methane produced by using hydro mining. The New Zealand
Department of Labor did not have the resources or focus to make
sure that the mine was in compliance with regulations.
Normalization of deviance is evidenced by the twenty-one times
that levels of methane exceeded the LEL in the months preceding
the incident. The decision to move the non-explosion-protected
fan underground, into a mine with a potential for an explosive
methane atmosphere, was opposed by a ventilation consultant
and by some staff, but it was placed there anyway. This fan failed
Chapter 7 Non-Oil/Chemical Incidents 321
in the explosion, and the backup fan in the ventilation shaft was
damaged.
In October, the width of the hydro mining cut was increased
by 50%. An expert consultant identified the risk of a roof collapse.
A major roof collapse did occur, and methane readings were high,
but an explosion did not occur. Work was continued without
assessment of the roof collapse.
7.5.1 Summary
On April 5, 2010, an explosion occurred in the Big Branch Coal
Mine in southern West Virginia. There were twenty-nine fatalities
and two injuries. Multiple employees and an executive were
convicted as a result of the incident.
Key Points
Process Safety Culture – Do not normalize deviance. When
tolerating shortcomings becomes normal and workers no
longer see the point in speaking up about safety issues, the
progression toward an incident has likely started.
Safe Work Practices – Protect the key risk barriers. Making sure
that practices support the integrity of barriers and do not allow
people to work-around them, are key to managing risk.
Measurement and Metrics – Measure what is important to
manage. Metrics should reflect the health of those barriers that
have been put in place to manage risk. If metrics solely address
production, it is time to review the process safety culture.
7.5.2 Description
Background. The Big Branch Coal Mine was owned by Massey
Energy and operated by its subsidiary, Performance Coal
Company. Work was behind schedule and pressure to produce
was high. The miners felt that leaving the job was not an option
unless there was an emergency, so they tolerated poor conditions
to produce coal (GIIP, 2011).
Process. Methane is released in the process of coal mining. Coal
dust is generated from the mining, from conveyor belts that
transport the coal, and from some coal seams. An industry
324 More Incidents that Define Process Safety
practice is to apply rock dust over the coal dust to prevent coal
dust explosions. Refer to Figure 7.5-1.
What Happened. The initial explosion involved methane gas
released from the coal and ignited by the friction of the shearing
operation as it hit the surrounding rocks. The methane explosion
caused the coal dust to be dispersed in the air, which then
supported subsequent coal dust explosions. The coal dust
explosions traveled more than two miles around the various mine
tunnels. Reports said it sounded like thunder, went on for
minutes, and threw wood cribbing, signs, and other materials
around. It damaged the ventilation system and electrical system.
The workers died from blast injuries and from carbon monoxide
poisoning.
The miners attempted to put on their “rescuers”, a self-
contained, self-rescue breathing apparatus which provides less
than one hour breathing air. One man stayed with his team for
forty-five minutes. He tried to call on the radio and use the
tracking device, but there was no response. Mine employees who
were in the on-site offices heard the sound of the ventilation fans
7.6.1 Summary
There have been a number of incidents in university laboratories
that resulted in severe injuries and fatalities. The laboratories
failed to manage process safety almost in its entirety. These
incidents have prompted changes in the way many university
laboratories address process safety. The CSB has created a video
entitled “Experimenting with Danger” that is aimed at highlighting
the hazards at university chemical labs (CSB, 2011e).
328 More Incidents that Define Process Safety
Key Points
Process Safety Culture – Make sure process safety is part of
your safety culture. Regardless of what culture you are in, if
there are process safety hazards, then process safety should be
a key part of your culture.
Hazard Identification and Risk Analysis – It all starts here.
Identify hazards. If you don’t identify the hazard and assess the
risk, then you will not be able to put barriers in place and
manage the risk.
Incident Investigation – If something unexpected happens,
question why. Investigate it. You might identify a hazard or a
broken barrier. Then document it and share your learning with
others.
7.6.2 Description
Three incidents are used to discuss the Key Points in this Chapter
1. University of Hawaii. On March 16, 2016, a hydrogen/oxygen
explosion occurred at the Manoa campus, resulting in a
postdoctoral researcher losing her arm and suffering
additional severe injuries. The lab was using hydrogen,
oxygen, and carbon dioxide in the green production of
bioplastics and biofuels. This gas mixture has a very large
flammability range as seen in Figure 7.6-1. The gas mixture
was likely ignited by a static discharge involving the
researcher, the tank, and a gauge. The equipment was not
bonded and grounded, and the gauge was not intrinsically
safe (UC, 2016).
2. University of California at Los Angeles. In December 2008, a
staff research associate was fatally burned when the t-butyl
lithium she was working with caught fire. The plunger on the
syringe came loose and the pyrophoric compound spilled on
her clothing, igniting spontaneously. No flame-resistant lab
coats were used. No hazard assessment was performed and
Chapter 7 Non-Oil/Chemical Incidents 329
7.7.1 Summary
The Mars Climate Orbiter (MCO) was launched on December 11,
1998, and contact was lost on September 23, 1999, as it entered
into an orbit around Mars.
Key Points
Stakeholder Outreach – Are you speaking the same language?
In large projects and complex operations, it is important that
people have the same understanding of relevant terminology
and are using the same basis such that all the project/operation
parts work safely together.
Conduct of Operations – Trust. And verify. Conducting good
operations and projects requires managers to trust that the
competent people on the job will do a good job. They should
also understand that people make mistakes. Thus, they should
verify that the job, especially the safety aspects, was completed
as planned.
7.7.2 Description
Background. The Mars Surveyor '98 program included the Mars
Climate Orbiter and the Mars Polar Lander, which were launched
separately. The intent was to study the weather on Mars. The
MCO would also serve as a communication relay for the Mars
Polar Lander (NASA, 2018).
Process. The Mars Climate Orbiter includes propulsion and
equipment modules. The mass at launch is 629 kg (1,387 lb) which
includes 291 kg (642 lb) of propellant.
What Happened. The spacecraft reached Mars. It passed behind
Mars, and contact was not re-established. Some of the spacecraft
commands were in English units instead of being converted to
Chapter 7 Non-Oil/Chemical Incidents 335
Appendix 1
.PSF*ODJEFOUTUIBU%FGJOF1SPDFTT4BGFUZ
By $$14
¥5IF"NFSJDBO*OTUJUVUFPG$IFNJDBM&OHJOFFST
Appendix 1 339
340 More Incidents that Define Process Safety
Appendix 1 341
342 More Incidents that Define Process Safety
References
ABET 2015. “Criteria for accrediting engineering programs,”
Accreditation Board for Engineering and Technology,
Baltimore, MD.
ACS 2018. “Guidelines for Chemical Laboratory Safety,” viewed
July 30, 2018, www.acs.org/content/acs/en/chemical-
safety/guidelines-for-chemical-laboratory-safety.html,
American Chemical Society.
AFPM. “Safety Portal Event Sharing Database, American Fuel &
Petrochemical Manufacturers,” www.afpm.org/safetyportal
(accessed December 1, 2017), Login credentials required.
Arm-Tex. Viewed on March 12, 2019. www.arm-tex.com/hamer-
line-blind-valves.html
Arco 1991. “A Briefing on the ARCO Chemical Channelview plant
July 5, 1990 accident.” ARCO Chemical Company, January
1990.
API 2009, API RP 939-C: “Guidelines for Avoiding Sulfidation
(sulfidic) corrosion failures in oil refineries, American
Petroleum Institute, Washington, D.C.
Barton, J. & Rogers, R. 1997. Chemical Reaction Hazards: A Guide to
Safety. Institute of Chemical Engineers, Elsevier, Amsterdam,
Netherlands.
BBC. “Lagos pipeline blast kills scores.” Viewed May 16, 2018.
http://news.bbc.co.uk/2/hi/africa/6209845.stm
BEA 2012. “Final Report on the accident on 1st June 2009 to the
Airbus A330-203 registered F-GZCP operated by Air France
flight AF 447 Rio de Janeiro – Paris.” Bureau d’Enquetes et
d’Analyses pour la securite de l’aviation civile, July 2012.
Bills, Kym and Agostini, David. 2009. “Varanus Island incident
investigation,” Government of Western Australia, June.
www.slp.wa.gov.au/salesinfo/varanusinquiry.pdf
.PSF*ODJEFOUTUIBU%FGJOF1SPDFTT4BGFUZ
By $$14
¥5IF"NFSJDBO*OTUJUVUFPG$IFNJDBM&OHJOFFST
References 343
CCPS 2007. Guidelines for Risk Based Process Safety. Center for
Chemical Process Safety of the American Institute of Chemical
Engineers, New York, NY.
CCPS 2007a. Human Factors Methods for Improving Performance
in the Process Industries. Center for Chemical Process Safety
of the American Institute of Chemical Engineers, New York,
NY.
CCPS 2008. Incidents that Define Process Safety. Center for
Chemical Process Safety of the American Institute of Chemical
Engineers, New York, NY.
CCPS 2008a. Guidelines for Chemical Transportation Safety, Security
and Risk Management. Center for Chemical Process Safety of
the American Institute of Chemical Engineers, New York, NY.
CCPS 2009. Inherently safer chemical processes. Center for
Chemical Process Safety of the American Institute of Chemical
Engineers, New York, NY.
CCPS 2011. Guidelines for Vapor Cloud Explosion, Pressure Vessel
Burst, BLEVE and Flash Fire Hazards, 2nd Edition. Center for
Chemical Process Safety of the American Institute of Chemical
Engineers, New York, NY.
CCPS 2012. Guidelines for Engineering Design for Process Safety, 2nd
Edition. Center for Chemical Process Safety of the American
Institute of Chemical Engineers, New York, NY.
CCPS 2012a. Guidelines for Evaluation Process Plant Building for
External Explosions, Fires, and Toxic Releases, 2nd Edition. Center
for Chemical Process Safety of the American Institute of
Chemical Engineers, New York, NY.
CCPS 2016. Guidelines for Asset Integrity Management. Center for
Chemical Process Safety of the American Institute of Chemical
Engineers, New York, NY.
CCPS 2017. Guidelines for Pressure Relief and Effluent Handling
Systems, 2nd Edition (CCPS 2017). Center for Chemical Process
Safety of the American Institute of Chemical Engineers, New
York, NY.
References 345
http://oecdkorea.org/common/attachfile/attachfileDownload
.do?attachNo=00002828
Kwon 2016. “System Theoretic Safety Analysis of the Sewol-Ho
Ferry Accident in South Korea. Yisug Kwon”, Submitted to the
System Design and Management Program in Partial
Fulfillment of the Requirements for the Degree of Master of
Science in Engineering and Management at the
Massachusetts Institute of Technology, February 2016.
Lexis/Nexis. 2016. “Workers Injured In Chemical Plant Explosion
Obtain $30 Million Verdicts In Two Louisiana State Court Trials
Against Plant Owners/Operators.” LexisNexis December 8.
www.lexisnexis.com/jvsubmission/b/case_of_week/archive/2
016/12/08/workers-injured-in-chemical-plant-explosion-
obtain-30-million-verdicts-in-two-louisiana-state-court-trials-
against-plant-owners-operators.aspx?Redirected=true
Marmo, L., Piccinni, N., Russo, G., Russo, P., Munaro, L. Multiple
tank explosions in an edible oil refinery plant: A case study.
Chemical Engineering Technology, V. 36, No. 7, p.1131-1137.
MIIB 2008a. “The Buncefield incident, Vol. 1.” Major Incident
Investigation Board,
MIIB 2008b. “The Buncefield incident, Vol. 1.” Major Incident
Investigation Board,
MOM 2011. “Update on MOM’s investigation on fire at Pulau
Bokum.” Singapore Ministry of Manpower Press Release, 2-
October. www.mom.gov.sg/newsroom/press-
releases/2011/update-on-moms-investigation-on-fire-at-
pulau-bukom
MOM 2011b. “Shell fined $80,000 for 2011 Pulau Bokum refinery
fire.” Singapore Ministry of Manpower Press Release, 29-
October. www.mom.gov.sg/newsroom/press-
releases/2012/shell-fined-80000-for-2011-pulau-bukom-
refinery-fire
MoPNG Committee. 2010. Constituted by Govt. of India.
Independent Inquiry Committee, Report on Indian Oil
References 353
INDEX
Air France
AF 447, 331
Concorde, 335
ARCO Channelview, 69, 71
Asset Integrity and Reliability, 46, 71, 74, 98, 116, 124, 157, 158,
174, 178, 188, 199, 201, 205, 218, 232, 240, 246, 250, 269, 274,
276, 277, 283, 308, 318, 324, 327, 330
Auditing, 49, 275, 290, 294
Azote de France, Toulouse, 100
Bartlo Packaging, Inc., 100
Bayer CropScience, 101
Bhopal, 37, 39, 42, 230, 264, 300
Big Branch Coal Mine, 357, 358, 359, 360
BLSR Operating Ltd., 105, 106, 134-140, 218
BP
Grangemouth, UK, 226
Texas City, TX, 226
Buncefield Depot, 147-159, 163
CAPECO Storage Tank, Puerto Rico, 157, 159
Celanese Pampa, 166, 168, 171
Challenger, FL, 334, 372
Chemical Safety and Hazard Investigation Board (CSB), 14, 39, 41,
53, 55, 57, 58, 62-64, 74, 75, 79, 82, 100, 101, 105, 112-116, 122,
138, 141, 158, 184, 185, 187, 190, 192, 196, 197, 207, 211, 219,
224, 231, 237, 239, 242, 245, 249, 250, 267, 284, 290, 362
Chernobyl, USSR, 39, 372
Chevron Richmond, 115, 117, 122, 124, 126
CITGO, Corpus Christi, 105, 106, 141, 290, 291, 293, 294, 378
Columbia, TX, 335, 372
Combustible dust, 41, 105, 108, 113, 114, 181, 182, 185, 188-191,
196, 228
.PSF*ODJEFOUTUIBU%FGJOF1SPDFTT4BGFUZ
By $$14
¥5IF"NFSJDBO*OTUJUVUFPG$IFNJDBM&OHJOFFST
Index 359
Commit to Process Safety, 43, 44, 61, 67, 73, 81, 87, 97, 112, 122,
132, 139, 155, 171, 187, 197, 204, 210, 224, 238, 250, 272, 297,
308, 313, 330, 343, 349, 360, 366
Compliance with Standards, 44, 61, 81, 86, 87, 97, 105, 106, 112,
123, 127, 132, 135, 139, 150, 155, 187, 198, 204, 210, 219, 224,
238, 246, 250, 269, 272, 295, 297, 304, 308
ConAgra Foods, 207, 208
Concept Sciences, Inc., 100
Conduct of Operations, 14, 24, 48, 50, 66, 68, 160, 164, 173, 178,
179, 183, 189, 199, 241, 310, 313, 314, 317, 327, 330-333, 347,
350, 360, 369, 372
Contractor Management, 46, 140, 233, 240, 352, 355, 370
Courrieres Mine, France, 372
Deepwater Horizon, 230-233, 240-243, 252
DPC Enterprises, 276, 278-283
DuPont
Belle Plant, 267, 269, 272, 274
LaPorte Plant, 259
Elf Refinery, France, 226
Emergency isolation valves, 15, 25, 105, 133, 134
Emergency Management, 48, 63, 76, 84, 116, 124, 158, 160, 165,
214, 246, 251, 253, 259, 266, 275, 277, 284, 286, 289, 290, 293,
295, 299, 304, 309, 310, 313, 314, 317, 319, 325, 346, 347, 351,
356, 361
Engineering design, 51, 199, 241, 242
Erika, France, 300
Exxon Valdez, AK, 333, 334
Flash Airlines, Egypt, 335
Flight TS 236, Atlantic, 335
Freedom Industries, Inc., 244-246, 248, 249, 250, 251
Fukushima Daiichi Nuclear Plant, 338, 339, 343, 344, 346
Gaylord Chemical, 314-317
Georgia-Pacific, 284, 286
Goodyear, TX, 180
Hayes Lemmerz, 147, 191, 196, 197, 198, 199
Hazard Identification and Risk Analysis, 16, 45, 46, 58, 62, 84, 88,
92, 97, 103, 127, 133, 156, 168, 171, 188, 198, 199, 214, 218, 253,
257, 260, 265, 273, 286, 288, 324, 331, 333, 339, 343, 363, 368
360 More Incidents that Define Process Safety
Understand Hazards and Risk, 43, 45, 62, 83, 92, 97, 133, 139, 156,
171, 188, 198, 217, 257, 264, 273, 288, 324, 333, 343
University laboratory incidents, 379
Valero-McKee, 105, 128
Varanus Island, Australia, 147, 201, 202, 204-206
West Fertilizer Company, TX, 41, 74, 75, 76, 77, 81, 146
Williams Olefins, 174
Workforce Involvement, 45, 50