Documente Academic
Documente Profesional
Documente Cultură
Lot 1: Debre Markos – Debre Elias - Temcha (km0+000 – 75+000) Construction Supervision Manual (Draft), Dec 2019
Table of Contents
Page
1 INTRODUCTION ............................................................................................... 3
1.1 Background and Descriptions of project ................................................................. 3
1.2 Objectives of Construction Supervision and Quality Assurance ............................. 3
1.3 Contents of the Manual .......................................................................................... 3
2 ABBREVIATIONS AND DEFINITIONS ............................................................. 4
2.1 Abbreviations ......................................................................................................... 4
2.2 Definitions .............................................................................................................. 5
3 IMPLEMENTATION OF QUALITY ASSURANCE PLAN ................................ 11
3.1 Responsibility to Implement Quality Assurance Plan ........................................... 11
3.2 Enforcement of Controls for Quality Assurance ................................................... 11
3.3 Applicable Standards and Specifications ............................................................. 12
3.3.1 Standards ............................................................................................ 12
3.3.2 Specifications ....................................................................................... 12
3.4 Sequential Steps of Quality Control ..................................................................... 12
4 CONTRACT ADMINISTRATION ..................................................................... 14
4.1 General ................................................................................................................ 14
4.2 Pre-Construction Activities ................................................................................... 14
4.2.1 Activities During Mobilization ............................................................... 14
4.2.2 Administrative and Contractual Matters................................................ 14
4.2.3 Staff Appointment and Mobilization ...................................................... 15
4.2.4 Staff Duties and Responsibilities .......................................................... 16
4.3 Communications and Organization Chart ............................................................ 24
4.4 Approval Procedures ........................................................................................... 26
4.5 Publicity and Public Relation ................................................................................ 26
4.6 Program and Progress ......................................................................................... 26
4.6.1 General ................................................................................................ 26
4.6.2 Work Program...................................................................................... 27
4.6.3 Monitoring Progress ............................................................................. 28
4.6.4 Dealing with Delays ............................................................................. 28
4.6.5 Dealing with Substandard Works ......................................................... 29
4.6.6 Supply of Information to Contractor ...................................................... 30
4.7 Financial Reviews ................................................................................................ 30
4.7.1 General ................................................................................................ 30
4.7.2 Information Required ........................................................................... 30
APPENDICES
1 INTRODUCTION
1.1 Background and Descriptions of project
Subsequently the tendering process was conducted, negotiations successfully concluded and
the Contract agreement for the construction of Debre Markos – Debre Elias – Kuch Design and
Build Road Project, Lot 1: Debre Markos – Debre Elias – Temcha (km 0+000 – 75+000) and
Chemit Spur (Chemit Junction – End of Chemit Town) was made on April 19th, 2019 and the
effective commencement date for the works contract is agreed to be on September 18 th, 2019.
The basic objectives of providing supervision on road construction projects is to ensure that the
quality of work specified is maintained, the work conform with Contract documents and of nearly
equal importance is needed to control and manage the costs of construction and to provide
proper and consistent as built records and other project documentation.
These objectives clearly point that there is a requirement and need in maintenance, optimization
and balance in quality, time and cost together with adherence to the construction contract
documentation for the construction works.
This manual deals with the various categories of construction activities, nature and properties of
construction materials to be used, the respective methods and procedures of quality control
performances, and checklists and guidelines for the activities.
A construction supervision manual will be prepared which will form a guideline for the
supervision system. This manual includes:
Abbreviations and Definitions
Implementation of Quality Assurance Plan
Contract Administrating
Construction Supervision
Defects Liabilities Period
Annexes
2.1 Abbreviations
Wherever in this Supervision Manual or in other contract documents the following abbreviations,
terms, words or expressions shall have the meanings here by assigned to them:
Kg Kilogram
KW Kilowatt
Ha Hectare
Ton Meter
0 Degree
0
C Degree Centigrade
0
F Degree Fahrenheit
L.S Lump Sum
G Grade (%)
Definitions
Unless inconsistent with the context, in this Construction Supervision and Quality Control
Manual, the following terms, words or expressions shall have the meanings here by assigned to
them
Word or Phrase Meaning
Aggregate Crushed stone of specified size and quality to be applied as sub-base
or base course material or to be used in surface treatments, asphalt
concrete or cement concrete.
Asphalt A mixture to predetermined proportion of aggregate, filler and
bituminous binder material prepared off the road and usually placed by
means of a paving machine.
Asphalt Surfacing The layers of asphalt and crushed surface aggregates constructed on
top of the base and, in some cases, the shoulder.
Base Course The layer of specified material and thickness placed immediately below
the surfacing constructed on top of the sub-base or in the absence
thereof, the selected layer complying with the requirement. A base may
extend to out-side the traveled way.
Bituminous High quality, thoroughly controlled hot mixture of asphalt cement and
Mixture Surfacing well-graded high quality aggregate thoroughly compacted into a
uniform, dense mass and usually placed by means of paving machine.
Borrow area/pit An area within designated boundary, approved for the purpose of
obtaining borrow material. A borrow pit is the excavated pit in a borrow
area.
Borrow Material Any gravel, sand, soil or as obtained from borrow areas dumps or
sources other than cut within the road prism and which is used in the
construction of the works. It shall not include crushed stone from
quarries or sand obtained from commercial sources.
Bridge A structure erected over a depression, river watercourse, railway line,
road or other obstacle for carrying traffic and having a span of 6m or
more, measured between the abutment faces along the centerline of
the road at girder-bed level.
In order to ensure that the works are executed in accordance with established standards,
criteria, specifications and procedures, and approved designs and environmental aspects in
accordance with International and Environmental Guidelines as well as construction schedule, a
Quality Assurance (QA) System will be evolved and instituted for proper implementation.
The Resident Engineer and the Assistant Resident Engineer will be responsible for the
implementation of the Quality Assurance System, and the implementation will be verified by the
Project Director of the Consultant.
Every effort will be made by the Consultants’ team to keep the Contractor fully informed about
work which is likely to be rejected, on the basis that the function of quality control is not to reject
work but to ensure that such work is constructed to a high standard in the first instance and
hence avoiding the need for remedial works. The Consultant shall order special tests of
materials and/or completed works, and/or order removal and substitution of improper materials
and/or works as required.
All steps in the construction process will be closely inspected and appropriate tests made so as
to ensure that corrective action is taken as construction proceeds, rather than after construction
is completed.
In general, the proposed Quality Assurance System will include the following:
Procedure for selection and approval of material sources, quarry and borrow area
operations
Procedure for storing of materials to be used in pavement and permanent works
Type, frequency and procedure of tests for different kinds of materials and related
pavement works
Norms and procedures for control of alignment, surface regularity for pavement layers
and concrete structures
Works and workmanship in regard to temporary works of various types
Organization of materials testing laboratory (personnel, equipment)
Equipment and man power organization for field tests and sampling for laboratory tests
Norms for sampling of materials from stockyards during laying and finished works
Procedures for monitoring of compaction equipment and field compaction
Procedures for monitoring of bitumen plants during production, laying and compaction
Procedures for monitoring concrete production, laying and compacting concrete
Tests of concrete for strength including its ingredients and mix designs
Formats for recording and compilation of test data
Reporting system for test results and for actions to be taken in respect of quality, etc.
3.3.1 Standards
All material to be furnished and design to be incorporated for project performance shall conform
to the standard Specification for Highway Bridges, issued by the American Association of State
Highway and Transportation Officials (AASHTO), American Society for Testing and Material
(ASTM), British Standard Code of Practice (BS) Standards, so applicable and other national or
international standard may be accepted provided that the requirements therein are equivalent to
the said standards. The Contractor shall request the Consultant's approval for any items of
materials that he wishes to bring into the Sites, based on the standards other than the said
standards.
3.3.2 Specifications
Besides to the standard Technical Specification specified for the project, additional applicable
specifications; when any argument takes place in the matter that is not specified in these
specifications, authorized standards and Specification in the following should also be referred to
and applied to the works.
commences (e.g. compacting and surface preparation for a section must be satisfactorily
completed before the next pavement operation commences on that same section).
4 CONTRACT ADMINISTRATION
4.1 General
The administration of the Contract, although an important and integral part of the overall
supervision service, it is primarily concerned with the processing of matters which are not
directly associated with the physical construction of the Works. As such, it deals with subjects on
whom action must be taken under both the contract between the Client and the Contractor, and
the Agreement between the Client and the Consultant.
The main purposes of the contract administration services are to ensure that the project
progresses as smoothly as possible, in order that the Contractor’s activities can proceed as
planned without interruption, while concurrently establishing effective lines of communication
with the Client so that he is at all times fully informed of actions being taken in respect of any
measures that he will in due course be required to approve before they can be implemented, or
of which he should otherwise be generally aware of.
The Consultant at all times will ensure that the Conditions of Contract are strictly adhered to and
that all contractual obligations of the Contractor (and his Sub-Contractors, if any) are fulfilled. In
order to achieve efficient and timely administration of the Contract, the Consultant should have
sufficient powers and authority to deal with day-to-day matters and carryout (minor) changes to
the works as may become necessary
Appointed Work
No. Staff Initials Initiated by Assignment
by Station
Act Act
following following
1 Project Director PD Head Office
signing of signing of
(Head Office
Contract. Contract.
support)
Resident Engineer Permanent
2 RE PC PD Site
basis
A/ Resident Permanent
3 ARE RE PD Site
Engineer basis
Pavement
Permanent
4 /Materials PME RE PD Site
basis
Engineer
Geotechnical Intermittent
5 GE RE PD Site
Engineer basis
Head Intermittent
6 Highway Engineer HE RE PD
Off/Site basis
Head Intermittent
7 Structural SE RE PD
Off/Site basis
Hong- Ik in JV with Lidet in sub-consultancy with G and Y Consultants 15
Debre Markos – Debre Elias – Kuch Design and Build Road project, Ethiopian Roads Authority
Lot 1: Debre Markos – Debre Elias – Temcha (0+000 to 75+000) Construction Supervision Manual (draft), Dec 2019
Appointed Work
No. Staff Initials Initiated by Assignment
by Station
Engineer
Permanent
8 Quantity Surveyor QS RE PC Site
basis
Permanent
9 Senior Surveyor SS RE PC Site
basis
Laboratory Permanent
10 LT PME PC Site
Technicians basis
Permanent
11 Material Inspectors MI PME PC Site
basis
Permanent
12 Surveyors SR RE PC Site
basis
Structural Permanent
13 SI RE PC Site
Inspector basis
Permanent
14 Draftsperson DP RE PC Site
basis
Permanent
15 Inspector of Works IW RE PC Site
basis
Permanent
16 Secretary SC RE PC Site
basis
Coordinate and supervise the design team for review, checking and approval of
designs, submitted by the design and construct Contractor, that includes geometric
design, pavement design, hydraulic and structural design of drainage structures
Check Contractor’s work programme including deployment of manpower,
construction equipment, plant and organization
Inspect and approve quality of construction materials and methods of construction
Give directions, instructions and advice to ensure that the execution of works is in
compliance with the Contract Document, plans, drawings and Technical
Specifications
Resident
Engineer Prepare monthly, quarterly and annual progress reports
Check and review measurements and approve payment certificates
Assess and analyze possible financial claims, time extension and preparing variation
order for additional works not included in the bill of quantities
Documentation of project records and proper handling of back-up sheets for future
reference
Liaison with Employers Counterpart and Regional Representatives on relevant
issues
Plan, organize & coordinate the activities of the design supervision team and the
construction supervision team, ensure the execution of the project in accordance
with the contract documents
Check, review, comment and approve method statements and work program
submitted by the Contractor prior to commencement of the works
Perform minor design changes as necessary to suit field conditions during
construction period
Prepare Engineer’s Instructions and Variation Orders as recommended or
necessary, complete with the associated measurement and payment instructions
Issue Engineer’s Instruction and Variation Orders to the Contractor in writing
Assistant
Advise the Employer (ERA of Design Changes, Engineer’s Instructions and Variation
Resident
Orders and of the associated cost and quality implications
Engineer
Approve working drawings and prepare detailed as-built record drawings.
Monitor and supervise the inspection and testing of works conducted by the
supervision staff
Monitor the project progress and expenditure and insure that the predetermined
work schedules are attained
Keep and maintain proper documentation.
Review and check field investigation and pavement design prepared by the design
and construct contractor
Carry out all the necessary investigation for the review and approval of the
pavement design prepared by the design and construct contractor
Interpretation of test results in the in the design review process and finalizing design
for the turnkey project work
Supervise all laboratory and field works for quality control that includes checking of
Pavement/Materi
all materials used for construction to be within the quality standards as specified in
als Engineer
the Contract Documents;
Performing mix design for cement concrete mix designs;
Keeping necessary records of the project specially for the items related to material
per activity
Keep and maintain detailed records of the Contractor’s equipment on site and
establish equipment availability figures for each category of equipment.
Inspect the construction of road and major and minor drainage structures including
quality of materials and workmanship
Inspect proper watering of concrete structures after construction
Responsible for quality control of all construction materials and workmanship of each
construction activity
Supervise and keep records of field tests on the road and structure making materials
Check compliance of all construction materials to the Technical Specification with
respect to quality
Inspector of Record daily site activities and report to the DRE
Works
Check quality of excavated material for use prior to hauling
Check if benching is considered wherever such is recommended
Keep and maintain detailed records of the Contractor’s equipment on site and
establish equipment availability figures for each category of equipment
Inspect the construction of road and major and minor drainage structures including
quality of materials and workmanship
Inspect proper watering of concrete structures after construction
Supervise and keep records of field tests on the structure making materials
Check compliance of materials to the Technical Specification with respect to quality
Review Engineering designs and documents, prepared by the design and construct
Contractor
Check and approve analysis and working drawings and method statement made by
Structural the Contractor in respect of drainage structures
Engineer Review Contractor’s proposed working drawing/plans and associated calculations in
respect of drainage structures
Advice RE for approval or reject the proposals accordingly and identify any changes
required
Intermittently inspect the Works both under construction and completed, for
compliance with the Technical Specifications and the approved method statement
Check and verify accuracy of measurements for structures during interim payment
certificate
Work in discussion with the RE and ARE for matters requiring common solutions in
design and construction supervision activities
Provide on-the-job training to the civil engineer assigned by ERA in respect of
structural matters associated with the project
Inspection of the structural works for provisional and final acceptance
Check and follow up the preparation of as-built drawings for structures along the
road
Inspection of the structural works for provisional and final acceptance
Check and follow up the preparation of as-built drawings for structures along the
road
Supervise delineation of catchment’s areas and study of hydrologic analysis for all
structural designs works done by the Contractor
Check and supervise hydraulic calculations for opening sizes of the drainage
Hydrologist/Hydra structures
ulic Engineer
Check and supervise Contractor’s method of hydrology and hydraulic works
Ensure the compensation rates, amounts and quantities that are determined by the
rate establishing committee are fair, correct and as per the relevant applicable laws
Right of Way and regulations
Management
Translate data from ROW documents in to the land management software data base
Specialist
which will be developed by the Employer in the future
Other works for right of way management
Prepare a plan and activity schedule for the road safety assessment and inspection
Prepare checklists for road safety assessment, inspections and recording of
deficiencies identified
Road safety and
safety audit Review of preconstruction phase road safety audit carried out as part of the project
specialist design
Carry out evaluation of road safety during construction phase
Carry out evaluation of road safety for the post construction phase
At site level all formal communications with the Representative of Employer (if assigned at site
level), Contractor and local authorities should be through the Resident Engineer
When writing to the Employer, Local Authorities and Contractor, the RE should sign as “Resident
Engineer”. In the absence of the RE, an A.R.E acting as his deputy should act on his behalf and
should sign as “for Resident Engineer”.
Besides, all the staff members shall communicate to each other either assigned horizontally on
parallel positions or vertically to subordinating or supervisory positions. In general, to smooth the
progress of work the line of the communication of the Supervision staff and Contractor’s
employees shall be on parallel level. All supervisors shall communicate with personnel assigned
by the Contractor on equivalent position. In view of this, the Contractor is required to notify the
position of his personnel.
In general, neither the R.E. nor member of his staff should give instruction to the Contractor’s
employee other than Agent, except in cases of emergency. However, arrangements may be
made between the R.E. and Project Manager (Contractor’s representative) for short-cutting this
procedure for example by allowing communication between Inspectors and Foremen. The R.E.
should satisfy himself that all arrangements thus made operate smoothly without generation of ill
feeling amongst the Contractor’s staff, who in some cases might resist receiving instruction in
this way.
The R.E should not communicate directly with the Contractor’s head office. In addition, the R.E.
should communicate with the authorities of the Client only through the Counterpart Engineer
assigned for this purpose. However, official communications can be copied to Construction
Contract Implementation Division o f the Employer.
Accordingly, the Consultant jointly with the Contractor will prepare “Request for Approval” form
containing:
Date and time of submission of request for approval
Contractor’s attachment to the request for approval i.e., tests results, compliance with
respect to geometrical tolerances.
Approval/rejection by Consultant’s RE, inspectors, surveyor etc. and reasoning
Date and time of returning the “Request for Approval”
The Contractor should obtain approval to commence any aspect of the work and to obtain
approval on completion; the RE’s team must not unnecessarily delay the Contractors as this can
give to a claim and needless expenditure of money. The RE’s team must check each stage of
the work as it proceeds and have any errors corrected. A final inspection should be made when
the Contractor says that he is ready to proceed to the next stage.
It is not the benefit of the project for Inspector/s to leave his/their Comment/s on work until the
Contractor has completed it. Comment should be made after the work is being done.
If testing is required the laboratory should be notified in good time. Test results should be made
known to the Contractor immediately.
4.6.1 General
During project implementation, main concerns are quality of work, completion time and
construction cost. Based on the General Conditions of Contract the Contractor is fully
responsible for the timely completion of Works. The contract states: “The Contractor… shall
proceed with the works with due expedition” and … “the whole of the works shall be completed
within the time stated in the tender… or extended time… if the Contractor shall fail… he shall
pay liquidated damages.”
Nevertheless, the Engineer can often see the overall progress position better than the
Contractor, thus he has the duty to:
Provide the Contractor with information and necessary help and
Exercise effective pressure on him at time when delay occur
A program is a tool to help progress and it must thus show the works in sufficient detail for
planning, mentoring and reporting purposes. The program needs to be supported by cash-flow
and equipment and manpower utilization schedules.
The over all program, once approved by the Employer, cannot be changed unless due to
approved Variation (or Change) 0rder, Suspension Orders or time extensions since these will
affect completion time, contract cost, price escalation and liquidated damages.
Nevertheless, the practice of having sub-programs at the site should be encouraged and
whenever the Contract is suffering slippage the Engineer should insist on the submission of
weekly schedules. This will assist in meeting partial targets (slippage of one week shall be
recovered within the succeeding week) to cope with monthly scheduled progress.
At section level, reviews must be carried out weekly and at project level, twice a month to
monthly. The principal monthly progress meetings must be backed up reports and
updated/revised sub-programs.
Whenever the Contractor is late, or going to be late, for a particular work item, this should be
brought to his attention in writing or at monthly meetings. The Contractors must then submit in
writing his redial proposals. Remedial measures may include
i) improving the site organization:
ii) augmenting the quantity of equipment:
iii) increasing the labor force and/or
iv) Extending the working hours.
If progress does not improve it may be necessary to institute weekly scheduling subject to
review during corresponding weekly meetings. These are intended to keep a firmer grip on the
situation but, at the same time, to ensure more flexibility.
Often, time delays are closely related to the Contractor’s cash-flow problems which result in a
lack of financial support to the Site organization. Typically, indicators of lack of financial support
are:
i) delayed payment of salaries and wages,
ii) short-age of fuel and spare parts,
iii) shortage of construction materials and
iv) Claims emanating from subcontractors/suppliers, amongst others.
When such occurrences happen, the R.E should report them to his Head Office for these
matters to be discussed at the Employer and Contractor’s Management level.
However, the use of these powers may cause a deterioration of relation between the R.E. and
Contractor’s Project Engineer, making effective supervision more difficult. Hence they should be
used only after persistent efforts to improve matters through close coordination and carefully
supervision.
If the Contractor neglects to remedy such situation the R.E must inform his Head Office for the
Head Office/Employer to apply pressure on the Contractor’s Management.
Incase of an exceptionally difficult Contractor, the R.E may have to resort to a recommendation
that.
1. a certificate is withheld or reduced
2. The Project Manager is replaced or
3. The contract is terminated/expelled whenever the Contractor “is not executing the works
in accordance with the contract or is persistently or fragrantly neglecting to carry out his
obligation”
The power delegated to the R.E. are intended to give weight to his effort to achieve effective
supervision, but the R.E. should resort to such powers only after having exerted all other means
and effort reach an amicable and supportive settlement to carry out the works in a proper
manner.
The Engineer must follow up with the Employer so as to obtain timely decisions on relevant
matters, particularly regarding the finalization of plans and requirements, and press him on items
which are the responsibility of the Employer such as access to site, ROW acquisition availability
of permits, visas, etc.
Throughout the project implementation, data should be supplied to the Contractor in good time
and early in the work. The RE and Contractor should jointly prepare a list giving the latest dates
in or the availability of working drawings, details of provisional sums and other Pay Items.
4.7.1 General
It is good practice to Review the estimated final cost of all contracts every quarter, or earlier if
considered necessary, and report to the Employer the estimated final cost and completion date.
Essential information, such as cost and completion date, can be indicated on a single graph or
table, showing actual and anticipated expenditure against time. Explanations of any major
fluctuations in cost can be given on an accompanying sheet together with the reasons for any
change in completion dates.
Back-up date/information can be prepared by the P.C. This should include a list of claims
submitted, but not yet decided, with their anticipated costs.
The P.D (Head office) must pay special attention to ensure that changes decided upon or under
consideration, of which the PC may not yet be fully aware, are included in the Review submitted
to the Employer.
Such variations usually go through a long progress prior to approval being gated for the revision
of the progress Charts.
The proposed quarterly Financial Review is therefore a means to keep both the financial status
and implementation time of the contract updated.
4.7.4 Vehicles
For the Contractor’s vehicles the RE should check the policies to ensure that they cover the third
party risks, including passengers, when driven by the Engineers Staff as sometimes these may
be used as replacement vehicles. For vehicles supplied for the specific use of the Consultant
check whether these are covered by comprehensive insurance policies. During the course of the
contract the RE should examine receipts for premiums and ensure the policies are update to
account for variations/time extension that may have occurred.
4.8.1 Payments
The Engineer should make his best efforts so as to minimize delay in payment:
a. Interim Measurement – Should not quibble over minor details and estimate what ever is
reasonable
b. Certificates- Should not wait for submission of claims by the Contractor before starting
the measurement. Daily measurements of accomplished work should be made available
by inspectors; after that it is only a matter of compilation. At any given time the RE should
be aware of the value of the work done and of the materials on site. The Engineer should
determine the measurement and not the Contractor.
c. Payment by employer- Submission of interim certificates shall conform to the approved
flow chart given with these guidelines, the maximum time frame for payment is indicated
in the flow-chart.
d. Variation Orders (V.O’S) and Claims- RE must press for prompt action on V.O.s
(possibly allocating a member of their staff for this job). The Contractor should be
pressed to submit proper details and rates so that early settlements can be made.
Quantities and rates covered by V.O. can be paid only upon approval of the Employer,
with some exceptions. RE must follow the relative flow- chart given with these guidelines.
Time Extension (longer duration of the Contract) also affects the computation of the price
escalation and the application of time related items of work.
a. Extra or additional work, provided that the affected activities are on the critical path of the
PERT/CPM network:
b. Unworkable day in excess of the number of rainy/unworkable days predetermined in the
tender documents;
c. Delay due to major calamities;
d. Failure to grant possession of site;
e. “Meritorious Causes” as determined by the Engineer and Employer for events beyond
the control of the Contractor and of the Employer.
Except for (a) which would be dealt with by means of Variation orders (C.O, E.W.O and S.A), all
other circumstances are dealt with by suspension order and Resume Orders.
Suspension should be claimed by the Contractor “as soon as practicable” after the
circumstances have arisen by a Suspension order can unilaterally be issued by the R.E.
whenever the safety of the works or lives are at the stake.
Suspension of the works can be for a total shutdown of operations or for sections of work. The
works can be resumed, by means of a Resume order, as soon as it is practical.
Suspension order and Resume orders must be submitted to the Employer together with a
Special report describing in detail the causes and effect of the suspension (supported by a
photographic report) and recommending the corresponding Time Extension (CTE) to be granted
to the Contractor.
In case of a total “Shutdown” the CTE is the number of days from the time of Suspension to the
time of Resumption.
Otherwise, in case of partial Suspension, the CTE should be evaluated on the basis of the
PERT/CPM diagram. Activities to be considered are those falling in the critical-path and
computation are to be made on the original outputs.
The recommended CTE is therefore subject to the employer approval of the S.O.R.O and
Engineer’s recommendations. The approval by the Employers is also conditional upon an
evaluation by the coordinating consultants.
On the approval of the CTE the Contractor must promptly revise the Original progress schedule
accordingly. The Engineer should make sure that the revision is done properly or the original
schedule will not be altered.
A common approach by Contractors is to try to revise the original schedule to use the actual
starting date in such a manner that slippages will be reduced or nullified. This is not permissible.
The effect of suspensions and CTE is that both original schedule and actual progress should be
“flat” and moved the same number of days as per approved CTE. The CTE can be graphically
reflected and shown in the progress chart together with its S.O. and R.O. number.
Typically the word “claim” appears to be an emotive one-and for little reason. Payments made
under a claim are those to which a Contractor is entitled. There are, infect, clauses in the
Conditions of Contract under which such additional payments may be due.
One reason for the emotion is that many Contractors have difficulty in formulating their request
for additional payment; this results either in their submitting (and arguing about) a half-baked
request about which they have not really though, or in their leaving difficult questions until the
end. Again, some Contractors tenaciously pursue groundless claims in the hope of getting
something.
These factors tend to lead to considerable correspondence and loss of mutual confidence-some
of which is avoidable. In an attempt to minimize correspondence and argument, the following
action is recommended:
(a) For design changes, a draft V.O. should be issued with, or soon after, the relevant drawing is
made.
(b) It should be pointed out to the Contractor that, on matters of additional payment, the burden
is on him to make a request before costs are incurred, not afterwards when nothing can be
done to minimize them.
Encourage the Contractor to submit a summary of his requests. This should help him
formulate the claim and minimize delay, muddled thinking and groundless claims. (In many
cases this might replace several weeks of misunderstood correspondence)
(a) If the principle of his request is acknowledged, a draft V.O should be issued;
(b) If the principle is not accepted (or, alternatively, if the Engineer sympathized with the claim
but it is not contractually sound), the Contractor should be clearly informed of the Engineer’s
reasons.
4.10.1 List of Clauses under which the Contractor may be due additional payment
Ambiguity or discrepancy in Contract Documents
Physical conditions or artificial obstruction, which could not have been reasonably
foreseen.
“Excepted risks”
Damage to person and properties
Payment of fees
Extraordinary traffic
Other Contractors
Substantial completion is therefore a minimum of 95% of the total value of works, provided that
all major items are 100% completed.
Upon reaching this condition the Contractor shall submit a request to the Engineer. The request
must be supported by computations showing the actual progress, together with a list of
outstanding works.
The Contractor’s request shall be verified by the Engineer and if found to be correct the
Engineer shall:
i) prepare a recommendation/ request to the Employer to form an inspectorate team for the
provisional taking-over;
ii) Suspend the contract time at the date of the Contractor’s request.
In case that the Contractor’s request does not meet the minimum requirement, the Engineer
shall so notify the Contractor and the process will be readjusted to a later date.
The inspectorate team should include, but not limited to, the following:
Prior to concurrence on the minutes the Engineer shall make sure that the Contractor has
furnished with the maintenance bond.
Together with Certification of Taking-Over the Engineer shall turnover to the Employer the
following documentation:
- Laboratory Test Results
- Original As-Built Drawings
- Final Accounts
- Final Change Order and Last Interim Certificate for payment (prior to the final/certificate
which is issued only at the end of the Defects Liability Period) that shall be based on the
Approved Final Change Order.
5 CONSTRUCTION SUPERVISION
It is equally important to gain the Contractor’s trust. This can be achieved at the early stage of
the contract, by the supervision consultant Engineer when the Engineer’s knowledge of the
works in great that of Contractor, offering the Contractor all necessary helps and information
concerning the contract. It is thus important, if the RE is new to the project, that as early as
possible he is fully briefed on all aspects of the project by the PC (having had the longer
connection with the project) who should ensure that a maximum effort is made in order to help
the Contractor.
Construction Supervision works are sub divided into two phases, which are Mobilization and the
Main Works phases. Accordingly, the activities scheduled for each phases are presented here
below:
Task
Description Responsible Checked By
No.
103 General Site Assessment RE PC
106 Verification and Re-establishment of
Ground Control and Survey Stations SS
RE
and Topographic Surveying
107 Liaison in Assessment of
Compensation with respect to Right- SS RE
of-Way
108 Assessment of Land Acquisition
SS RE
Status and Recommendation
111 Detailed Record of Contractor’s
IW RE
Equipment Mobilization
112 Joint Meeting with Contractor RE RE
113 Establishment of Construction
RE RE
Supervision Manual
117 Follow up of Contractor’s
IW RE
Establishment
118 Quality Assurance RE RE
119 Review the Contractor’s Proposal for
RE RE
the Construction of Diversion Roads
Task
Description Responsible Checked By
No.
120 Site Diary IW RE
121 Traffic Count IW RE
Additional
Verify Contractor’s motor pool RE RE
Arrange temporary facilities for the
RE RE
staff including vehicles
Arrange with Contractor for personnel
RE RE
to be assigned to RE’s Office
Identify measure to be taken for
RE RE
Protection of the Environment
Verify calibration of Laboratory
PME RE
Equipment
Establish Work-request System and
also monitoring, testing and reporting PME RE
system
Task
Description Responsible
No.
301 Issuing Drawings and Supplementary Information to RE
the Contractor
302 Liaison with ERA RE
303 Liaison with Regional Administration RE
304 Verification and Re-establishment of Ground Control SS
and Survey Stations
305 Modification to Design and Specifications RE/SE
306 Land Slide Investigation GE
307 Revision of Contractor's Method Statements and RE/QS
Proposals
308 Day-to-Day Record Keeping RE
Task
Description Responsible
No.
309 Recording and Analyzing the Contractor’s RE
Equipment
310 Reviewing Contractor’s Working Drawing RE
311 Preparation and Compilation of As-built Drawings RE
312 Checking of Setting Out of the Works RE
313 Monitoring of Progress of Work RE
314 Approval of Sub-Contractors RE
315 Resolution of Contractor’s Queries RE
316 Site Meeting RE
317 Quality Control of Materials RE
318 Inspection of the Works RE
319 Site Measurement and Interim Payment Certificates RE
320 Alerting the Client on Delay to Payments and validity RE
of insurances/Guarantees
321 Analysis of Contractor’s Request for Extension of RE
Time for Completion
322 Report on Construction Cost and Completion Date RE
Routinely
323 Environmental Protection RE
324 Additional Sources Material Investigation and RE
Inspection of Proper Utilization
325 Traffic Count RE
326 Ensure Safe Working Practice RE
327 Implementation of Sexual transmitted disease RE
protection program
328 Training RE
329 Photographs RE
330 Initial Handover/Certificate of Substantial Completion RE
a) Earthworks
Classification of Earthworks Materials
The general classification of suitability or otherwise of soils will be done by the laboratory after
testing. However, experience gives a good indication and the following is suggested to
inspectors. For instance, one can pick up a handful of material and roll it into a ball and see what
happens. Is it sticky and messy or does it crumbles? One should try to relate these conditions to
the laboratory moisture content and can make a good guess.
Look at the top surface of the earth when equipments in particular trucks, run over it. If the
movement under the wheels is small (in the order of 25mm) then the material should normally be
acceptable. If the movement is grater than 25 mm inform your superior and advise the
Contractor that you have doubts.
If surface cracking occurs, try to establish if this is more than a few centimeters deep. If it is only
on the surface there is probably no problem. However, if the cracks are deep consult your
superior and inform the Contractor.
Look at the excavation area as well as the fill areas. Always check that both cuts and fills drain
naturally.
Check with your superior over approvals for all tip areas, stockpile areas and borrow areas. Note
these in your Daily Report.
The Contractor should keep the R.E informed as and when he intends to use explosives. The
R.E. must check that all permits and safety precautions are taken when blasting is carried out.
Excavation of Cutting
If the material from the cut is to be used in fill areas the inspector should check that sufficient
spreading and compaction equipment is on site. The Contractor should submit to the R.E. A:
work request” form for this and the R.E. must check on the equipment available before signing
off the appropriate section of the “work Request”
It is the Contractor’s responsibility to keep such excavation dry either by temporary drainage or
pumping.
The inspector should check that the Contractor maintains natural drainage out of and away from
the excavation wherever possible. Water which is uncertainly trapped in an excavation or within
fill material can cause problems if the underlying ground is soft.
If the Contractor fails to keep the excavation dry any remedial works which may be required will
be at his expense.
Where fill is to be placed unavoidably on ponds or on weak material, granular fill will normally be
used. Compaction will either by tracking with a bulldozer or with a roller after about meter depth
has been placed.
Where granular fill is placed on week material a filter fabric may be required. Care must be taken
to see that the filter fabric is not ripped or punctured.
On the top of all rock fill, one or more blinding layers are required to seal the surface and prevent
loss of fine material from the next layers of fill.
It is the Contractor’s responsibility to keep such excavation dry either by temporary drainage or
pumping.
The inspector should check that the Contractor diverts natural drainage out of and away from the
excavation wherever possible. Water which is unnecessarily trapped in an excavation to within
fill material can cause problems if the underlying ground is soft.
If the Contractor fails to keep the excavation dry any remedial works which may be required will
be at his expense.
Where fill is to be placed unavoidably in standing water or on weak material, granular fill will
normally be used. Compaction will either by tracking with a bulldozer or with a roller after about I
mere depth has been placed.
Where granular fill is placed on weak material a filter fabric may be required. Care must be taken
to see that the filter fabric is not ripped or punctured.
On the top of all rock fill, one or more blinding layers are required to seal the surface and prevent
loss of fine materials the next layers of fill.
layer thickness is permissible. For any thing over this the Contractor should be made to reduce
the layer thickness.
An easy method of checking the layer thickness of un compacted material is to push in length of
20mm steel rebar until it meets reasonable resistance (i.e. the top of the layer below) and check
the depth of penetration. To save measuring a line can be painted on the bar at the maximum
permitted depth including tolerances.
Where density has to have the moisture content reduced the inspector should arrange to have
the moisture content checked. Bear in mind, however, that the performance of the material is
important. If on compaction there is little or no movement under a wheel load there is probably
nothing wrong.
Where density determination is the acceptance criteria the inspector must inform the laboratory
in good time.
The inspector should check that compaction is carried out to the edge of embankment. He
should remember that side slopes are to be trimmed and that un-compacted portions should re
rejected.
Where an existing embankment needs to be widened, the inspector should check that benching
in accordance with the drawings is followed by Contractor.
The inspector must always ensure that the method of working gives material drainage.
Where rock fill is required it should be graded so that is can be placed in layers not exceeding
1.00 mere. Compaction may be by means of tracked machines or grid roller. A blinding layer is
required to seal the surface.
Back fill to culverts must be brought up evenly on both sides of the structure.
If the Contractor wishes to use the competed embankment as haul route he will be expected to
provide reshaping and re-compaction at his own expense.
Movement of heavy equipment near the edge of embankments under stage loading can also
affect the stability of the edge of the embankment. The inspector should warm the Contractor of
this and, if he does not listen the warning, inform his superior.
Materials
The Inspector should ensure that he is aware of the correct materials that are to be used at any
location.
When materials arrive at site they should be checked for dimensions to ensure that they are
correct according to the drawings or as approved by the Engineer.
The material should also he checked for quality. Any materials that are obviously defective
should be rejected and the Contractor be told to remove them from the site. If there is any
resistance on the part of the Contractor whenever he is told to do this, the inspector should
inform the R.E. In the case of minor changes the inspector should refer to the R.E. for his
instruction as to whether or not the material can be used.
Setting Out
The primary setting out will be done by the Contractor and checked by the Consultant’s
surveyor. The Inspector should ensure that the necessary requests are sent to the surveyors in
good time.
The Inspector should check the setting out by eye particularly the invert level of any type of pipe
or culvert relative to the water course that is going to flow through it. If the invert appears higher
at any point than the stream bed or significantly lower, the Inspector should inform the R.E and
find out whether the invert level should be adjusted.
The secondary setting out is usually offset by tape from reference points and this should be
checked by the Inspector.
Excavation
Unless classified as unsuitable by the Laboratory tests, the excavated material may be used for
embankment formation.
The Contractor will be instructed either through the drawings or by the Resident Engineer, if soft
material is to be removed from the formation. The Inspector should check to see whether soft
materials remain after the specified depth has been removed; if so the R.E should be informed.
The R.E can then decide weather more excavation is to be carried out.
On completion of any excavation of soft materials the volume of excavation must be measured.
If it is a large volume then this should be done by the surveyors otherwise it should be done by
the Inspector. It is important that this be done jointly with the Contractor’s representatives and
the records signed.
During any excavation for culverts and pipe, the Inspector must examine the ground for any
potential failure of the excavation and notify the Contractor immediately.
The Inspector should find out what material is to be used for backfilling, and ensure that it is
placed and compacted in accordance with specifications.
b) Drainage
Bedding
The Inspector should find out from the drawings the type of bedding that is to be used for each
location.
The bedding should be properly compacted, shaped and leveled to the correct slope for the
pipe. The inside of the pipes shall be smooth with no displaced joints.
Laying Pipe
Pipelines for any drainage works must he laid true to line and level. The pipes shall be laid hard
up against each other so as to obtain tight joints. Ogee type pipes must be laid with the spigot
end pointing down stream.
The materials must be handled carefully by the Contractor and in accordance with the
specifications.
In concrete pipe rings, the joints must be checked to see that they are acceptable. When
mortared joints are used the inspector must check that these are neatly finished and the mortar
well rammed in to place.
The material which is to be used for backfilling must be ascertained. Where filter media is
required, ensure that the laboratory gradation test has taken place.
Ditches/Canals
Open drain excavation shall consist of re-excavating or excavating open drains and channels
inside or out side the road reserve, including channels to direct the course of streams, all as
shown on drawings or directed by the Engineer. Open drains shall be constructed true to line,
grade and cross section and shall be so maintained for the duration of the contract. Care shall
be exercised to avoid excavation below the required grade for the drains and any excavation
carried below the required grade shall be back filled with suitable material and compacted to the
required density at the expense of the Contractor. The inspector should always check that he
knows the invert width and the required side slope.
Local undulations in the existing ground may result before the Contractor leaves the area, the
contractor has to clear the area before leaving remembering that remobilization of the equipment
and machinery costs money.
c) Pavement
a. Before pavement construction can be allowed it is necessary for both the horizontal and
vertical alignment to be confirmed by the Resident Engineer.
b. The level of the formation will be confirmed to the Contractor in writing by the Resident
Engineer giving the required thickness of sub base. This information will be given to the
Inspector by the RE.
c. On the embankment areas the width of the earthworks should be checked to ensure that
the minimum embankment width has been constructed and that the compaction of the
slope is satisfactory.
d. The detailed method of setting out will vary between different Contractors and will be
agreed by the Resident Engineer. Essentially, some form of markers will be required at set
intervals (and usually 10 meter) along the road to enable the line and level to be controlled.
Normally these are lengths of steel rebar hammered in to the sub grade.
f. The inspector should always “eye in “the pins to see that they give an acceptable
alignment and grade.
Checking Formation
b) The CBR/ compaction of the earthworks will have been checked by the laboratory and
the thickness of sub base confirmed to the Contractor.
c) The tolerance or the formation level is plus 20mm and -30mm. The finished work should
be between these limits.
d) When the formation level has been prepared a fine nylon line should be stretched
between the markers on the setting out pins and the distance between the line and the
earth measured. If the measurement (“dip”) shows the formation to be high the
Contractor must remove the surplus material.
e) If the dip shows the formation to be low the Contractor should scarify to a depth of
150mm add more material and re-compact. However he Contractor may prefer to lay a
great depth of sub base. This is acceptable but the inspector should inform the R.E. the
inspector should also check to see that the maximum layer thickness of sub base will not
be exceeded.
f) The levels (dips) which are accepted should be recorded with the Contractor on the
standard dip sheet and signed by the inspector and the Contractor representative.
g) Since the cross section are 10m apart, the inspector should check by eye that the areas
in between are reasonably smooth i.e. no humps or hollows. If in doubt check by using
the nylon line diagonally across the carriageway.
Material
a) The gradation and the plasticity of the stockpiled material must be checked by the
laboratory and the inspector should ensure that the stockpile is approved.
Spreading and compacting
a) Sub base is normally spread from tipped piles by grader or spreader box. The inspector
must watch to see that segregation is not taking place. If it does occur the inspector
should draw this to the attention of the Contractor and ensure that the material is properly
mixed.
b) Compaction of sub base is by the end result method. That inspector nevertheless must
obtain information from the Contractor as to the equipment that he intends to use and
determine the required number of passes through trial section.
c) If there is no specific requirement for moisture content: Then inspector should remember
that material which is either too wet or dry will not be compacted.
d) Before a layer is covered the inspector should inspect it carefully for transverse or
longitudinal cracks. These will indicate that something is wrong with the layer the material
is to be spread.
e) Before compaction the layer should appear to have an even surface without humps or
hollows. The Contractor will give an allowance for compaction when he spreads the
material.
f) After compaction the surface tolerance must be checked by dipping. These dips must be
done jointly with the Contractor and the Contractor should sign the dip sheet.
Finished level
a) Areas that are outside tolerance on the high side should be reduced in level by grading
and the surplus material is removed and re-compacted. Low areas should be scarified
addition material added and the whole area graded and re-compacted.
b) As far as possible, trucks bringing in material should not run on the formation.
c) Once the formation has been compacted no further construction traffic should be allowed
on the area until the next construction course is laid.
f) Prime Coat
Material
The prime coat is cut back bitumen, which is made liquid (low viscosity) by adding kerosene
complying with BS 3690 and / or AASHO M82
Application
a) The prime coat is spread on to the surface of the aggregate base, normally using a
tanker with a spray bar at the back
b) The rate of spread is controlled by the forward speed of the tanker.
c) The tanker should have a special speedometer for slow speeds to enable the speed to
be controlled with in the limits.
d) The rate of spread and thus the forward speed will be determined by the Pavement/
Material Engineer.
e) The Inspectors must watch carefully to see that the jets are giving an even spray. If they
are not, Contractor must be informed immediately to clean the jets. If there is excess
prime coat at the start or end of a run this should be blotted with sand so that it will not
affect the asphalt concrete base course.
Acceptance
a) The prime coat as laid will be a dark brown film on the wet mix which should be of a
uniform cover.
b) The brown color will turn black as the kerosene evaporates and the material will lose its
stickiness.
c) Once laid no traffic should be allowed on the surface until the asphalt concrete base
course is laid.
Material
a) The design of the asphalt leveling course will be approved by the Resident Engineer after
reviewing the laboratory tests:
b) The Inspector should make a visual inspection of all loads to check that all stone are fully
coated with bitumen and reject the truck load of material if there is uncoated stone.
c) Check each load for appearance in respect of segregation, bitumen content whether it is
excess or deficient , contamination and overheating etc. (Note: due smoke indicates over
heating: a stiff mix or uncoated material may mean that the mixing was too cold: if the
load is flat in the back this may mean too much bitumen: if the mix looks lean this may
mean too little bitumen):
d) Samples should normally be taken every 300 tones or 200m of carriageways but
additional samples should be taken if the material does not look right;
e) The temperature of material from each truck-load should be taken and should be in the
range 105 to 130 Degree. If slightly outside these limits the material may be used after
being sent back to the asphalt plant to adjust the temperature in mixing. If well outside,
material should be rejected.
a) Asphalt concrete base course is laid by paving machines that are normally wire guided
for level.
b) With the approval of the Resident Engineer it may be permissible for the Contractor to lay
a constant thickness of material provided that the surface tolerance of the base course is
within the +600 required for asphalt concrete base course;
c) Which ever method is adopted, the Contractor will have to make an allowance for
compaction of the thickness of the course, usually 20 % of the course thickness. Again a
trial section is recommended.
d) Compaction will be by means of smooth wheeled rollers and PTR’s. The rolling
temperature should be checked (not less than 122 Degree).
Acceptance
a) On completion of Compaction, the surface tolerance must be checked by dipping and the
results recorded and signed by the Senior Surveyor and the Contractor.
b) Rectification of material that is out of tolerances is not possible with Asphalt concretes.
The Inspector should report these findings to his R.E who will take a decision on the
remedial measures necessary.
c) Compaction must be checked by taking cores. The Inspector should ensure that the core
holes are properly refilled.
The criteria laid down for the Base course apply equally to the wearing course.
b) The rolling must always finish with a tandem smooth wheeled roller to remove any track
marks that may be induced.
Acceptance
a) The dipping must be carried out as before and signed by both the Inspector and
Contractor.
b) The dipping only confirms the construction at the 10 meter cross section intervals. Other
tests must be used such as the static straight edge;
c) Details of work required to be carried out using these instrument will be detailed by the
pavement/ Material Engineer.
d) The acceptance of the wearing cause is on density basis determined from cores taken
from the finished work. Unless these are properly compacted when refilled they are
shown up as depressions. The inspector must carefully monitor the Contractor when core
holes are being refilled.
i) Structures
False work
False work shall consist of, purpose made or proprietary timber or metal props, beams or ties
adequate to support the forces imposed during construction of the concrete structure without
excessive deflection.
False work shall be erected in accordance with the approved drawings incorporating such
modification as required by the Engineer.
The Contractor shall take precautions to prevent deterioration of foundations during the course
of construction.
The false work shall incorporate features, which will permit adjustment to the alignment of the
form work to neutralize the expected settlement and deflection under load.
Detailed plans for the construction of the false work that will support formwork as prepared by
the Contractor will be reviewed by the R.E. This review will be guided by the following
considerations:
a) Material and configuration of the false work adopted for the project will be evaluated
against the incidence of floods at the site during the period of construction.
b) The axial bearing stress of vertical members shall not exceed the axial bearing stress
allowed for the material of the false work under permanent loading.
c) Sole plates at the foot of the vertical members shall be of such size as to impact lower
pressure on the bearing soil for the purpose of minimizing settlements. The anticipated
value shall not exceed the permissible value.
d) Lateral supports and diagonal bracings in both longitudinal and traverse directions will be
checked for adequacy.
e) Magnitude of elastic shortening and settlement that will be sustained by the vertical
members and by the bearing plates respectively must be calculated and must be allowed
for in establishing the level of the formwork
Establishment of the alignment and of the elevation of the points of support of the form
work shall be controlled by the use of Engineer’s transit and Engineer’s level. The transit
and the level shall be positioned on firm ground or on a firm platform constructed for the
purpose and must be protected against disturbances.
Formwork
to avoid undue strain. The structural inspector should check the Contractor’s detailed
formwork proposals before construction.
a. F3 for all exposed surfaces of kerbs, parapets edge beams soffits of deck slab
and pre-stressed girder/beams, columns, crossheads, wing walls and abutments
of bridges and internal faces of vehicular, pedestrians, and drainage box culverts.
The formwork shall be set to line and level within the specified tolerance and shall include
any camber which may be required. Inspection by eye along the top of a form will reveal
very clearly to the Inspector if it is out of line, measurements can be made from a string
line set between corners.
The joints should be sufficiently tight to prevent loss of grout from the concrete. A useful
indication of this is to look for daylight through joints which are not tight enough.
To prevent damages to the concrete, the surface of the form must be coated with a release
agent prior to concreting. A hardwood fillet shall be fixed to the formwork to form chamfers
25mm x25mm on all external corners of the concrete.
Immediately before concreting all shavings, loose wires and other debris shall be removed
from within the formwork.
All formwork shall be removed without damages to the concrete in appearance, strength
and durability. Where it is intended to reuse form work, it shall be cleaned to the
satisfaction of the Engineer.
6.1 General
There are instances when the Employer and Contractor do not appear to understand their
obligations during the Defect Liability Period and the following note has been prepared to help
clarify the various responsibilities. The purpose of the Defects Liability Period is to allow time
after completing construction for defects in the Works to come to light and to be put right by the
Contractor while he is still on call. It is not a period during which the Contractor has to rectify the
effects of fair wear and tear free of charge.
In most of contracts, the Defects Liability Period runs for twelve months from the date when the
works are completed. During this period the Contractor has to fulfill his remaining obligations
under the contract, i.e. complete outstanding works if any and carry out any work called for by
the Engineer “to the intent that the Works shall be delivered up to the Employer in as good and
perfect a condition (fair wear and tear expected) to the satisfaction of the Engineer as that in
which they were at the commencement of the Period”.
The Contractor is entitled to additional payment for all this work, except for:
(a) Completing outstanding works
(b) Remedying defects “due to the use of materials or workmanship not in accordance with the
contract or failure to comply with any obligation under the Contract”
(c) Correcting for a defect for which he is liable
Procedure
Before the issue of the Taking-Over Certificate the R.E. should list the outstanding work and
press the Contractor to execute it while he still has plant and skilled labour on the site. An
efficient Contractor is usually keen to complete this quickly and close down the site as soon as
possible though he will usually leave behind some limited resources to tackle remedial work
during the Maintenance Period. Alternatively, he may wish to leave all remedial work until the
end of the Defects Liability Period and return to do it all at once. Provided the defects do not
affect operations, this is usually acceptable.
An exception to this is the carrying out of any remedial or repair work which the Engineer
considers to be urgently necessary for security. These are ordered under Clause 64 of the
Conditions of Contract and must be done by the Contractor at once. Failing this the Engineer
should have them carried out by another Contractor or by the Client’s own forces duly charging
the Contractor with the appropriate costs.
Before the end of the Defects Liability Period the Engineer must inspect the works and then
inform the Contractor within two weeks of the expiry date, of the defects still to be remedied or
searched for.
6.3 Remedial Work after the Expiration of the Defects Liability Period
After the expiry of the Defects Liability period for any part of the work the Contractor has no
obligation to remedy defects which may be discovered in that part of the work, unless they arise
from faulty materials or workmanship. Such remedial works shall be remedied by the
Contractor, or at his expense, in accordance with the Conditions of Contract.
Until the Defects Liability Certificate is issued, the Employer withholds from the Contractor so
much of the retention money as the cost of any remedial work or searching for defects as the
Engineer may have required. After the issue of the Defects Liability Certificate if any defects are
discovered arising from faulty materials or workmanship the Employer will have still to charge
the cost of remedying the work to the Contractor.
6.4 Miscellaneous
Additional Work
The ordering of additional work during the Defects Liability period or before the issue of the
Defects Liability Certificate, will obviously be governed by whether such work is within the
capability of the Contractor’s current site organization at the time.
Insurance
During the Defects Liability Period, and up to the issue of the Defects Liability Certificate, the
Contractor’s obligations to insure are reduced and the Employer’s increased. Against ‘risks’ the
Contractor need only insure work actually being carried out by him during the period and, for the
rest of the works, for damage resulting from a cause arising before the Taking-Over Certificate
or from the carrying out of any outstanding or remedial works. He still has to insure his workmen
and third party damage arising out of the permanent occupation and use of the Works.
End of Contract
The Defects Liability Certificate should be issued four weeks after the end of the Defects Liability
Period, or when remedial works or all his obligations under the Contract are complete, if later. It
marks the end of the Contract and the Employer is not liable to the Contractor for anything
arising out of the Contract for which the Contractor has failed to make a claim in writing before
the issue of the Defects Liability Certificate.
APPENDICES