Documente Academic
Documente Profesional
Documente Cultură
SCHOOL OF ENGINEERING
Submitted by:
Isaac Baamu
15/U/19973/PS
Submitted in partial fulfillment of the requirements for the award of the degree of
Bachelor of Science in Electrical Engineering
Approval
i
ii
Declaration
iii
iv
Dedication
First and foremost, I dedicate this report to my parents who sought it wise to put before
me all the financial support needed and taught me that the best kind of knowledge to
have in life is that which is learned for its own sake and that even the largest task can be
accomplished if it is done one step at a time.
Secondly, I dedicate it to my brothers and sisters and all individuals who have played
an important role in my academics for the words of encouragement which have kept me
going up to this point in time and the only word i have to say is “thank you”.
v
Acknowledgment
In accomplishment of this report, I am indebted to a lot of people. Since these people
are many I feel sorry that I cannot mention all of them by names in a single page. I wish
therefore, to thank Makerere University for permission to attend my B.Sc. studies. Sin-
cere gratitude should go to my supervisors Dr. Jonathan Serugunda, Mr Enock Mwebesa
and Mr. Patrick Mugwanya for their invaluable criticisms, comments and contributions
without which this thesis would not have been a success.
My sincere thanks and appreciation also go to my parents for the tuition, assistance,
counselling, etc., my fellow colleagues, friends for their prayers, support, help and encour-
agement during the entire course of this project.
Lastly, I thank my project partner Gloria Kisakye for her cooperation, time and ev-
erything towards this project.
vi
Abstract
Increased exploitation of renewable energies for electricity generation has resulted into
increase in the number of the mini grids operated either in island mode or grid connected
mode. Increased generation capacity along with entrance of mini grids to the main grid
causes increase in short circuit current magnitude in distribution and transmission grid
substations. This project involved modelling West Nile Rural Electrification Company
(WENRECO) and section of the main grid that will supply the power to that network
and then connected them together.
A three phase short circuit simulation and then fault analysis was made considering fault
currents and fault MVA which showed an inrease in fault magnitudes. A study was also
made on the operation and coordination of the network circuit breakers and relays. Dig
Silent power factory was used in the simulation and analysis of the networks mentioned
above. We propose use of SCADA for WENRECo and installation of series reactors on
the line joining WENRECo to the main grid to reduce of the fault current magnitudes
during fault conditions.
vii
Acronyms
AFB Arua Feeder Breaker.
AL Average Load.
KV Kilo Volt.
viii
Contents
Approval i
Declaration iii
Dedication v
Acknowledgment vi
Abstract vii
Acronyms viii
List of figures x
List of tables xi
1 Introduction 1
1.1 Project background . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.2 Problem statement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
1.3 Justification . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
1.4 Project Objectives . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
1.4.1 Main Objective . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
1.4.2 Specific Objectives . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
1.4.3 Research scope . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
2 Literature Review 4
2.1 Mini Grid and Main grid Concept . . . . . . . . . . . . . . . . . . . . . . 4
2.2 Overview of Uganda’s Energy Sector . . . . . . . . . . . . . . . . . . . . . 5
2.3 Fault Analysis of Power Systems . . . . . . . . . . . . . . . . . . . . . . . . 6
2.3.1 Significance of fault analysis[9] . . . . . . . . . . . . . . . . . . . . . 6
2.3.2 Fault Analysis Solution Techniques . . . . . . . . . . . . . . . . . . 6
2.3.3 Measures to reduce on the fault current levels . . . . . . . . . . . . 10
2.3.4 Consequences of increased fault current . . . . . . . . . . . . . . . . 10
2.4 Related work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
2.5 Case Study; Wenreco Network . . . . . . . . . . . . . . . . . . . . . . . . . 12
ix
3 Methodology 13
3.1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
3.2 Data collection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
3.3 Modelling and simulation . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
3.4 Protection equipment upgrade and coordination . . . . . . . . . . . . . . . 14
3.5 Project presentation and report documentation . . . . . . . . . . . . . . . 15
5 Network Protection 28
5.1 Island operation mode . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
5.2 Protection reconfigured in island mode . . . . . . . . . . . . . . . . . . . . 28
References 32
6.5 Appendix . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35
x
List of Figures
6.1 The very low water levels of River Nyagak showing reduction in waterlevel
from the brown line. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35
6.2 The channel that leads to the generation station. . . . . . . . . . . . . . . 36
xi
List of Tables
xii
Chapter 1: Introduction
This chapter provides a brief project background, background of electricity supply, project
objectives and also explains the problem being faced in the West Nile region.
West Nile Rural Electrification Company is the sole generator and distributor of elec-
tricity in the West Nile region operating a 33 KV distribution island grid[1]. The primary
objective for its construction was to supply power to its small population in West Nile
which had no connection to main grid due to the long distances and insignificant power
demand before. Its generation capacity is 3.5 MW with a load/demand of 4.6 MW and
confronted with many challenges such as; inadequate generating capacity with a supply
deficiency of 1 MW, poor performance of the networks, failure to introduce renewable
energy resources to the grid, increased demand on the network, ageing infrastructure,
etc. Nyagak dam in Zombo has a reduced spinning reserve margin requirement. West
Nile has since 2007 experienced load shedding which can be avoided if there is distributed
generation which isn’t the case due to limited renewable sources.
The fact that Nyagak river is seasonal and its water is used for irrigation in the Congo
region greatly reduces on the volume of water required to turn the turbines hence gener-
ation shut down during dry seasons, load shedding and also increased demand compared
to the generated capacity, Propositions are being made to connect this network to the
main grid which stops in Moyo through Yumbe for purposes of power reliability [2]. REA
master plan for West Nile shows an 8% economic growth rate and load forecast of 9.3
MW by 2023 which means that expanding the distribution system will enable achieve
full electrification coverage in the West Nile by; Intensifying the existing grid network,
Expansion of off-grid service to areas that cannot be economically served by the grid,
Expansion of grid resources for example connection to main grid which currently stops
in lira for 133 KV transmission network or 33 KV distribution network which stops in
Moyo which is the primary aim of this project. It’s therefore evident that modern power
1
systems have developed over a long period of time due to increase in the efficiency and
economies of scale based on current society depending much more on provision of not
only cheap but reliable electricity. This has facilitated the connection of small generating
plants on the large national electricity grid.
However, connection to the main grid results in an increase in the fault current magni-
tudes since it becomes a multi-source power system when small grids are connected to it
hence need for a fault analysis [3]
Fault current, like normal load current, flows from electricity generation source, through
the network to the fault point and is only limited by network impedance. It’s typically
high in areas of high demand where the network is strong, such as large urban areas in
close proximity to generation.
1.3 Justification
Uganda Electricity Transmission Company Limited (UETCL) has a plan to connect the
main grid to the WENRECO network to cater for the supply deficiency in the region.
Connection of the main grid to this network will result in increase in fault currents requir-
ing technical compatibility and operational coordination of the network power equipment
more especially the over current protection equipment i.e. relays, circuit breakers, auto
reclosers, etc.
WENRECo network will be connected to the main grid through Lira- Gulu-Moyo-Yumbe
33 kV distribution line as the region waits for extension of the main grid through the
Lira-Gulu-Nebbi-Arua 132 kV transmission line that will most likely be commissioned
before 2022.
Proper selection and coordination of over current protection equipment requires knowl-
edge about fault currents flowing through the network and this is done through network
simulations of both WENRECo and section of the main grid to determine the maximum
and minimum fault current magnitudes that may flow after interconnection and thus a
need for fault analysis.
2
1.4 Project Objectives
The primary objective of this research project is to do a fault current analysis when a
mini grid is connected to the main grid.
Generally, this work aims at evaluating the potential effects of mini grids on the operation
of electric power system with particular reference to both transmission and distribution
system.
1. To model and analyze the WENRECo network and the main grid section.
3. To evaluate measures on how to reduce the fault impact on the WENRECo network.
This research work focuses on WENRECo connection to main grid and is limited to the
steady state concerns of short circuit studies, fault FMA and protection coordination.
Below is my thesis Organization;
1. Chapter 1 Introduction.
3. Chapter 3 Methodology.
5. Chapter 5 Protection
3
Chapter 2: Literature Review
This chapter gives an understanding of the main grid and mini grids, some related work
and brief information concerning the case study, protection and all associated literature
of the project.
These small grids are a practical and cost effective solution for areas which don’t have
access to the main grid and are endowed with potential energy sources as mentioned
above [5] and they also help to improve power reliability to areas with poor voltage pro-
files especially when the mini plant generated capacity is significant. The joint energy
and environment project installed a micro grid for over 102 households in Kasese with
solar, potential hydro sites as documented by MEMD are over 33 hydro sites including
Kakira, kinyara sugar works power plants which generate power for factory use and then
the excess is supplied to the main grid.
Mini grids can appear in two different forms i.e. renewable and non-renewable. Renewable
technologies include solar PV, geothermal plants, hydro plants and others. Non-renewable
technologies include cogenerations, combustion turbines and micro turbine. Exploitation
of renewable technologies is important in combination with the mini grids which are in-
dependent entities with regards to the main grid.
A main grid is defined as a network comprising power producers and consumers con-
nected together by transmission and distribution lines [6]. It consists of generators that
produce electricity, HV transmission lines that transfer electricity over long distances,
distribution lines that deliver the electricity to consumers, substations that connect the
pieces to each other and the energy control centers to coordinate the operation of the
components.
4
2.2 Overview of Uganda’s Energy Sector
The installed capacity of Uganda’s electricity generation increased to 1177 MW in March
2019 following the commissioning of the Isimba HPP that added 183 MW to the National
Grid[7] with 1031.5 MW supplied from Hydro power and the remaining generated from
other sources like solar, peat, geothermal and biomass. Also the Government of Uganda
through the Ministry of Energy and Mineral Development is constructing more power
stations like Karuma (600 MW) which is yet to be commissioned in December, Sindhiya
in bundibuggyo, Ayago, etc. However the government plans to upgrade the existing trans-
mission lines to a voltage of 220 KV ring around Lake Victoria in conjunction with Kenya
and Tanzania and 400 KV for Karuma Kawanda line for bulk energy transmission.
In 2001, the Government launched the Rural Electrification Strategy and Plan (RESP)
for the years of 2001 to 2010. However due to delayed implementation, the policy did
not meet the expected results which included failure increase in the use solar PV in rural
areas, low percent increase in rural access to electricity among others.
Following this, the electrification strategy and plan 2013-2022, was published by Ru-
ral Electrification Agency. This strategy was supported by the World Bank to ensure
that the rural electrification program, is implemented through introducing a sales based
performance subsidy scheme that also provides business development support to private
PV dealers, which is expected to increase PV sales. Uganda is blessed with abundant
sunshine hence has a solar irradiation of 1.5 kWh/m2/day which makes it possible to
produce electricity from sunlight. In the past years, solar energy has been used on a small
scale and off grid majorly in rural areas which have a large portion of Uganda’s population
yet they have the least access to electricity.
5
2.3 Fault Analysis of Power Systems
A fault in a power network is any failure that interferes with the normal flow of current to
the load.Consideration of overcurrent and overvoltage values in electricity grids is one of
the important issues that has been investigated in some papers. Developments of power
systems necessitate annual investigation and observation of fault levels in all power sub-
stations. Also, it is necessary to analyze cut-off capacity and operation type of power
switches to replace them with new switches of higher cut-off power or to add equipment
such as fault current limiters to existing grids.
The most important factors of increased short circuit level could be categorized as follows:
2. To determine the highest current value to ensure safety of devices during a fault.
3. To determine the maximum current the circuit breakers need to interrupt in order
to appropriately rate them.
Circuit models used during a fault allow the network to be shown as a linear circuit.
There are two methods for solving for fault currents;
1. Direct/ simple method: This uses pre fault conditions and constants to solve internal
machine voltages, apply the fault and solve directly. Here, loads are not considered
and i’ts represented as (IEC60909/VDE0102)
6
• First voltage just represents the pre-fault operating point
For the following network assume a fault on the terminal of the generator; all data is
per unit except for the transmission line reactance, a line with impedance 0.5, another
transformer with impedance 0.1 and a motor with impedance 0.1.
Solution
We need to first estimate the internal voltages for the generator and motor.
7
For the generator;
100 < −18.2
S= = 1 < −18.2 (2.1)
100
Then
Ea = 1.0932 < −118.21 (2.2)
T erminal voltage = 1.02 < 0 − (0.9804 < −18.2) × j0.3 = 0.9692 < −16.75 (2.3)
Internal voltage = 0.9692 < −16.75 − (0.9804 < −18.2) × j0.2 = 0.9839 < −28.21 (2.4)
Faulted condition
4.PNG
Figure 2.3: Illustration of a faulted condition.
Here the fault is shown as two equal but opposing voltage sources, each with a magnitude
equal to the pre-fault voltage.
The total voltages and currents are equal to the sum of the pre-fault condition (represented
by 1) and the conditions with the single voltage source at the fault location represented
8
Figure 2.4: A figure showing an exact equivalent to the faulted condition.
by 2) Pre-fault condition. Pre fault implies the fault was not there before thus If 1 is equal
to zero
If = If 1 + If 2 = If 2 + 0 (2.8)
9
Figure 2.6: Variation of fault current with location of series reactor
1. Series reactors; these are current limiters installed at various points on the network
to resist against increasing of short circuit current while encountering a fault by
increasing the impedance of the system.They can also compensate for network re-
active power thus improving on the transmission capacity of the lines. It is cheap
and easy to use than any other method.
3. High impedance transformer; the impedance can be used as a current limiting char-
acteristic of a transformer. It is used for determining the current limiting capacity
of the transformer so as to protect the primary of the transformer. The impedance
is used for determining the maximum short circuit current and this helps in the
sizing of fuses, circuit breakers that will act if that rated short circuit current is
exceeded.
10
1. Nuisance tripping
Increase in fault current on the grid can change fault response by the protection
system for example if a DG is installed near a substation and a fault takes place on
the feeders other than that were located on this DG, the breaker of this DG may
also trip due a current emanating from the DG to the fault point.
2. Failure of sectionalizers to operate when they should because the mini grid keeps a
line energized and desensitization of breakers and re-closers due to unplanned mini
grid currents.
Figure 2.7: The reach of the relay for a sample distribution network.
11
2.4 Related work
Researchers at U.S Department of Energy’s Argonne National Laboratory also studied
the impact of micro grids on the main grid and suggested the following measures on how
to minimize grid interconnection problems; defining the micro grid generation within the
power market, updating distribution protection systems, improving monitoring for power
quality and others [13].
Mini grids have also been implemented in other areas of Zambia, India, Canada and
thus increased electrification. A study was also done by Patrick Mugisha who holds a
MSc in Renewable Energies from the University of Oldenburg (West Germany) and is
currently a lecturer at Makerere University and also works under TECO (Technology
Consults) as a consultant on electrical and energy matters on the integration of mini
grids to the distribution and transmission network and he used the UEB network and
mobuku integration [14].
12
Chapter 3: Methodology
3.1 Introduction
This section precisely answers two main questions i.e. How was data collected or generated
and how it was analyzed to achieve success of the project? However, the chapter com-
mences with data collection and analysis, modelling of WENRECo network and section
of the main grid, three phase fault simulation and analysis, upgrading and coordinating
protection relays on the WENRECo network, presentation to a panel of examiners and
lastly report writing and documentation.
1. Lay out structure of the WENRECo network (Single line diagram for the WENRECo
network).
2. Feeders’ data (Feeder length and the amount of MW energy supplied to these feeder)
3. Metering points
Secondly, data concerning HV and MV transmission networks in the areas of interest shall
be obtained from UEDCL (UMEME) and UETCL offices located in Kampala and also
some of the data concerning our case study shall be gotten from the UEDCL offices, this
data shall be analyzed for the next step.
13
3.3 Modelling and simulation
Software such as PSS/E, MATLAB, DIgSILENT, ETAP, and PSCAD are used build, anal-
yse and to calculate load flows, contingency analysis, fault analysis and reliability[17].Dig
SILENT Power Factory software is deployed in this project to develop models and sim-
ulate both the WENRECo. grid and a section of the main grid because it has been
confirmed by Lund et al. (2005), Kaberere et al. (2005) and other authors for being a
versatile, educative and commercial power system program. Besides, Dig SILENT has
set standards and trends in power system modelling, analysis and simulation for more
than 25 years (Dig SILENT, 2013). Its advantages include; overall functional integration,
applicable in modelling of generation, transmission, distribution and industrial grids, and
the analysis of these grids’ interactions. This software provides a library of standard
electrical components or models such as transformers, machines, and transmission lines.
Therefore network models and three phase short circuit simulations are to be executed
using Dig SILENT Power Factory Version 15.1.7 and thereafter fault analysis done and
lastly protection assessed and coordination if there is need.
T
T.M.S = (3.2)
Tm
Where, T - is the required time for operation. Tm - is the time obtained from the relay
characteristics curve at TMS 1.0 and using the Plug Setting Multiplier (PSM) equivalent
to the maximum fault current. Objectives of Coordination are; to determine the charac-
teristics, ratings, and settings of overcurrent protective devices, Minimize the equipment
damage, process outage costs and network shutdowns, protect personnel from the effects
of these failures. Many times, it is required to discriminate between faults in front of
the breaker and faults behind the breaker. This is possible only if we take into account,
14
not only the magnitude of the current but also its phase with respect to the voltage at
the relay location. In such cases, the protection is known as the directional over-current
protection.
15
Chapter 4: Models and Simulations
4.1 Data Collected
The single line diagram of the network is a 33 KV network diagram and it shows the in-
formation below; Transformer ratings, Conductor types, the conductor lengths, Switching
points and Auto reclosure, Drop out fuses, Surge arrestors.
16
17
Figure 4.1: WENRECo single line diagram.
4.1.2 Data concerning the relays on the network
The relays are all overcurrent and follow the normal inverse curve. The normal inverse
curve is one where by as the current increases the time of operation of the relay decreases.
This is the most effective type of relay because it helps to avoid the disadvantages of the
independent time and current relays.
Relays are meant to operate in the sequence that the relay next to the fault operates first
before any other relays operate. Thus this means that they are supposed to be coordinated
well. This data will help in the setting of the relays in on the network.
Feeder length and the amount of MW energy supplied to these feeder, metering points.
The WENRECO network has two feeders from the Nyagak power station i.e. Vurra feeder
and Nebbi feeder.
These operate like circuit breakers though their difference is that they try in the line
for a certain number of times according to the settings before an actual circuit breaker
operates. They can be placed anywhere on the network un like circuit breakers. On the
WENRECo model, they will be represented as circuit breakers because there is no auto
reclosure symbol.
18
Table 4.2: Table showing data concerning the auto re closure settings
Loads on each of the distribution transformer, Number of transformers, their ratings and
connected loads, Conductor data (line lengths and types of conductors used), Amount of
energy supplied to the distribution network from Nyagak generation plant.
1. Electricity poles falling and this can be as a result of line over loading or lack of
enough stand in the ground.
2. Birds resting on the lines thus leading to single line to ground faults.
3. Lightning striking the lines thus leading to over voltages on the lines.
2. Failure of the wired fuse link to blow after a line short circuit.
19
2. Improving on the earthing.
5. For the cases of transformer failures, they are replaced and for some cases earthing
is re done with surge arrestors.
Single line diagram of the WENRECo mini grid the networks was modelled in DigSILENT
power factory simulation software version 15.1 The effective step-down transformer KVA
values were then scaled down using a scaling factor and then represented as loads. The
line parameters such as type, resistance per kilometer and distance of the line from one
transformer to the next were used as inputs. The transformer types and ratings were also
input.
20
4.2.1 WENRECo model
This model consists of Nyagak generating station in paidha Zombo district having two
generators rated 6.2 KV, 1.75 MW connected to a 33 KV step up transformer which is
the distribution voltage. This voltage is fed to six feeders as shown above by the different
colour codes with feeder 1 and 2 being the main feeders. It has a switching station at
Arua where the thermal generators were previously installed and it lastly shows point of
connection of the main grid. The feeders of this terminate with auto-reclosures or circuit
breakers that are located on the substation.
21
4.2.2 Main grid section
Data concerning the main grid was obtained from UETCL through interaction with the
people under the planning department. The information included the line parameters in-
cluding the line types, lengths, resistance per kilometer and distance of the line from one
transformer to the next the generator data. These were used as inputs in the simulation
model.
An external grid was connected at Lira substation since in practice it’s not possible to
determine the generating source since there are three of them supplying to Lira Substation.
An external grid is connected to Lira substation which steps down the voltage from
132 KV to 33 KV, its then transmitted to Gulu and then lastly Moyo where the main
grid stops.
22
Table 4.4: Simulation results for Main grid.
4.2.3 Observation
Simulations for WENRECo and the main grid indicate that; the fault currents and fault
MVA are high near the generating sources i.e. Nyagak and external grid and low at points
far away from the source.
This project doesnt consider feasibility study since it was already carried out by UETCL.
It involves constructing a 132 kV transmission line of about 314 km to connect Lira Sub-
station to Arua through Gulu and Nebbi. Extension of the Main grid to the west nile
region will increase electricity supply to the region, evacuate excess power from Nyagak 2
Hydro power plant as agreed between UETCL and UEGCL in the Power Purchase Agree-
ment and also increase grid reliability due to the n-1 resilience but into the transmission
line (double circuit line will be used for the project) with an investment cost estimated
at US$82.8 million. However, the project is expected to be completed by 2022 yet there
is urgent need for generation expansion in West Nile [7].
23
Figure 4.4: Combined network.
4.2.6 Observation
1. The fault currents increased after the mini grid was connected.
4. Case 4- series reactor at the line connecting the main grid to WENERECo network.
Explanation Case 1: Low fault reduction due to less feeder loading thus connecting
a series reactor on it causes insignificant change.
Case 2: Relatively good reduction on faults currents because this feeder is over loaded as
24
Figure 4.5: Reduction in fault current at different buses with use of a series reactor.
Percentage change; Case1=0.2, Case2=0.31, Case3=0.38, Case4=0.41.
compared to feeder one. It also supplies power to Arua switching station supplying feeder
3 and feeder 4. Thus in other words, feeder 2 carries the load of feeder 3 and feeder 4.
Case 3: Significant fault magnitude reduction for series reactors connected on both feeders
from nyagak.
Case 4: More significant fault reduction because the main grid contributes high fault
currents under fault conditions.
25
26
Percentage change; Case1=0.17, Case2=0.21, Case3=0.253, Case4=0.318.
Figure 4.6: Reduction in fault MVA at different buses with use of a series reactor.
Using;
√
F aultM V A = F aultcurrent × 3 × V oltage (4.1)
Areduction in fault current reduces fault MVA and still case 4 presents improved results
compared to other cases.
27
Chapter 5: Network Protection
5.1 Island operation mode
28
Figure 5.2: Protection reconfigured in island mode operation.
Basing on load forecast by Rural Electrification Agency (REA) master plan for the West
Nile region every after two years per feeder, New settings in terms of pick up current and
tripping time for which the relay should operate were re-calculated. Faut simulation at
the same point only de-energized only the affected portion.
Where; Power factor is 0.9, TDS is time dial setting, I is the relay pick up current,
Sb ase=73.48. The CT ratio is 100:1.
29
Table 5.1: New relay settings.
30
Chapter 6: Challenges, Recommen-
dation and Conclusion
In this chapter,conclusions are drawn, challenges and recommendations are aslo provided.
6.1 Challenges
Long distance to our case study was tiresome and also expensive tansport fares hindering
make frequent visits.
Inadequate data due to confidentiality of the people we interacted with.This caused delays
in project progress but however due to persistence we were able to get them.
6.2 Conclusion
This project commenced with data collection done through site visits,literature and in-
teraction with technical personells. Thereafter developed the WENRECo model and a
section of the main grid in Dig silent version 15.1, three phase short circuit simulations
done independently for both models,results were later tabulated and fault analysis shows
high fault magnitudes on the main grid model as compared to the WENRECo. Model.
Secondly, both models were combined and still a three phase short circuit simulations
and fault analysis indicates that connection of WENRECO to the main grid increases
fault level magnitudes ie. Fault current and fault MVA. This is due to the introduction of
an additional generating source to the grid which increses current flow to the fault point
during fault conditions. Connection of a series reactor between WENRECo and the main
grid helps to reduce the fault magnitude.
Lastly, relay tripping settings had to be modified to respond to the increased fault current
magnitudes and network discrimination was achieved for both island and grid operation
for WENRECo.
31
6.3 Recommendation
Implement SCADA. A supervisory and Control system should also be used to improve
monitoring for power quality and automatically record network data which may be helpful
in future during system analysis.
Connect a series current limiting reactor to the line connecting the WENRECo network
to the main grid to help to reduce on fault magnitude.
In grid connected mode, the operators at Nyagak should increase excitation to increase
voltage so as to take on the entire load and therefore meet the requirements of the main
grid at the point of common coupling. This is referred to as synchronization.
However, Unsymmetrical faults for example Single Line to ground with a 60%-75% of
occurrence, Double line to ground and other transient faults can also be analysed to
achieve a more effective protection system.
32
References
[1] . K. D. NETWORK, ”Generating Hope For A Brighter Future, Bringing electricity
to Arua, Uganda,”,” Aga Khan Development Networks, 2016.
[2] Rural Electrification Strategy and Plan 2013-2022,” Ministry of Energy and Mineral
Development, Kampala, 3rd July 2013 .
[3] . A. Odipio, ”Report On Public Education And Awareness For Protection Of River
Nyagak Catchment In Zombo District, West Nile Sub-region,” NEMA, Kampala,
2017.
[5] JIRSET, ”Analysis of Micro-Grid System during Faults on Transmission Line,” In-
ternational Journal of Innovative Research in Science, Engineering and Technology,
vol. Vol. 5, no. Issue 3, pp. 3813-3819, March 2016.
33
[15] arasanth Karoda and Aryadevi Remanidevi Devidas,”Studying the impact of AC
microgrid on themain grid and it's fault analysis",Biennial interna-
tional Conference on Power and Energy Systems:,” Towards Sustainable En-
ergy(PESTSE),2016,Kampala,2016
[16] ural Electrification Strategy and Plan 2013-2022,” Ministry of Energy and Mineral
Development, Kampala, 3rd July 2013 .
[18] . E. Agency, ”West Nile Service Territory Business Plan,” NRECA International For
USAID No. AID-OAA-A10-00028, Kampala, September 7, 2018.
34
6.5 Appendix
Figure 6.1: The very low water levels of River Nyagak showing reduction in waterlevel
from the brown line.
35
Figure 6.2: The channel that leads to the generation station.
36