Documente Profesional
Documente Cultură
B 16-03-2019 Issued for Information D.C. CHON S.G. SUNG S.S. JUNG
A 28-02-2019 Issued for Information D.C. CHON S.G. SUNG J.T. BAIK
Rev. Date Description DSGN CHKD APPD
PROJECT :
INDONESIA
OWNER :
OWNER’S DESIGN :
CONTRACTOR :
SUBCONTRACTOR :
PREPARED BY DATE
KARANGMAS 16-03-2019 Method Statement for
UNGGUL Excavation and Pile Head Cutting
CHECKED BY DATE
for Buildings
HDEC (ARCH) 16-03-2019
APPROVED BY DATE Document Number Rev.
HDEC (PM) 16-03-2019 CB2-Q-ZEN-05-60301 B
Comment and Response Sheet
(Cirebon 2, 1x1000MW Coal Fired Power Plant Project, Indonesia)
Related Dwg. / Doc. CB2-Q-ZEN-05-60301 Method Statement for Excavation and Pile Head Cutting for Buildings
Dwg. / Doc. Title Method Statement for Excavation and Pile RD □ Received for Distribution RR □ Release for Record HO □ Hold
Head Cutting for Buildings
VO □ Void SS □ Superseded
2 Page 6:
Barricade will be provided for falling protection Reflected on Rev. B
3 Page 7:
Pile cut at elevation as per drawings Reflected on Rev. B
Page 1 / 2
4 Page 10:
these drawing is overlapped one with another. Revise correctly Reflected on Rev. B
Page 2 / 2
Method Statement for Excavation and Pile Doc. No. CB2-Q-ZEN-05-60301
Head Cutting Works for Buildings Rev. B page 1 / 13
Table of Contents
1. Introduction
1.1 General
1.2 Building List
1.3 Reference Drawings
3. Resource Allocation
3.1 Manpower mobilization
3.2 Equipment mobilization
7. Attachment
7.1 Appendix A : Hazard and Risk Assessments
7.2 Appendix B : Job Safety Analysis
Method Statement for Excavation and Pile Doc. No. CB2-Q-ZEN-05-60301
Head Cutting Works for Buildings Rev. B page 3 / 13
1. Introduction
1.1 General
- This Method Statement is established for general excavation and pile head
cutting work for all buildings for Cirebon 2 Coal Fired Power Plant Project.
- The purpose of this method statement is to set guidelines and work method
to be followed during actual excavation and pile head cutting work.
1. survey inspection
2. lean con’c pre-pouring
inspection on subgrade
pouring lean concrete
(at GL -5.00.)
Mat FDN
1
0.5
Base Exc. Elv. -5.00
Gutter
2.2.1 Excavation
Prior to starting excavation, the construction equipment, e.g., excavator,
dump trucks, etc. shall be inspected and approved for work such as
normal shall be utilized for excavation works in accordance with project
HSE requirement. The constructed PC piles shall be carefully maintained
to prevent any damage and displacement during excavation work. PC pile
shall be cut off by using a concrete saw cutter at the cut-off level position
as shown on below photo. For proper and effective excavation work, PC
piles can be cut partially if required before excavation work. Survey
checking shall be carried out during excavation and before pile cut to
prevent over excavation or wrong cutting. Clearance for excavation area
shall be minimum one meter from edge of foundation, and slope for
excavation shall be less than 45 degrees on filled soil layer, or ½ ratio for
length to height on original soil layer at open cut area.
Elv. +0.50
Elv. +/- 0.00
1
1
1/1
Wall
Mat FDN
1/0.5
1
0.5
Base Exc. Elv. -5.00
Gutter
Open
<1st Step of Cut Excavation
Excavation andMethod
Pile Cut>
Excavation Area
66m x 42m
Elv. +0.50
Elv. +/- 0.00
1
1
1/1
Wall
Mat FDN
1/0.5
1
0.5
Base Exc. Elv. -5.00
Gutter
1st Excavation
GL0.00 to GL-3.00
2nd Excavation
GL-3.00 to GL-5.00
1) Seepage water from ground level and rain fall will be dewatered by
temporary drainage system during underground construction work.
2) To protect excavated area from ground water, berm will be made at the
surrounding excavation area as shown on the below sketch.
3) Collecting sump pit with submersible pump will be prepared at two places.
4) Pumping out water will be leaded to the main drainage trench on ground
level.
5) To avoid idle time of work due to water flooding, dewatering will be
controlled for seven days and 24 hours.
Method Statement for Excavation and Pile Doc. No. CB2-Q-ZEN-05-60301
Head Cutting Works for Buildings Rev. B page 9 / 13
Main Drainage
To Main Drainage
Water Flow
Pump Location
To Main Drainage
Elv. +0.50
Elv. +/- 0.00
1/1
1
1
Wall
Mat FDN
1 1/2
0.5
Base Exc. Elv. -5.00
Drainage Method
Method Statement for Excavation and Pile Doc. No. CB2-Q-ZEN-05-60301
Head Cutting Works for Buildings Rev. B page 10 / 13
1
0.5
Pit Detail
The excavated soil, if suitable for backfill, shall be selected and stockpiled
at designated area in site boundary. However, unsuitable soil for backfill (for
example, natural underground muddy clay soil) shall be disposed to the
designated area which assigned by the EPC Contractor within site boundary.
3. Resource Allocations
- Site Manager
1) The site manager is entrusted by the company to take full charge of the
production, operation and management of this project, implementation of
project manager responsibility system and the completion of the contract
signed with the employer.
2) Be responsible for the compliance with the lines, principles and policies
made by the country as well as laws, regulations and rules required by the
country and superiors and bylaws of the company.
3) Play a leading role to organize, formulate and implement the production
plan. Operation target and implement and fulfil various responsibility targets
signed between the employers and the company.
4) Be responsible to coordinate the work and relationship between PMTs with
employer, supervisor and the local.
5) As “the first responsible person for safe production”. The quality manager
shall put safety and quality first and strike a balance among safety, quality,
progress and yield, ensuring that safety and quality policy and target will be
successfully implemented and realized.
6) Be responsible to guarantee that occupational safety & hygiene and
environmental management system, quality system and measurement
system are effectively operate in this project.
7) Scientifically manage human, money and material resources and enhance
cost accounting so as to reduce project cost.
8) Perform the safe production and civilized construction well, enhance
labour protection measures and be highly responsible for company’s
property and employer’s safety.
9) Ensure and honest and clean construction, promote spiritual civilization of
construction team. Maintain a stable construction, and insist to place equal
emphasis on material and spiritual advancement.
10) Be responsible for training and assessment work, strengthening the
ability of construction team, caring for the employers and guarantee that
employers may exercise civil rights legally. All in all, the management shall
be “people oriented”
- QA/QC Manager
1) The QA/QC Manager shall be responsible for monitoring of the work in
relation to this method statements, approved drawing contractor and material
specification
2) Detect and report non-conformance
3) Ensure that all non-conformance product or activities identified are reported
4) Propose the corrective and preventive by report format
5) The QA/QC Engineer and construction engineer shall be responsible also
for the inspection test plan (ITP) to be carried out all the activities involved in
the work.
Method Statement for Excavation and Pile Doc. No. CB2-Q-ZEN-05-60301
Head Cutting Works for Buildings Rev. B page 13 / 13
- Safety Manager
1) In charge of safety and environment management, safety campaign
planning of this project and supervision of its implementation.
2) Assist the director with building up safety management network and
carrying out safety production activities.
3) In charge of directing and supervising effective operation of occupational
health and safety production activities. In charge of communication,
negotiation and disposal of matters in relation to safety and environment
management system. In charge of planning and supervising
implementation of safety regular meetings, routine inspection, internal
system audit, special activities in this project.
4) In charge of examining and verifying the part in relation to occupational
health and safety in construction scheme and operation instruction book.
5) In charge of auditing safety qualifications of personnel for special posts
and special types, of annual evaluation of subcontractors, of supervising
health examination and training for its own employees, labor service
personal and workers from subcontractors
6) In charge of organizing and participating in investigation of occupational
health safety and environment accidents and events as well as offering
disposal advice and prevention measures.