Documente Academic
Documente Profesional
Documente Cultură
MINISTRY OF INFRASTRUCTURE
DEVELOPMENT
Submitted by:
2
TABLE OF CONTENTS PAGE
1.0 BACKGROUND 1
3.2 Ramp 2
3.2.1 Sizing 2
4.0 CONCLUSION 4
ANNEX 5
i
1.0 BACKGROUND
The boundaries for the project area are not well defined. It is possible that position
of the new ramps may interfere with the areas belonging to Kivukoni College.
Following the need to have enough space to accommodate ferry ramps and shelter
facilities at Magogoni, the Client instructs K& Associates Professional Services
Ltd (KAPSEL) to consider all requirements so as to accommodate all ferry facilities
including ramps, terminals, walkways, etc. for acquisition of land.
The Consultants searched for ramp facilities design manuals and standards
guidelines from the Ministry of Infrastructure Development (MOID) but not much
was obtained. The Consultant however managed to obtain some standards from
Federal States to ensure safety of the facilities. Further, the following documents,
recommended by the Ministry of Infrastructure Development (formally Ministry of
Works), will also be used:
(a) Pavement and Materials: Pavement and Materials Design Manual, 1999
(MOW)
In addition the Consultant will use the Ohio Boating Facilities Standards and
Guidelines, First edition, 2003.
1
3.0 DESIGN OF FERRY FACILITIES AND SPACE UTILIZATION
We understand that the available space is limited. As a result, the Consultant has
prepared ferry concepts / layouts which utilize the space at optimum capacity. The
master plan will include boarding facilities, ticketing area, parking lots and ramps.
The total coverage width is 100m by 100m, which gives a coverage area of about
10,000m2. In order to have a comprehensive master plan the Consultant has
prepared draft layouts of the facilities and preliminary design of the structures for
the Client’s approval and /or comments before detailed design is carried out.
3.2 Ramp
3.2.1 Sizing
Two ramps on both sides are proposed to accommodate bigger ferry while the small
ramps are to be constructed adjacent to the big ones to be used by small ferries.
The approximate width for the big and small ramps is 10m. However, the exact size
of each ramp will depend on the approved ferry facilities to be accommodated on
the terminals. The preliminary drawings have been attached for the Client’s
comments and / or approval.
The following parameters are recommendable on alignment and slope of the ramp:
a) The alignment for ramp is perpendicular to the bank line, to an allowance of Zero
(00) degrees rotation.
b) The preferred launch ramp slopes range from 12% to15%. The recommended
slope for design purpose is 15%, which allows the boat trailer to be in deep
enough water to launch and retrieve from the trailer without the rear tires of the
tow vehicle being in the water. The design of boat ramp slopes has been
matched with the required depth needed to launch a typical trailerable boat from
its trailer.
c) Design water elevations will be established and compared with the available data
given on the Terms of Reference (TOR). The Ordinary Low Water (OLW) and
Ordinary Low Water (OHW) elevations are used for the facility design, the
refence records of high and low water elevations from Tanzania Ports Authority
(TPA) Tide Tables for 2009 will also be used to check the trend.
2
d) During construction these tables will also be used to plan activities depending on
tide levels.
The dimensions of high and low tide levels will be explained in details in the final
design report.
As stated in section 2.0 of this report, standards approved by the MOID will be used.
Possible construction materials to be used for ramps and terminal facilities are same
as those applied to road construction and buildings. However, the Consultant will
critically assess and carefully choose materials that will withstand the adverse effects
attributed to the ocean, which will include cement, steel, roofing, etc
The preliminary structural engineering design has been prepared based on the
following Standards and Guidelines:
i) Design Standards
1. British Standards Concrete, BS 8110:1997
2. British Standards for Bridges, BS 5400
3. British Standards for Structural Steel work, BS 5950
iv) Materials:
1. Cement, Ordinary Portland Cement (Resistance to corrosion to be
determined using Laboratory Tests)
3
2. Hardcore to be proposed by Geotechnical Engineer and ascertained by
Laboratory Tests
3. Base materials to be proposed by Geotechnical Engineer and ascertained
by Laboratory Tests
The joint terminal lounge was proposed for both normal and VIP passengers waiting
to board. The passenger lounge is proposed to carry up to normal 2000 Pax, and
10Pax for VIP. Architectural design considers interactions between passengers’
ticketing area, parking lots and passengers lounges.
⅓ of all normal passengers will be seated (experience shows that most of the
passengers will be standing and the time for waiting is short. The children,
elderly, sick, etc will be among the passengers on the seats).
Walkways will be covered from the end of the ramps to the exit.
4.0 CONCLUSION
The report summarizes all design parameters which may be required for the new
ferry terminals at Kigamboni whereby the area is belongs to Mwalimu Nyerere
College. The ferry expansion at Magogoni side will be considered the same way after
receiving clarifications on the correct location. The details of the design depend
much on the location of available land for the ramp facilities. The Client’s approval
on these issues is crucial and is expected to be given as soon as possible in order to
enable the Consultant to finalize the design.
4
ANNEX