Sunteți pe pagina 1din 7

Feature Report

Engineering Practice

Piping for Process Plants Part 6:


Testing & Verification
Proper documentation, determination of the fluid service category
and operating conditions are among the factors necessary
to perform the correct leak test on a piping system

W. M. Huitt Documentation 18. Signatures and dates


W. M. Huitt Co. In documenting the leak testing activ- Also make certain that
ity there are certain forms that will be the testing contractor has

T
his sixth and final part of a series needed. They consist of the following: current calibration logs of
of articles [1–5] on piping for pro- 1. A dedicated set of piping and in- his or her test instruments,
cess plants discusses practical is- strumentation diagrams (P&IDs) to such as pressure gages.
sues of leak testing and verifica- identify the limits and number the
tion of piping systems. test circuits Primary leak tests
2. A form to record components that ASME B31.3 defines five pri-
Leak testing were either installed or removed mary leak tests as follows:
Leak testing and pressure testing are prior to testing Initial service leak test. This applies
often used synonymously. However, 3. A checklist form for field supervi- only to those fluid services meeting the
pressure testing is a misnomer when sion to ensure that each step of the criteria as defined under ASME B31.3
referring to leak testing of piping sys- test process is accomplished Category D fluid service. This includes
tems. By definition, a pressure test is 4. Leak-test data forms fluids in which the following apply:
the procedure performed on a relief The two sets of documents, from • The fluid handled is nonflamma-
valve to test its set-point pressure. those listed above, that need to be ble, nontoxic, and not damaging to
The intent, when pressure testing a retained are the P&ID’s and the leak- human tissue
relief valve, is not to check for leaks, test data forms. The other two sets of • The design gage pressure does not
but to test the pressure set point of the forms are procedural checklists. exceed 1,035 kPa (150 psi)
valve by gradually adding pressure to The leak-test data forms should con- • The design temperature is from
the relief valve until it lifts the valve tain key data such as the following: –29°C (–20°F) through 186°C (366°F)
off of the seat. 1. Test circuit number The initial service leak test is a pro-
A leak test, on the other hand, is 2. P&ID number(s) cess by which the test fluid is the fluid
performed to check the sealing integ- 3. Date of test that is to be used in the intended pip-
rity of a piping system by applying 4. Project name or number, or both ing system at operating pressure and
internal pressure to a pre-determined 5. Location within facility temperature. It is accomplished by
limit, based on design conditions, then 6. Line number(s) connecting to the fluid source with a
checking joints and component seals 7. Design pressure valved connection and then gradually
for leaks. It is not intended that the 8. Test pressure opening the source valve and filling
MAWP (maximum allowable working 9. Test fluid the system. In liquid systems, air is
pressure) of a piping system be veri- 10. Test fluid temperature purged during the fill cycle through
fied or validated. 11. Time (military) recorded test begins high point vents. A rolling examination
Before discussing the various types 12. Pressure at start of test of all joints is continually performed
of leak tests and leak-test procedures 13. Time (military) recorded test ends during the fill cycle and for a period
I would like to briefly talk about con- 14. Pressure at end of test of time after the system is completely
trolling and tracking this activity. 15. Total elapsed time of test filled and is under line pressure.
Testing, like many aspects of a project, 16. Total pressure differential (plus or In a situation in which the pipeline
should be a controlled process. There minus) from the beginning to the that is being tested has distribution
should be a formal method of docu- end of test period on multiple floors of a facility, there
menting and tracking this activity as 17. Comment section (indicate if leaks will be pressure differentials between
the contractor proceeds through the were found and system was repaired the floors due to static head differ-
leak testing process. and retested or if system passed) ences. This will occur in operation
48 Chemical Engineering www.che.com June 2008
a discussion of the design pressure).
PT = 1.5 ⋅ P While design pressure is held, all
 (2)
joints are examined for leaks. It is not
Unlike initial service test- required that the examination take
ing, pressure variations due to place while holding test pressure.
static head differences in eleva- There is more to the entire proce-
tion have to be accommodated in dure that is not included here. Please
hydrostatic testing. That means refer to B31.3 or B31.1 for full details
the calculated test pressure is on pneumatic leak testing.
the minimum pressure required Sensitive leak test. This leak test
for the system. When hydrostati- is performed when there is a higher-
cally testing a multi-floor system, than-normal potential for fluid leak-
the minimum calculated test age, such as for hydrogen. I also recom-
pressure shall be realized at the mend its use when a fluid is classified
highest point. This is not stated, as a Category M fluid service. B31.1
but is inferred in B31.3. refers to this test as Mass-Spectrom-
Pneumatic leak test. This test eter and Halide Testing.
is performed using air or a pre- In B31.3, the process for sensitive
ferred inert gas. This is a rela- leak testing is as follows:
tively easy test to perform simply The test shall be in accordance with
from a preparation and cleanup the gas and bubble test method speci-
standpoint. However, this test has fied in the BPV Code, Section V, Article
a hazardous potential because of 10, or by another method demonstrated
the stored energy in the pressur- to have equal sensitivity. Sensitivity of
ized gas. And for that reason alone the test shall be not less than 10–3 atm.
and is acceptable under initial ser- it should be used very selectively. mL/s under test conditions.
vice test conditions. When pneumatic testing is per- a. The test pressure shall be at least the
The test pressure achieved for ini- formed, it must be done under a lesser of 105 kPa (15 psi) gage, or 25%
tial service testing is what it will be strictly controlled procedure with on- [of] the design pressure.
in operation. The only difference is site supervision in addition to coordi- b. The pressure shall be gradually in-
that the flowing fluid during opera- nation with all other crafts and per- creased until a gage pressure the lesser
tion will incur an amount of pressure sonnel in the test area. of one-half the test pressure or 170 kPa
drop that will not be present during The test pressure for pneumatic (25 psi) gage is attained, at which time
the static test. leak testing under B31.3 is calculated a preliminary check shall be made.
Hydrostatic leak test. This is the using Equation (3), for B31.9 it is cal- Then the pressure shall be gradually
most commonly used leak test and is culated using Equation (4), and for increased in steps until the test pres-
performed by using a liquid, normally B31.1 it is calculated using Equation sure is reached, the pressure being
water, and in some cases with addi- (5). held long enough at each step to equal-
tives to prevent freezing, under a pres- ize piping strains.
PT = 1.1 ⋅ P
sure calculated by Equation (1):  (3) In testing fluid services that are
extremely difficult to seal against, or
1.5 ⋅ P ⋅ ST PT = 1.4 ⋅ P
PT = (1)  (4) fluid services classified as a Category
S M fluid service, I would suggest the
PT = 1.2 ⋅ P to 1.5 ⋅ P
where  (5) following in preparation for the pro-
PT = Test pressure, psi One misconception with pneumatic cess described under B31.3:
P = Internal design gage pressure, leak testing is in its procedure, as de- • Prior to performing the sensitive
psig scribed in B31.3. There is a misconcep- leak test, perform a low-pressure
ST = Stress value at test temperature, tion that the test pressure should be test (15 psig) with air or an inert gas
psi (see ASME B31.3, Table A-1) maintained while the joints are ex- using the bubble test method. Check
S = Stress value at design tempera- amined. This is not correct. As B31.3 every mechanical joint for leakage
ture, psi (see B31.1, Table A-1) explains, pressure is increased gradu- • After completing the preliminary
However, as long as the metal tem- ally until the test pressure is reached. low-pressure pneumatic test, purge
perature of ST remains below the At that point, the test pressure is held all of the gas from the system using
temperature at which the allowable until piping strains equalize through- helium. Once the system is thor-
stress value for ST begins to dimin- out the system. oughly purged, and contains no less
ish and the allowable stress value of After a sufficient amount of time is than 98% He, continue using He to
S and ST are equal, then ST and S allowed for piping strains to equalize, perform the sensitive leak test with
cancel each other leaving the simpler the pressure is then reduced to the a mass spectrometer tuned to He.
Equation (2): design pressure (see Reference [3] for Helium is the trace gas used in this
Chemical Engineering www.che.com June 2008 49
Engineering Practice

process and has a size that is close to L = Developed length of piping be- general procedures for cleaning and
that of the hydrogen molecule; this tween anchors, in. (or mm) testing are presented below.
makes it nearly as difficult to seal U = Anchor distance, straight line As in all other project functions,
against as H2 without the volatility. between anchors, ft (or m) control and documentation is a key
Test each mechanical joint using the K1 = 208,000 SA/Ea, (mm/m)2 element in the cleaning and testing
mass spectrometer to determine leak = 30 SA/Ea, (in./ft)2 of piping systems. It does, however,
rate, if any. SA = Allowable displacement stress need to be handled in a manner that
Alternative leak test. In lieu of per- range per Equation (1a) of is dictated by the type of project.
forming an actual leak test, in which ASME B31.3, ksi (MPa) That means you don’t want to bury
internal pressure is used, the alterna- Ea = Reference modulus of elasticity yourself in unwarranted paperwork
tive leak test takes the examination at 70°F (21°C), ksi (MPa) and place an unnecessary burden on
and flexibility analysis approach. One example in which an alternative the contractor.
This test is conducted only when it leak test might be used is in making Building a commercial or institu-
is determined that either hydrostatic a branch tie-in to an existing, in-ser- tional type facility will not require
or pneumatic testing would be det- vice line using a saddle with an o-let the same level of documentation and
rimental to the piping system or the branch fitting with a weld-neck flange stringent controls that an industrial
fluid intended for the piping system, welded to that, and a valve mounted type facility would require. But even
an inherent risk to personnel, or im- to the flange. Within temperature within the industrial sector there are
practical to achieve. limitations, the fillet weld used to varying degrees of required testing
As an alternative to testing with weld the saddle to the existing pipe and documentation.
internal pressure, it is acceptable to can be examined using the dye pen- To begin with, documentation re-
qualify a system through examination etrant or magnetic particle method. quirements in industry standards are
and flexibility analysis. The process The circumferential butt or groove simplistic and somewhat generalized,
calls for the examination of all groove weld used in welding the weld neck as is apparent in ASME B31.3, which
welds, and includes longitudinal welds and the o-let fitting together should states in Para. 345.2.7:
used in the manufacture of pipe and be radiographically or ultrasonically Records shall be made of each piping
fittings that have not been previously examined. And the flange joint con- system during the testing, including:
tested hydrostatically or pneumati- necting the valve should have the (a) Date of test
cally. It requires a 100% radiograph or torque of each bolt checked after visu- (b) Identification of piping system
ultrasonic examination of those welds. ally ensuring correct type and place- tested
Where applicable, the sensitive leak ment of the gasket. (c) Test fluid
test shall be used on any untested me- There are circumstances, regarding (d) Test pressure
chanical joints. This alternative leak the tie-in scenario we just discussed (e) Certification of results by examiner
test also requires a flexibility analysis for alternative leak testing, in which These records need not be retained after
as applicable. a hydrostatic or pneumatic test can completion of the test if a certification
Very briefly, a flexibility analysis be used. It depends on what the fluid by the inspector that the piping has
verifies, on a theoretical basis, that an service is in the existing pipeline. If satisfactorily passed pressure testing
installed piping system is within the it is a fluid service that can be con- as required by this Code is retained.
allowable stress range of the material sidered a Category D, then it is quite ASME B31.3 goes on to state, in
and components under design con- possible that a hydrostatic or pneu- Para. 346.3:
ditions if a system: (a) duplicates or matic leak test can be performed on Unless otherwise specified by the
replaces without significant change, the described tie-in. engineering design, the following re-
a system operating with a successful By capping the valve with a blind cords shall be retained for at least 5
service record; (b) can be judged ad- flange modified to include a test rig of years after the record is generated for
equate by comparison with previously valves, nipples and hose connectors, the project:
analyzed systems; and (c) is of uni- you can perform a leak test rather (a) Examination procedures; and
form size, has no more than two points than an alternative leak test. As men- (b) Examination personnel qualifica-
of fixation, no intermediate restraints, tioned, this does depend on the exist- tions
and falls within the limitations of em- ing service fluid. If the existing fluid Standards that cover such a broad
pirical Equation (6). service is steam or a cryogenic fluid, array of industrial manufacturing, do
then you might want to consider the not, as a rule, attempt to get too spe-
D⋅ y alternative leak test. cific in some of their requirements. Be-
≤ K1
(
 L −U 2
) (6)
More on documentation
yond the essential requirements, such
as those indicated above, the owner,
where As seen in Equations (1–5), the leak engineer or contractor has to assume
D = Outer dia. of pipe, in. (or mm) test pressure, except for initial service responsibility and know-how for pro-
y = Resultant of total displacement testing, is based on design pressure viding more specific and proprietary
strains to be absorbed by piping and design temperature, both of which requirements for a particular project
system, in. (or mm) are described in Reference [3]. A few specific to the particular needs of the
50 Chemical Engineering www.che.com June 2008
Table 1. Areas under Consideration for Category D
Group Description Yes No
1 Personnel occupied space √
2 Corridor frequented by personnel √
owner. The following will help, to some 3 Sensitive equipment (MCC, control room, and so on) √
extent, fill that gap. 4 Corridor infrequently used by personnel √
5 Maintenance & operations personnel only access √
Which fluid service category?
While Category-D fluid services third degree burns. An approximate a significant impact to operations and
qualify for initial service leak testing, half-minute exposure to 130°F water production. This could translate into
there are caveats that should be con- will result in third degree burns. And lost production and could be consid-
sidered. This is a situation in which an approximate ten minute exposure ered a high degree of importance.
ASME provides some flexibility in to 120°F water can result in third- You could also extend this logic a bit
testing by lowering the bar on require- degree burns. further by assigning normal fluid-ser-
ments where there is reduced risk in With the maximum temperature vice status to the primary headers of
failure, provided that if failure should limit of 366°F (185.5°C) for Category- a chilled water system and assigning
occur, the results would not cause D fluid services, what the owner Category D status to the secondary
catastrophic damage to property or ir- needs to consider are three factors: (1) distribution branches, then leak test
reparable harm to personnel. within that range of 140°F (60°C), the accordingly. You need to be cautious in
The owner’s responsibility for any temperature at which discomfort be- considering this. By applying different
fluid service selected for initial ser- gins to set in, to 366°F (185.5°C), the category significance to the same pip-
vice leak testing lies in determining upper limit of Category-D fluids, what ing system it could cause more confu-
what fluid services to place into each do we consider hazardous; (2) what is sion than it is worth. In other words
of the fluid service categories: Nor- the level of opportunity for risk to per- it may be more value added to simply
mal, Category D, Category M, and sonnel; and (3) what is the level of as- default to the more conservative cat-
High Pressure. sured integrity of the installation egory of normal.
Acids, caustics, volatile chemicals Assured integrity means that, if Once it has been established that
and petroleum products are usually there are procedures and protocols in there is a high assured integrity value
easy to identify as those not quali- place that require, validate and docu- for these piping systems, there are two
fying as a Category-D fluid service. ment third-party inspection of all pipe remaining factors to be considered.
Cooling tower water, chilled water, air fabrication, installation and testing, First, within the temperature range
and nitrogen are all easy to identify then there is a high degree of assured indicated above, at what temperature
as qualifyiers for Category-D fluid integrity in the system. If some or all should a fluid be considered hazard-
services. The fluid services that fall of these requirements are not in place ous? Second, how probable is it that
within the acceptable Category D then there is no assured integrity. personnel could be in the vicinity of a
guidelines, but still have the poten- All three of these factors — tem- leak, should one occur?
tial for being hazardous to personnel perature, risk of contact and assured For this discussion, let us deter-
are not so straight forward. integrity — have to be considered to- mine that any fluid at 160°F (71°C)
Consider water as an example. At gether to arrive at a reasonable deter- and above is hazardous upon contact
ambient conditions, water will sim- mination for borderline Category-D with human skin. If the fluid you are
ply make you wet if you get dripped fluid services. If, for instance, a fluid considering is within this tempera-
or sprayed on. By OSHA standards, service is hot enough to be considered ture range, then it has the potential
once the temperature of water exceeds hazardous, but is in an area of a fa- of being considered a normal fluid, as
140°F (60°C), it starts to become det- cility that sees very little personnel defined in B31.3, pending its location
rimental to personnel upon contact. At activity, then the fluid service could as listed in Table 1.
this point, the range of human toler- still be considered as a Category-D For example, if you have a fluid that
ance becomes a factor. However, as the fluid service. is operating at 195°F (90.6°C), it would
temperature continues to elevate, it One factor I have not included here be considered hazardous in this evalu-
eventually moves into a range that be- is the degree of relative importance of ation. But, if the system is located in
comes scalding upon human contact. a fluid service. If a system failed, how a Group 5 area (Table 1) it could still
Human tolerance is no longer a factor big of a disruption would it cause in qualify as a Category D fluid service.
because the water has become hazard- plant operation, and how does that
ous and the decision is made for you. factor into this process? Leak test examples
Before continuing, a point of clari- For example, if a safety shower After the above exercise in evaluating
fication. The 140ºF temperature men- water system has to be shut down for a fluid service, we can now continue
tioned above is with respect to sim- leak repair, the downtime to make the with a few examples of leak test pro-
ply coming in contact with an object repairs has little impact on plant oper- cedures. Using the designations given
at that temperature. Brief contact at ations. This system would therefore be in Table 2, these leak test procedures
that temperature would not be detri- of relatively low importance and not a will be categorized as follows:
mental. In various litigation related factor in this evaluation process. Testing Category T-1.
to scalding it has been determined If, on the other hand, a chilled water T-1.1 — This category covers liquid
that an approximate one-second ex- system has to be shut down for leak re- piping systems categorized by ASME
posure to 160°F water will result in pair to a main header, this could have B31.3 as Category-D fluid service and
Chemical Engineering www.che.com June 2008 51
Table 2. General Leak Testing
Engineering Practice Scenarios
Category Description
T-1 Initial service leak test
T-2 Hydrostatic leak test
will require initial service leak test- vice and will require initial service
ing only. leak testing. T-3 Pneumatic leak test
1. If the system is not placed into ser- 1. After completion of the blow-down T-4 Sensitive leak test
vice or tested immediately after process, the system shall be connected T-5 Alternative leak test
flushing and cleaning, and has set to its permanent supply source, if not
idle for an unspecified period of already done so, and to all of its ter- allow proper high-point venting to
time, it shall require a preliminary minal points. Open the block valve be accomplished. Hold pressure to
pneumatic test at the discretion of at the supply line and gradually feed its minimum until the system is
the owner. In doing so, air shall be the gas into the system. completely filled and vented.
supplied to the system to a pressure 2. Increase the pressure to a point 4. Once it is determined that the sys-
of 10 psig and held there for 15 min equal to the lesser of one-half the tem has been filled and vented
to ensure that joints and compo- operating pressure or 25 psig. Make properly, gradually increase pres-
nents have not been tampered with, a preliminary check of all joints by sure until 50% of the test pressure
and that the system is still intact. sound or bubble test. If leaks are is reached. Hold that pressure for
After this preliminary pressure found, release pressure, repair approximately two minutes to allow
check, proceed. leak(s) and begin again with Step 1. piping strains to equalize. Continue
2. After completion of the flushing and If no leaks are identified, continue to supply the system gradually until
cleaning process, connect the sys- to Step 3. test pressure is achieved.
tem, if not already connected, to its 3. Continue to increase pressure in 25 5. During the process of filling the sys-
permanent supply source and to all psi increments, holding that pres- tem and increasing pressure to 50%
of its terminal points. Open the block sure momentarily (approximately of the test pressure, check all joints
valve at the supply line and gradu- 2 min) after each increase to allow for leaks. Should any leaks be found,
ally feed the liquid into the system. piping strains to equalize, until the drain system, repair leak(s) and
3. Start and stop the fill process to operating pressure is reached. begin again with Step 1.
allow proper high-point venting to 4. Check for leaks by sound or bubble 6. Once the test pressure has been
be accomplished. Hold pressure to test, or both. If leaks are found, re- achieved, hold it for a minimum of
its minimum until the system is lease pressure, repair leak(s) and 30 min or until all joints have been
completely filled and vented. begin again with Step 2. If no leaks checked for leaks. This includes valve
4. Once it is determined that the sys- are found, the system is ready for and equipment seals and packing.
tem has been filled and vented prop- service. 7. If leaks are found, evacuate system
erly, gradually increase pressure 5. Record test results and fill in all re- as required, repair and repeat from
until 50% of operating pressure is quired fields on the leak test form. Step 2. If no leaks are found, evacu-
reached. Hold that pressure for ap- Category T-3.1 — Hydrostatic Leak ate system and replace all items
proximately two minutes to allow Test. T-3.1. — This category covers temporarily removed.
piping strains to equalize. Continue liquid piping systems categorized by 8. Record all data and activities on
to supply the system gradually until ASME B31.3 as normal fluid service. leak test forms.
full operating pressure is achieved. 1. If the system is not placed into ser- The three examples above should
5. During the process of filling the sys- vice or tested immediately after provide an idea as to the kind of guide-
tem, check all joints for leaks. Should flushing and cleaning, and has set line that needs to be created in provid-
leaks be found at any time during idle for an unspecified period of ing direction to the contractor respon-
this process, drain the system, re- time, it shall require a preliminary sible for the work.
pair leak(s) and begin again with pneumatic test at the discretion of
Step 1. (Caveat: Should the leak be the owner. In doing so, air shall be Preparation
no more than a drip every minute or supplied to the system to a pressure For leak testing to be successful on
two on average at a flange joint, it of 10 psig and held there for 15 min- your project, careful preparation is
could require simply checking the utes to ensure that joints and com- key. This preparation starts with
torque on the bolts without draining ponents have not been tampered gathering information on test pres-
the entire system. If someone forgot with, and that the system is still in- sures, test fluids, and the types of
to fully tighten the bolts, then do so tact. After this preliminary pressure tests that will be required. The most
now. If it happens to be a threaded check, proceed. convenient place for this information
joint you may still need to drain the 2. After completion of the flushing and to reside is the piping line list or pip-
system, disassemble the joint, clean cleaning process, with the flush/test ing system list.
the threads, add new sealant and re- manifold still in place and the tem- A piping line list and piping system
connect the joint before continuing.) porary potable water supply still list achieve the same purpose, only to
6. Record test results and fill in all re- connected (reconnect if necessary), different degrees of detail. On some
quired fields on the leak test form. open the block valve at the supply projects, it may be more practical to
T-1.2. — This category covers pneu- line and complete filling the system compile the information by entire
matic piping systems categorized by with potable water. service fluid systems. Other projects
ASME B31.3 as Category-D fluid ser- 3. Start and stop the fill process to may require a more detailed approach
52 Chemical Engineering www.che.com June 2008
by listing each to and from line along ufacturing Practice (cGMP) and U.S. of having time to consider just what
with the particular data for each line. Food and Drug Administration (FDA) those requirements are and how they
The line list itself is an excellent requirements. These CFR Titles and should be defined without the time
control document that might include FDA requirements drove the need to pressures imposed when this activity
the following for each line item: demonstrate or prove compliance. is project driven.
1. Line size These requirements can cover Performing this kind of activity
2. Fluid everything from verification of ex- while in the heat of a project sched-
3. Nominal material of construction amination and inspection, documen- ule tends to force quick agreement to
4. Pipe specification tation of materials used, software specifications and requirements writ-
5. Insulation specification functionality and repeatability to ten by parties other than those with
6. P&ID welder qualification, welding ma- the owner’s best interest at heart.
7. Line sequence number chine qualification, and so on. Validating a piping system to ensure
8. From and to information The cGMP requirements under compliance and acceptability is always
9. Pipe code 29CFR Titles 210 and 211 are a beneficial and money well spent.
10. Fluid service category vague predecessor of what valida-
11. Heat tracing tion has become, and continues to Final remarks
12. Operating pressure become. From these basic govern- Before concluding this series of ar-
13. Design pressure mental outlines, companies, and the ticles, there are just a couple of final
14. Operating temperature pharmaceutical industry as a whole, points to be made.
15. Design temperature have increasingly provided improved
16. Type of cleaning interpretation of these guidelines to Evolving standards
17. Test pressure meet many industry-imposed, as well We have previously discussed industry
18. Test fluid as self-imposed requirements. standards and how they are selected
19. Type of test To a lesser extent, industrial proj- and applied on a project [4]. What was
Developing this type of information on a ects outside the pharmaceutical, food not covered is the fact that most proj-
single form provides everyone involved and beverage, and semi-conductor ects will actually have a need to com-
with the basic information needed for industries, industries not prone to ply with multiple industry standards.
each line. Having access to this line-by- require such in-depth scrutiny, could In a large grassroots pharmaceuti-
line information in such a concise, well- benefit from adopting some of the es- cal project you may need to include
organized manner reduces guess-work sential elements of validation, such industry compliance standards for
and errors during testing. as: material verification, leak-test re- much of the underground utility pip-
Test results, documented on the test cords, welder and welding operator- ing, ASME B31.1 for boiler external
data forms, will be maintained under qualification records, and so on. piping (if not included with packaged
separate cover. Together, the line list At face value this exercise would pro- boilers), ASME B31.3 for chemical and
provides the required information on vide an assurance that the fabricating utility piping throughout the facility,
each line or system, and the test-data and installing contractor is fulfilling its and ASME-BPE for any hygienic pip-
forms provide signed verification of contractual obligation. The added ben- ing requirements.
the actual test data of the test circuits efit is that, in knowing that this degree These and other standards, thanks
that make up each line or system. of scrutiny will take place, the contrac- in large part to the cooperation of the
tor will take extra measures to mini- standards developers and ANSI, work
VALIDATION mize the possibility of any rejects. hand-in-hand with one another by ref-
The process of validation has been This is not to imply that all con- erencing each other where necessary.
around for longer than the 40 plus tractors are out to get by with as These standards committees have
years the author has been in this little as they can. Just the opposite is enough work to do within their de-
business. You may know it by its less actually true. Most contractors quali- fined scope of work without inadver-
formal namesakes walk-down and fied to perform at this level of work tently duplicating work done by other
checkout. Compared to validation, are in it to perform well and to meet standards organizations.
walk-down and checkout procedures their obligations. Most will already An integrated set of American Na-
are not nearly as complex, stringent, have their own verification proce- tional Standards is the reason that,
or all inclusive. dure in place. when used appropriately, these stan-
Validation is actually a subset ac- The bottom line is that the owner dards can be used as needed on a proj-
tivity under the umbrella of commis- is still responsible for the end result. ect without fear of conflict between
sioning and qualification (C&Q). It is No one wants to head for the litiga- those standards.
derived from the need to authenticate tion table at the end of a project. And One thing that should be understood
and document specifically defined re- the best way to avoid that is for the with industry standards is the fact that
quirements for a project and stems in- owner to be proactive in developing they will always be in a state of flux; al-
directly from, and in response to, the its requirements prior to initiating ways changing. And this is a good thing.
Code of Federal Regulation 29CFR a project. This allows the specifica- These are changes that reflect updating
Titles 210 and 211 current Good Man- tion writers and reviewers the benefit to a new understanding, expanded clar-
Chemical Engineering www.che.com June 2008 53
Engineering Practice

ification on the various sections that fication Part (CR). This is all part of dustrial piping in order to provide a
make up a standard, staying abreast the ever-evolving understanding of basic broad understanding of some
of technology, and simply building the the needs of the industrial community key points, without going into great
knowledge base of the standard. and improved clarification, through detail on any specific topic. It is hoped
For example, two new parts are discussion and debate on content. that the readers of this series will dig
being added to the seven parts cur- deeper into this subject matter to dis-
rently existing in ASME-BPE. There Conclusion cover and learn some of the more fi-
will be a Metallic Materials of Con- This series of articles attempted to nite points of what was discussed in
struction Part (MMOC), and a Certi- cover a wide range of topics on in- this and previous articles. It is hoped
that this series provides enough basic
knowledge of piping for you to recog-
nize when there is more to a piping
issue than what you are being told. n
Edited by Gerald Ondrey

Acknowledgement
My deep appreciation again goes to
Earl Lamson, senior project manager
with Eli Lilly and Co., for taking the
time to review each of these articles.
His comments help make the articles
better documents than they otherwise
would have been. He obliged me by
applying the same skill, intelligence
and insight he brings to everything he
does. His comments kept me concise
and on target.
References
1. Huitt, W.H., Piping for Process Plants: The
Basics, Chem. Eng. February 2007, pp. 42–47.
2. Huitt, W.H., Piping for Process Plants:
Flanges, Chem. Eng. March 2007, pp. 56–61.
3. Huitt, W.H., Piping for Process Plants: Design
Elements, Chem. Eng. July 2007, pp. 50–57.
4. Huitt, W.H., Piping for Process Plants: Codes
and Fabrication, Chem. Eng. October 2007,
pp. 68–76.
5. Huitt, W.H., Piping for Process Plants: In-
stallation and Cleaning, Chem. Eng. April
2008, pp. 48–58.

Author
W. M. (Bill) Huitt has been
involved in industrial piping
design, engineering and con-
struction since 1965. Positions
have included design engineer,
piping design instructor, proj-
ect engineer, project supervi-
sor, piping department super-
visor, engineering manager
and president of W. M. Huitt
Co. (P.O. Box 31154, St. Louis,
MO 63131-0154. Phone: 314-
966-8919; Email: wmhuitt@aol.com) a piping
consulting firm founded in 1987. His experience
covers both the engineering and construction
fields and crosses industrial lines to include
petroleum refining, chemical, petrochemical,
pharmaceutical, pulp and paper, nuclear power,
and coal gasification. He has written numerous
specifications including engineering and con-
struction guidelines to ensure that design and
construction comply with code requirements,
owner expectations and good design practices.
Bill is a member of ISPE (International Society
of Pharmaceutical Engineers), CSI (Construction
Specifications Institute) and ASME (American
Society of Mechanical Engineers). He is a con-
tributor to ASME-BPE and sits on two corporate
specification review boards.
Circle 27 on p. 86 or go to adlinks.che.com/7373-27
54 Chemical Engineering www.che.com June 2008

S-ar putea să vă placă și