ID Task Name Duration Start Finish

February 9, 2020 February 23, 2020 March 8, 2020 March 22, 2020 April 5, 2020
Mon 2/17 Fri 2/21 Tue 2/25 Sat 2/29 Wed 3/4 Sun 3/8 Thu 3/12 Mon 3/16 Fri 3/20 Tue 3/24 Sat 3/28 Wed 4/1 Sun 4/5 Thu 4/9 Mon 4/13
6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4
0 Parking & Guard's House 45 days Mon 2/24/20 Wed 4/8/20 2/24 45 days
1 1 STEEL STRUCTURE WORK 45 days Mon 2/24/20 Wed 4/8/20 2/24 45 days
2 1.1 Structural Design 0 days Mon 2/24/20 Mon 2/24/20 2/24
3 1.1.1 Approval Drawing & Shop Drawing 0 days Mon 2/24/20 Mon 2/24/20 2/24
4 1.2 Production 20 days Mon 2/24/20 Sat 3/14/20 2/24 20 days
5 1.2.1 Fabrication 20 days Mon 2/24/20 Sat 3/14/20 2/24 20 days
6 1.3 Transportation 2 days Sun 3/15/20 Mon 3/16/20 3/15 2 days
7 1.3.1 Dilevery 2 days Sun 3/15/20 Mon 3/16/20 3/15 2 days
8 1.4 Errection Work 21 days Tue 3/17/20 Mon 4/6/20 3/17 21 days
9 1.4.1 Setting up Anchor bolts 2 days Tue 3/17/20 Wed 3/18/20 3/17 2 days
10 1.4.2 Frame Errection 14 days Thu 3/19/20 Wed 4/1/20 3/19 14 days
11 1.4.3 Decking Installation 3 days Thu 4/2/20 Sat 4/4/20 4/2 3 days
12 1.4.4 Saircase Erection 2 days Sun 4/5/20 Mon 4/6/20 4/5 2 days
13 1.5 Defected Works 2 days Tue 4/7/20 Wed 4/8/20 4/7 2 days
14 1.5.1 Touch-up Paiting 2 days Tue 4/7/20 Wed 4/8/20 4/7 2 days

Task External Tasks Duration-only External Tasks Progress


Split External Milestone Manual Summary Rollup External Milestone Deadline
Project: Parking & Guard's House Milestone Inactive Milestone Manual Summary Baseline
Date: Mon 2/17/20
Summary Inactive Summary Start-only Baseline Milestone
Project Summary Manual Task Finish-only Baseline Summary