Annexure-I

Sl. Package Package Description Execution Agency Discipline Area Date of submission to BSP Work
No. No. Mode awarded on
TS TAR
1. 077-02 (Balance Works of External Water System for Mills & Fire Water Pumphouses

i. 077-02B-1 Balance civil works for NTK M/s Civil BRM 06.06.16 16.06.16 24.06.16
completion of WTP-5 at BRM Sudhansu
under External water system Brothers
for Mills & Fire water
pumphouses

ii. 077-02B-2 Erection, testing & NTK M/s Gimex Mechanical URM & 25.06.2016 27.08.16 08.09.16
commissioning of balance India Project BRM
Mechanical plant & & Engg Pvt.
equipment and piping works Ltd
under External water system
for Mills & Fire water
pumphouses

iii. 077-02B-3 Balance civil & structural NTK M/s HSCL Civil & URM & 10.06.2016 29.06.16 12.08.16
works for completion of all Structural BRM
WTPs in URM & BRM
(except WTP-5 for BRM) and
cable tunnel & pipe cum
cable gallery at BRM under
External water system for
Mills & Fire water
pumphouses

iv. 077-02B-4 Erection, testing and NTK M/s Electrical URM & 15.06.16 07.07.16 20.07.16
commissioning of electrical Shambhu BRM
equipments in BRM & URM singh
under External water system
for Mills & Fire water
pumphouses

v. 077-02C-1 Civil works for completion of NTK Civil URM & 27.07.2016 24.09.16 03.11.16

Page 1 of 3
Sl. Package Package Description Execution Agency Discipline Area Date of submission to BSP Work
No. No. Mode awarded on
overhead tanks of URM & BRM
BRM under External water
system for Mills & Fire water
pumphouses

Annexure-II

Sl. Package Package Description Execution Agency Discipline Area Date of submission to BSP Work
No. No. Mode Awarded on
TS TAR
2. 077-01 (Balance works of External Water System for SMS-III)

i. 077-01A1 TS for Balance Civil NTK M/s A Civil WTP-1, 23.03.16 19.04.16 25.04.2016
works of Essential Mohan Common
facilities under External pump
Water System for SMS-III house,
ECR for
SST PH
ii. 077-01A2 TS for Civil work for NTK M/s HSCL Civil WTP-2 13.04.16 31.05.16 24.06.2016
WTP-2
iii. 077-01D TS for EOHT (Structural) NTK M/s Structural WTP-3,4 02.05.2016 25.05.16 02.06.2016
Sanmathi &5
-

Page 2 of 3
Annexure-III

Sl. Package Package Description Execution Agency Discipline Area Date of submission to Work
No. No. Mode BSP Awarded on
TS TAR
3. 078 (Balance works of Augmentation of Make-Up and Drinking Water System)

i. 078B1 TS for Balance out door NTK M/s I A Das Mechanical Trunk 18.05.16 10.06.16 24.06.16
piping work main
pipes
ii. 078B2 TS for Civil work for NTK M/s I A Das Civil Trunk main 04.06.16 11.06.16 25.06.16
Balance outdoor Piping pipes
and cable gallery
iii. 078B3 TS for Structural work for NTK M/s BCCI Structural Trunk main 18.05.16 10.06.16 25.06.16
Balance outdoor Piping pipes
and cable gallery
iv. 078C Civil work for NTK M/s Five Civil MARAODA 25.06.16 02.07.16 03.08.16
IWPH,DWPH,MWPH & Star, Bhilai -I &
ECRs MARODA-II
v. 078D Erection for Balance NTK M.K.ANSARI Mechanical MARAODA 16.07.16 06.09.16 20.01.17
Mechanical Equipment , BHILAI -I &
MARODA-II
vi. 078E Erection for Balance NTK RN Electrical MARAODA 07.07.16 09.09.16 16.09.16
Electrical Equipment Electricals -I &
MARODA-II

Page 3 of 3