Suppose we have five jobs, each of which has to be processed on two machines A & B in the order AB. Processing times ar
following table:
1 6 3
2 2 7
3 10 8
4 4 9
5 11 5
Determine an order in which these jobs should be processed so as to minimize the total processing time.
"The time is the most valuable thing." -Vinay Chhabra & Manish Dewan
Solution.
The minimum time in the above table is 2, which corresponds to job 2 on machine A.
Now we eliminate job 2 from further consideration. The reduced set of processing times are as follows:
5 11 5
The minimum time is 3 for job 1 on machine B. Therefore, this job would be done in last. The allocation of jobs till this stage would b
2 1
After deletion of job 1, the reduced set of processing times are as follows:
3 10 8
4 4 9
5 11 5
2 4 3 5 1
Once the optimal sequence is obtained, the minimum elapsed time may be calculated as follows:
2 0 2 2 9
4 2 6 9 18
3 6 16 18 26
5 16 27 27 32
Idle time for machine A = total elapsed time - time when the last job is out of machine A
36 - 33 = 3 hours
Idle time for machine B = Time at which the first job in a sequence finishes on machine A + {( time when the ith job starts on
Idle time for machine B = 2 + (9 - 9) + (18 - 18) + (27 - 26) + (33 - 32) = 4 hours
Printing Binding
A 5 2
B 1 6
C 9 7
D 3 8
E 10 4
We wish to determine the order in which books should be processed on the machines, in order to minimize the total time required.
Solution.
The minimum time in the above table is 1, which corresponds to the book B on printing machine.
B
Book Time In Hours
Printing Binding
A 5 2
C 9 7
D 3 8
E 10 4
The minimum time is 2 for book A on binding machine. Therefore, this job should be done in last. The allocation of jobs till this stage
B A
Printing Binding
C 9 7
D 3 8
E 10 4
B D C E A
Once the optimal sequence is obtained, the minimum elapsed time may be calculated as follows:
C 4 13 15 22
E 13 23 23 27
A 23 28 28 30
Idle time for printing process = total elapsed time - time when the last job is out of machine A
30 - 28 = 2 hours
Idle time for binding process = 1 + (7 - 7) + (15 - 15) + (23 - 22) + (28 - 27) = 3 hours