Documente Academic
Documente Profesional
Documente Cultură
TABLE OF CONTENTS
Page No.
1.0 PREAMBLE 3
8.3.1 480V 50% Lighting and Receptacles and other station auxiliaries 70
ATTACHMENT:
1.0 PREAMBLE
Saudi Electric Company - Central Operating Area (SEC-COA), Power Plant PP9, Stage-II, Block-F, comproses twelve 12
nos.gas turbine GT 45,46,47,48,49,50,51,52,53,54,55,56. arranged in six pairs, feed the generated power to 380 kV
system through six ( 6) three winding transformers and XLPE cables to 380 kV GIS substation.
Each GT is interconnected to generator transformer over generator and system circuit breaker with a tap off
connection over current limiting reactor at 13.8kV circuit breaker for connection to unit auxiliary transformer for
supplying power to unit auxiliaries. Auxiliary power requirement of each unit is derived at 480V over 13.8/0.48V unit
auxiliary transformer.
13.8kV station switchgear is formed taking tap off connection of power at 13.8kV from unit 52 & 53 that is located at
station electrical room. Power at 13.8kV is stepped down to 4.16kV over two (2) transformers for supplying station
auxilaries for entire power block of Plant 'F'. Provision is also made for interconnection with Plant 'D' for emregency
purpose. Further 13.8kV station switchgear shall have the provision for interconnection with future station switchgear.
4.16kV starting motor of each unit is fed from station 4.16kV station switchgear. Also auxiliary power requirement for
fuel and gas system of each unit is fed seperately over 4.16/0.48V transformer.
Plant essential and non essential loads are also fed from station 13.8kV system over separate auxiliary transformers.
Power distribution arrangement with relaying & metering as shown in below mentioned drawings, is considered for
for Protection
Protection Studies
Studies andand relay
relay setting
setting calculations.
calculations.
h) BNF-F20-BHB00-2014 Single Line Diagram For 480V Unit Fuel Oil / Gas Heater
Switchgear - For GT 51,52,53,54,55 & 56
i) BNF-F10-BHB00-2016 Single Line Diagram For 480V Unit Fuel Oil / Crude Oil
Heater Switchgear - For GT 45.46,47,48,49,50
For Generator transformer, transformer differential protection and restricted earth fault protection are provided in the
Transformer Management relay (T60) provided in generator protection panel located at the control room of local
electrical building for each pair of GT units. Back up overcurrent and earthfault protection are also covered with the
same relay. Each T60 relay covers the entire zone from 380 kV Bushing of GSU Transformer, upto one complete leg of
GSU LV winding and equipment connected downstream (i.e. winding of one GT Generator and tap-off to unit auxiliary
breaker 52U). Thus, for the 3-winding transformer case there are two T60 relays and each relay covers upto 52S
breaker connected from the other LV winding of GSU Transformer, thus creating an overlap of the zone between the
two (2) 52S breakers.
For 13.8kV unit switchgear, protective relaying mainly limited to generator protection that is covered with generator
management relay (G60) and generator circuit mangement relay (C60) that are covered under GE document
RECOMMENDED RELAY SETTINGS. Otherwise, system circuit breaker provided in 13.8kV system does not have
seperate relaying other than to facilitate inter tripping of the circuit breaker due to fault in associated system. For
busbar differential protection, relays are provided in 13.8kV unit switchgear located at the local electrical building for
each pair of GT units.
For 13.8kV and 4.16kV station switchgear, protection relays for incomer, bus coupler and outgoing feeders are
provided in the switchgear panel loacated at the station electrical building.
For 480V switchgear, circuit breakers are provided with in-built releases.
2 E R + ECT
t '= ( 100
ER = Relay error
) t + t CB +t 0 +t S
Total relay and CT error is assumed to be limited to 20% considering numerical relays. Fixed time
margin due to circuit breaker operating time, relay overshoot and safety margin is considered as
200ms.
Time interval for protection co-ordination is proposed to adopt as follows:
3.1A CASE1 :OVERALL DIFFERENTIAL PROTECTION (87U) WITHOUT TAP OFF TO STN. SWGR.
The differential protection has to be stabilized such that it does not operate for a (through
fault), i.e. a fault outside the zone of protection.
It is established the attached Short Circuit Report that the maximum current for which the
Differential Protection is to be stabilised shall be equal to 666.4 Amps on 380 kV
I.e 18350 Amps on 13.8 kV side
(Refer Attachment-2, 3-Phase Fault at Bus-53, Page-15).
* CT Ratio:
* 380 kV CT = 600 1 Amp
* 83.2 MW Gen Neutral CT = 6000 1 Amp
* 52S CT (UNIT-55) = 6000 1 Amp
* 52U CT (UNIT-56) = 6000 1 Amp
Calculation of CT Margin:
Magnitude Compensation Factors (M) are the scaling values by which each winding current is
multiplied to refer it to the reference winding.
The Phase Reference winding is the winding which will have a phase shift of 0° applied to it.
The Phase Compensation angle is the angle by which a winding current is shifted to refer it to
the phase reference winding.
Magnitude & Phase Angle Compensation factor for 13.8kV Gen CT:
* Phase Angle shift of current seen by 13.8kV Gen CT with respect to phase angle shift
of current seen by the reference CT i.e. 52S CT (Unit-55) shall be 0°.
* Phase angle of current seen by 52S (UNIT-55)CT with respect to phase angle of current seen by
the reference CT i.e. 52S (UNIT-55)CT shall be 0°.
* Phase Angle shift of current seen by 52U CT (UNIT-56) with respect to phase angle shift
of current seen by the reference CT i.e. 52S CT (Unit-55) shall be 0°.
Vector Group of the transformer is YNd1d1. Therefore, Phase Angle shift of current seen by
380 KV CT with respect to phase angle shift of current seen by the reference CT
NOTE:
The Maximum allowed magnitude compensation factor (& hence, the maximum allowed CT
Ratio mismatch) is 32.
Phase
Angle
CT Primary / Magnitude
S.No. CT Margin Comp
Location Secdry. Compensation
ensati
380 kV Side of on
1 GSU Transformer
Generator side of 600/1 1.8 C1 = 2.75 +30°
2 GSU Transformer 6000/1 1.4 C2 = 1.00 0°
3 52S (UNIT-46) 6000/1 1.3 C3 = 1.00 0°
4 52U (UNIT-45) 6000/1 95.2 C4 = 1.00 0°
This setting defines the minimum differential current required for operation. It is chosen,
based on the amount of differential current that might be seen under normal operating
conditions.
Two factors may create differential current during the normal transformer operation:
a) Errors due to CT inaccuracies.
b) Current variation due to OLTC operation.
Considering the above, we select an Initial differential current setting of 25% i.e.
This setting defines the differential restraint during normal operating conditions to assure
sensitivity to internal faults. The setting must be high enough, however, to cope with CT
saturation errors during saturation under small current magnitudes but significant and long
lasting DC components (such as during distant external faults in vicinity of Generators).
The SLOPE-1 setting defines the ratio of differential to restraint current above, which the
element will operate.
The criteria for setting this slope are:
= 0.25 x Ir
1) To allow for mismatch when operating at the limit of the transformer’s tap changer
range; +14 to -10% tap changer range, this criterion contributes up to about 14% to the
slope setting.
2) To accommodate for CT errors. With a Class C400 CT, the CT errors up to 1 to 20 times the
rated secondary current. Thus, the second criterion contributes maximum ratio error up to 10%
to the slope setting.
From the above criteria, the composite contribution for Slope Settings comes to 25%.
The settings for Break-1 and Break-2 depends very much on the capability of CTs to correctly
transform primary into secondary currents during external faults.
Break-1 should be set below a current that would cause CT saturation due to DC
components and/or residual magnetism.
To determine the maximum DC component current that would cause saturation of the CT
due to a through fault, a comparison of two fault locations have been considered.
Therefore,
Select Break Point -1 = 1.2
Break-2 should be set below the fault current that is most likely to saturate some CTs due
to an AC component alone. The 52S CT (Unit-55) shall see the maximum AC
component current alone due to high through fault current. The heaviest through fault current
of this differential zone shall be seen by the 52S CT (Unit-55), for a 3-Phase Fault at Bus-53.
= 3.06
Therefore,
Select Break Point - 2 = 3.0
The Slope -2 setting ensures stability during heavy through fault conditions, where CT
saturation results in high differential current. Slope-2 should be set high to cater for the
worst case where one set of CTs saturates but the other set doesn't. In such a case,
the ratio of the differential current to restraint current can be as high as 95 to 98%.
As it has been seen earlier for this differential zone, the extreme case of complete
Saturation of one CT has been considered for a through fault at Bus-53.
Assuming “No saturation” of any CT, the differential measured by the Relay shall be:
Where, C1, C2, C3 & C4 are the Magnitude & Phase Angle Compensation factors for the 4 CT
inputs.
The Restraint current input computes Ir = higher of the absolute values [Is1 * C1], [Is2 * C2] &
[Is4 * C4].
Thus,
Ir = 2.89
Ir = 3.1
= 98.0 %
= 98 %
If set to "Per Phase", the relay performs inrush inhibit individually in each phase. If used on
modern transformers, this setting should be combined with adaptive 2nd harmonic function.
If set to "2-out-of-3", the relay checks 2nd harmonic level in all three phases individually.
If any two phases establish a blocking condition, the remaining phase is restrained
automatically.
If set to "Average", the relay first calculates the avearge 2nd harmonic ratio, then applies the
inrush threshold to the calculated average. This mode works only in conjuction with the
traditional 2nd harmonic function.
3.1B OVERALL DIFFERENTIAL PROTECTION (87U) WITH TAP-OFF TO 13.8kV STN. SWGR.
The differential protection has to be stabilized such that it does not operate for a (through
fault), i.e. a fault outside the zone of protection.
It is established the attached Short Circuit Report that the maximum current for which the
Differential Protection is to be stabilised shall be equal to 666.4 Amps on 380 kV
I.e 18350 Amps on 13.8 kV side
(Refer Attachment-3, 3-Phase Fault at Bus-17).
* Irated (13.8 kV- Stn. Swgr. side Side) -(UNIT-52) = 698.70 Amps
CT Ratio:
* 380 kV CT = 600 1 Amp
* 83.2 MW Gen Neutral CT = 6000 1 Amp
* 52S CT (UNIT-51) = 6000 1 Amp
* 52U CT (UNIT-52) = 6000 1 Amp
* 13.8kV CT For tap-off to Stn. Swgr. = 6000 1 Amp
Calculation of CT Margin:
Magnitude Compensation Factors (M) are the scaling values by which each winding current is
multiplied to refer it to the reference winding.
The Phase Reference winding is the winding which will have a phase shift of 0° applied to it.
The Phase Compensation angle is the angle by which a winding current is shifted to refer it to
the phase reference winding.
Magnitude & Phase Angle Compensation factor for 13.8kV Gen CT:
* Phase Angle shift of current seen by 13.8kV Gen CT with respect to phase angle shift
of current seen by the reference CT i.e. 52S CT (Unit-51) shall be 0°.
* Phase angle of current seen by 52S (UNIT-51) CT with respect to phase angle of current seen by
the reference CT i.e. 52S (UNIT-51) CT shall be 0°.
* Phase Angle shift of current seen by 52U CT (UNIT-52) with respect to phase angle shift
of current seen by the reference CT i.e. 52S CT (Unit-51) shall be 0°.
* Vector Group of the transformer is YNd1d1. Therefore, Phase Angle shift of current seen by
380 KV CT with respect to phase angle shift of current seen by the reference CT
i.e. 52S (UNIT-51) CT shall be +30°.
Magnitude & Phase Angle Compensation factor for 13.8 kV Stn. Swgr. CT :
Phase Angle shift of current seen by 13.8kV Station Swgr CT with respect to phase angle shift
of current seen by the reference CT i.e. 52S CT (Unit-51) shall be 0°.
NOTE:
The Maximum allowed magnitude compensation factor (& hence, the maximum allowed CT
Ratio mismatch) is 32.
Phase
Angle
CT Primary / Magnitude
S.No. CT Margin Comp
Location Secdry. Compensation
ensati
380 kV Side of on
1 GSU Transformer
Generator side of 600/1 1.8 C1 = 2.75 +30°
2 GSU Transformer 6000/1 1.4 C2 = 1.00 0°
3 52S (UNIT-51) 6000/1 1.3 C3 = 1.00 0°
4 52U (UNIT-52) 6000/1 95.6 C4 = 1.00 0°
5 13.8 kV Stn. Swgr CT 6000/1 8.6 C5 = 1.00 0°
Operate times:
Harmonic Inhibits selected : 20 to 30 ms
No Harmonic inhibits selected : 5 to 20 ms
Dropout Level : 97 to 98% of pickup
Level Accuracy : (+/- 0.5% of reading or +/- 1% of rated)
(Whichever is greater)
Instanteneous Differential:
Pickup Level : 2.00 to 30.00 pu in steps of 0.01
Dropout level : 97 to 98% of pickup
Level Accuracy : (+/- 0.5% of reading or +/-1% of rated)
(Whichever is greater)
This setting defines the minimum differential current required for operation. It is chosen,
Considering the above, we select an Initial differential current setting of 25% i.e.
~ 0.25 x In.
This setting defines the differential restraint during normal operating conditions to assure
sensitivity to internal faults. The setting must be high enough, however, to cope with CT
saturation errors during saturation under small current magnitudes but significant and long
lasting DC components (such as during distant external faults in vicinity of Generators).
The SLOPE-1 setting defines the ratio of differential to restraint current above, which the
element will operate.
The criteria for setting this slope are:
= 0.25 x Ir
1) To allow for mismatch when operating at the limit of the transformer’s tap changer
range; +14 to -10% tap changer range, this criterion contributes up to about 14% to the
slope setting.
2) To accommodate for CT errors. With a Class C400 CT, the CT errors up to 1 to 20 times the
rated secondary current. Thus, the second criterion contributes maximum ratio error up to 10%
to the slope setting.
From the above criteria, the composite contribution for Slope Settings comes to 25%.
The settings for Break-1 and Break-2 depends very much on the capability of CTs to correctly
transform primary into secondary currents during external faults.
Break-1 should be set below a current that would cause CT saturation due to DC
components and/or residual magnetism.
To determine the maximum DC component current that would cause saturation of the CT
due to a through fault, a comparison of two fault locations have been considered.
Therefore,
Select Break Point -1 = 1.2
Break-2 should be set below the fault current that is most likely to saturate some CTs due
to an AC component alone. The 52S (Unit- 51) CT shall see the maximum AC
component current alone due to high through fault current. The heaviest through fault current
of this differential zone shall be seen by the 52S (Unit- 51) CT, for a 3-Phase Fault at Bus-17.
= 3.1
Therefore,
Select Break Point - 2 = 3.1
The Slope -2 setting ensures stability during heavy through fault conditions, where CT
saturation results in high differential current. Slope-2 should be set high to cater for the
worst case where one set of CTs saturates but the other set doesn't. In such a case,
the ratio of the differential current to restraint current can be as high as 95 to 98%.
As it has been seen earlier for this differential zone, the extreme case of complete
Saturation of one CT has been considered for a through fault at Bus-17.
Is5 = 0.0094
< (-85.91) deg (with respect to LV line-to-line voltage phas
Assuming “No saturation” of any CT, the differential measured by the Relay shall be:
Where, C1, C2, C3 & C4 are the Magnitude & Phase Angle Compensation factors for the 4 CT
inputs.
The Restraint current input computes Ir = higher of the absolute values [Is1 * C1], [I s2 * C2], [Is4 * C4] &
[Is5 * C5].
Thus,
Ir = 3.06
Ir = 3.1
If set to "Per Phase", the relay performs inrush inhibit individually in each phase. If used on
modern transformers, this setting should be combined with adaptive 2nd harmonic function.
If set to "2-out-of-3", the relay checks 2nd harmonic level in all three phases individually.
If any two phases establish a blocking condition, the remaining phase is restrained
automatically.
If set to "Average", the relay first calculates the avearge 2nd harmonic ratio, then applies the
inrush threshold to the calculated average. This mode works only in conjuction with the
traditional 2nd harmonic function.
Maximum Earth Fault Current Igf (max) from the short circuit report for L-G & L-L-G, seen by
REF CTs on 380 kV side, the maximum is taken as:
= 83.78 Amps
The Phase Current Iph increases due to the fault are negligible, therefore,
3 Io = 0 Amps
The Per-Unit V/Hz value is calculated using the maximum of the three-phase voltage inputs or the auxiliary
voltage channel Vx input, if the source is not configured with the phase voltages.
Inverse Curve A:
The Curve for the Volts/Hertz Inverse Curve A shape is derived from the formula given below:
Where,
T = Operating Time
TDM = Time Delay Multiplier (Delay in Sec)
V = Fundamental RMS Value of Voltage (pu)
F = Frequency of Voltage Signal (pu)
instanteneous Pickup:
Trfr.Impedance: 58 %
Maximum Through Fault Current = Incomer Transformer MVA X 1000/ Xfr. % Imp/(sqrt(3) X 132)
= 576.30 Amps at 380 kV
= 576.00 Amps (Say) at 380 kV
= 52615.38 Amps at 4.16 kV
= 52615.00 Amps (Say) at 4.16 kV
Time interval for proper co-ordination with downstream 13.8 kV Station switchboard Incomer
is proposed to be adopted as follows:
For proper coordination with downstream Station switchboard Incomer, operating time of 13.8 kV Incomer
corresponding to a high set current of 32370.00 is set at :
= 1.52 Sec
= 1.50 Sec considered
Required TMS Setting for Normal Inverse type Overcurrent Protection to achieve desired operating
time of 1.50 sec at 32370 / 30692 i.e 1.05 times of Set Current
Calculated as follows:
0.14
1.5 = TMS X
(I/Ipickup).02 - 1
Selected Setting:
IDMT Overcurrent Setting = 0.56 X In
Curve = Normal Inverse
TMS = 0.06
Instanteneous Overcurrent pickup is proposed to be set so that the relay does not operate under
Transformer Through Fault Current.
Definite Time is proposed to be set at 100 msec corresponding to instanteneous set current.
Selected Setting:
instanteneous Overcurrent Setting = 1.25 X In
Definite Time = 0.10 Sec
Time interval for proper coordination with 380 kV line side relay is proposed to be adopted as follows:
t' = 0.2 + 0.2 X t where t = normal operating time of line side relay
For proper coordination between transformer line side relay and generator transformer neutral side relay,
operating time is considered as 0.75 sec considering 0.45 sec relay operating time of line side
circuit breaker at 20 times relay set current.
Required TMS Setting for Normal Inverse type Earth fault Protection to achieve desired operating
time at 20.00 times relay set current is calculated as follows:
0 .14
0.75 = TMS X
(I/Ipickup).02 - 1
Selected Setting:
For Generator Protection, ‘G-60’ relay is provided in the Generator Protection panel. These relays
. Distance Backup
are integrated Protection*
protection systems which cover the following protections.:
. Volts/Hertz
. Under Voltage
. Third Harmonic
. Directional Power
. Loss of Excitation
. Negative Sequence overcurrent
. Out of Step*
. Voltage restrained Overcurrent*
. Phase Over voltage
. Overvoltage, Neutral (Gnd Protection)
Under frequency
Generator Stator Differential
Generator circuit management relay 'C60' is also provided in the Generator Protection panel.
Protection features covered under these relays are as follows:
. Breaker Failure protection*
. Phase overcurrent*
. Phase undervoltage*
. Neutral overvoltage*
. Synchrocheck
. Inadvertent energization protection
For the * marked functions, relay setting calculation is covered in the subsequent clauses.
Generator Data:
CT/PT Data
LV PT Ratio 14400/120
LV CT Ratio 6000/1
HV CT Ratio 600/1
HV PT Ratio 380000/115
Transformer impedance, Zt 29 % @ 110 MVA base
Transformer MVA 110 MVA for each winding
Transformer kV 380 kV
PP9 EXTENSION REINFORCEMENT
BNE-F00-BDO00-2040 24 OF 187
(BLOCK F)
REV A
PROTECTION STUDIES AND RELAY SETTING CALCULATIONS
Generator Data
ZGen (pri) + Z H-X1 (Pri) = 194.11 ohms 89.55 deg.+380.678 ohms 89.53 deg.
= 1.5245 + j 194.1045 + 3.1503 + j
= 4.6748 + j 574.7693
= 574.79 ohms 89.53 deg.
For a fault on 380 kV system, Generator fault contribution is 380/(1.732X ZGen (pri) + Z H-X1 (Pri)
382 Amps
with
Minimum = 25.10 ohms 89.53 deg. + 0.9 x 0.0443 ohms 84.67 deg.
infeed = 0.2077 +j 25.1017 + 0.9x 0.0041 +j
(K=1) is = 0.2114 +j 25.14
= 25.1423 ohms 89.52 deg.
= 51.20 %
With an offset of 40% of the reach setting, backup protection is supplied to 40/ 51.20
PP9 EXTENSION REINFORCEMENT
BNE-F00-BDO00-2040 26 OF 187
(BLOCK F)
REV A
PROTECTION STUDIES AND RELAY SETTING CALCULATIONS
= 78.13 % of the Gas turbine Generator stator winding.
Time delay setting is recommended as 0.8 sec in line with the practice adopted for the existing
Generators
Settings :
Reach setting: 25.00 ohms
Offset: 40%
Impedance angle: 89.52 deg.
Delay 0.8 sec.
Relay Data:
Diameter Setting:
Transformer Reactance:
Generator Reactance:
Offset Setting:
Setting = - 2 Xd’
Xt is Transformer reactance
Xd’ is Transient reactance of the Generator
Xs is System Reactance
j is 90 degree
a is 120 degree
System Reactance:
Transformation Ratio, Tr = 50
System Reactance (relay ohms), X sys (rel) = Xsys(Pri)x (VGen / VLine)2 x Tr
Primary fault clearing time at 380kV levels is assumed as 80ms. Accordingly delay setting is 5 cycles.
Generator Data:
CT/PT Data
LV PT Ratio 14400/120
LV CT Ratio 6000/1
The function is backup protection and should be set to co-ordinate with the Power system protective relays
used at the Generating Station. The pickup is set for 150% times generator rated load current.
Generator maximum base output = 74.34 MW at 13.8kV, 0.80pf and 60Hz.
= 92.93 MVA
1
1.50 x3888 0.972A
6000
Ir = 0.972 A
T, operate time in seconds should be selected to back-up the relays on transmission lines/ cables out of the
generating station.
Considering , Zone 2 = 0.45s (27 cycles).
1
Generator Contribution , If =( 3888 x )/ 0 . 4699=1 . 38 A ,sec ondary
6000
Multiple of pick-up = If / Ir
= 1.38 / 0.972 = 1.42
E
T If 1
Ipickup X Pickup reduction
TDM (Multiplier setting) =
K
The scheme determines a breaker failure condition via three 'paths'. Each of these paths is
equipped with a time delay, after which a failed breaker is declared & trip signals are sent to
all breakers required to clear the zone.The delayed paths are associated with breaker failure
timers 1, 2 & 3, which are intended to have delays increasing with increase timer numbers.
These delayed paths are individually enabled to allow for maximum flexibility.
The current supervision elements reset in less than 0.7 of a power cycle upto the multiple of
pickup of 100 (threshold set at 0.01 of the actual fault current).
Selected Settings:
Trfr.Impedance: 6%
Maximum Through Fault Current = Incomer Transformer kVA/ Xfr. % Imp/(sqrt(3) X 13.8)
= 1045.92 Amps at 13.8 kV
= 3469.65 Amps at 4.16 kV
= 3470.00 Amps (Say) at 4.16 kV
Time interval for proper coordination with downstream 0.48 kV Incomer is proposed to
be adopted as follows:
For proper coordination with downstream incomer of 0.48 kV Switchboard Incomer, operating
time of 13.8 kV Outgoing Feeder to 1.5 MVA Transformer corresponding to an high set
PP9 EXTENSION REINFORCEMENT
BNE-F00-BDO00-2040 33 OF 187
(BLOCK F)
REV A
PROTECTION STUDIES AND RELAY SETTING CALCULATIONS
current of 3470.00 Amps is required to be set at : 0.68 sec
= 0.70 sec Say
Required TMS Setting for Very Inverse type Overcurrent Protection to achieve desired operating
time of 0.70 sec at 3470/ 266 i.e 13.05
= 13.00 Say times of Set Current is
calculated as follows:
13.5
0.6 = TMS X
(I/Ipickup)1.0 - 1
Selected Setting:
IDMT Overcurrent Setting = 0.80 X In
Curve = Very Inverse
TMS = 0.60
Instateneous Overcurrent pickup is proposed to be set so that the relay does not operate under
Transformer Through Fault Current.
Definite Time is proposed to be set at 100 msec corresponding to instanteneous set current.
Selected Setting:
Instateneous Overcurrent Setting = 13.60 X In
Definite Time = 0.10 Sec
Selected Settings:
Selected Settings:
Pickup : 0.1 p.u.
CT Parameters :
52G & 52S CT:
CT Ratio : 8000 1 Amps
Class : 5P20
Burden : 30.00 VA
Rct : 15.00 Ohms (Assumed)
52U CT:
CT Ratio : 8000 1 Amps
Class : 5P20
Burden : 30.00 VA
Rct : 15.00 Ohms (Assumed)
System Parameters:
Voltage : 13.80 kV
Fault Level : 63.00 kA for 1 sec
SEL-587Z is a voltage operated high impedance relay. When Through Fault current passes through the
CT, certain additional voltage is developed in the CT secondary across the relay.
To ensure stability as well as to protect mal operation of the relay, the set
Where,
Vs = Minimum Setting Voltage (Calculated)
If = Maxm. Value of Through Fault Current for which protection must remain stable
RCT = C.T Secondary Resistance
The Relay Plug Setting Voltage V R must be set to the nearest tap above V s.
The minimum primary current for the relay operation is given by:
Therefore,
IP = 840.00 = 840.00 Amps (Say)
Full Load Current of the Section is assumed to be equal to 75% of the rated busbar current
= 4500 Amps
Therefore,
Sensitivity (%) = (IP / IL) x 100%
= 18.67 = 19 %
Since, the Sensitivity is sufficiently high, therefore, there is no requirement of providing an
additional Shunt Resistance for improving the Relay Sensitivity.
5.2 BUSBAR DIFFERENTIAL PROTECTION (APPLICABLE FOR THREE (3) WINDING TRANSFORMER WITH TAP
For Differential Protection of 13.8kV Unit Switchgear Busbar, Relay SEL-587Z has been
provided.
CT Parameters :
52G & 52S CT:
CT Ratio : 8000 1 Amps
Class : 5P20
Burden : 30.00 VA
Rct : 15.00 Ohms (Assumed)
System Parameters:
Voltage : 13.80 kV
Fault Level : 63.00 kA for 1 sec
SEL-587Z is a voltage operated high impedance relay. When Through Fault current passes through the
CT, certain additional voltage is developed in the CT secondary across the relay.
To ensure stability as well as to protect mal operation of the relay, the set
Where,
Vs = Minimum Setting Voltage (Calculated)
If = Maxm. Value of Through Fault Current for which protection must remain stable
RCT = C.T Secondary Resistance
RL = Lead resistance between furthest C.T and relay connection point
N = Turns Ratio of C.T
The Relay Plug Setting Voltage V R must be set to the nearest tap above V s.
The minimum primary current for the relay operation is given by:
Therefore,
IP = 920.00 = 920.00 Amps (Say)
Full Load Current of the Section is assumed to be equal to 75% of the rated busbar current
= 4500 Amps
Therefore,
Instanteneous Pickup:
Sensitive Ground Fault (51G): 0.005 to 0.12 Amp in steps of 0.001 Amp
Trfr.Impedance: 9%
Maximum Through Fault Current = Incomer Transformer kVA/ Xfr. % Imp/(sqrt(3) X 13.8)
= 1487.54 Amps at 13.8 kV
= 4934.62 Amps at 4.16 kV
= 4935.00 Amps (Say) at 4.16 kV
Time interval for proper coordination with downstream 0.48 kV Incomer is proposed to
be adopted as follows:
For proper coordination with downstream incomer of 0.48 kV Switchboard Incomer, operating
time of 13.8 kV Outgoing Feeder to 3.2 MVA Transformer corresponding to an high set
current of 4935.00 Amps is required to be set at : 0.92 sec
= 0.90 sec Say
Required TMS Setting for Very Inverse type Overcurrent Protection to achieve desired operating
time of 0.90 sec at 4935 / 465 i.e 10.61
= 10.00 Say times of Set Current is
calculated as follows:
13.5 13.5
0.7 = TMS X
0.9
(I/Ipickup) (I/I
1.0
- 1pickup)1.0 - 1
Selected Setting:
IDMT Overcurrent Setting = 0.70 X In
Curve = Very Inverse
TMS = 0.60
Instateneous Overcurrent pickup is proposed to be set so that the relay does not operate under
Transformer Through Fault Current.
Definite Time is proposed to be set at 100 msec corresponding to instanteneous set current.
Selected Setting:
Instataneous Overcurrent Setting = 9.80 X In
Definite Time = 0.10 Sec
For transformer vector group of delta star connection, contribution for the ground fault on low voltage
side will not be transmitted to 4.16 kV side. Hence, the current pick up and TMS is proposed to set at the
minimum values.
Selected Setting:
Current Setting = 0.10 X In
Curve = Normal Inverse
TMS = 0.10
Selected Setting:
Current Setting = 0.12 Amp
Definite Time = 1.00 sec
Trfr.Impedance: 9%
Maximum Through Fault Current = Incomer Transformer kVA/ Xfr. % Imp/(sqrt(3) X 13.8)
= 1626.99 Amps at 13.8 kV
= 5397.24 Amps at 4.16 kV
= 5400.00 Amps (Say) at 4.16 kV
Time interval for proper coordination with downstream 0.48 kV Incomer is proposed to
be adopted as follows:
For proper coordination with downstream incomer of 0.48 kV Switchboard Incomer, operating
time of 13.8 kV Outgoing Feeder to 3.5 MVA Transformer corresponding to an high set
current of 5400.00 Amps is required to be set at : 1.28 sec
= 1.20 sec Say
Required TMS Setting for Very Inverse type Overcurrent Protection to achieve desired operating
time of 1.20 sec at 5400 / 531 i.e 10.17
= 10.00 Say times of Set Current is
calculated as follows:
13.5
1.20 = TMS X
(I/Ipickup)1.0 - 1
Selected Setting:
IDMT Overcurrent Setting = 0.80 X In
Curve = Very Inverse
TMS =
Instateneous Overcurrent pickup is proposed to be set so that the relay does not operate under
Transformer Through Fault Current.
Definite Time is proposed to be set at 100 msec corresponding to instanteneous set current.
Selected Setting:
Instataneous Overcurrent Setting = 10.50 X In
Definite Time = 0.10 Sec
For transformer vector group of delta star connection, contribution for the ground fault on low voltage
side will not be transmitted to 4.16 kV side. Hence, the current pick up and TMS is proposed to set at the
minimum values.
Selected Setting:
Current Setting = 0.10 X In
Curve = Normal Inverse
TMS = 0.10
Selected Setting:
Current Setting = 0.12 Amp
Definite Time = 1.00 sec
6.3 13.8 kV Outgoing 8/10 MVA, 13.8 / 4.16 kV Transformer Feeder (F-00BA-10 & 11)
Trfr.Impedance: 9%
Maximum Through Fault Current = Incomer Transformer kVA/ Xfr. % Imp/(sqrt(3) X 13.8)
= 4648.55 Amps at 13.8 kV
= 15420.68 Amps at 4.16 kV
= 15422.00 Amps (Say) at 4.16 kV
Time interval for proper coordination with downstream 4.16 V Incomer is proposed to
be adopted as follows:
For proper coordination with downstream incomer of 4.16 kV Switchboard Incomer, operating
time of 13.8 kV Outgoing Feeder to 10 MVA Transformer corresponding to an high set
current of 14256.0 Amps is required to be set at : 0.85 sec
= 0.85 sec Say
Required TMS Setting for Very Inverse type Overcurrent Protection to achieve desired operating
time of 0.85 sec at 14256 / 1330 i.e 10.72
= 10.80 Say times of Set Current is
calculated as follows:
13.5
0.9 = TMS X
(I/Ipickup)1.0 - 1
Selected Setting:
IDMT Overcurrent Setting = 0.80 X In
Curve = Very Inverse
TMS = 0.62
instanteneous Overcurrent pickup is proposed to be set so that the relay does not operate under
Transformer Through Fault Current.
Definite Time is proposed to be set at 100 msec corresponding to instanteneous set current.
Selected Setting:
instanteneous Overcurrent Setting = 12.00 X In
Definite Time = 0.10 Sec
For transformer vector group of delta star connection, contribution for the ground fault on low voltage
side will not be transmitted to 4.16 kV side. Hence, the current pick up and TMS is proposed to set at
the minimum values.
Selected Setting:
Current Setting = 0.10 X In
Selected Setting:
Current Setting = 0.12 Amp
Definite Time = 1.00 sec
Feeder Capacity: 16700 kVA ( Considering all transformer loads on one bus-section)
Time interval for proper coordination with downstream 13.8 kV outgoing 10 MVA Transformer feeder is
proposed to be adopted as follows:
Relay operating time of downstream 13.8 kV Outgoing Transformer Feeder set at 19904.00 Amps at
4.16 kV = 0.80 sec
For proper coordination with downstream 13.8 kV Outgoing Transformer Feeder, operating
time of 13.8 kV Tie Feeder corresponding to a high set current of 19904.0 is set at :
= 1.16 Sec
= 1.20 Sec Say
0.14
1.20 = TMS X
(I/Ipickup)0.02 - 1
Selected Setting:
IDMT Overcurrent Setting = 0.70 X In
Curve = Normal Inverse
TMS = 0.30
Instanteneous Overcurrent pickup is proposed to be set so that the relay does not operate
during energisation of Aux. Transformers in the section.
Selected Setting:
instanteneous Overcurrent Setting = 5.50 X In
Definite Time = 0.30 Sec
For proper protection corodination with outgoing feeder, operating time of relay is set at :
0.48 sec
0.45 sec (say) corresponding to a maximum earth fault current of = 1000
Required TMS Setting for Normal Inverse type Overcurrent Protection to achieve desired operating
time of 0.45 sec at 1000 / (1250 X 0.1) i.e 8.00 times of Set Current is
calculated as follows:
0.14
0.45 = TMS X
(I/Ipickup)0.02 - 1
Selected Setting:
Current Setting = 0.12 Amp
Definite Time = 1.00 sec
Feeder Capacity: 16700 kVA ( Considering all transformer loads on one bus-section)
Time interval for proper coordination with downstream 13.8 kV outgoing 10 MVA Transformer feeder is
proposed to be adopted as follows:
Relay operating time of downstream 13.8 kV Outgoing Transformer Feeder set at 19904 Amps at 4.16 kV
0.8
For proper coordination with downstream 13.8 kV Outgoing Transformer Feeder, operating
time of 13.8 kV Tie Feeder corresponding to a high set current of 15370.0 is set at :
= 1.16 Sec
= 1.20 Sec Say
Required TMS Setting for Normal Inverse type Overcurrent Protection to achieve desired operating
time of 1.20 sec at 19904 / 2900 i.e 5.30 times of Set Current is
calculated as follows:
0.14
1.20 = TMS X
(I/Ipickup)0.02 - 1
Selected Setting:
IDMT Overcurrent Setting = 0.70 X In
Curve = Normal Inverse
TMS = 0.30
Instanteneous Overcurrent pickup is proposed to be set so that the relay does not operate
during energisation of Aux. Transformers in the section.
Selected Setting:
instanteneous Overcurrent Setting = 6.00 X In
Definite Time = 0.30 Sec
For proper protection corodination with outgoing feeder, operating time of relay is set at :
0.48 sec
0.45 sec (say) corresponding to a maximum earth fault current of = 1000
Required TMS Setting for Normal Inverse type Overcurrent Protection to achieve desired operating
time of 0.45 sec at 1000 / (1250 X 0.1) i.e 8.00 times of Set Current is
calculated as follows:
0.14
0.45 = TMS X
(I/Ipickup)0.02 - 1
Selected Setting:
Current Setting = 0.10 X In
Curve = Normal Inverse
TMS = 0.15
Selected Setting:
Current Setting = 0.12 Amp
Definite Time = 1.00 sec
Selected Setting:
C.T Parameters:
Selected Setting:
IDMT Overcurrent Setting = 1.00 X In
Curve = Normal Inverse
TMS = 0.10
For proper protection corodination with outgoing feeder, operating time of relay is set at :
0.80 sec
0.80 sec (say) corresponding to a maximum earth fault current of = 1000
Required TMS Setting for Normal Inverse type Overcurrent Protection to achieve desired operating
time of 0.80 sec at 1000 / (500 X 0.1) i.e 25.00 times of Set Current is
calculated as follows:
0.14
0.8 = TMS X
(I/Ipickup)0.02 - 1
Selected Setting:
Current Setting = 0.10 X In
Curve = Normal Inverse
TMS = 0.30
Feeder Capacity: 16700 kVA (Considering 10,3.2 & 3.5 MVA Transformer energised in section)
Time interval for proper coordination with downstream 13.8 kV outgoing 10 MVA Transformer feeder is
proposed to be adopted as follows:
Relay operating time of downstream 13.8 kV Outgoing Transformer Feeder set at 19904 Amps at 4.16 kV
is = 0.87 sec
For proper coordination with downstream 13.8 kV Outgoing Transformer Feeder, operating
time of 13.8 kV Bus Coupler corresponding to a high set current of 19904.0 is set at :
= 1.24 Sec
= 1.20 Sec Say
Required TMS Setting for Normal Inverse type Overcurrent Protection to achieve desired operating
time of 1.20 sec at 19904 / 3320 i.e 6.00 times of Set Current is
calculated as follows:
0.14
1.20 = TMS X
(I/Ipickup)0.02 - 1
Selected Setting:
IDMT Overcurrent Setting = 0.40 X In
Curve = Normal Inverse
TMS = 0.30
Instanteneous Overcurrent pickup is proposed to be set so that the relay does not operate
during energisation of Aux. Transformers in the section under during ABT.
Selected Setting:
Instateneous Overcurrent Setting = 3.00 X In
For proper protection coordination with outgoing feeder, operating time of relay is set at :
0.48 sec
0.50 sec (say) corresponding to a maximum earth fault current of = 1000
Required TMS Setting for Normal Inverse type Overcurrent Protection to achieve desired operating
time of 0.50 sec at 1000 / (2500 X 0.1) i.e 4.00 times of Set Current is
calculated as follows:
0.14
0.50 = TMS X
(I/Ipickup)0.02 - 1
Selected Setting:
Current Setting = 0.10 X In
Curve = Normal Inverse
TMS = 0.10
Feeder Capacity: 33400 kVA (Considering 10, 3.2, 3.5 MVA Transformers energised
of both the sections of the Switchboard energised from this Incomer
instanteneous Overcurrent element of 13.8 kV Bus Coupler is set at = 24900.0 Amps at 4.16 kV
Time interval for proper coordination with 13.8 kV Bus Coupler is proposed
to be adopted as follows:
Relay operating time of 13.8 kV Bus Coupler set at 24900 Amps at 4.16 kV
is = 1.02 sec
PP9 EXTENSION REINFORCEMENT
BNE-F00-BDO00-2040 51 OF 187
(BLOCK F)
REV A
PROTECTION STUDIES AND RELAY SETTING CALCULATIONS
Required TMS Setting for Normal Inverse type Overcurrent Protection to achieve desired operating
time of 1.40 sec at 24900 / 4976 i.e 5.00 times of Set
Current is calculated as follows:
0.14
1.40 = TMS X
(I/Ipickup)0.02 - 1
Selected Setting:
IDMT Overcurrent Setting = 0.60 X In
Curve = Normal Inverse
TMS = 0.30
instanteneous Overcurrent pickup is proposed to be set so that the relay does not operate under
Transformer Through Fault Current.
Selected Setting:
instanteneous Overcurrent Setting = 3.90 X In
Definite Time = 0.60 Sec
For proper protection corodination with outgoing feeder, operating time of relay is set at :
0.8 sec
0.80 sec (say) corresponding to a maximum earth fault current 1000
Required TMS Setting for Normal Inverse type Overcurrent Protection to achieve desired operating
time of 0.80 sec at 1000 / (2500 X 0.1) i.e 4.00 times of Set Current is
calculated as follows:
0.14
0.80 = TMS X
(I/Ipickup)0.02 - 1
PP9 EXTENSION REINFORCEMENT
BNE-F00-BDO00-2040 52 OF 187
(BLOCK F)
REV A
0.14
0.80 = TMS X PROTECTION STUDIES AND RELAY SETTING CALCULATIONS
(I/Ipickup)0.02 - 1
Selected Setting:
Current Setting = 0.10 X In
Curve = Normal Inverse
TMS = 0.15
6.9 8/10 MVA 13.8 / 4.16 kV Station Auxiliary Transformer (F-00BBA-10 & F-00BBA-11) Differential Protection
For differential protection of Unit Auxiliary transformer, GE Multilin relay DTP-B has been provided in
the 13.8kV switchgear incomer panel. The relay provides for multiple protection function of which only
the differential protection function is selected.
CT Parameters
HV Winding Side
CT ratio : 500 1 Amp 15 VA, 5P20
Rct : 6.00 Ohms (Estimated)
LV Winding Side
CT ratio : 1600 1 Amp 15 VA, 5P20
Rct : 6.00 Ohms (Estimated)
Differential protection is based on current comparison. The relay has the feature of phase shift
compensation and zero-sequence current elimination in the “INTERNAL COMPENSATION” mode. The
main purpose of the percent-slope characteristic of the differential.
PP9 EXTENSION REINFORCEMENT
BNE-F00-BDO00-2040 53 OF 187
(BLOCK F)
REV A
PROTECTION STUDIES AND RELAY SETTING CALCULATIONS
The initial differential PICKUP setting defines the minimum differential current required for operation.
The Initial setting is chosen based on the amount of differential current that might be seen under normal
operating load current conditions.
The SLOPE 1 setting defines the ratio of differential to restraint current above which the element will
operate. The slope is set to ensure sensitivity to internal faults at normal operating current levels. The
setting of this slope is determined by the sum of "
K1-K2 inflexion/ bias slope-1 limit is the limiting or end point of bias SLOPE 1(K1 percentage restraint).
It must be set to a current value (times the tap) higher than the forced cooling situation, and lower than
the admitted emergency overload level (momentary). In this case the Transformer is ONAN type and
there is no admitted emergency overload. Therefore we set the value just above full load condition.
The SLOPE 2/ K2 percentage restraint setting is implemented in DTP-B relay in order to deal with
unbalances caused by saturated CTs due to high currents borne during external faults.It can be set to the
same value as Slope-1 ( K1), or to a higher value, depending on the provisions of possible CT saturations.
The range of K2 is 15-100%.
This is the set point for high 3-phase differential fault current under an un-biased operation. This should
We assume a situation where an infinite bus is connected on the upstream the Station Transformer and
the transformer is evacuating power on the LV side.
Maximum Through Fault Current on 13.8kV side = (Transformer MVA/(% Impedance)) /(Sqrt(3) X13.8)
= 4650.00 Amps
Therefore, the magnetizing current is less than the maximum through fault current. Thus the high
current setting is selected from the larger of the two.
For differential protection of 13.8 kV Switchgear Busbar, ALSTOM relay MFAC34 has been provided in
the 13.8 kV Incomer Panels. Out of the two sections of the 13.8 kV Busbar, only one section is
considered for calculation purpose.
CT Parameters
Incomer & Outgoing Feeder Line Side:
CT ratio: 2500 1 Amp
Class: 5P20
Burden: 15.00 VA
Rct: 4.00 Ohms (Assumed)
System Parameters:
Voltage: 13.80 kV
Fault Level: 16.00 kA for 1 sec
MFAC34 is a voltage operated high impedance relay. When through fault current passes through the CT
where
Vs = Minimum Setting Voltage (Calculated),
If = Maxm. Value of Through Fault Current for which protection must remain stable
RCT = C.T Secondary Resistance
RL = Lead resistance between furthest C.T and relay connection point
N = Turns Ration of C.T
The Relay Plug Setting Voltage V R must be set to the nearest tap above V s.
Therefore, VR is selected to be = 50.00 Volts
IP = N (IR + nIE)
Full Load Current of the Section is assumed to be equal to 75% of the rated busbar current
= 1875 Amps
Since the sensitivity is sufficiently high, there is no requirement of providing additional Shunt Resistance
for inproving Relay Sensitivity
For check synchronism VA Tech make Argus 7 has been provided in the 13.8kV Buscoupler panel
PT details
Type: Argus 7
Selected Setting:
Dead Voltage - 14 V
(less than 20% of rated voltage 120/root 3)
Line Voltage - 55 V
(greater than 80% of rated voltage 120/root 3)
For neutral overvoltage protection VA Tech make Argus 8 has been provided for 13.8kV switchboard
Type: Argus 8
Selected Setting:
Vs setting - 7V
(10% of rated voltage 120/3)
For undervoltage protection GE Multilin make MIVII 1000 has been provided for 13.8kV switchboard
Relay Details:
Selected Setting:
Instanteneous Pickup:
Sensitive Ground Fault (51G): 0.005 to 0.12 Amp in steps of 0.001 Amp
Trfr.Impedance: 5%
Maximum Through Fault Current = Incomer Transformer kVA/ (sourceimp+Xfr.% Imp)/(sqrt(3) X 4.16)
considering source of 115 MVA = 2364.50 Amps at 4.16 kV
= 2370.00 Amps (Say) at 4.16 kV
Time interval for proper coordination with downstream 480 V Feeder is proposed to
be adopted as follows:
Relay operating time of downstream 480 V Crude Oil Heater Switchboard Incomer
is set at = 0.3 sec
For proper coordination with downstream incomer of 480 V Crude Oil Heater Switchboard, operating
time of 4.16 kV Outgoing Feeder to 1 MVA Transformer corresponding to the maximum through fault
current of 2370.00 Amps is required to be set at : 0.56 sec
= 0.60 sec Say
Required TMS Setting for Very Inverse type Overcurrent Protection to achieve desired operating
time of 0.60 sec at 2370 / (200 X 1.0) i.e 11.85
= 12.00 Say times of Set Current is
calculated as follows:
13.5
0.60 = TMS X
(I/Ipickup)1.0 - 1
Selected Setting:
IDMT Overcurrent Setting = 1.0 X In
Curve = Very Inverse
TMS = 0.60
Instanteneous Overcurrent pickup is proposed to be set so that the relay does not operate under
Transformer Through Fault Current.
Definite Time is proposed to be set at 100 msec corresponding to instanteneous set current.
Selected Setting:
Instanteneous Overcurrent Setting = 16.00 X In
Definite Time = 0.10 Sec
For transformer vector group of delta star connection, contribution for the ground fault on low voltage
side will not be transmitted to 4.16 kV side. Hence, the current pick up and TMS is proposed to set at
the minimum values.
Selected Setting:
Current Setting = 0.10 X In
Curve = Normal Inverse
TMS = 0.10
Selected Setting:
Current Setting = 0.12 Amp
Definite Time = 1.00 Sec
Relay Data
Rated full load current considering a p.f o 0.90 and efficiency 94.00 % is
Utilizing 369 standard overload curves, pick up threshold current I tap = 115% x Ir(sec) = 1.15 x [102 /
(150/1)] = 0.78
For a starting current : 5.5 times the motor rated full load current and starting time of
8.00 seconds, the Overcurrent relay shall not operate during starting time.
Thus, the relay is set ar 10.00 sec (> starting time at rated voltage) at
I = [(5.5 X 102)] / (150/ 3.74 Amps
Therefore, I/Itap = 4.78 = 5.00 Say and utilising Standard Overload Curves,
the equation becomes:
Time delay: 0.01 sec to avoid nuisance tripping due to momentary faults
Acceleration Trip
Selected setting is = 28.00 sec considering longest acceleration time under both starting and
overload condition
Relay Data
Type : MIF Digital Feeder Protection
Sensitive ground fault (51G) : 0.005 to 0.12 A
Definite time : 0.00 to 600.0 sec in steps of 0.01 s
Selected Setting
Current Setting : 0.12 Amp
Definite Time : 1.00 sec
Instanteneous Pickup:
Sensitive Ground Fault (51G): 0.005 to 0.12 Amp in steps of 0.001 Amp
Feeder Capacity: 10000 kVA (Considered the same as the Incomer Capacity)
Instantaneous Overcurrent element of 1000 kVA outgoing 4.16 kV Transformer feeder is set at
16 X In I.e 3200.00 Amps.
Time interval for proper coordination with downstream 4.16 kV Outgoing Transformer Feeder is
proposed to be adopted as follows:
Relay operating time of downstream 4.16 kV Outgoing Transformer Feeder set at 3200 Amps at
4.16 kV = 0.63 sec
For proper coordination with downstream 4.16 kV Outgoing Transformer Feeder, operating
time of 4.16 kV Bus Coupler corresponding to a high set current of 3200.00 is set at :
= 0.96 Sec
= 0.9 Sec Say
Required TMS Setting for Normal Inverse type Overcurrent Protection to achieve desired operating
time of 0.90 sec at 3200 / (1600 X 0.90) i.e 2.22 times of Set Current is
calculated as follows:
0.14
0.9 = TMS X
(I/Ipickup)0.02 - 1
Instanteneous Overcurrent pickup is proposed to be set so that the relay does not operate
during energisation of Aux. Transformers connected to the section during ABT.
Selected Setting:
instanteneous Overcurrent Setting = 6.80 X In
Definite Time = 0.30 Sec
For proper protection corodination with outgoing feeder, operating time of relay is set at :
0.44 sec
0.45 sec (say) corresponding to a maximum earth fault current of = 1000
Required TMS Setting for Normal Inverse type Overcurrent Protection to achieve desired operating
time of 0.45 sec at 1000 / (1600 X 0.1) i.e 6.25 times of Set Current is
calculated as follows:
0.14
0.45 = TMS X
(I/Ipickup) 0.02
-1
Selected Setting:
Current Setting = 0.10 X In
Curve = Normal Inverse
TMS = 0.10
Instanteneous Pickup:
Sensitive Ground Fault (51G): 0.005 to 0.12 Amp in steps of 0.001 Amp
Time interval for proper coordination with 4.16 kV Bus Coupler is proposed
to be adopted as follows:
Relay operating time of 4.16 kV Bus Coupler set at 10880 Amps at 4.16 kV
is = 0.34 sec
Required TMS Setting for Normal Inverse type Overcurrent Protection to achieve desired operating
time of 0.60 sec at10880 / (1600 X 0.90) i.e 7.56 times of Set Current is
calculated as follows:
0.14
0.6 = TMS X
(I/Ipickup)0.02 - 1
Selected Setting:
IDMT Overcurrent Setting = 0.90 X In
Instanteneous Overcurrent pickup is proposed to be set so that the relay does not operate
during energisation of Aux. Transformers connected to the section during ABT.
Selected Setting:
instanteneous Overcurrent Setting = 8.90 X In
Definite Time = 0.50 Sec
For proper protection corodination with 4.16 kV Bus Coupler, operating time of relay is set at :
0.74 sec
0.75 sec (say) corresponding to a maximum earth fault current of = 1000
Required TMS Setting for Normal Inverse type Overcurrent Protection to achieve desired operating
time of 0.75 sec at 1000 / (1600 X 0.1) i.e 6.25 times of Set Current is
calculated as follows:
0.14
0.75 = TMS X
(I/Ipickup)0.02 - 1
Selected Setting:
Current Setting = 0.15 X In
Curve = Normal Inverse
TMS = 0.20
For restricted earth fault protection of 8/10 MVA, 13.8/4.16 KV Station transformer,
ALSTOM relay MFAC14 has been provided in the 4.16 kV Incomer panels.
CT Parameters
Incoming Feeder Line Side:
CT ratio: 1600 1 Amp
Class: 5P20
Burden: 15.00 VA
RCT 10.00 Ohms (Assumed)
System Parameters:
Voltage: 4.16 kV
Through fault current of the transformer: 17135 A for 1 sec
MFAC14 is a voltage operated high impedance relay. When through fault current passes through the CT
certain additional voltage is developed in the CT secondary across the relay. To ensure stability as well
as to protect mal operation of the relay, the set
where
Vs = Minimum Setting Voltage (Calculated),
If = Maxm. Value of Through Fault Current for which protection must remain stable
RCT = C.T Secondary Resistance
RL = Lead resistance between furthest C.T and relay connection point
N = Turns Ration of C.T
The Relay Plug Setting Voltage V R must be set to the nearest tap above V s.
Therefore, VR is selected to be = 125.00 Volts
IP = N (IR + nIE)
Instanteneous Pickup:
Time interval for proper coordination with 4.16kV incomer is proposed to be adopted as follows:
t' = 0.2 + 0.2 X t where t = normal operating time of line side relay
For proper coordination between incoming side relay and transformer neutral side relay, operating
time is considered as 1.10 sec considering 0.75 sec relay operating time of line side
circuit breaker at 6.25 times relay set current.
Relay operating time of line side breaker at 6.25 times set current is 0.75 sec
Required TMS Setting for Normal Inverse type Earth fault Protection to achieve desired operating
time at 6.25 times relay set current is calculated as follows:
0 .14
1.10 = TMSX
(I/Ipickup).02 - 1
Selected Setting:
IDMT Overcurrent Setting = 0.10 X In
Curve = Normal Inverse
TMS = 0.20
For check synchronism VA Tech make Argus 7 has been provided in the 4.16kV Buscoupler panel
Setting shall be adopted same as 13.8kV Station switchgear mentioned under item 7.10
For neutral overvoltage protection VA Tech make Argus 8 has been provided for 4.16kV switchboard
Setting shall be adopted same as 13.8kV Station switchgear mentioned under item 7.11
For undervoltage protection GE Multilin make MIVII 1000 has been provided for 4.16kV switchboard
Setting shall be adopted same as 13.8kV Station switchgear mentioned under item 7.12
8.1 480 V Unit Crude Oil Heater Switchboard for GT (F-16BHB, F-15BHB, F-14BHB,
F-13BHB, F-12BHB, F-11BHB, F-21BHB, F-22BHB, F-23BHB & F-24BHB , F-25BHB & F-26BHB))
Type of Circuit Breaker: ABB MCCB TYPE- TMAX , T6L, FIXED VERSION, PR221 LS/I
MCCB Parameters:
Long Time Protection:
Pickup (I1) adjustable from 0.4 to 1.0 X In in steps of 0.04
Long Time Characteristic:t=k/I 2
At 6XI1, Trip time (t1) =3-12 sec
Instataneous Protection
Current Setting (I3) : 1 to 10 X In in steps of 0.5
Instanataneous Characteristic:t=k
Trip time < or = 0.04 sec
Selected Setting:
Long Time Protection = 1.00 X MCCB Trip Rating
= 1.00 X In
Therefore, Short Time Protection of MCCB (I 2) is set at 2.0 X In (Nearest Available setting)
Selected Setting:
Long Time Protection = 0.80 X ACB Trip Rating
I1 = 0.80 X In
Selected Setting:
Short Time Protection = 3.00 X In
Short Time Delay = 0.30 sec
Selected Setting:
Earth Fault Pickup = 0.40 X In
Time Delay = 0.20 sec
Trfr.Impedance: 5%
Time interval for proper coordination with 480V line side relay is proposed to be adopted as follows:
t' = 0.2 + 0.2 X t where t = normal operating time of line side relay
For proper coordination between 480V line side relay and transformer neutral side relay,operating time
is considered as 0.4 sec considering 0.2 sec relay operating time of line side circuit
breaker at 20 times relay set current.
Relay operating time of 480V line side breaker at 40% set current, i.e., 800A at 480V, is 0.2 sec
Required TMS Setting for Normal Inverse type Earth fault Protection to achieve desired operating
time at 800 / (1600 X 0.4) I.e., 1.25 times relay set current is calculated as follows:
0.14
0.24= TMS X
(I/Ipickup).02 - 1
Selected Setting:
PP9 EXTENSION REINFORCEMENT
BNE-F00-BDO00-2040 71 OF 187
(BLOCK F)
REV A
PROTECTION STUDIES AND RELAY SETTING CALCULATIONS
IDMT Overcurrent Setting = 0.20 X In
Curve = Normal Inverse
TMS = 0.05
For undervoltage protection ABB make REU 610 has been provided for 480V switchboard
Relay Details:
1 = curve C
Selected Setting:
8.2 480 V Unit Switchboard for GT (F-16BHA,F-15BHA, F-14BHA, F-13BHA, F-12BHA, F-11BHA,
F-21BHA, F-22BHA, F-23BHA, F-24BHA, F-25BHA & F-26BHA)
Type of Circuit Breaker: ABB MCCB TYPE T-MAX, T7L, FIXED VERSION, PR231 'LS/I'
MCCB Parameters:
Long Time Protection:
Pickup (I1) adjustable from 0.4 to 1.0 X In in steps of 0.04
Long Time Characteristic:t=k/I 2
At 6XI1, Trip time (t1) =3-12 sec
Selected Setting:
Long Time Protection = 0.80 X MCCB Trip Rating
Type of Circuit Breaker: ABB MCCB TYPE T-MAX, T7L, FIXED VERSION, PR231 'LS/I'
MCCB Parameters:
Long Time Protection:
Pickup (I1) adjustable from 0.4 to 1.0 X In in steps of 0.04
Long Time Characteristic:t=k/I 2
At 6XI1, Trip time (t1) =3-12 sec
Rated Current of Tie from Essential Switchboard is considered same as the 480 V Incomer to Unit
Switchboard = 1500 kVA/(sqrt(3)X0.48)
= 1804.22 Amps = 1804.00 Amps (Say) at 480 V
= 208.15 Amps = 208.00 Amps (Say) at 4.16 kV
In = 2000 A at 480V
= 230.77 A at 4.16kV
say 231 A at 4.16kV
Selected Setting:
Long Time Protection = 0.90 X ACB Trip Rating
I1 = 0.90 X In
Time interval for proper coordination with downstream 480 V Outgoing Feeder is proposed to
be adopted as follows:
I2 = 3 X In
= 6000 A @ 480V
Relay operating time of downstream 480 V Outgoing Feeder at 6000A is 0.28
Selected Setting:
Short Time Protection = 3.00 X In
Short Time Delay = 0.40 sec
Maximum Through Fault Current = Incomer Transformer kVA/ Xfr. % Imp/(sqrt(3) X 0.48)
= 30070.33 Amps at 480 V
= 3469.65 Amps at 4.16 kV
= 3500.00 Amps (Say) at 4.16 kV
Selected Setting:
Earth Fault Pickup = 0.4 X In
Time Delay = 0.2 sec
In = 2000 A at 480V
= 230.77 A at 4.16kV
say 231 A at 4.16kV
Selected Setting:
Long Time Protection = 0.90 X ACB Trip Rating
I1 = 0.90 X In
Time interval for proper coordination with downstream 480 V Outgoing Feeder is proposed to
be adopted as follows:
I2 = 3 X In
= 6000 A @ 480V
Relay operating time of downstream 480 V Outgoing Feeder at 6000A is 0.28
Selected Setting:
Short Time Protection = 3.00 X In
Short Time Delay = 0.40 sec
Maximum Through Fault Current = Incomer Transformer kVA/ Xfr. % Imp/(sqrt(3) X 0.48)
= 30070.33 Amps at 480 V
= 3469.65 Amps at 4.16 kV
= 3500.00 Amps (Say) at 4.16 kV
Selected Setting:
Earth Fault Pickup = 0.4 X In
Time Delay = 0.2 sec
Trfr.Impedance: 6%
Time interval for proper coordination with 480V line side relay is proposed to be adopted as follows:
t' = 0.2 + 0.2 X t where t = normal operating time of line side relay
For proper coordination between 480V line side relay and transformer neutral side relay,operating time
is considered as 0.4 sec considering 0.2 sec relay operating time of line side circuit
breaker at 20 times relay set current.
Relay operating time of 480V line side breaker at 40% set current, i.e., 800A at 480V, is 0.2 sec
Required TMS Setting for Normal Inverse type Earth fault Protection to achieve desired operating
time at 800 / (1000 X 0.4) I.e., 2.00 times relay set current is calculated as follows:
0.14
0.4= TMS X
(I/Ipickup).02 - 1
Selected Setting:
IDMT Overcurrent Setting = 0.20 X In
Curve = Normal Inverse
TMS = 0.05
For undervoltage protection ABB make REU 610 has been provided for 480V switchboard
Relay Details:
1 = curve C
Selected Setting:
8.3.1 480 V 50% Lighting and Receptacles and other stn auxiliaries (F-00BFB-05 & F-00BFB-18)
Type of Circuit Breaker: ABB MCCB TYPE- TMAX , T6L, FIXED VERSION, PR221 LS/I
MCCB Parameters:
Long Time Protection:
Pickup (I1) adjustable from 0.4 to 1.0 X In in steps of 0.04
Long Time Characteristic:t=k/I 2
At 6XI1, Trip time (t1) =3-12 sec
Selected Setting:
Long Time Protection = 1.00 X MCCB Trip Rating
= 1.00 X In
Therefore, Short Time Protection of MCCB (I 2) is set at 2.0 X In (Nearest Available setting)
MCCB Parameters:
Long Time Protection:
Pickup (I1) adjustable from 0.4 to 1.0 X In in steps of 0.04
Long Time Characteristic:t=k/I 2
At 6XI1, Trip time (t1) =3-12 sec
Selected Setting:
Long Time Protection = 1.00 X MCCB Trip Rating
= 1.00 X In
Selected Setting:
Short Time Protection = 2.00 X In
Maximum Through Fault Current = Incomer Transformer kVA/ Xfr. % Imp/(sqrt(3) X 0.48)
= 46776.06 Amps at 480 V
= 5397.24 Amps at 4.16 kV
PP9 EXTENSION REINFORCEMENT
BNE-F00-BDO00-2040 80 OF 187
(BLOCK F)
REV A
PROTECTION STUDIES AND RELAY SETTING CALCULATIONS
= 5400.00 Amps (Say) at 4.16 kV
Rated Current of Tie from Essential Switchboard is considered same as the 480 V Incomer to Unit
Switchboard = 1500 kVA/(sqrt(3)X0.48)
= 1804.22 Amps = 1804.00 Amps (Say) at 480 V
= 208.15 Amps = 208.00 Amps (Say) at 4.16 kV
In = 2000 A at 480V
= 230.77 A at 4.16kV
say 231 A at 4.16kV
Selected Setting:
Long Time Protection = 0.90 X ACB Trip Rating
I1 = 0.90 X In
Time interval for proper coordination with downstream 480 V Outgoing Feeder is proposed to
be adopted as follows:
I2 = 3 X In
= 6000 A @ 480V
Selected Setting:
Short Time Protection = 3.00 X In
Short Time Delay = 0.60 sec
Maximum Through Fault Current = Incomer Transformer kVA/ Xfr. % Imp/(sqrt(3) X 0.48)
= 30070.33 Amps at 480 V
= 3469.65 Amps at 4.16 kV
= 3500.00 Amps (Say) at 4.16 kV
In = 4000 A at 480V
= 461.54 A at 4.16kV
say 462 A at 4.16kV
Selected Setting:
Long Time Protection = 1.00 X ACB Trip Rating
I1 = 1.00 X In
Time interval for proper coordination with downstream 480 V Outgoing Feeder is proposed to
be adopted as follows:
Relay operating time of Unit Switchboard end breaker of the Tie Feeder
is set at = 0.6 sec
Selected Setting:
Short Time Protection = 2.00 X In
Short Time Delay = 0.90 sec
Maximum Through Fault Current = Incomer Transformer kVA/ Xfr. % Imp/(sqrt(3) X 0.48)
= 46776.06 Amps at 480 V
= 5397.24 Amps at 4.16 kV
= 5400.00 Amps (Say) at 4.16 kV
Selected Setting:
Earth Fault Pickup = 0.40 X In
Time Delay = 0.68 sec
= 0.80 sec (Say) for proper discrimination with
downstream 480 V Tie Feeder Earth
Fault Protection Delay Setting
In = 4000 A at 480V
= 461.54 A at 4.16kV
say 462 A at 4.16kV
Selected Setting:
Long Time Protection = 1.00 X ACB Trip Rating
I1 = 1.00 X In
Time interval for proper coordination with downstream 480 V Outgoing Feeder is proposed to
be adopted as follows:
Relay operating time of Unit Switchboard end breaker of the Tie Feeder
is set at = 0.6 sec
Selected Setting:
Short Time Protection = 2.00 X In
Short Time Delay = 0.90 sec
Maximum Through Fault Current = Incomer Transformer kVA/ Xfr. % Imp/(sqrt(3) X 0.48)
= 46776.06 Amps at 480 V
= 5397.24 Amps at 4.16 kV
= 5400.00 Amps (Say) at 4.16 kV
Selected Setting:
Earth Fault Pickup = 0.40 X In
Time Delay = 0.68 sec
= 0.80 sec (Say) for proper discrimination with
downstream 480 V Tie Feeder Earth
Fault Protection Delay Setting
Trfr.Impedance: 9%
Time interval for proper coordination with 480V line side relay is proposed to be adopted as follows:
t' = 0.2 + 0.2 X t where t = normal operating time of line side relay
For proper coordination between 480V line side relay and transformer neutral side relay,operating time
is considered as 1.04 sec considering 0.7 sec relay operating time of line side circuit
breaker at 20 times relay set current.
Relay operating time of 480V line side breaker at 40% set current, i.e., 1600A at 480V, is 0.45 sec
Required TMS Setting for Normal Inverse type Earth fault Protection to achieve desired operating
time at 1600 / (2000 X 0.4) I.e., 2.00 times relay set current is calculated as follows:
0.14
1.28= TMS X
(I/Ipickup).02 - 1
Selected Setting:
IDMT Overcurrent Setting = 0.20 X In
Curve = Normal Inverse
TMS = 0.10
8.3.7 For undervoltage protection ABB make SPAU130C has been provided for 480V switchboard
Relay Details:
Selected Setting:
8.4.1 480 V Outgoing feeder to Local Electrical & Control Room Loads- GT 45/46,47,48,49,50,53/54
& 55/56 and Stn. Area DB, Local Electrical and Control room Loads- GT 51/52
Type of Circuit Breaker: ABB MCCB TYPE- TMAX , T6L, FIXED VERSION, PR221 LS/I
MCCB Parameters:
Long Time Protection:
Pickup (I1) adjustable from 0.4 to 1.0 X In in steps of 0.04
Long Time Characteristic:t=k/I 2
At 6XI1, Trip time (t1) =3-12 sec
Selected Setting:
Long Time Protection = 1.00 X MCCB Trip Rating
= 1.00 X In
Therefore, Short Time Protection of MCCB (I 2) is set at 2.0 X In (Nearest Available setting)
Rated Current of Bus Coupler is considered same as the 480 V Incomer to Non Essential
Switchboard = 3200 kVA/(sqrt(3)X0.48) = 3850.00 Amps (Say) at 480 V
= 3849.00 Amps = 445.00 Amps (Say) at 4.16 kV
= 444.23 Amps
Selected Setting:
Long Time Protection = 1.00 X ACB Trip Rating
I1 = 1.00 X In
Time interval for proper coordination with downstream 480 V Outgoing Feeder is proposed to
be adopted as follows:
Selected Setting:
Short Time Protection = X In
Short Time Delay = 0.30 sec
Selected Setting:
Earth Fault Pickup = 0.40 X In
Time Delay = 0.20 sec
Selected Setting:
I1 = 1.00 X In
Therefore, Short Time Protection of ACB is set at 2.0 X I n ( Nearest available setting)
Time interval for proper coordination with downstream 480 V Outgoing Feeder is proposed to
be adopted as follows:
Selected Setting:
Short Time Protection = 2.00 X In
Short Time Delay = 0.60 sec
Selected Setting:
Earth Fault Pickup = 0.40 X In
Time Delay = 0.20 sec
Trfr.Impedance: 9%
Time interval for proper coordination with 480V line side relay is proposed to be adopted as follows:
t' = 0.2 + 0.2 X t where t = normal operating time of line side relay
For proper coordination between 480V line side relay and transformer neutral side relay,operating time
is considered as 0.4 sec considering 0.2 sec relay operating time of line side circuit
breaker at 20 times relay set current.
Relay operating time of 480V line side breaker at 40% set current, i.e., 1600A at 480V, is 0.2 sec
Required TMS Setting for Normal Inverse type Earth fault Protection to achieve desired operating
time at 1600 / (2000 X 0.4) I.e., 2.00 times relay set current is calculated as follows:
0.14
0.68 = TMS X
(I/Ipickup).02 - 1
PP9 EXTENSION REINFORCEMENT
BNE-F00-BDO00-2040 91 OF 187
(BLOCK F)
REV A
0.14
0.68 = TMS X
PROTECTION STUDIES AND RELAY SETTING CALCULATIONS
(I/Ipickup).02 - 1
Selected Setting:
IDMT Overcurrent Setting = 0.20 X In
Curve = Normal Inverse
TMS = 0.05
For undervoltage protection ABB make REU 610 has been provided for 480V switchboard
Relay Details:
1 = curve C
Selected Setting:
Station
0kV GSU
comproses twelve 12
ated power to 380 kV
53 that is located at
supplying station
'D' for emregency
e station switchgear.
wer requirement for
xiliary transformers.
, is considered for
Generator
metering
on Switchgear
on Switchgear
n Service Switchgear -
& metering.
n Service Switchgear -
etering.
witchgear -For GT
witchgear-For GT
g feeders are
or the auxiliary
) at 4.16 kV
erating
set current Ir
set current Ir (Say)
as follows:
deg.
deg
380.6648
Z H-X1 (Pri)
)
) tan (j -(a/2))
deg.
tan (j -(a/2))
+ 0.289)(tan (90-60))
s 5 cycles.
rent/CT ratio
out of the
MVA
)
MVA
is Greater)
) at 13.8 kV
) at 4.16 kV
set current Ir
set current Ir (Say)
Greater)
through the
emain stable
emain stable
ondary value)
) at 4.16 kV
set current Ir
set current Ir
ow voltage
d to set at the
) at 4.16 kV
of Set Current is
ow voltage
d to set at the
) at 13.8 kV
) at 4.16 kV
set current Ir
set current Ir (Say)
us-section)
) at 13.8 kV
) at 4.16 kV
mer feeder is
Amps at
s set at :
) at 4.16 kV
set current Ir at 4.16 KV
set current Ir
.16 kV
at 13.8 kV
Amps
erating
et Current is
) at 13.8 V
) at 4.16 V
mer feeder is
mps at 4.16 kV
s set at :
erating
et Current is
at 13.8 kV
Amps
erating
et Current is
erating
et Current is
energised in section)
) at 13.8 V
) at 4.16 V
mps at 4.16 kV
s set at :
erating
et Current is
) at 4.16 kV
set current Ir at 4.16 kV
at 13.8 kV
set current Ir at 4.16 kV
set current Ir at 4.16 kV
erating
et Current is
energised
d from this Incomer
) at 13.8 kV
) at 4.16 kV
) at 4.16 kV
Amps at 4.16 kV
erating
times of Set
set current Ir
Amps
erating
et Current is
ovided in
which only
at 10 MVA
A, 5P20
A, 5P20
mode. The
ement will
levels. The
e restraint).
nd lower than
N type and
ondition.
n be set to the
CT saturations.
. This should
nsformer and
t(3) X13.8)
Amps (Say)
he high
rovided in
l steps)
rough the CT
nt Resistance
root 3 / 120V/3
chboard
(3) X 4.16)
of Set Current is
set current Ir
set current Ir (Say)
ow voltage
d to set at
ng time of
1.60
T secondary current
momentary faults
s set at :
erating
et Current is
set current Ir
set current Ir (Say)
erating
Amp.
s set at :
erating
et Current is
Amps
erating
et Current is
rough the CT
bility as well
tchboard
& F-26BHB))
) at 480 V
) at 4.16 kV
) at 4.16 kV
PP9 EXTENSION REINFORCEMENT
BNE-F00-BDO00-2040 149 OF 187
(BLOCK F)
REV A
X In (Say)
) at 480 V
) at 4.16 kV
X In (Say)
s follows:
erating time
ne side circuit
as follows:
) at 480 V
) at 4.16 kV
) at 480 V
) at 4.16 kV
o Unit
) at 480 V
) at 4.16 kV
sec.
co-ordination
) at 480 V
) at 4.16 kV
) at 4.16 kV
X In (Say)
sec.
co-ordination
erating time
ne side circuit
as follows:
) at 480 V
) at 4.16 kV
) at 4.16 kV
) at 480 V
) at 4.16 kV
) at 4.16 kV
) at 4.16 kV
X In (Say)
) at 480 V
) at 4.16 kV
) at 4.16 kV
X In (Say)
) at 480 V
) at 4.16 kV
) at 4.16 kV
X In (Say)
erating time
ne side circuit
.45 sec
as follows:
) at 480 V
) at 4.16 kV
) at 480 V
) at 4.16 kV
X In (Say)
) at 4.16 kV
s follows:
erating time
ne side circuit
as follows:
1 73 432
2 146 108
6 12
2 146 108
2 146 1.6
8 584 0.1
10 730 0.06
2776 0.06
2.4 72
3 435 46
3 435 0.30
2776 0.30
SEL-551 Protection for 4.16 kV Outgoing Transformer Feeder
P = 1 K = 0
1.2 240 13.5 1 0.6 40.50 Points removed from Corodination Curve for
1.3 260 13.5 1 0.6 27.00 proper fitment to the right of the downstream
1.4 280 13.5 1 0.6 20.25 ACB characteristic
1.5 300 13.5 1 0.6 16.20
1.6 320 13.5 1 0.6 13.50
1.7 340 13.5 1 0.6 11.57
1.8 360 13.5 1 0.6 10.13
1.9 380 13.5 1 0.6 9.00
2 400 13.5 1 0.6 8.10
2.5 500 13.5 1 0.6 5.40
3 600 13.5 1 0.6 4.05
3.5 700 13.5 1 0.6 3.24
4 800 13.5 1 0.6 2.70
4.5 900 13.5 1 0.6 2.31
5 1000 13.5 1 0.6 2.03
5.5 1100 13.5 1 0.6 1.80
6 1200 13.5 1 0.6 1.62
6.5 1300 13.5 1 0.6 1.47
7 1400 13.5 1 0.6 1.35
7.5 1500 13.5 1 0.6 1.25
8 1600 13.5 1 0.6 1.16
8.5 1700 13.5 1 0.6 1.08
9 1800 13.5 1 0.6 1.01
9.5 1900 13.5 1 0.6 0.95
10 2000 13.5 1 0.6 0.90
12 2400 13.5 1 0.6 0.74
14 2800 13.5 1 0.6 0.62
15 3000 13.5 1 0.6 0.58
16 3200 13.5 1 0.6 0.54
3200 0.10
15422 0.10
369 Standard Overload Curves Starting vs. time Running curve
1.01 103.0 2.75 11972.44 100 102.0 8.5 25 200 204.0 1000
1.05 107.1 2.75 2347.71 150 153.0 8.5 25 225 229.5 700
1.1 112.2 2.75 1145.88 200 204.0 8.5 25 250 255.0 550
1.2 122.4 2.75 546.87 250 255.0 8.5 25 320 326.4 280
1.3 132.6 2.75 348.71 300 306.0 8.5 25
P = 0.02 K = 0
P = 0.02 K = 0
P = 0.02 K = 0
P = 0.02 K = 0
P = 1 K = 0
a = 0.02
NORMAL INVERSE
Outgoing to FH Panel -
Long Time Time
GSU Transformer
1 INCOMER TO FUEL
OIL SWBD Damage Curve GSU
Transformer
100
Time (Sec)
13.8 kV OUTGOING
STALLED 10MVA TRANSF
CONDITION
STARTING
CURVE (80%)
10
STARTING CURVE
(100%) 380KV GSU TRANSF
4.16 KV INCOMER
4.16KV BUSCOUPLER
13.8 kV BUSCOUPLER
13.8KV INCOMER
GSU Tr.
4.16 kV Incomer
4.16 kV Buscoupler
13.8KV Buscoupler
13.8KV INCOMER
Outgoing to FH Panel -
Short Time
100000 1000000