Project Details
Project Title : Daily-Refresh @ 4 : Store Fresh 2019-20 Department Name : Format
Priority : Urgent Start/End Date : 11/07/2019 - 11/07/2019
Assigned To : Department Manager/ Assistant Department Manager - Store Fresh Launch Date : 11/07/2019
Business Sponsor : Format Gatekeeper-Format Project Length : 1day(s)
Effort : 0h 0m Created By : Aamod Laghate
Task List
Organize, spruce-up and clean the primary and secondary displays, with stock 11/07/2019 - Department Manager/ Assistant 0h 1
10/266
replenished to full 11/07/2019 Department Manager - Store Fresh 0m Days
Remove unwarranted merchandise/ excess stocks from the floor. Left over 11/07/2019 - Department Manager/ Assistant 0h 1
14/266
merchandise and trolleys to go back to respective places. 11/07/2019 Department Manager - Store Fresh 0m Days
Ensure right price signage/wobbler is displayed in the primary and secondary 11/07/2019 - Department Manager/ Assistant 0h 1
10/266
display as per display standards. 11/07/2019 Department Manager - Store Fresh 0m Days
Decide on the excess boxes, gunny bags or crates to be kept in the hold zone (if 11/07/2019 - Department Manager/ Assistant 0h 1
14/266
available on shofloor). Ensure hold area is properly organized, for quick refill. 11/07/2019 Department Manager - Store Fresh 0m Days
Refresh@4.png
Survey Questions
Question
Survey Title Question Options
Type
Task Completion Surveys - Organize, spruce-up and clean the primary and secondary Has the primary and secondary display been set as
Yes/No Yes, No
displays, with stock replenished to full per standards? share photos.
Task Completion Surveys - Ensure right price signage/wobbler is displayed in the Does the signage/ wobbler reflect right
Yes/No Yes, No