Documente Academic
Documente Profesional
Documente Cultură
1. Two-pass method
2. Enumeration method
The pass is then is then used to calculate the early finish, which is the early start
plus the estimated duration (FS + Duration = EF). In this case 0 + 5 =5 means the
activity “determine new product features’ can be completed after five days. Each
activity that is a source or can start as soon as its predecessor activity is complete.
Therefore, the next two activities can each start after five days. To calculate the
early finish for each of these activities, add its duration to the early start of 5, for
early completion times of 25 and 15, respectively. The difficult part of calculating
the first pass comes when an activity has more than one predecessor. For example,
“perform sales calls” cannot begin until all three preceding activities (“produce
prototypes, “design graphics,” and “conducting marketing”) are complete.
Therefore, its early start is 45. This is true even though “produce prototypes “ and
“design graphics” have earlier finish times because “conduct marketing “ cannot
be completed until day 45.
A D F
Determine Conduct
new product Design
Marketing marketing 30
features 5
campaign 10
Legend and
activity code
ES EF
Activity
Name
Duration
LS LF
Solutions
25 C 35
Produce
prototype
5 B 25
Acquire
15 E 25 45 G 70
prototype
materials 25
Design Performs
20 graphics sales calls 25
0 A 5 5 D 15 15 F 45
Determine Conduct
new product Design
Marketing marketing
features 5
campaign 10
Legend
Activity code
ES EF
Activity
Name
NB: the earliest the entire project can be completed is 70 work days. Duration
LS LF
The second pass is sometimes called the background pass. The background is “ the
calculation of late finish dates and late start date for the uncompleted portions of
all schedule activities “ when performing the backward pass, teams starts at the
end and work backwards asking ,”How late each activity be finished and started “
unless there is an imposed date , the late finish for the last activity during
planning is the same as the early finish date . In our example we know the
earliest we can finish the entire project is 70days so we will use that as late
finish date for the last activity . If the activity “perform sales calls “ must end no
later than 700 and it takes 25 days , then it must start no later than day 45. In other
words, calculate the late start by subtracting the duration from the late finish (CF –
duration = LS). The confusing part of calculating the second pass is when there is
more than one successor. In example one place this occurs at the first activity
“Determine new product features “since two activities are immediate successors.
Enough time must be left for all of the successors, so whichever one must start
soonest dictates the late finish date of the predecessor. In this example, “design
marketing campaign “ must start no later than after day 5, therefore, five days is
the late finish for the first activity.
Example 2
25 C 35
Produce
prototype 10
5 B 25
Acquire
prototype 35 E 45 45 G 70
materials Design Performs
20 graphics 10 sales calls 25
Legend
0 A 5 15 F 45
5 D 15 Activity code
Determine new Conduct
product Design ES EF
marketing marketing 30
features 5 Float Activity
campaign 10
Name
Duration
5 15 LS LF
- Once both passes are complete, the early and late start dates for every
activity and the amount of time the entire project will take to complete are
known. However, the team also wants to know the critical path. This is
calculate easily by first determining each activity’s float can be total float,
which is “the total amount of time a schedule activity may be delayed from
its early start date without delaying the early start of any immediacy
following schedule activities” A project manager wants to know how much
float each activity has in order to determine where to spent her time and
attention.
- Activities with a great deal of float can be scheduled in a flexible manner
and do not cause a manager much concern.
- Activities with no float or very little float that on the other hand, need to be
scheduled very carefully.
- Float is calculated by the equation float = late start - Early start ( float =LS-
ES)
- The critical path is the sequence of activities from start to finish in the
network that have no float in example 3, activities A, D, F and G have no
float and, therefore, create the critical path.
- It is typical to mark the critical path in red or in bold face to call attention to
it. Activities B, C, and E each have float and are not on the critical path. If
activity B would delay the start of activity C. on the other hand, activities C
and E can be delayed by 10 and 20 days, respectively, without causing any
other activity to be delayed. Therefore, their float is free float impacting
neither the overall project nor any activity in it.
- Project managers carefully monitor the critical activities. They also closely
watch activities that have little float – think of these as “near critical
activities. A project with many activities that have little float is not very
stable. Even small delays on near – critical activities can change the critical
path. Project managers can sometimes “borrow “resources from an activity
with plenty of float to use first on activity that is either already critical or
nearly critical.
Two pass complete schedule example
25 C 35
Produce
prototype 10
5 B 25
Acquire
prototype 35 E 45 45 G 70
materials Design Performs
20 graphics 10 sales calls 25
Legend
0 A 5 15 F 45
5 D 15 Activity code
Determine new Conduct
product Design ES EF
marketing marketing 30
features 5 Activity
campaign 10
Name
Duration
5 15 LS LF
The second method of determining the critical path is the enumeration method to
complete this; a person lists or enumerates all of the paths through the network.
The advantages of this method are that since all of the paths are identified and
timed, if a team needs to compress the project schedule, they will know both the
critical path and the other paths that may be nearly critical for those with very little
float). It is imperative to keep track of both critical and near- critical paths when
compressing a schedule. In example 4 below, three paths are identified and the
total duration for each is calculated. ADFG is the critical path with an expected
duration of 70 days just as was determined with the two pass method. Now
however, we also know that path ABCFG is expected to take 60 days (10 less than
the critical path), and path ADEG is expected to take 50 days (20 less than the
critical path)
Example 4
C
Produce
prototype
10
B
Acquire
prototype E G
materials Design Performs
20 graphics 10 sales calls 25
A D F
Determine Conduct
new product Design
marketing marketing 30
features 5
campaign 10
Legend
Activity code
ES EF
Activity
Name
Duration
LS LF
ADEG 50
ADFG 70
Show the project schedule on a Gantt chart
The Gantt chart is a horizontal bar chart showing each activity’s early start and
finishes each activity stretched out finish. The simplest Gantt charts show a bar for
each activity stretched out over a time line. The units of time are the units the
projects team used in creating the schedule, whether that is hours, days, weeks or
another measure a Gantt chart is shown in example 5. It is easy to understand when
each activity should be performed. However the basic Gantt chart does not show
other useful information such as critical path predecessor – successor relationships,
late start and finish dates so forth.
Time in workdays
Determine new
product features
Acquire prototype
pre-materials
Produce prototype
Design marketing
campaign
Design graphics
Conduct marketing
Perform sales calls