The document proposes purchasing a fabricated movable material recovery facility for 55,000 Philippine pesos. The facility will be located in Barangay Santiago, Gingoog City. It will be a single unit made of steel matting, angle bars, and GI sheet roofing with a metal cart wheel. The project aims to purchase one unit of the fabricated facility for 50,000 pesos to be funded through the IRA appropriation.
The document proposes purchasing a fabricated movable material recovery facility for 55,000 Philippine pesos. The facility will be located in Barangay Santiago, Gingoog City. It will be a single unit made of steel matting, angle bars, and GI sheet roofing with a metal cart wheel. The project aims to purchase one unit of the fabricated facility for 50,000 pesos to be funded through the IRA appropriation.
The document proposes purchasing a fabricated movable material recovery facility for 55,000 Philippine pesos. The facility will be located in Barangay Santiago, Gingoog City. It will be a single unit made of steel matting, angle bars, and GI sheet roofing with a metal cart wheel. The project aims to purchase one unit of the fabricated facility for 50,000 pesos to be funded through the IRA appropriation.
Project Title Purchase of Fabricated Movable Material Recovery Facility Category Source of Fund : Physical Target 1- UNIT IRA Location BRGY. SANTIAGO Appropriation Allotment : City Gingoog City Php 55, 000.00 Total Project CostPhp 55,000.00 Implementation Mode : BRGY Project Description : Duration : Equipment Needed : Purchase 1-unit of Fabricated Technical Personnel Required: Movable Material Recovery Facility ESIMATED COST OF PROPOSED WORK BY ITEM ( Materials, Labor and Equipment ) ITEM SCOPE OF WORK TO BE DONE % of Total Unit Quantity Unit Price Amount Purchase 1-unit of Fabricated ITEM I Movable Material Recovery 100.00 UNIT 1.0 50,000.00 50,000.00 Facility
TOTAL 100.00 50,000.00
BREAKDOWN OF ESTIMATED EXPENDITURES
A. DIRECT COST % of Total 1. Materials 88.89 50,000.00 2. Equipment Expenses 3. Labor 4. Miscellaneous SUB- TOTAL 50,000.00 B. INDIRECT COST 5. Contractor's Profit 6. Project Contingencies ( OCM ) 7. Tax/ VAT 8. Mobilization / Demobilization SUB- TOTAL TOTAL OF A & B Php C. ESTIMATED GOVERNMENT EXPENSES 9. Eng'g. Admin Expenses ( 5% ) 10. Quality Control 11. RROW 12. Reserved for Extra Works 11.11 5,000.00 TOTAL ESTIMATED PROJECT COST 100.00 55,000.00
PREPARED BY : CONFORMED BY: REVIEWED BY:
MARK ZEUSTY M. NAMBATAC JOSEPH R. GOMEZ MARIABUNA R. PEREZ
Engineer I Brgy. Captain Engineer IV
RECOMMENDING APPROVAL : APPROVED :
GUALBERTO C. OBEDENCIO FELIPA M. BARANDA
Assistant City Engineer City Engineer PROJECT : PURCHASE OF FABRICATED MOVABLE RECOVERY FACILITY LOCATION : BRGY. SANTIAGO, GINGOOG CITY SUBJECT : BILL OF MATERIALS AND COST ESTIMATE
ITEM I- PURCHASE OF FABRICATED MOVABLE MATERIALS RECOVERY FACILITY
Quantity : 1 UNIT
a.) MATERIALS Unit Quantity Unit Cost Amount
Fabricated Movable Material Recovery Facility Made of Steel Matting, Angle Bar, Unit 1.00 50,000.00 50,000.00 G.I. Sheet Roofing w/ Metal Cart Wheel
Note : SEE DIMENSION @ PLAN
SUMMARY Amount
Purchase 1-unit of Fabricated
ITEM I Movable Material Recovery 50,000.00 Facility TOTAL PROJECT COST 50,000.00
PREPARED BY : CONFORMED BY: REVIEWED BY:
MARK ZEUSTY M. NAMBATAC JOSEPH R. GOMEZ MARIABUNA R. PEREZ