ITB SECTION REQUIRED INFORMATION

REFERENCE
ITB 3.3(g)(2)(ii)(b) Works to be specified in layout plan8 for
Interception and Diversion Works:
1. Diversion Structure
2. Intercepting Sewer
and/orSewerage Network:
1. Primary and Trunk sewerage network
2. Secondary and collector lines on the sewerage network;
3. Sewage Pumping Station(s);
4. Inspection chambers and manholes;
5. Infrastructure, if any, proposed for reuse of treated effluent
ITB 3.3(h)(4)(ii)(b) Language capabilities for Bidder‘s Personnel: English
ITB 3.3(h)(4)(ii)(b), List of Key Staff to be deployed by the Operator for each town project
3.3(h)(5) (Danapur, Phulwarishariff & Fatuha) during the Design buildservices for
STP and Sewerage Network and/or Interception & Diversion Works as
stipulated in SCC 8.3 is reproduced here.

S.No Staff No Minimum Qualifications


*
A Graduate in Civil Engineering with
Project not less than 10 years‘ experience in
1 1
Manager construction of Sewage Treatment
Plants/ Sewerage networks.
A Civil Engineer (Graduate Engineer)
with not less than eight years‘
Civil
2 2 experience in construction of similar
Engineer
engineering works or Diploma in Civil
Engineering with 8 years‘ experience
A Electro /Mechanical Engineer
(Graduate Engineer) with not less than 8
Electro
years‘ experience in construction of
3 Mechanical 1
similar engineering works or Diploma in
Engineer
Electro/ Mechanical Engineering with 10
years‘ experience
Diploma in Civil Engineering with
Civil
4 3 minimum 2 years‘ experience in
Supervisors
Construction of Civil Engineering works
Environmen Graduate in civil Engineering /
5 1
tal Engineer environmental Science / environmental