Sunteți pe pagina 1din 21

INSTALLATION MANUAL

BPP CMC4
Flat Landing Operating Panel CMC-4

TABLE OF CONTENT
1 DESCRIPTION ....................................................................................................... 2

1.1 INTRODUCTION................................................................................................. 2

1.2 FUNCTIONALITIES ............................................................................................. 2

1.2.1 24VDC Input Functions ............................................................................... 2

1.2.2 24VDC Output Functions.............................................................................. 3

1.2.3 Other functionalities ................................................................................... 3

2 TECHNICAL SPECIFICATIONS ................................................................................. 4

3 CONNECTOR LAYOUT............................................................................................ 5

4 ELECTRICAL LAYOUT............................................................................................. 9

5 BPP OPERATION ADJUSTMENTS ...........................................................................11

5.1 ENTERING FUNCTION SELECTION AND BPP BEHAVIOUR MODE ..............................11

5.2 SELECTING PROGRAMMABLE INPUT/OUTPUT FUNCTIONS.....................................13

5.3 OTHER PROGRAMMABLE MODES OF OPERATION .................................................14

5.4 CENTRAL PUSH BUTTON CONFIGURATION ..........................................................14

5.5 UCP CONNECTION FOR FURTHER FUNCTIONS .....................................................14

6 INDICATIONS ......................................................................................................17

6.1 RUN LED INDICATOR.........................................................................................17

6.2 BUZZER...........................................................................................................17

7 OTHER FEATURES................................................................................................17

8 FIRMWARE UPDATE..............................................................................................17

9 INSTRUCTIONS TO REPLACE A BPP........................................................................18

10 DIMENSIONS.......................................................................................................20

DOCUMENT NO. 2664.65.01


REVISION: 1
ThyssenKrupp Elevator Manufacturing Spain
©Copyright 2011
Pag. 1 of 21
DATE: 07.12.2011 Any partial or total reproduction of the document should be done with written consent of
ThyssenKrupp Elevator Manufacturing Spain, S.L.
DISTRIBUTION: CONTROLLED
INSTALLATION MANUAL
BPP CMC4
Flat Landing Operating Panel CMC-4

11 FIGURE INDEX .....................................................................................................21

12 REVISIONS..........................................................................................................21

1 DESCRIPTION

1.1 INTRODUCTION
The flat landing operating panel BPP ensures a decentralized communication
with the control board through CAN bus communications (shaft CAN bus) of
the different signalling devices, detection devices, etc. (peripheral) located on
the floor. The main advantages of a decentralized system lies in the reduction
of the cabling needed, using up less space in the shaft and shorter assembly
times which result in lower maintenance and installation costs. Apart from the
CAN bus, the control system has a TEACH IN signal used to configure BPPs
(level, access, and elevator).
This board is based on the UCP (floor board) but with somewhat less
functionalities. The board integrates the push buttons and arrows.

Since it is a decentralized system, temporary loss of power in the BPP,


shortcuts in the outputs or board failure will not cause the whole system to
fail.

Regarding connectors; these have been made compatible with existing


peripheral components such as LIP4, LIP6, lamps, etc. (CMC3 standard).

To control all functions the BPP has a small and low cost RENESAS R8C/23
microprocessor. This microprocessor is constantly analyzing information from
the peripheral devices and sends signals to the control board via the CAN bus
for processing. The microprocessor analyzes instructions from the control
board, interprets them, and acts on the connected peripheral devices.

1.2 FUNCTIONALITIES

Functionalities are grouped according to whether they are input or output


functionalities:

1.2.1 24VDC Input Functions

- Programmable input that can behave as:

DOCUMENT NO. 2664.65.01


REVISION: 1
ThyssenKrupp Elevator Manufacturing Spain
©Copyright 2011
Pag. 2 of 21
DATE: 07.12.2011 Any partial or total reproduction of the document should be done with written consent of
ThyssenKrupp Elevator Manufacturing Spain, S.L.
DISTRIBUTION: CONTROLLED
INSTALLATION MANUAL
BPP CMC4
Flat Landing Operating Panel CMC-4

o Special upward call


o Special downward call
o Presence input or open door signal (in reduced overhead/pit).
o Out of order
o VIP
o Floor cancelation
- Firemen turnkey.
- Fire detector.
- Teach-in.

1.2.2 24VDC Output Functions

- Serial or LCD TKE indicator.


- Programmable output that can behave as:
o Out of order register
o VIP register
o Upward register (special)
o Downward register (special)
- Upward arrows.
- Downward arrows.
- Firemen service indicator.
- Teach-out

1.2.3 Other functionalities

- Shortcut protected outputs.


- Power monitoring and watchdog.
- Configuration via UCM.
- Flash and Eeprom programmed in situ from PC or PDA.
- In situ programming via pushbutton in PCB
- Buzzer and LED indicator in board.
- CAN bus termination resistor selected with a switch.

DOCUMENT NO. 2664.65.01


REVISION: 1
ThyssenKrupp Elevator Manufacturing Spain
©Copyright 2011
Pag. 3 of 21
DATE: 07.12.2011 Any partial or total reproduction of the document should be done with written consent of
ThyssenKrupp Elevator Manufacturing Spain, S.L.
DISTRIBUTION: CONTROLLED
INSTALLATION MANUAL
BPP CMC4
Flat Landing Operating Panel CMC-4

2 TECHNICAL SPECIFICATIONS

POWER SUPPLY [X2 PINS 1,2]


Parameter Min Typical Max
Voltage Vcc 8Vdc 24Vdc 30Vdc
Current Icc(0) 37mA(Vcc=24V) 200mA
Max Current Icc(max) 170mA(40ºC) 200mA(20ºC) 230mA(0ºC)
Protection 200mA Fuse MiniSmd020
INPUTS [teach_in, PROG, Firemen, fire sensor]
Parameter Min Typical Max
High level VinH 22Vdc 24Vdc 31.5Vdc
Low level VinL 0 0 4Vdc
Input resistance Rin(Vin=24V) 11.3K 12K 14.4K
OUTPUT [FIREMEN]
Parameter With active output
Output voltage Vout 0.5..0.7V
Max. Output voltage Iout(max) 200mA with individual short circuit detection.
OUTPUTS [PROG, arrows, position, teach_out]
Parameter With active output
Output voltage Vout Vcc-0.5V..Vcc-0.7V
Max. Output voltage Iout(max) 200mA with individual short circuit detection.
HARDWARE
Microprocessor RENESAS R8C/23 R5F21236#U0
Oscillator 10Mhz type: quartz crystal/resonator.
CAN Baud-rate 100Kbps
Input protection Zener diode
Internal power supply Linear regulator 5V-500mA
Board indicators Led RUN, buzzer
CAN termination resistor Simple access: 120 Ohms Double access:180 Ohms

DOCUMENT NO. 2664.65.01


REVISION: 1
ThyssenKrupp Elevator Manufacturing Spain
©Copyright 2011
Pag. 4 of 21
DATE: 07.12.2011 Any partial or total reproduction of the document should be done with written consent of
ThyssenKrupp Elevator Manufacturing Spain, S.L.
DISTRIBUTION: CONTROLLED
INSTALLATION MANUAL
BPP CMC4
Flat Landing Operating Panel CMC-4

3 CONNECTOR LAYOUT
The following figure shows the arrangement of the connectors and other items in the
PCB and BPP:
X5 X4 X3 X2 X1

P3 Status Led

X7

X8

X6 J2 SW1 J1

Figure 1. BPP board

DOCUMENT NO. 2664.65.01


REVISION: 1
ThyssenKrupp Elevator Manufacturing Spain
©Copyright 2011
Pag. 5 of 21
DATE: 07.12.2011 Any partial or total reproduction of the document should be done with written consent of
ThyssenKrupp Elevator Manufacturing Spain, S.L.
DISTRIBUTION: CONTROLLED
INSTALLATION MANUAL
BPP CMC4
Flat Landing Operating Panel CMC-4

The following table shows the function of each pin:

Connecto Pins
r Functionality P1 P2 P3 P4 P5 P6

X1 Firemenconnector +24V Firemenregister Firemenkey Fire


Teach
X2 CAN connector +24V 0V Can H CAN L Teach in out
IN Out
X3 Programmable function +24V 0V Programmable Programmable
X4 Arrows 0V Up Down
position
indicator
X5 Position indicator +24V 0V LS/PIU
X7 Up key +5V Key
X8 Down key +5V Key
AMP MicroMatch 6 pins
E8 Programming, and
BPP series
X6 configuration +5V GND RX TX MODE RESET

Input pins Direct micro input (max. 5V)


Output pins Programming pins
Bidirectional Pins Direct micro output (5V max.)

X1. Firemen connector

4 pin AMP male connector p2.54mm.


The connector has the following signals:
• Input for Firemen key connection with +24V. Activation is by close contact.
• Fire sensor input. Fire condition when sensor activates +24V input voltage.
• Firemen output. In compliance with EN81-73.

X2. CAN IN/OUT

6 pin AMP male connector p2.54mm.


The connector receives the following signals from shaft bus:
• 24V power supply for internal processors and to supply peripheral devices.
• CAN H and CAN L bus differential signals for CAN communication connecting
UCP-BPP-UCM-UCC. This is the communication bus.

DOCUMENT NO. 2664.65.01


REVISION: 1
ThyssenKrupp Elevator Manufacturing Spain
©Copyright 2011
Pag. 6 of 21
DATE: 07.12.2011 Any partial or total reproduction of the document should be done with written consent of
ThyssenKrupp Elevator Manufacturing Spain, S.L.
DISTRIBUTION: CONTROLLED
INSTALLATION MANUAL
BPP CMC4
Flat Landing Operating Panel CMC-4

• TEACH_IN. This signal is sent by the UCM, runs through all BPP in a “chain”,
mode, i.e. one output is connected to the next input. This is used for
installation automatic teach-in.
• TEACH_OUT. Output signal of the BPP. Once the BPP has received all
information during the teach process it sets this signal to a high level
indicating the next board that the information is going to.

X3. PROGRAMMABLE FUNCTION

4 pin AMP male connector p2.54mm.


The connector has the following signals:
• +24V and GND to send registers and detect input.
• Programmable input: an input that may work in different manners depending
on the programming set via P3.
• Programmable output: an output that may work in different manners
depending on the programming set via P3.

X4. ARROWS

3 pin AMP male connector p2.54mm.

The connector has the following outputs:


• Output DS and DB necessary together with GND to activate the arrows, they
are active at high level.
• Additional GND for powering devices.

X5. POSITION INDICATOR

3 pin AMP male connector p2.54mm.


The connector has the following signals:
• +24V and GND for powering the position indicator or LCD TKE.
• Data output with two modes of operation: LS mode when a serial light is
connected or PIU mode when a LCD TKE is connected.

X7. MAIN UPWARD KEY

Right angle SPOX male connector with 2 pins p2.50mm.

DOCUMENT NO. 2664.65.01


REVISION: 1
ThyssenKrupp Elevator Manufacturing Spain
©Copyright 2011
Pag. 7 of 21
DATE: 07.12.2011 Any partial or total reproduction of the document should be done with written consent of
ThyssenKrupp Elevator Manufacturing Spain, S.L.
DISTRIBUTION: CONTROLLED
INSTALLATION MANUAL
BPP CMC4
Flat Landing Operating Panel CMC-4

When a key is used the current push button has to be removed (cutting the joined areas
and pressing the push button until it is removed). The key will be placed in the resulting
space. The upward key connection is done with X7.
Warning: opposed to other connectors, the voltage in this connector is 5V.

X8. MAIN DOWNWARD CALL

Right angle SPOX male connector with 2 pins p2.50mm.


When a key is used the current push button has to be removed (cutting the joined areas
and pressing the push button until it is removed). The key will be placed in the resulting
space. The upward key connection is done with X8.
Warning: opposed to other connectors, the voltage in this connector is 5V.

X6. PROGRAMMER

Programming connector. This connector includes power supply and control signals for
the programming process.

DOCUMENT NO. 2664.65.01


REVISION: 1
ThyssenKrupp Elevator Manufacturing Spain
©Copyright 2011
Pag. 8 of 21
DATE: 07.12.2011 Any partial or total reproduction of the document should be done with written consent of
ThyssenKrupp Elevator Manufacturing Spain, S.L.
DISTRIBUTION: CONTROLLED
INSTALLATION MANUAL
BPP CMC4
Flat Landing Operating Panel CMC-4

4 ELECTRICAL LAYOUT

Figure 2. Signalling and control panel

DOCUMENT NO. 2664.65.01


REVISION: 1
ThyssenKrupp Elevator Manufacturing Spain
©Copyright 2011
Pag. 9 of 21
DATE: 07.12.2011 Any partial or total reproduction of the document should be done with written consent of
ThyssenKrupp Elevator Manufacturing Spain, S.L.
DISTRIBUTION: CONTROLLED
INSTALLATION MANUAL
BPP CMC4
Flat Landing Operating Panel CMC-4

Figure 3. Board interconnection to shaft bus

DOCUMENT NO. 2664.65.01


REVISION: 1
ThyssenKrupp Elevator Manufacturing Spain
©Copyright 2011
Pag. 10 of 21
DATE: 07.12.2011 Any partial or total reproduction of the document should be done with written consent of
ThyssenKrupp Elevator Manufacturing Spain, S.L.
DISTRIBUTION: CONTROLLED
INSTALLATION MANUAL
BPP CMC4
Flat Landing Operating Panel CMC-4

BUS END RESISTANCE SELECTION.

The end board of the bus requires an end load resistance for the CAN bus. This is done
using a J1 jumper or SW1 according to the below table (also detailed in figure 2).

BUS END RESISTANCE (assembling options)

with SW1 with J1 Type of Installation

All boards

Boards at bus endings (furthest from UCM) in linear bus


(single access)

Boards at bus endings (furthest from UCM) in bifurcated bus


(double access)

5 BPP OPERATION ADJUSTMENTS

5.1 ENTERING FUNCTION SELECTION AND BPP BEHAVIOUR MODE

To enter function selection mode for the programmable inputs/outputs, please follow the
instructions below:

- Ensure the board has no power supply

- Power it up

- During the first 5 seconds on powering the board press P3 (note ¡Error! No se
encuentra el origen de la referencia. )

- The board is now in selection mode to select Programmable input/output


function.

To choose type of behaviour or to assign a functionality to the programmable


input/output follow these instructions:

DOCUMENT NO. 2664.65.01


REVISION: 1
ThyssenKrupp Elevator Manufacturing Spain
©Copyright 2011
Pag. 11 of 21
DATE: 07.12.2011 Any partial or total reproduction of the document should be done with written consent of
ThyssenKrupp Elevator Manufacturing Spain, S.L.
DISTRIBUTION: CONTROLLED
INSTALLATION MANUAL
BPP CMC4
Flat Landing Operating Panel CMC-4

- Enter the input/output programmable selection mode (following steps above)

- Press P3 as many times as necessary until you reach desired mode of


operation. With each P3 pulse you will change choice. The board indicates the
function or behaviour making LEDS flash as described in table 1. LEDs status
during BPP “Function selection” )

LEDs

FS FB P1 P2 Function description

Flash Flash Flash Flash Door presence input

OFF OFF OFF ON Out of order input

OFF OFF ON OFF VIP (input and registration)

OFF OFF ON ON Cancel floor

ON OFF OFF OFF Upward special call

OFF ON OFF OFF Downward special call

Flash Flash OFF OFF Arrows off

ON ON OFF OFF Arrows on

ON ON ON ON BPP + UCP in same floor

1. LEDs status during BPP “Function selection” mode.

- Please wait 5 seconds. The BPP will confirm with various beeps that
programming has been successful.

DOCUMENT NO. 2664.65.01


REVISION: 1
ThyssenKrupp Elevator Manufacturing Spain
©Copyright 2011
Pag. 12 of 21
DATE: 07.12.2011 Any partial or total reproduction of the document should be done with written consent of
ThyssenKrupp Elevator Manufacturing Spain, S.L.
DISTRIBUTION: CONTROLLED
INSTALLATION MANUAL
BPP CMC4
Flat Landing Operating Panel CMC-4

Figure 4. LEDs and push button to select Programmable function

5.2 SELECTING PROGRAMMABLE INPUT/OUTPUT FUNCTIONS

The functions we can choose from are:

- Door presence (only input)

- Out of order (only input)

- VIP (input and registry)

- Cancel floor (only input)

- Upward special call (input and registry)

DOCUMENT NO. 2664.65.01


REVISION: 1
ThyssenKrupp Elevator Manufacturing Spain
©Copyright 2011
Pag. 13 of 21
DATE: 07.12.2011 Any partial or total reproduction of the document should be done with written consent of
ThyssenKrupp Elevator Manufacturing Spain, S.L.
DISTRIBUTION: CONTROLLED
INSTALLATION MANUAL
BPP CMC4
Flat Landing Operating Panel CMC-4

- Downward special call (input and registry)

5.3 OTHER PROGRAMMABLE MODES OF OPERATION

Apart from input/output Programmable functions there are other selectable BPP
behaviours:

- Configuring BPP + UCP in the same floor (for special configurations where a
single BPP cannot cover all required functions for said floor. In this case the
programmable input/output has no function, and further inputs and outputs
have to be connected to the UCP that remains in parallel.

- Activate/deactivate board arrows. The input/output stays as before, i.e. the


activation or deactivation of arrows does not affect programmable
input/outputs (if for example you wish to deactivate arrows and select FS the
process has to be done in two steps, the first to deactivate, for example, the
arrows and the second to select FS mode)

5.4 CENTRAL PUSH BUTTON CONFIGURATION

Due to the multiple configuration of the operating panel (1 button, 2 push buttons, keys,
etc) you may want to change the behaviour of the P1 push button.

Push button P1 can operate as an upward call button or as a downward call button
depending on J2 jumper. If J2 jumper is present (by default) then P1 operates as a
downward call. If jumper J2 is removed, P1 will act as the upward button.

5.5 UCP CONNECTION FOR FURTHER FUNCTIONS

Although BPP has a programmable input/output it may be that more than one function
be needed in one floor (e.g. presence and VIP). In this case one BPP is not enough.

The solution as previously mentioned is to make BPP work as a “BPP + UCP in the same
floor”. In this way all functions are connected to UCP while BPP can be used for calls.
I/O PROG in this case would have no function.

The way to do the connection is as follows:

If the control board is located on the top of the shaft, installation is done up to this floor,
(including BPP for that floor where further BPP functions will be required), but the UCP is

DOCUMENT NO. 2664.65.01


REVISION: 1
ThyssenKrupp Elevator Manufacturing Spain
©Copyright 2011
Pag. 14 of 21
DATE: 07.12.2011 Any partial or total reproduction of the document should be done with written consent of
ThyssenKrupp Elevator Manufacturing Spain, S.L.
DISTRIBUTION: CONTROLLED
INSTALLATION MANUAL
BPP CMC4
Flat Landing Operating Panel CMC-4

placed between TCAN connection box of that floor and the floor below, cabling the
additional items to the UCP.

If the control board is located at the bottom of the shaft, the same can be done, taking
into account that the UCP must be placed between TCAN at this level and the next one
above, cabling additional items to the UCP.

To join TCAN connection box to the landing board the same bundle of cables as with the
TCAN should be used.

DOCUMENT NO. 2664.65.01


REVISION: 1
ThyssenKrupp Elevator Manufacturing Spain
©Copyright 2011
Pag. 15 of 21
DATE: 07.12.2011 Any partial or total reproduction of the document should be done with written consent of
ThyssenKrupp Elevator Manufacturing Spain, S.L.
DISTRIBUTION: CONTROLLED
INSTALLATION MANUAL
BPP CMC4
Flat Landing Operating Panel CMC-4

Figure 5. UCP-BPP connection for extended functions at floor level. Control Board on top of the
shaft.

DOCUMENT NO. 2664.65.01


REVISION: 1
ThyssenKrupp Elevator Manufacturing Spain
©Copyright 2011
Pag. 16 of 21
DATE: 07.12.2011 Any partial or total reproduction of the document should be done with written consent of
ThyssenKrupp Elevator Manufacturing Spain, S.L.
DISTRIBUTION: CONTROLLED
INSTALLATION MANUAL
BPP CMC4
Flat Landing Operating Panel CMC-4

6 INDICATIONS

6.1 RUN LED INDICATOR

This LED indicates BPP operation:

LED status BPP board status


Board is not programmed and LED is light fixed with power
ON fixed
on
Flashing , 1 pulse Normal operation.
Flashing , 3 pulses Teaching failure. An error has occurred during teach-in.
Possible failure in CAN communication. BPP does not
Flashing , 5 pulses
receive messages from displays for more than 2 seconds.
Power supply of the board is under 14-15V, and has gone
OFF
into power saving mode.

6.2 BUZZER

The floor board buzzer is activated when:


• Preregistration/registration of calls
• Resetting the board, BPP sends a short beep.
• When there is a shortcut between 24V output and board 0V sending out
periodical beeps.
• When confirming programmable input/output has been programmed.

7 OTHER FEATURES

If the Programmable input is programmed as presence detection of open door (in


reduced overhead/reduced pit, when the power supply in X2 falls below 15V, BPP goes
into power saving mode, deactivating RUN led and CAN driver and all 24V outputs
except 24V to Firemen connector X1 and to input/output programmable connector X3.

8 FIRMWARE UPDATE

To program or update firmware in the BPP you need:

• USB CMC4 particular programmer or E8 RENESAS programmer.


• Programmer-BPP connection cable with micromatch.

DOCUMENT NO. 2664.65.01


REVISION: 1
ThyssenKrupp Elevator Manufacturing Spain
©Copyright 2011
Pag. 17 of 21
DATE: 07.12.2011 Any partial or total reproduction of the document should be done with written consent of
ThyssenKrupp Elevator Manufacturing Spain, S.L.
DISTRIBUTION: CONTROLLED
INSTALLATION MANUAL
BPP CMC4
Flat Landing Operating Panel CMC-4

• USB cable (connector USB A type to mini USB-B) to connect PC programmer.


• Installation CD with: programmer drivers, CMC4-win application, FDT software
and BPP file (*.mot, *.tke) that has the firmware.

These are the steps to follow:

Carry out the next steps without connecting the programmer.


• Insert CD and follow the installation steps.
• Connect first the programmer to the BPP board (using AMP micromatch 6
pins connector (small red). Connect USB cable to link programmer and
PC.
• Connect programmer to PC. Please take into account the connection
order so the micro goes into programming mode.
• Execute FDT software from CMC4-win.
• Select Microprocessor R8C/23 (R5F21236).
• Select new com port COM (max. COM8). (Refer to help menu in CD)
• Select .MOT file for BPP.
• Press “Program Flash”.

If any error message appears please refer to the help files in the installation
CD.

9 INSTRUCTIONS TO REPLACE A BPP

To replace a board follow these instructions:

- First disconnect X2 connector (power supply)

- Then disconnect rest of connectors.

- Replace the old board and verify that switch SW1 or jumper J1 and jumper J2
of the new board are in the same position as the old one.

- Do not connect X2. Connect first all other connectors

- Connect X2.

- Configure the programmable input and output if necessary following paragraph


5.1

- After changing a board, cut control board power supply and power up again so
all boards start from reset and a teach-in is carried out.

DOCUMENT NO. 2664.65.01


REVISION: 1
ThyssenKrupp Elevator Manufacturing Spain
©Copyright 2011
Pag. 18 of 21
DATE: 07.12.2011 Any partial or total reproduction of the document should be done with written consent of
ThyssenKrupp Elevator Manufacturing Spain, S.L.
DISTRIBUTION: CONTROLLED
INSTALLATION MANUAL
BPP CMC4
Flat Landing Operating Panel CMC-4

- Verify that the RUN LED in the new board and that all other LEDs are ok (1 flash
per second)

DOCUMENT NO. 2664.65.01


REVISION: 1
ThyssenKrupp Elevator Manufacturing Spain
©Copyright 2011
Pag. 19 of 21
DATE: 07.12.2011 Any partial or total reproduction of the document should be done with written consent of
ThyssenKrupp Elevator Manufacturing Spain, S.L.
DISTRIBUTION: CONTROLLED
INSTALLATION MANUAL
BPP CMC4
Flat Landing Operating Panel CMC-4

10 DIMENSIONS

Figure 6. BPP dimensions

DOCUMENT NO. 2664.65.01


REVISION: 1
ThyssenKrupp Elevator Manufacturing Spain
©Copyright 2011
Pag. 20 of 21
DATE: 07.12.2011 Any partial or total reproduction of the document should be done with written consent of
ThyssenKrupp Elevator Manufacturing Spain, S.L.
DISTRIBUTION: CONTROLLED
INSTALLATION MANUAL
BPP CMC4
Flat Landing Operating Panel CMC-4

11 FIGURE INDEX

Figure 1. BPP Board ...............................................................................................................5

Figure 2. Signalling and control devices ....................................................................................9

Figure 3. Board connection to well bus....................................................................................10

Figure 4. LEDs and push button to select programmable function ...............................................13

Figure 5. UCP-BPP connection to extend funtionality on one level. Superior control board. .............16

Figure 6. BPP dimensions .....................................................................................................20

12 REVISIONS

Ed. Changes Date


1 1st edition. 07/12/11 FMorgado

DOCUMENT NO. 2664.65.01


REVISION: 1
ThyssenKrupp Elevator Manufacturing Spain
©Copyright 2011
Pag. 21 of 21