Sunteți pe pagina 1din 4

CHAPTER IV.

MONITORING AND EVALUATION

The School Planning Team (SPT) will conduct the monitoring and evaluation based on the time set by the Project Team in their project
design. The tool to be used is the Project Monitoring Form.

Issues/ Recommendations Signature of


Name of Project Project Objectives and Targets Date of Accomplishments Problem/ / SPT and
Monitoring / Status to Date Challenges Action Points Project Team
Leader

To increase enrolment From 104 to


Project REACH
150 in 3 years

Adopt-A-Child Program To maintain Zero (0) Drop out

To increase LAPG MPS by 15 in 3


Project DIAPAN
years

To eradicate number of NR/NN From


Project ERACA
15 to 0 in 3 years

To decrease cases of SW and W


Project Busog-lusog
pupils From 15 to 0 in 3 years

To increase participation in scouting,


Project Talino, Tikas at Lakas
sports & academic quiz bee

Project REFORMAT To reproduce varied School Forms

CARE FOR TEACHERS To provide teachers supplies


CONCERN FOR PUPILS To provide pupils school supplies

To procure DRRM materials &


Project SAFE
facilities

School ko, linisin, ayusin at To conduct Brigada Eskwela


Pagandahin ko activities

Oplan Kalinga sa mga To formulate and implement Child


Kabataan sa Paaralan Protection Policy

Project WOW (War on To administer deworming pills twice


Worms) a year

To administer medicine in an
Oplan Iwas at Alis disease
emergency cases

To Produce/Print/Reproduce LR
Oplan LRMDS
materials

To procure, repair & maintenance of


SBM Wins/Wash
SBM Wins/Wash materials & facilities

OPLAN Pagbabakod sa To construct 60 spans of Perimeter


Paaralan Fence in 3 years

To conduct School site relocation


OPLAN Sukat at Tanda
survey in 3 years

To eject Two (2) illegal/unauthorized


OPLAN demolition
settlers in the school site in 3 years

To construct Four (4) additional


Instructional Classroom
classrooms in 3 years
To construct BHS/Covered Mini-gym
BHS/Covered Mini-gym
in 3 years

To conduct minor repair of Two (2)


Minor Repair of Classrooms
classrooms in 3 years

Signages To enhance school directional sign

To construct school gate with


School Gate with Pergola
pergola in 3 years

School Stage with Covered To construct school stage with


Mini-gym covered mini-gym in 3 years

To construct footwalk along school


FOOTWALK
premises

To construct school library/reading


Library/Reading Center
center in 3 years

To enhance/repair and maintain


Provision of School Toilets
School Toilets

To attend Trainings, INSET, LAC,


Talino ko, Share ko
Conferences

Project ILAW To pay electric bill on time

To allocate funds for the


OFFICE SUPPLIES
procurement of office supplies

To pay the services of the school


UTILITY WORKER
utility worker
To Allocate funds for monthly
SCHOOL COMMUNICATION
internet bills and cellphone loads

FIDELITY BOND To allocate funds for fidelity bond

To provide enough budget for


Graduation/Recognition
recognition and graduation
Expenses
ceremonies
ICT Procurement and To allocate funds for ICT
Maintenance procurement and maintenance

To allocate funds for SH travel


TRAVEL ALLOWANCE
allowance

To procure health and sanitary


HEALTH and SANITATION
materials and facilities

To put up a functional and


Gulayan sa Paaralan
sustainable Gulayan sa Paaralan