Sunteți pe pagina 1din 2

Roll No-

Environmental Engineering-II
TE (Civil)
Mid-Term Test
Date-20/2/2015 Max. Marks – 50
Time – 9 am to 11.00 am Min. marks -20
Instructions: - 1) All questions are compulsory in Q no. 1.
2) Solve any three questions from Q no.2 to Q no. 5.
3) Assume suitable data whenever required.
4) Figure to the right indicates full marks.

Q1. Rewrite the statement by filling in the blank with correct option in your answer sheet.
(10 marks)
1. Pick out the odd one - _________.
a) lateral b) trunk
c) outfall d) rising main
4. Sewage flow in summer season is known as ______________.
a) WWF b) DWF
c) FDW d) WFW
7. Screening is _____________ process.
a) Preliminary b) Secondary
c) Tertiary d) None of these
10. Detention period commonly adopted for grit chamber is ______
a) 60 sec b) 2 mins
c) 2 hrs d) 10 sec
o
13. Standard BOD value is measured at ___ C and After ___ days.
a) 30, 5 b) 10, 5
c) 20, 5 d) 15,5
16. Grit chamber removes ____________________________________________.
a) Grit, sand, silt b) metal fragments
c) Egg shells d) All of above
19. Screen chamber removes ______________________.
a) Colloidal particles b) clay
c) Large SS d) All of above
22. In solids test, for finding SS concentration, ___________________filter paper is used.
a) Whatmans b) Catmans
c) Batmans d) Hatmans
25. Grit chamber removes particles having sp gr in the range of _____ to _____.
Roll No-
a) 2.2.,2.65 b) 2.4,2.65
c) 2,3 d) 1,1.5
28. Self-cleansing velocity in the sewer should be ____ m/s.
a) 0.75 b) 1.5
c) 1 d) None of above
Q 2] a) Explain factors affecting dry weather flow. (5)
b) Write significance of providing grit chamber (2)
c) Design a sewer section running half full for following data (6)
Flow= 900 lit/sec
N= 0.013
Gradient= 1:800
Q 3] a) Find BOD after 8 days at 300C for a wastewater sample whose standard (6)
BOD is 200 mg/lit. Take k=0.0.1 (base 10)
c) Explain significance of pumping station. Also draw a neat sketch of (7)
pumping station

Q4] a) Discuss design of grit chamber with special emphasis on velocity control (6)
devices.
b) Draw a flow sheet of domestic wastewater treatment plant consisting of (7)
Trickling filter as biological treatment unit.

Q5] Write short notes (Any two) (14)


1. Types of screen chamber.
2. BOD test
3. Classification of sewers

S-ar putea să vă placă și