EMAILED FROM THE VENDOR TO APPLUS+ BEFORE YOU DEPART FOR THE DAY.
Client: M/S Hyundai E&C ·
Vendor: M/S Towell Engineering Group
Project Sub-Vendor: -
PO No.: - Location:
02 Test Air blowing and walk down done in line for hydro package
pack for following test pack in area 93 Offshore
Test pack no: TP-93-11-U121-105-WF-011 Hydro package
Test pack no: TP-93-11-U121-105-WF-010 Hydro package
Status: Done
02 Test Bolt torqueing done for following test pack prior to Hydro
pack test inspection in area -93 Offshore
Test pack no: TP-93-11-U121-105-WF-011 Hydro package
Test pack no: TP-93-11-U121-105-WF-010 Hydro package
Status: Done
02 Test Hydro test- leak tight test and strength test for following
Pack test pack ongoing in area -98
Test pack no: TP-90-98-01-U122-105-15 Hydro package
Test pack no: TP-90-98-01-U122-105-17 Hydro package
Status: Ongoing
L5-FMT-060 Rev. 03
RESULTS OF Accepted Not Compliant ORDER STATUS: Complete Incomplete
INSPECTION:
AREAS OF CONCERN
-In area 85 Supports are not seated properly on pipe rack/ structure due to clamp support located too near to the
joint. Line no- OP and TP line.
TYPE OF VISIT:
Pre-Inspection Meeting Witness Mechanical Tests Witness Pressure Tests
Review all Certificates Dimension & Workmanship
Intermediate Inspection Witness NDT Coating & Painting
Review Radiographs Packing & Marking
Final Inspection Witness Performance Tests Loading
Inspector: Signed:
Page 2 of 2