Sunteți pe pagina 1din 23

Detailed Estimate of Residencefor Mr.Perera Augustine& Mrs.

MiniAugustine at Adarsnagar
Thiruvananthapuram Taluk,Thiruvananthapuram District.

Sl.No. Description of work NO Length Width Height Qty Qty Total Unit Rate
1 SITE CLEARANCE
Clearing the site including labour 1000.00 L.S
charge, watering ramming, etc.
complete
2 EARTH WORK
Earth work excavation in hard 2 13.95 0.80 0.80 17.86 70.35 M3 200.00
soil for foundation and 1 3.00 0.80 0.80 1.92
depositing on bank with initial 1 12.25 0.80 0.80 7.84
bed upto 50m and lift upto 1 8.80 0.80 0.80 5.63
1.50m including breaking
2 11.82 0.80 0.80 15.13
clods,watering,ramming and
sectioning of spoil bank etc. 1 10.37 0.80 0.80 6.64
complete. 1 10.29 0.80 0.80 6.59
1 13.67 0.80 0.80 8.75
70.35
3 PLAIN CEMENT CONCRETE
Cement concrete 1:4:8 using 2 13.95 0.80 0.10 2.23 8.79 M3 3,400.00
40mm broken stone including 1 3.00 0.80 0.10 0.24
watering labour charges, curing 1 12.25 0.80 0.10 0.98
etc.complete. 1 8.80 0.80 0.10 0.70
2 11.82 0.80 0.10 1.89
1 10.37 0.80 0.10 0.83
1 10.29 0.80 0.10 0.82
1 13.67 0.80 0.10 1.09
8.79
4 SAND FILLING 2 13.95 0.80 0.10 2.23 8.79 M3 90.00
1 3.00 0.80 0.10 0.24
1 12.25 0.80 0.10 0.98
1 8.80 0.80 0.10 0.70
2 11.82 0.80 0.10 1.89
1 10.37 0.80 0.10 0.83
1 10.29 0.80 0.10 0.82
1 13.67 0.80 0.10 1.09
8.79
5 RANDOM RUBBLE MASONRY
Random rubble masonry with 2 13.70 0.60 0.60 9.86 39.21 M3 2,100.00
hard stone in cement mortar 1:6, 1 3.00 0.60 0.60 1.08
for retaining walls walls in plinth 1 12.00 0.60 0.60 4.32
and foundation including 1 8.54 0.60 0.60 3.07
levelling up with cement
2 11.82 0.60 0.60 8.51
concrete 1:6:12
(a)FOUNDATION 1 10.37 0.60 0.60 3.73
1 10.29 0.60 0.60 3.70
1 13.67 0.60 0.60 4.92
39.21
(b) BASEMENT 2 13.40 0.45 0.45 5.43 21.81 M3 2,200.00
1 3.00 0.45 0.45 0.61
1 11.70 0.45 0.45 2.37
1 8.24 0.45 0.45 1.67
2 11.82 0.45 0.45 4.79

Page 1
1 10.37 0.45 0.45 2.10
1 10.29 0.45 0.45 2.08
1 13.67 0.45 0.45 2.77
21.81
5 PLINTH BEAM
Reinforced cement concrete 2 12.95 0.23 0.15 0.89 3.65 M3 6,000.00
1:2:4, for plinth beams using 1 2.94 0.23 0.15 0.10
with 20mm nominal size 1 11.25 0.23 0.15 0.39
brockenstone including the cost 1 7.80 0.23 0.15 0.27
of centering and shuttering etc.
2 11.82 0.23 0.15 0.82
complete.
1 10.37 0.23 0.15 0.36
1 10.29 0.23 0.15 0.36
1 13.67 0.23 0.15 0.47
3.65
6 EARTH FILLING
Filling the escavated earth for 60.93 M3 90.00
basement including labour
charge, watering ramming, etc.
complete .
1 21.08 1.00 0.45 9.49
1 3.60 3.20 0.45 5.18
1 1.57 0.90 0.45 0.64
1 1.39 1.45 0.45 0.91
1 2.13 1.65 0.45 1.58
1 4.20 3.60 0.45 6.80
1 4.50 3.00 0.45 6.08
1 3.23 1.50 0.45 2.18
1 6.69 3.60 0.45 10.84
1 12.81 1.95 0.45 11.24
1 13.32 1.00 0.45 5.99
60.93
7 BRICK WORK
Brick work in cement mortar 1:6
with country burnt bricks as per
the standard specifications
A Ground floor 2 12.95 0.23 3.00 17.87 61.29 M3 3,000.00
1 2.94 0.23 3.00 2.03
1 11.25 0.23 3.00 7.76
1 7.80 0.23 3.00 5.38
2 11.82 0.23 3.00 16.31
1 10.37 0.23 3.00 7.16
1 10.29 0.23 3.00 7.10
1 13.67 0.23 3.00 9.43
DEDUCTION
DEDUCTION FOR DOOR 1 1.00 0.23 2.10 -0.48
6 0.90 0.23 2.10 -2.61
2 0.80 0.23 2.10 -0.77
4 0.60 0.23 1.50 -0.83
2 1.50 0.23 1.50 -1.04
1 1.80 0.23 1.50 -0.62
1 1.80 0.23 2.00 -0.83
1 2.40 0.23 2.00 -1.10
1 1.10 0.23 2.00 -0.51
1 2.40 0.23 2.00 -1.10

Page 2
1 2.70 0.23 2.00 -1.24
1 0.60 0.23 0.60 -0.08
1 0.90 0.23 0.60 -0.12
1 1.20 0.23 1.50 -0.41
1 1.50 0.23 1.00 -0.35
61.29
B FIRST FLOOR 2 5.30 0.23 3.00 7.31 12.14 M3 3,100.00
2 4.50 0.23 3.00 6.21
DEDUCTION FOR OPENINGS 2 0.90 0.23 2.1 -0.87
1 1.50 0.23 1.5 -0.52
12.14
Brick work in cement mortar 1:6
with country burnt bricks for
sunshade& parapet wall as per
the standard specifications

GROUND FLOOR ,sunshade 1 30.00 0.12 0.30 1.08 6.34 2,700.00


Parapet 1.00 58.40 0.12 0.75 5.26
6.34
FIRST FLOOR,
sunshade 1.00 5.00 0.12 0.30 0.18 2.12 3,000.00
Parapet 1.00 18.00 0.12 0.90 1.94
2.12
WOOD WORK-DOORS
Supplying and fixing panelled
doors shutter frames with
locking arrangements etc.in
country wood.
A GROUND FLOOR 1 1.00 2.10 2.10 16.80 m2 5,500.00
6 0.90 2.10 11.34
2 0.80 2.10 3.36
16.80
B FIRST FLOOR 2 0.90 2.18 3.92 3.92 m2 5,500.00
3.92
9 WOOD WORK-WINDOWS
Providing and fixing approved
quality of teakwood glazed
Windows all fittings,locks
etc.complete. in country wood

A GROUND FLOOR 4 0.60 1.50 3.60 35.80 m2 6,000.00


2 1.50 1.50 4.50
1 1.80 1.50 2.70
1 1.80 2.00 3.60
1 2.40 2.00 4.80
1 1.10 2.00 2.20
1 2.40 2.00 4.80
1 2.70 2.00 5.40
1 0.60 0.60 0.36
1 0.90 0.60 0.54
1 1.20 1.50 1.80
1 1.50 1.00 1.50
35.80
B FIRST FLOOR 1 1.50 1.5 2.25 2.25 m2 6,000.00

Page 3
B
2.25
Supplying and fixing in place MS
grill work with Square rods as
per the specification and
drawings in all floors.
400.00 400.00 KG 42.00
10 REINFORCED CEMENT CONCRETE
Reinforced cement concrete
1:2:4, for lintels & beam, using
with 20mm nominal size
brockenstone including the cost
of centering and shuttering etc.
complete.
`
A Ground floor-Lintel 2 12.95 0.23 0.15 0.89 4.75 M3 6,000.00
1 2.94 0.23 0.15 0.10
1 11.25 0.23 0.15 0.39
1 7.80 0.23 0.15 0.27
2 11.82 0.23 0.15 0.82
1 10.37 0.23 0.15 0.36
1 10.29 0.23 0.15 0.36
1 13.67 0.23 0.15 0.47
Beam 1 11.90 0.23 0.40 1.09
4.75
C First floor -Lintel 1 19.60 0.23 0.10 0.45 0.45 M3 6,100.00
11 REINFORCED CEMENT CONCRETE
RCC1:2:4,for sunshade and slab
using 20mm nominal size
brockenstone including
centering shuttering etc.

A GROUND FLOOR 1 30.00 0.60 0.10 1.80 1.80 M3 6,000.00


FIRST FLOOR 1 3.00 0.60 0.10 0.18 0.18 M3 6,000.00
12 REINFORCED CEMENT CONCRETE
RCC1:2:4,for FLATROOF using
20mm nominal size brokenstone
including centering shuttering
etc. complete.

A Ground floor 1.0 108.00 1.00 0.10 10.80 10.80 M3 6,100.00


10.80
B First floor 1.0 10.00 1.00 0.10 1.00 1.00 M3 6,200.00
1.00
RCC1:2:4,for staircase using
20mm nominal size brokenstone
including centering shuttering
etc. complete.
1.0 1.07 1.00 1.07 1.07 M3 6,000.00
14 REINFORCEMENT WORK
1890.00 Kg 42.00
Reinforcement for all RCCwork
like
columns,beams,lintels,slab,etc.c
omplete including bending ,tying
and placing in position with
binding wire as directed etc
complete.
15 PLASTERING SLABS

Page 4
15
Plastering underside of Slab,
etc.with cement mortar 1:3,9mm
thick,floated hard and trowelled
smooth including all cost of
material, labour, scaffolding
curing etc complete.

A Ground floor 1 11.52 1.00 11.52 107.84 M2 110.00


1 22.77 1.00 22.77
1 2.01 1.00 2.01
1 4.60 1.00 4.60
1 3.51 1.00 3.51
1 15.66 1.00 15.66
1 13.50 1.00 13.50
1 12.81 1.00 12.81
1 6.69 1.00 6.69
1 9.93 1.00 9.93
1 4.84 1.00 4.84
107.84
C FIRST FLOOR 1.0 9.90 1.00 9.90 9.90 M2 115.00
16 Sunshade Plastering 9.90
Plastering underside of
sunshade etc.with cement
mortar 1:3,9mm thick,floated
hard and trowelled smooth
including all cost of material,
labour, scaffolding curing etc
complete.

Ground floor 2 30.00 0.60 36.00 36 110


First floor 2 3.00 0.60 3.60 3.6 115
Plastering with cement
mortar1:5 inside and sough
finish 12mm thick wall to correct
line and plumb,curing
,etc.complete.
B Ground floor 1 13.60 3.00 40.80 339.35 M2 100.00
1 23.76 3.00 71.28
1 5.68 3.00 17.04
1 7.58 3.00 22.74
1 16.56 3.00 49.68
1 15.00 3.00 45.00
1 15.06 3.00 45.18
1 11.04 3.00 33.12
1 12.76 3.00 38.28
1 9.46 3.00 28.38
DEDUCTION FOR OPENINGS 1 1.10 2.10 -2.31
5 1.00 2.10 -10.50
3 0.80 2.10 -5.04
4 0.60 1.50 -3.60
2 1.50 1.50 -4.50
1 1.80 1.50 -2.70
1 1.80 2.00 -3.60
1 2.40 2.00 -4.80
1 1.10 2.00 -2.20

Page 5
1 2.40 2.00 -4.80
1 2.70 2.00 -5.40
1 0.60 0.60 -0.36
1 0.90 0.60 -0.54
1 1.20 1.50 -1.80
339.35
B First Floor 1 12.76 3.00 38.28 34.14 M2 105.00
DEDUCTION 1 0.90 2.10 -1.89
1 1.50 1.50 -2.25
34.14
Plastering with cement
mortar1:5 outsidewall & parapet
wall and sough finish 12mm
thick wall to correct line and
plumb,curing ,etc.complete.

Ground floor 1 58.84 3.45 203.00 247.13 120.00


2 58.84 0.75 44.13
247.13
first floor 1 12.76 3.00 38.28
2 3.00 0.90 2.70
40.98 40.18 125.00
17 TWO COAT PLASTERING

A GROUND FLOOR 1.0 80.00 1.00 80.00 80.00 M2 130.00


80.00
B FIRST FLOOR 1.0 9.90 1.00 9.90 9.90 M2 135.00
9.90
Water proofing the roof slabs,
floors of the toilet, and wherever
required as per directions with
approved quality (ROFFE or
equivalent) water proofing
application two coats and tested
as per standard.

GROUND FLOOR 1.0 80.00 1.00 80.00 80.00 M2 180.00


18 FLOORING-P C C
Cement concrete 1:4:8 using
40mm broken stone including
watering labour charges, curing
etc
A Ground floor 1 11.52 1.00 11.52 107.84 M2 100.00
1 22.77 1.00 22.77
1 2.01 1.00 2.01
1 4.60 1.00 4.60
1 3.51 1.00 3.51
1 15.66 1.00 15.66
1 13.50 1.00 13.50
1 12.81 1.00 12.81
1 6.69 1.00 6.69
1 9.93 1.00 9.93
1 4.84 1.00 4.84

Page 6
107.84
19 WHITE WASHING-SLABS
Providing newly plastered slab
with water proof cement paint
and priming coat,icluding one
coat of cement washing, all cost
of materials,labour etc.complete.

A Ground floor. 120.00 120.00 m2 40.00


As per item no.15b
B FIRST FLOOR 15.00 15.00 m2 40.00
As per item no.15c
20 WALLS-PAINTING
Providing newly plastered
internal walls with quality
emulsion of approved colour
(Nerolac/equivalent) after
washing and scraping including
two coats putty over a priming
coat of cement primer
etc.complete.

A Ground floor 350.00 350.00 M2 110.00


As per item No.16b
B FIRST FLOOR 35.00 35.00 M2 120.00
As per item No.14c
21 Providing and finshing newly
plastered walls with exterior
quality whether proof emulsion
paint, (Apex or Equilalent), as
per standard specification over a
priming coat on the exterior
walls as per approved colour.

GROUND FLOOR 245.00 245.00 M2 120.00


FIRST FLOOR 45.00 45.00 M2 130.00
PAINTING-ENAMEL

Providing two coats of first


quality enamel paint for
doors,windows,grills,etc. over a
priming coat of metal of wooden
primer, filling the voids with putty
etc.complete.
A GROUND FLOOR
As per item No 8a&9a 1 2.25 20.72 46.62 46.62 m2 100.00
B FIRST FLOOR
As per item No.8b&9b 1 1.50 38.05 57.08 57.08 m2 100.00
22 TILES-FLOORING
Providing flooring using
approved quality and type of
ceramic tile for bedroom,toilet
and kitchen to line and level
cutting joints neatly pointing
using compound and wipping
clean etc. complete.

Page 7
22
Providing flooring using
approved quality and type of
ceramic tile for bedroom,toilet
and kitchen to line and level
cutting joints neatly pointing
using compound and wipping
clean etc. complete.

A GROUND FLOOR 1 11.52 1.00 11.52 73.17 M2 1,000.00


1 22.77 1.00 22.77
2.01 1.00 0.00
4.60 1.00 0.00
3.51 1.00 0.00
15.66 1.00 0.00
13.50 1.00 0.00
1 12.81 1.00 12.81
1 6.69 1.00 6.69
1 4.84 1.00 4.84
17 0.18 0.90 2.71
16 0.28 0.90 4.03
Skerting @ 12% 7.80
73.17
B First floor 1 11.17 1.00 11.17 12.47 M2 950.00
Skerting @ 12% 1.30
12.47
23 WALL TILES
Providng glazed tiles of
equivalent along the walls of
bathrooms,to a height of 2.1
m ,along the walls of kitchen and
work area finishing the joijnts
with cement grout etc. complete.

A GROUND FLOOR 1 13.18 2.10 27.68 30.92 M2 650.00


1 8.10 0.40 3.24
1 8.40 0.40 3.36
Deduction for openings 2 0.80 2.10 -3.36
30.92
24 EXTERIOR TILES
Providing flooring using
approved quality and type of
exterior Tiles to line and level
cutting joints neatly pointing
using compound and wipping
clean etc. complete.

A PORCH 1 18.00 1.00 18.00 18.00 M2 550.00


25 Supplying and fixing granite slab 3.54 M2
2,500.00
for kitchen top GROUND
FLOOR
1 3.30 0.60 1.98
1 2.60 0.60 1.56
3.54
26 HAND RAILS
Providing Hand rails using 7.50 RM 1800.00
M.S.Pipes and frames etc.
complete for balcony and
staircases

Page 8
Providing 8 mm groove work
during the course of plastering
to the wall or RCC surfaces
including all cost of materials
and labour,etc.complete.

Ground floor 1.00 300.00 300.00 300.00 RM 15.00


Providing 8 mm groove work for
external wall during the course
of plastering to the wall
including all cost of materials
and labour,etc.complete.

Ground floor 4.00 58.00 232.00 232.00 15.00

First floor 4.00 12.00 48.00 48.00 15.00

Providing cornice work for


parapet wall during the course
of plastering including all cost of
materials and
labour,etc.complete.
First floor 1.00 58.00 58.00 RM 300.00
Providing cornice work for
sunshade wall during the
course of plastering including all
cost of materials and
labour,etc.complete.
Ground floor 1.00 30.00 30.00 RM 250.00
First floor 1.00 3.00 3.00 RM 250.00
Providing pargola to the top of 20.00 1.20 24.00 24.00 350.00
roof slab and size of 20cmand
5cm thickR.C.C including all
materials and labour etc
complete

Supplying and fixing 18.61 18.61 M2 130.00


polycarbonsheet including all
materials and labour etc
complete
TOTAL CIVIL WORK
27 Elecrical works (8% of the civil works)
28 Plumbing works (8% of the civil work)
29 UNFORESEEN
GRAND TOTAL
(Rupees Seventeen Lakhs Only)

Page 9
Mr.Perera Augustine& Mrs.MiniAugustine at Adarsnagar
am Taluk,Thiruvananthapuram District.

Amount

1,000.00

14,070.00

29,886.00

791.10

82,341.00

47,982.00

Page 10
21,900.00

5,483.70

183,870.00

Page 11
37,634.00

17,118.00

6,360.00

92,400.00

21,560.00

214,800.00

13,500.00

Page 12
16,800.00

28,500.00

2,745.00

10,800.00
1,080.00

65,880.00

6,200.00

6,420.00

79,380.00

Page 13
11,862.40

1,138.50

3960
414

33,935.00

Page 14
3,584.70

29,655.60

5,022.50

10,400.00

1,336.50

14,400.00

10,784.00

Page 15
4,800.00

600.00

38,500.00

4,200.00

29,400.00
5,850.00

4,662.00

5,708.00

Page 16
73,170.00

11,846.50

20,098.00

9,900.00
8,850.00

13500.00

Page 17
4500.00

3480.00

720.00

17400.00

7500.00
750.00
8400.00

2419.30

1,411,247.80
112,899.82
112,899.82

1,637,047.45

Page 18
Detailed Estimate of Residencefor Mr. at Thiruvananthapuram
Taluk,Thiruvananthapuram District.
Sl.No. Description of work Qty Total Unit Rate Amount
1 SITE CLEARANCE
Clearing the site including labour charge, 1000.00 L.S 1,000.00
watering ramming, etc. complete
2 EARTH WORK
Earth work excavation in hard soil for
foundation and depositing on bank with
initial bed upto 50m and lift upto 1.50m
including breaking clods,watering,ramming
and sectioning of spoil bank etc. complete.

70.35 M3 200.00 14,070.00


3 PLAIN CEMENT CONCRETE
Cement concrete 1:4:8 using 40mm broken 8.79 M3 3,400.00 29,886.00
stone including watering labour charges,
curing etc.complete.

4 SAND FILLING 8.79 M3 90.00 791.10


5 RANDOM RUBBLE MASONRY
Random rubble masonry with hard stone in 39.21 M3 2,100.00 82,341.00
cement mortar 1:6, for retaining walls walls
in plinth and foundation including levelling
up with cement concrete 1:6:12
(a)FOUNDATION
(b) BASEMENT 21.81 M3 2,200.00 47,982.00
5 PLINTH BEAM
Reinforced cement concrete 1:2:4, for plinth 3.65 M3 6,000.00 21,900.00
beams using with 20mm nominal size
brockenstone including the cost of
centering and shuttering etc. complete.
6 EARTH FILLING
Filling the escavated earth for basement 60.93 M3 90.00 5,483.70
including labour charge, watering ramming,
etc. complete
7 BRICK WORK
Brick work in cement mortar 1:6 with
country burnt bricks as per the standard
specifications
A Ground floor 61.29 M3 3,000.00 183,870.00
B FIRST FLOOR 12.14 M3 3,100.00 37,634.00
Brick work in cement mortar 1:6 with
country burnt bricks for sunshade& parapet
wall as per the standard specifications

GROUND FLOOR ,sunshade 6.34 3,000.00 19,020.00


FIRST FLOOR,
2.12 3,000.00 6,360.00
WOOD WORK-DOORS

Supplying and fixing panelled doors shutter


frames with locking arrangements etc.in
country wood.
A GROUND FLOOR 16.80 m2 4,500.00 75,600.00
B FIRST FLOOR 3.92 m2 4,500.00 17,640.00
9 WOOD WORK-WINDOWS
Providing and fixing approved quality of
teakwood glazed Windows all fittings,locks
etc.complete. in country wood

A GROUND FLOOR 35.80 m2 4,000.00 143,200.00


B FIRST FLOOR 2.25 m2 4,000.00 9,000.00
Supplying and fixing in place MS grill work
with Square rods as per the specification
and drawings in all floors.
400.00 KG 42.00 16,800.00
10 REINFORCED CEMENT CONCRETE
Reinforced cement concrete 1:2:4, for
lintels & beam, using with 20mm nominal
size brockenstone including the cost of
centering and shuttering etc. complete.

A Ground floor-Lintel 4.75 M3 6,000.00 28,500.00


C First floor -Lintel 0.45 M3 6,100.00 2,745.00
11 REINFORCED CEMENT CONCRETE
RCC1:2:4,for sunshade and slab using
20mm nominal size brockenstone including
centering shuttering etc.

A GROUND FLOOR 1.80 M3 6,000.00 10,800.00


FIRST FLOOR 0.18 M3 6,000.00 1,080.00
12 REINFORCED CEMENT CONCRETE
RCC1:2:4,for FLATROOF using 20mm
nominal size brokenstone including
centering shuttering etc. complete.

A Ground floor 10.80 M3 6,100.00 65,880.00

B First floor 1.00 M3 6,200.00 6,200.00

RCC1:2:4,for staircase using 20mm


nominal size brokenstone including
centering shuttering etc. complete. 1.07 M3 6,000.00 6,420.00
14 REINFORCEMENT WORK
Reinforcement for all RCCwork like 1890.00 Kg 42.00 79,380.00
columns,beams,lintels,slab,etc.complete
including bending ,tying and placing in
position with binding wire as directed etc
complete.
15 PLASTERING SLABS
Plastering underside of Slab, etc.with
cement mortar 1:3,9mm thick,floated hard
and trowelled smooth including all cost of
material, labour, scaffolding curing etc
complete.

A Ground floor 107.84 M2 110.00 11,862.40


C FIRST FLOOR 9.90 M2 115.00 1,138.50
16 Sunshade Plastering
Plastering underside of sunshade etc.with
cement mortar 1:3,9mm thick,floated hard
and trowelled smooth including all cost of
material, labour, scaffolding curing etc
complete.
Ground floor 36 110 3960
First floor 3.6 115 414
Plastering with cement mortar1:5 inside
and sough finish 12mm thick wall to correct
line and plumb,curing ,etc.complete.

B Ground floor 339.35 M2 100.00 33,935.00


B First Floor 34.14 M2 105.00 3,584.70
Plastering with cement mortar1:5
outsidewall & parapet wall and sough finish
12mm thick wall to correct line and
plumb,curing ,etc.complete.
Ground floor 247.13 120.00 29,655.60
first floor
40.18 125.00 5,022.50
17 TWO COAT PLASTERING
Plastering Two Coats with Cement Mortar
1;4 12 mm thick over RCC portions.

A GROUND FLOOR 80.00 M2 130.00 10,400.00


B FIRST FLOOR 9.90 M2 135.00 1,336.50
Water proofing the roof slabs, floors of the
toilet, and wherever required as per
directions with approved quality (ROFFE or
equivalent) water proofing application two
coats and tested as per standard.
GROUND FLOOR 80.00 M2 180.00 14,400.00
18 FLOORING-P C C
Cement concrete 1:4:8 using 40mm broken
stone including watering labour charges,
curing etc
A Ground floor 107.84 M2 100.00 10,784.00
19 WHITE WASHING-SLABS
Providing newly plastered slab with water
proof cement paint and priming
coat,icluding one coat of cement washing,
all cost of materials,labour etc.complete.

A Ground floor. 120.00 m2 40.00 4,800.00


As per item no.15b
B FIRST FLOOR 15.00 m2 40.00 600.00
As per item no.15c
20 WALLS-PAINTING
Providing newly plastered internal walls
with quality emulsion of approved colour
(Nerolac/equivalent) after washing and
scraping including two coats putty over a
priming coat of cement primer
etc.complete.

A Ground floor 350.00 M2 110.00 38,500.00


As per item No.16b
B FIRST FLOOR 35.00 M2 120.00 4,200.00
As per item No.14c
21 Providing and finshing newly plastered
walls with exterior quality whether proof
emulsion paint, (Apex or Equilalent), as per
standard specification over a priming coat
on the exterior walls as per approved
colour.

GROUND FLOOR 245.00 M2 120.00 29,400.00


FIRST FLOOR 45.00 M2 130.00 5,850.00
PAINTING-ENAMEL

Providing two coats of first quality enamel


paint for doors,windows,grills,etc. over a
priming coat of metal of wooden primer,
filling the voids with putty etc.complete.
A GROUND FLOOR
As per item No 8a&9a 46.62 m2 100.00 4,662.00
B FIRST FLOOR
As per item No.8b&9b 57.08 m2 100.00 5,708.00
22 TILES-FLOORING
Providing flooring using approved quality
and type of ceramic tile for bedroom,toilet
and kitchen to line and level cutting joints
neatly pointing using compound and
wipping clean etc. complete.

A GROUND FLOOR 73.17 M2 1,000.00 73,170.00


B First floor 12.47 M2 950.00 11,846.50
23 WALL TILES
Providng glazed tiles of equivalent along
23
Providng glazed tiles of equivalent along
the walls of bathrooms,to a height of 2.1
m ,along the walls of kitchen and work area
finishing the joijnts with cement grout etc.
complete.
A GROUND FLOOR 30.92 M2 650.00 20,098.00
24 EXTERIOR TILES
Providing flooring using approved quality
and type of exterior Tiles to line and level
cutting joints neatly pointing using
compound and wipping clean etc.
complete.
A PORCH 18.00 M2 550.00 9,900.00
25 Supplying and fixing granite slab for kitchen 3.54 M2 2,500.00 8,850.00
top GROUND FLOOR
26 HAND RAILS
Providing Hand rails using M.S.Pipes and 7.50 RM 1800.00 13500.00
frames etc. complete for balcony and
staircases
Providing 8 mm groove work during the
course of plastering to the wall or RCC
surfaces including all cost of materials and
labour,etc.complete.
Ground floor 300.00 RM 15.00 4500.00
Providing 8 mm groove work for external
wall during the course of plastering to the
wall including all cost of materials and
labour,etc.complete.
Ground floor 232.00 15.00 3480.00
First floor 48.00 15.00 720.00
Providing cornice work for parapet wall
during the course of plastering including all
cost of materials and labour,etc.complete.

First floor 58.00 RM 300.00 17400.00


Providing cornice work for sunshade wall
during the course of plastering including all
cost of materials and labour,etc.complete.

Ground floor 30.00 RM 250.00 7500.00


First floor 3.00 RM 250.00 750.00
Supplying and fixing polycarbonsheet 18.61 M2 130.00 2419.30
including all materials and labour etc
complete
TOTAL CIVIL WORK 1,307,929.80
27 Elecrical works (8% of the civil works) 104,634.38
28 Plumbing works (8% of the civil work) 104,634.38
29 UNFORESEEN 2,801.43
GRAND TOTAL 1,520,000.00
( Rupees Fifteen Lakhs Twenty Thousand Only)