Storage Tanks Racks Classic EPS/WBS Layout 03-mar-20 09:52

ID tâche Chemin le plus Critique Nom de la tâche Durée Durée % d'avancement Début Fin Marge
long initiale restante - Planning totale

Storage Tanks & Racks 61.46 61.46 0% 17-fév-20 24-avr-20 09:39 12.17
08:00
Tank Modeling 46.46 46.46 0% 17-fév-20 08:00 08-avr-20 09:39 12.17

Technical Modeling 33.00 33.00 0% 24-fév-20 15:45 01-avr-20 08:45 12.17


Calcul Préliminaire 4.50 4.50 0% 24-fév-20 15:45 28-fév-20 10:45 12.17
A1010 Fluid introduction 1.50 1.50 0% 24-fév-20 15:45* 25-fév-20 17:45 12.17
A1020 Materiel's Type 1.50 1.50 0% 25-fév-20 17:45* 27-fév-20 08:45 12.17
A1030 Isolation's Type 1.50 1.50 0% 27-fév-20 08:45* 28-fév-20 10:45 12.17
Dimensionnement du bac 10.50 10.50 0% 28-fév-20 10:45 11-mar-20 15:45 12.17
A1100 DESIGN CONSIDERATIONS & Calculation hypothesis
1.50 1.50 0% 28-fév-20 10:45 02-mar-20 12:45 12.17
A1110 Shell Design 1.50 1.50 0% 02-mar-20 12:45 03-mar-20 15:45 12.17
A1120 SHELL OPENINGS 1.50 1.50 0% 03-mar-20 15:45 04-mar-20 17:45 12.17
A1310 TOP AND INTERMEDIATE STIFFENING RINGS 1.50 1.50 0% 04-mar-20 17:45 06-mar-20 08:45 12.17
A1320 ROOFS 1.50 1.50 0% 06-mar-20 08:45 09-mar-20 10:45 12.17
A1330 WIND LOAD ON TANKS (OVERTURNING STABILITY)
1.50 1.50 0% 09-mar-20 10:45 10-mar-20 12:45 12.17
A1340 Tank Anchorage 1.50 1.50 0% 10-mar-20 12:45 11-mar-20 15:45 12.17
Nomenclature du Bac 1.50 1.50 0% 11-mar-20 15:45 12-mar-20 17:45 12.17
A1130 Create the Nomenclature with details 1.50 1.50 0% 11-mar-20 15:45 12-mar-20 17:45 12.17
Calcul de Génie Civil 15.00 15.00 0% 12-mar-20 17:45 30-mar-20 17:45 12.17
A1200 Define the Shell Attachments 1.50 1.50 0% 12-mar-20 16-mar-20 12.17
17:45 08:45
A1210 Choose the Bottom Connections 1.50 1.50 0% 16-mar-20 08:45 17-mar-20 10:45 12.17
A1220 Sizing the Roof Manholes 1.50 1.50 0% 17-mar-20 10:45 18-mar-20 12:45 12.17
A1230 Design the Roof Venting 1.50 1.50 0% 18-mar-20 12:45 19-mar-20 15:45 12.17
A1240 Sizing the Rectangular Roof Openings 1.50 1.50 0% 19-mar-20 15:45 20-mar-20 17:45 12.17
A1250 Specify the Water Drawoff Sumps 1.50 1.50 0% 20-mar-20 17:45 24-mar-20 08:45 12.17
A1260 Choose the Scaffold-Cable Support 1.50 1.50 0% 24-mar-20 08:45 25-mar-20 10:45 12.17
A1270 Sizing the Threaded Connections 1.50 1.50 0% 25-mar-20 10:45 26-mar-20 12:45 12.17
A1280 Choose the suitable Platforms, Walkways, 1.50 1.50 0% 26-mar-20 27-mar-20 12.17
and Stairways 12:45 15:45
A1290 Define the Other Appurtenances and Attachments 1.50 1.50 0% 27-mar-20 15:45 30-mar-20 17:45 12.17
Nomenclature de Génie Civil par rapport au stock 1.50 1.50 0% 30-mar-20 17:45 01-avr-20 08:45 12.17
A1350 Define the Allowable Stresses 1.50 1.50 0% 30-mar-20 17:45 01-avr-20 08:45 12.17
Economical Modeling 43.46 43.46 0% 17-fév-20 08:00 03-avr-20 16:39 12.17

Remaining Level of Effort Primary Ba... Page 1 of 6 TASK filter: Toutes les tâches
Actual Level of Effort Second Ba... © Oracle Corporation
Storage Tanks Racks Classic EPS/WBS Layout 03-mar-20 09:52

Marge totale Trimestre


1 2
12.17 24-avr-20 09:39, Storage Tan

12.17 08-avr-20 09:39, Tank Modeling

12.17 01-avr-20 08:45, Technical Modeling


12.17 28-fév-20 10:45, Calcul Préliminaire
12.17 Fluid introduction
12.17 Materiel's Type
12.17 Isolation's Type
12.17 11-mar-20 15:45, Dimensionnement du bac
12.17 DESIGN CONSIDERATIONS & Calculation hypothesis
12.17 Shell Design
12.17 SHELL OPENINGS
12.17 TOP AND INTERMEDIATE STIFFENING RINGS
12.17 ROOFS
12.17 WIND LOAD ON TANKS (OVERTURNING STABILITY)
12.17 Tank Anchorage
12.17 12-mar-20 17:45, Nomenclature du Bac
12.17 Create the Nomenclature with details
12.17 30-mar-20 17:45, Calcul de Génie Civil
12.17 Define the Shell Attachments
12.17 Choose the Bottom Connections
12.17 Sizing the Roof Manholes
12.17 Design the Roof Venting
12.17 Sizing the Rectangular Roof Openings
12.17 Specify the Water Drawoff Sumps
12.17 Choose the Scaffold-Cable Support
12.17 Sizing the Threaded Connections
12.17 Choose the suitable Platforms, Walkways, and Stairways

12.17 Define the Other Appurtenances and Attachments


12.17 01-avr-20 08:45, Nomenclature de Génie Civil par rapport au stock
12.17 Define the Allowable Stresses
12.17 03-avr-20 16:39, Economical Modeling

Remaining Level of Effort Primary Ba... Page 2 of 6 TASK filter: Toutes les tâches
Actual Level of Effort Second Ba... © Oracle Corporation
Storage Tanks Racks Classic EPS/WBS Layout 03-mar-20 09:52

ID tâche Chemin le plus Critique Nom de la tâche Durée Durée % d'avancement Début Fin Marge
long initiale restante - Planning totale

Bottom-up model 41.21 41.21 0% 17-fév-20 08:00 01-avr-20 18:43 12.17


A1460 Aggregate an individual estimate of each task in order
1.12
to determine
1.12the resources needed
0% 17-fév-20
by the entire
08:00project.
17-fév-20 17:58 51.14
A1450 Identify the dependencies between the tasks and allocate
1.12 resources
1.12 to each task carefully
0% 01-avr-20 08:45 01-avr-20 18:43 12.17
Parametrical model: 2.24 2.24 0% 01-avr-20 18:43 03-avr-20 16:39 12.17
A1470 Determine the cost on the base of research and historical
1.12 data 1.12 0% 01-avr-20 18:43 02-avr-20 17:41 12.17
A1480 Determine estimate the whole project’s cost 1.12 1.12 0% 02-avr-20 17:41 03-avr-20 16:39 12.17
Software coding 3.00 3.00 0% 03-avr-20 16:39 08-avr-20 09:39 12.17
Model's insertion 1.50 1.50 0% 03-avr-20 16:39 06-avr-20 18:39 12.17
A1490 Creat the suitable fonctions based on the technicale/economical
1.50 1.50
Algorithme 0% 03-avr-20 16:39 06-avr-20 18:39 12.17
Model's verification 1.50 1.50 0% 06-avr-20 18:39 08-avr-20 09:39 12.17
A1500 Verify the code's fonctionnality 1.50 1.50 0% 06-avr-20 18:39 08-avr-20 09:39 12.17
Rack Modeling 15.00 15.00 0% 08-avr-20 09:39 24-avr-20 09:39 12.17

Technical Modeling 6.00 6.00 0% 08-avr-20 09:39 14-avr-20 18:39 12.17


Applied Loads 1.50 1.50 0% 08-avr-20 09:39 09-avr-20 11:39 12.17
A1510 Define the applied loads on the structure 1.50 1.50 0% 08-avr-20 09:39 09-avr-20 11:39 12.17
Functional materials 1.50 1.50 0% 09-avr-20 11:39 10-avr-20 14:39 12.17
A1520 Choose the suitable materiel supporting the loads 1.50 1.50 0% 09-avr-20 11:39 10-avr-20 14:39 12.17
Design as a modular frame 1.50 1.50 0% 10-avr-20 14:39 13-avr-20 16:39 12.17
A1530 Design the rack as a modular fram base on the CM 66
1.50 1.50 0% 10-avr-20 14:39 13-avr-20 16:39 12.17
Rack foundation 1.50 1.50 0% 13-avr-20 16:39 14-avr-20 18:39 12.17
A1540 Sizing the foundation in order to support the different 1.50
loads applicated
1.50 0% 13-avr-20 16:39 14-avr-20 18:39 12.17
Economical Modeling 6.00 6.00 0% 14-avr-20 18:39 21-avr-20 16:39 12.17
Bottom-up model 3.00 3.00 0% 14-avr-20 18:39 17-avr-20 11:39 12.17
A1550 Identify the dependencies between the tasks and allocate
1.50 resources
1.50 to each task carefully
0% 14-avr-20 18:39 16-avr-20 09:39 12.17
A1560 Aggregate an individual estimate of each task in order
1.50
to determine
1.50the resources needed
0% 16-avr-20
by the entire
09:39project.
17-avr-20 11:39 12.17
Parametrical model: 3.00 3.00 0% 17-avr-20 11:39 21-avr-20 16:39 12.17
A1570 Determine the cost on the base of research and historical
1.50 data 1.50 0% 17-avr-20 11:39 20-avr-20 14:39 12.17
A1580 Determine estimate the whole project’s cost 1.50 1.50 0% 20-avr-20 14:39 21-avr-20 16:39 12.17
Software coding 3.00 3.00 0% 21-avr-20 16:39 24-avr-20 09:39 12.17
Model's insertion 1.50 1.50 0% 21-avr-20 16:39 22-avr-20 18:39 12.17
A1590 Creat the suitable fonctions based on the technicale/economical
1.50 1.50
Algorithme 0% 21-avr-20 16:39 22-avr-20 18:39 12.17
Model's verification 1.50 1.50 0% 22-avr-20 18:39 24-avr-20 09:39 12.17

Remaining Level of Effort Primary Ba... Page 3 of 6 TASK filter: Toutes les tâches
Actual Level of Effort Second Ba... © Oracle Corporation
Storage Tanks Racks Classic EPS/WBS Layout 03-mar-20 09:52

Marge totale Trimestre


1 2
12.17 01-avr-20 18:43, Bottom-up model
51.14 Aggregate an individual estimat
12.17 Identify the dependencies between
12.17 03-avr-20 16:39, Parametrical model:
12.17 Determine the cost on the ba
12.17
12.17 08-avr-20 09:39, Software coding
12.17 06-avr-20 18:39, Model's insertion
12.17
12.17 08-avr-20 09:39, Model's verification
12.17
12.17 24-avr-20 09:39, Rack Model

12.17 14-avr-20 18:39, Technical Modeling


12.17 09-avr-20 11:39, Applied Loads
12.17 Define the applied loads on the
12.17 10-avr-20 14:39, Functional materials
12.17 Choose the suitable materiel
12.17 13-avr-20 16:39, Design as a modular frame
12.17
12.17 14-avr-20 18:39, Rack foundation
12.17
12.17 21-avr-20 16:39, Economical Modeli
12.17 17-avr-20 11:39, Bottom-up model
12.17
12.17
12.17 21-avr-20 16:39, Parametrical mode
12.17
12.17
12.17 24-avr-20 09:39, Software co
12.17 22-avr-20 18:39, Model's insertio
12.17
12.17 24-avr-20 09:39, Model's ver

Remaining Level of Effort Primary Ba... Page 4 of 6 TASK filter: Toutes les tâches
Actual Level of Effort Second Ba... © Oracle Corporation
Storage Tanks Racks Classic EPS/WBS Layout 03-mar-20 09:52

ID tâche Chemin le plus Critique Nom de la tâche Durée Durée % d'avancement Début Fin Marge
long initiale restante - Planning totale

A1600 Verify the code's fonctionnality 1.50 1.50 0% 22-avr-20 18:39 24-avr-20 09:39 12.17

Remaining Level of Effort Primary Ba... Page 5 of 6 TASK filter: Toutes les tâches
Actual Level of Effort Second Ba... © Oracle Corporation
Storage Tanks Racks Classic EPS/WBS Layout 03-mar-20 09:52

Marge totale Trimestre


1 2
12.17

Remaining Level of Effort Primary Ba... Page 6 of 6 TASK filter: Toutes les tâches
Actual Level of Effort Second Ba... © Oracle Corporation

S-ar putea să vă placă și