OHS MANAGEMENT GUIDELINE

RMIT SG-
Title: Risk Assessment Guideline Number: 3.1Appendix A

Issue Date: 6-01-06

Risk Assessment Team (include name and position): Date: / /


1. 5.
2. 6.
3. 7.
4. 8
Portfolio: School:
Type of hazard (please tick and refer to relevant procedure if appropriate):

Chemical (RMIT-xx-00x) Electrical (RMIT-xx-00x) Work Environment (noise (RMIT-xx-


00x), slip/ trip/ falls, temperature etc)
Mechanical (plant/ equipment RMIT-xx-00x) Biological Radiation (RMIT-xx-00x)
Manual handling (RMIT-xx-00x) Vibration Other

Description of Hazard (include reason for assessment):

Location of Hazard:
Risk Assessment (rate the consequence, exposure and probability associated with the hazard):
FACTOR CLASSIFICATION RATING
1. CONSEQUENCE
a. Catastrophe; numerous fatalities; major disruption of activities 100
Most probable result b. Disaster; multiple fatalities; 50
of the potential c. Very serious; Fatality; 25
accident.
d. Serious; serious injury (amputation, permanent disability); 15
e. Important; disabling injury; 5
f. Noticeable; minor cuts, bruises, bumps; minor damage 1
2. EXPOSURE
Hazard exposure occurs:
The frequency of a. Continuously (or many times daily) 10
exposure to the
b. Frequently (approximately once daily) 6
hazard.
c. Occasionally (from once per week to once per month) 3
d. Infrequent (from once per month to once per year) 2
e. Rarely (it has been known to occur) 1
f. Very rarely (not known to have occurred) 0.5
3. PROBABILITY
Complete accident sequence:
Likelihood that the a. Almost certain likely or expected result; 1 in 10 chance 10
consequence will
b. Quite possible/not unusual; 1 in 10 to 1 in 100 chance 6
occur once the
individual is exposed c. Would be an unusual sequence or coincidence; 1 in 100 to 1 in 1000 chance 3
to the hazard. d. Would be a remotely possible coincidence 1 in 1000 to 1 in 10,000 chance 1
e. Has never happened after many years of exposure, but is conceivably possible; 1 in 10 000 to 1 in
0.5
100,000
f. Practically impossible sequence (has never happened) 1 in 100,000 chance or lower 0.1

Hard copies of this document are uncontrolled copies


\\Its-gn-blg57\shared\People and Culture\OH &S\ Guidelines\Hazard Management\Risk Assessment Form RMIT-SG-3.1
Appendix A.doc
OHS MANAGEMENT GUIDELINE
CONSEQUENC
EXPOSURE PROBABILITY RISK SCORE
E X X =
Risk Score:

RISK SCORE DEFINITION ACTION


500 Very high risk Immediate action required. HIGH PRIORITY.
300- 499 High risk Management attention needed. Hazards must be considered as NOT adequately controlled.
150- 299 Substantial risk Management attention needed. Hazards must be considered as NOT adequately controlled.
Hazard must be examined against current standards to determine whether the hazard is adequately/
60- 149 Moderate risk
not adequately controlled.
10- 59 Low risk Manage by routine procedures.

Risk Control Identification (to determine appropriate risk control measures(s) sequentially go through the
hierarchy of controls):
Practicability Test
Hierarchy of Risk Controls Ye No Comment
s
1. Eliminate
Is it possible to eliminate the hazard?

2. Reduce
Is it possible to reduce the level of risk posed by the hazard by
(priority order):
 Substitution (using less hazardous alternatives)
 Isolation (separating the operator from the risk)
 Engineering controls (re-designing plant or equipment).

3. Administration
Is it possible to reduce the level of risk posed by the hazard by
changing operating procedures, training, supervision, providing
information etc

4. Personal Protection
Is it possible to reduce the level or risk posed by the hazard by
wearing personal protective equipment and clothing?

Risk Control Action Plan (include short term and long term risk control measures):
Recommended Risk Control to be Implemented Responsibility Timeline Completed

(date/ initials)

Revised Risk Score (re-score the hazard risk score once recommended risk control measure(s) are implemented) :

Hard copies of this document are uncontrolled copies


\\Its-gn-blg57\shared\People and Culture\OH &S\ Guidelines\Hazard Management\Risk Assessment Form RMIT-SG-3.1
Appendix A.doc
OHS MANAGEMENT GUIDELINE
CONSEQUENC
EXPOSURE PROBABILITY RISK SCORE
E X X =
Risk Score:

RISK SCORE DEFINITION ACTION


500 Very high risk Immediate action required. HIGH PRIORITY.
300- 499 High risk Management attention needed. Hazards must be considered as NOT adequately controlled.
150- 299 Substantial risk Management attention needed. Hazards must be considered as NOT adequately controlled.
Hazard must be examined against current standards to determine whether the hazard is adequately/
60- 149 Moderate risk
not adequately controlled.
10- 59 Low risk Manage by routine procedures.

Signed:
Manager: Employee:
HSR:

Hard copies of this document are uncontrolled copies


\\Its-gn-blg57\shared\People and Culture\OH &S\ Guidelines\Hazard Management\Risk Assessment Form RMIT-SG-3.1
Appendix A.doc

S-ar putea să vă placă și