Documente Academic
Documente Profesional
Documente Cultură
TABLE OF CONTENTS
1. INTRODUCTION ......................................................................................................... 3
2. SCOPE OF WORKS ..................................................................................................... 3
3. STANDARDS AND REFERENCE DOCUMENTS .................................................... 4
3.1. STANDARDS ............................................................................................................... 4
3.2. REFERENCE DOCUMENTS....................................................................................... 5
4. METHOD STATEMENT ............................................................................................. 5
4.1. SOFT SOIL TREATMENT AREA............................................................................... 5
4.2. CONSTRUCTION FLOW CHART.............................................................................. 5
4.3. PVDS INSTALLATION ............................................................................................... 5
4.4. INSTALLATION OF HORIZONTAL PIPE SYSTEM ............................................... 9
4.5. CONSTRUCTION OF GEO-MEMBRANE AND GEOTEXTILE ........................... 12
4.6. INSTALLATION AND OPERATION OF VACUUM SYSTEM ............................. 17
4.7. MONITORING............................................................................................................ 20
4.8. SURCHARGE PROCESS ........................................................................................... 20
4.9. POST SOIL INVESTIGATION .................................................................................. 21
4.10. MAIN MACHINE-EQUIPMENT AND HUMAN RESOURCE ............................... 21
4.10.1. MAIN MACHINE - EQUIPMENT............................................................................. 21
4.10.2. HUMAN RESOURCE ................................................................................................ 21
5. CONSTRUCTION PROGRESS ................................................................................. 22
6. QUALITY MANAGEMENT ...................................................................................... 22
6.1. QUALITY OF PLAN AND GOAL ............................................................................ 22
6.2. QUALITY GUARANTEE SYSTEM ......................................................................... 22
7. HEALTH, SAFETY, ENVIRONMENT AND FIRE-EXPLOSION PREVENTION
(HSE) 23
7.1. HSE GOAL .................................................................................................................. 23
7.2. HEALTH MANAGEMENT ....................................................................................... 23
7.2.1. HEALTH AND PROTECTION .................................................................................. 23
7.2.2. HEALTH ON SITE ..................................................................................................... 23
7.3. SAFETY MANAGEMENT ........................................................................................ 23
7.3.1. SAFETY MANAGEMENT SYSTEM........................................................................ 23
7.3.2. ELECTRICAL SAFETY RULES ............................................................................... 24
7.3.3. ESTIMATION OF UNSAFE ITEM AND SOLVE SOLUTIONS ............................. 24
7.4. ENVIRONMENT MANAGEMENT .......................................................................... 25
7.5. FIRE/EXPLOSION PREVENTION ........................................................................... 25
7.5.1. FIRE/ EXPLOSION SEQUENCE .............................................................................. 25
7.5.2. FIRE/ EXPLOSION PREVENTION METHOD ........................................................ 26
7.5.3. FIRE/ EXPLOSION FIGHTING METHOD .............................................................. 26
7.6. COUNTERMEASURES AGAINST UNSAFE SOURCES ....................................... 27
1. INTRODUCTION
This document describes the soft soil improvement works by Vacuum consolidation method
(VCM) for internal roads, yards, parking, store and pavement areas of Jotun pain factory
project at Hiep Phuoc IZ, Nha Be district, Ho Chi Minh city.
2. SCOPE OF WORKS
Method statement included these work items as below:
PVD installation
Install the VCM system
Operating of VCM system
Monitoring and reporting
Surcharge filling
PVDs material shall be satisfied these specification requirements in following table as below:
Table 4.3.1 Specification requirements of PVDs
PVDs
1 Thichness TCVN 8220 mm ≥4
2 Strength at break ASTM D4595 kN >1.6
3 Elongation at break ASTM D4595 % >20
4 Elongation at pressure of 0.5kN TCVN 8871-1 % <10
Discharge capacity at pressure of 10
5 ASTM D4716 10-6 m3/s 80-140
kN/m2, gradient I=0.5
Discharge capacity at pressure of 300
6 ASTM D4716 10-6 m3/s 60-80
kN/m2, gradient I=0.5
PVDs filter
1 Trapezoid tearing force TCVN 8871-2 N >100
2 Breaking resistance TCVN 8871-5 kPa >900
3 Penetration resistance TCVN 8871-4 N >100
Test samples and catalogs of PVDs shall be submitted and approved prior to purchase and
deliver to the site for construction with distance and depth as design drawings. Each
100,000m length of PVDs shall get a laboratory sample taken. PVD is stored in the warehouse
to avoid exposure to rain, sunlight and damage.
PVDs mass
(3)
Acceptance and
(4) handover
(3) (4)
Installation D50 Installation D63
(6)
No Check No
Yes
Base on the construction drawing for horizontal pipe, setting out of position at the
site
(2) Dig the trench
For filtration pipe D50: Using a shovel to open trench with cross section is triangle
shape 15cm x 20cm or rectangular shape 15cm x 15cm x 20cm at PVDs rows (with
20cm depth of the trench).
For main pipe D63: The trench size of main pipe D63 is similar the trench size of
filtration pipe D50.
(3) Construction of filtration pipe D50
The filtration pipe system will be installed in the same position of PVDs rows. The
head of PVDs shall be wound to filtration pipe at least 2 cycles and tied by plastic
belt to ensure stability of connection and continuity of the permeability path during
the construction process
The filtration pipe system shall be connected to the main pipe by 3-way connection
or 4-way connection.
The position of connection point might follow the design drawing and shop drawing
of horizontal pipe.
(6) Check the horizontal pipe installation
PVDs were wrapped and tied to the filtration pipe and guarantee constant.
The connection point will be covered with geotextile to ensure without entered of
sand during vacuum operation process. This connection point also guarantees
constant, without breaking and failure follows the construction period.
After completed, fill sand in the trench, clean the site and prepare the next steps.
Figure 4.4.3 Illustration of main pipe D63 installation and connected with pipe D50
Noted: Level 1 of geoxtextile is used for the first geotextile layer under geo-membrane. Level
2 of the geotextile is used for the second geotextile layer upper Geo-membrane.
Figure 4.5.1 Flow chart of construction sequence of geo-membrane and the 1st geotextile
The construction site shall be cleaned before laying geotextile layer, particularly,
remove all strange objects, sharp objects to out of site.
(1) Laying the first geotextile layer
These rolls of geotextile shall be laid and sewn by sewing machine with overlap is
about 10cm.
Follow the treatment boundary, the edge of the geotextile is remained about 2.0m to
2.5m that shall be buried combine Geo-membrane into the trench.
Checking the sewed line to ensure enough of overlap and stable
Geotextile should be constructed in dry environment condition, if has water, It will
be heavy, these works such as transfer, laying, sewed become difficult.
between these devices with geo-membrane are also glued, tied carefully to ensure
airtight. Noted: Surface settlement plate has to cover by geotextile or bags when set
on the surface of geo-membrane to avoid breaking of geo-membrane.
Any connections have to ensure airtight (using rubber gasket, waterproofing tape if
necessary) to ensure no leakage of vacuum pressure during operation.
Finally, the power is connected to the pumping system: Each pump is connected to
one switch in the control EB to ensure easy switching when needed. The connection
must be performed by electricians, electrical safety during construction
5. CONSTRUCTION PROGRESS
The soil improvement work is proposed to carryout in six months. The detail S.I.W schedule
is shown in attachment “S.I.W schedule”, but this construction schedule must be updated and
approved by owner and supervisor.
6. QUALITY MANAGEMENT
6.1. QUALITY OF PLAN AND GOAL
A 100% acceptance upon completion.
A 100% quality acceptance. To satisfy quality requirement according to relate
standard and codes, reach or exceed the design requirement.
6.2. QUALITY GUARANTEE SYSTEM
processing rules, and benefit-penalty rules. The rules are carried by each tier to build
an environment of safe construction maintained by each person
Establish a safety responsibility system based on safe duties. Specify the safety
responsibilities of each tier personnel
The main safety precautions include mechanical injuries, electrical shocks, traffic
accidents, fire disasters and poisonous foods
Carry out safety examination rules stringently. Firstly, the Project Manager should
ensure they carry-out of rules. Secondly, any identified safety concern should be
subjected to reporting, reconstruction and removal. Thirdly, combine safety
examinations with rules modification
7.3.2. Electrical safety Rules
Upon constructions, examine stringently the tools and instruments. No use of unsafe
tools and instruments. Precautions on voltage, current and isolation should be abided
by. Electricians should wear protections and isolative tools.
Electricians should repair or install only if the power is switched off. Examinations
under electrical conditions should not be conducted alone, in which case, one
company should stand by and take necessary safety measures.
Temporary power lines should abide by safety specifications. Outdoor power lines
must not be exposed to bumps, mechanical ruins, chemical corrosions and rolling-
over. Connections should be protected from water and humidity and well isolated.
The open switch box must be equipped with electrical protections, whose
specifications and capacities should meet criteria. The switch box should protect
from rainfalls and wet conditions. After rainfalls, electricians should measure the
resistively of the switch box. Only if safe requirements are met, the switch box can
be used. The switch box should be used for one machine. Prohibit multiple machines
loaded by one switch box.
7.3.3. Estimation of unsafe item and solve solutions
Table 7.3.3.1 Table of Identification and assessement of unsafe source and factor
Frequency and Solution
No Actives Dangers Consequence Remark
Frequency Solution
Safety manager
Tel: ………….
Hospital
Tel: …………. Action to prevent
Site office accident
Victim’s
Organization of Cambodia -
Tel: …………
Contractor’s
Leader
Tel: …………
Government offices
concerned : Regional police
Tel: ………..
5 Methodstatment 7 days Sun 7/1/18 8:00 AM Sat 7/7/18 5:00 PM 7/1 7/7
9 Vacuum system installat25 days Sun 7/8/18 8:00 AM Wed 8/1/18 5:00 PM 7/8 8/1
10 Monitoring installation 15 days Sun 7/8/18 8:00 AM Sun 7/22/18 5:00 PM 7/8 7/22
11 Vacuum trial running 7 days Thu 8/2/18 8:00 AM Wed 8/8/18 5:00 PM 8/2 8/8
12 Sand compensation fillin30 days Thu 8/9/18 8:00 AM Fri 9/7/18 5:00 PM 8/9 9/7
13 Vacuum running 120 days Thu 8/9/18 8:00 AM Thu 12/6/18 5:00 PM 8/9 12/6
14 Monitoring and 147 days Fri 7/13/18 8:00 AM Thu 12/6/18 5:00 PM 7/13 12/6
15 Post soil investigation 20 days Fri 12/7/18 8:00 AM Wed 12/26/18 5:00 PM 12/7 12/26
16 Site clean and Handover 1 day Thu 12/27/18 8:00 AM Thu 12/27/18 5:00 PM 12/27 12/27
Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress