BILL OF QUANTITIES FOR NESCO EXIBITION HALL NO. 08


CIVIL WORKS Rev. - 2 DATE :- 1-11-2019

Date:- 23-11-2019
S.NO DESCRIPTION UNIT QUANTITY RATE AMOUNT Remarks

General Notes:
In case of any conflict between technical specifications and BOQ, the later shall prevail over the other for all the
items of BOQ
All rates shall be inclusive of maintenance of existing barricading works & yard lighting works as directed by
Engineer-in-charge whenever required.
All rates shall be inclusive of dewatering works for the area of construction as directed by Engineer-in-charge.

1.00 EARTH WORK


Excavation & carting away of excavated material outside site premises in all kinds of soil, soft rock,
(Manually/mechanically using JCB / Poclain) dense, wet or dry ( gravel or mixture of any kind etc.) clearing
shrubs, roots vegetation's from site, surface dressing in loose & slushy condition upto specified depth from given
surface for foundations, trenches, rafts of walls/columns,basements,plinthbeams, footings etc. including
levelling, all leads and lifts. Contractor to allow and fulfill obligations required towards fulfillment LEED Platinum
certification. The Contractor would include Clearing of shrubs, brushwood, small trees, Compound walls, fences,
road surfaces, gutters, curbs, random masonry, brick chambers etc all complete for clear and flat ground.The
Rates shall be inclusive of all Royalties, permissions from Local Statutory authorities and all fees payable for Quantity will be claimed as per Actual on
1.1 Cum 15250.00 915.00 1,39,53,750.00
carrying out the work. Rate to also include dewatering,bailing / pumping of water (wherever required) to keep Site.
the site dry at all times during excavation works in case of excess water well point dewatering need to be used,
making temporary stepping / sloping shoring, strutting, sectioning, trimming dressing etc. complete as directed
by the Project head. Mode of measurement will be working space of 600 mm from structure/footing face/ line,
further will not be considered for payment. Before & After execution the joint measurement has to be
completed.Mode of Measurements as per IS 1200.

Same as item (1) above but for HARD ROCK (unpoclanable) with the help of pneumatic breaker to any depth as Quantity will be claimed as per Actual on
1.2 Cum 1050.00 1076.00 11,29,800.00
required to levelled the excavated surface ready for laying foundation PCC. Site.

STERLING ENGINEERING CONSULTANCY SERVICES PVT LTD Page 1 of 13


NESCO

BILL OF QUANTITIES FOR NESCO EXIBITION HALL NO. 08


CIVIL WORKS Rev. - 2 DATE :- 1-11-2019

Date:- 23-11-2019
S.NO DESCRIPTION UNIT QUANTITY RATE AMOUNT Remarks

Back filling with selected earth behind retaining wall, ramp and wherever specified by Engineer in-charge up to
ground level with available approved granular soil / murrum at site / selected borrowed granular earth in layers
not exceeding 300mm thk with a lead of 150m including breaking clods, watering, compacting each layer with
Quantity will be claimed as per Actual on
1.3 vibratory compactor and in anaccessible place with wooden / steel rammers to achieve 90 to 95% proctor density Cum 8400.00 536.00 45,02,400.00
Site.
at optimum moisture content etc complete for all leads & depths etc complete as per specification & as directed
by Engineer-in-charge. The rates shall include conveyance of all materials, labour, machinery for all leads and
lifts.
Providing and laying inert material filling in plinth up to required depth including filling the interstices for binding, Quantity will be claimed as per Actual on
1.4 mechanical / manual compaction, spreading grit powder on top etc. complete as directed by EIC. Cum Q.R.O. 1055.00 - Site. (Basic Rate of material Considered is Rs
1400/- Brass)
Providing & laying compacted 230 mm thick dry rubble soling in plinth / plinth protection using hard stones
including breaking to required size & transportation to location of works, consolidating the same by ramming
with steel rammers or vibratory compactor including filling the interstices tightly with hand broken stone (metal
Quantity will be claimed as per Actual on
1.5 no. 4) and crush sand and blinding the top with 75 mm and down size stone chips to bring the top surface to Sqm 18100.00 727.00 1,31,58,700.00
Site.
even level including breaking large stones. Rate to include levelling and making up undulations in the base before
laying rubble packing and ramming, watering, consolidating and mechanical compaction to satisfaction of
Engineer In Charge.

Anti-termite
Anti - termite Treatment Soil treatment - Providing pre-constructional anti-termite treatment (As per IS-6313 II)
using approved chemical emulsifiable concentrate (Chlorpyrifos/ Imidacloprid 30.50 SC) supplied in sealed
containers, diluting in required approved proportions and injecting the same for treating bottom surface and
sides of excavation,backfill in immediate contact with foundation/footing/top surface of plinth filling(at the rate
1.8 of 5 litres of an emulsion concentrate of 1.0 percent of Chlorpyrifos 20 EC /at the rate of 5 litres of an emulsion Sq M 28900.00 91.00 26,29,900.00
concentrate of 0.075 percent of Imidacloprid 30.50 SC or equivalent approved chemical per sqm of the surface
area.) etc. complete as per EIC and Technical Specifications. The contractor shall furnish a guarantee for a
minimum period of ten years to maintain the treated area/structure free from termites. (Plan area at ground
floor level shall be measured for payment.)

TOTAL FOR EARTH WORKS 3,53,74,550.00

STERLING ENGINEERING CONSULTANCY SERVICES PVT LTD Page 2 of 13


NESCO

BILL OF QUANTITIES FOR NESCO EXIBITION HALL NO. 08


CIVIL WORKS Rev. - 2 DATE :- 1-11-2019

Date:- 23-11-2019
S.NO DESCRIPTION UNIT QUANTITY RATE AMOUNT Remarks

CONCRETE WORKS
2.00 PLAIN CEMENT CONCRETE
Notes:
Quoted rates shall be for all levels, lead and lifts, all locations, all shapes, sizes, thickness, as per drawings,
specifications and as directed by Engineer-in-charge.
Cement to be used shall be PPC confirming to IS 1489
Minimum Cement content to be used for PCC shall not be less than 250kg/m3 or as per IS 456 latest version.
Concrete to be used shall be design mix concrete (to be approved by consultant) manufactured in batching plant.

All works to be carried out as per IS standards. Unless noted otherwise measurements will be in accordance to IS
1200.
Quoted rate shall include for cost of materials, labour, loading and unloading charges, hire of machinery, tools &
plants, local dewatering if required, removal of slurry, fuel charges, transportation, scaffolding and all other
incidental charges etc., with all leads and lifts, complete and as directed by the Engineer-in-charge at all levels.

PCC:
Providing and laying ready mix plain cement concrete of grade M15 of min. 100 mm thickness below column
footing, basement raft, ramp, driveway etc. wherever required/specified including formwork sides, base
Quantity will be claimed as per Actual on
preparation, conveying (manually / mechanically) for all leads & depths, placing in position, compaction by
Site.
2.1 mechanical means, levelling & finishing of top surface, curing etc. complete all as per drawings, specifications and Cum 2300.00 6838.00 1,57,27,400.00
(Basic Rate of RMC considered is Rs 4900/-
as directed by EIC. Rate to include surface dressing of excavated surface upto 150mm depth including stacking &
Cum)
levelling of excavated earth/collapse earth within the site at disintegrated place. Dewatering of both ground &
surface water (Manually/Mechanical means) removal of sludge / slurry generated , keeping the area free of water
etc.

STERLING ENGINEERING CONSULTANCY SERVICES PVT LTD Page 3 of 13


NESCO

BILL OF QUANTITIES FOR NESCO EXIBITION HALL NO. 08


CIVIL WORKS Rev. - 2 DATE :- 1-11-2019

Date:- 23-11-2019
S.NO DESCRIPTION UNIT QUANTITY RATE AMOUNT Remarks

Plum Concrete:
Providing and laying plum concrete wherever required/ specified with ready mix concrete of grade M15 using
evenly distributed plums of basalt or trap (brought by contractor)of size 160mm & above upto any reasonable
size to a maximum limit of 40% of volume of concrete including base preparation, including necessary formwork,
Quantity will be claimed as per Actual on
supports, conveying (manually/mechanically) for all leads & depths, placing in position, mechanical compaction,
Site.
2.2 levelling, rough finishing of the top surface, curing etc. complete all as per approved construction drawings, Cum Q.R.O. 7338.00
(Basic Rate of RMC considered is Rs 5300/-
specifications and as directed by EIC. Rate to include surface dressing of excavated surface upto 150mm depth
Cum)
including stacking & levelling of excavated earth/collapse earth within the site at disintegrated place. Dewatering
of both ground & surface water (Manually/Mechanical means) removal of sludge / slurry generated , keeping the
area free of water etc.

TOTAL FOR PLAIN CEMENT CONCRETE 1,57,27,400.00

3.00 REINFORCED CEMENT CONCRETE

Notes:
1. The rate shall include cost of providing offsets, cutouts, pockets, construction joints & treament applying with
approved Polymer bond coat to construction joint & making holes in or cutting form work for taking out dowel
bars, hacking the exposed surfaces to receive plaster as necessary.
2. The rate shall includes cost of testing of all raw material of concrete as per the requirement of relivent I.S Code.
Q.R.O Means Quote Rate Only
3. Chemical Admixtures,wherever required, will be approved by EIC provided & used by contractor at no extra cost.
4. The rate includes concreting & finishing concrete surface with to give absoulate form finished concrete surface
with necessary grinding of edges & treatment to minor surface defects if any.
5.The rate includes cost of protecting newly placed Concrete from rain / heat with P V C sheet/ Tarpolin, marking
the date of concreteing locating area of debris.
Quoted rate shall include for cost of materials, labour, loading and unloading charges, hire of machinery, tools &
plants, shoring, strutting, dewatering, removal of slurry, fuel charges, transportation, scaffolding and all other
incidental charges etc., with all leads and lifts, complete and as directed by the EIC at all levels.
All works to be carried out as per IS standards. Unless noted otherwise, measurements will be in accordance to IS
1200.

STERLING ENGINEERING CONSULTANCY SERVICES PVT LTD Page 4 of 13


NESCO

BILL OF QUANTITIES FOR NESCO EXIBITION HALL NO. 08


CIVIL WORKS Rev. - 2 DATE :- 1-11-2019

Date:- 23-11-2019
S.NO DESCRIPTION UNIT QUANTITY RATE AMOUNT Remarks

Providing and laying ready mix concrete M30 in the following items at all levels and locations for structural
member including but not limited to footing, raft, stub columns, water tank, retaining wall, column, beam, slab,
deck slab, chajja, staircase waist slab, steps, pardis, lift shear wall etc including base preparation, conveying
(manually / mechanically) for all leads & depth, construction joint treatment, placing in position, compaction by
mechanical means, curing, levelling & finishing of top surface, staging & scaffolding for concreting, clearing the
area of debris and carting out of site, necessary struting and shoring for soil protection, supplying & laying cover (Basic Rate of RMC (M-30) Considered is
3.1
blocks of specified thickness , excluding cost of shuttering/ centering, reinforcement etc. complete all as per Rs5500/- Cum)
approved construction drawings, specifications and as directed by project incharge.
(Above item to include cost of all material ,labour and tools & machineries) etc. complete.

3.1.1 In Footings. Cum 1580.00 7938.00 1,25,42,040.00


3.1.2 In Columns. Cum 370.00 7998.00 29,59,260.00
3.1.3 In plinth beams. Cum 370.00 7976.00 29,51,120.00
3.1.4 In floor slabs. Cum 820.00 7998.00 65,58,360.00
3.1.5 In floor beams. Cum 720.00 7998.00 57,58,560.00
3.1.6 In stairs. Cum 70.00 7926.00 5,54,820.00
Quantity will be claimed as per Actual on
3.1.7 In Under ground tanks, S.T.P. & pipe and cable trenches Cum 1420.00 7966.00 1,13,11,720.00
Site.
3.1.8 RCC WALLS. Cum 160.00 7998.00 12,79,680.00
3.1.9 Slab on grade. Cum 3150.00 7998.00 2,51,93,700.00
3.1.10 RCC gutter Cum 110.00 7938.00 8,73,180.00

3.1.2 Extra over Item 3.1 for using M-40 grade concrete. All works in all levels. Cum Q.R.O. 1248.00

TOTAL FOR REINFORCED CEMENT CONCRETE 6,99,82,440.00

STERLING ENGINEERING CONSULTANCY SERVICES PVT LTD Page 5 of 13


NESCO

BILL OF QUANTITIES FOR NESCO EXIBITION HALL NO. 08


CIVIL WORKS Rev. - 2 DATE :- 1-11-2019

Date:- 23-11-2019
S.NO DESCRIPTION UNIT QUANTITY RATE AMOUNT Remarks

4.00 SHUTTERING WORKS


Notes:
Unless noted otherwise measurements will be in accordance to IS 1200.
Quoted rate shall include for cost of materials, labour, loading and unloading charges, hire of machinery, tools &
plants, fuel charges, transportation, scaffolding and all other incidental charges etc., with all leads and lifts,
complete, as directed by the Engineer-in-charge at all levels.
Providing and fixing shuttering with staging for all structural members including column,retaining wall,
raft,beams, ramp, pardi, tanks, staircase, chajjas,lintels and related works etc.. true to line & level to get good
finish concrete at all levels and places wherever needed /specified as per drawing using 12mm plastic coated
marine resistant waterproof ply with adjustable steel props / cuplock system with sufficient bracing as approved
by consultant / engineer-in-charge. Cost to include designing and installation of proper form work with staging
system to suit the structural strength of supporting members, submission of design calculations and shop
drawings for approval, sealing the joints with heavy duty brown self adhesive tape, aligning to line and levels Rates are quoted for Conventional
4.1
including MS ties with polythene sleeves, PVC Spacer, sacrificial tie rods for retaining walls, providing openings / Shuttering.
cutouts / pockets/PVC Sleeves of all diameters as specified, applying deshuttering chemical, fixing the electrical
dummy box, deshuttering as approved by the consultant, removing the polythene / PVC sleeves, grouting the
holes with non-shrink grout etc., complete. The rate quoted shall be for floor to floor height of up to 4.2m (
Design of Formwork, supporting system and staging to be provided by the contractor and approved by the
Consultant prior to commencement of work)
4.1.1 In Footings. Sqm 2470.00 935.00 23,09,450.00
4.1.2 In Columns. Sqm 2450.00 1234.00 30,23,300.00
4.1.3 In plinth beams. Sqm 2300.00 954.00 21,94,200.00
4.1.4 In floor slabs. Sqm 4950.00 1156.00 57,22,200.00
Quantity will be claimed as per Actual on
4.1.5 In floor beams. Sqm 4100.00 1019.00 41,77,900.00
Sqm
Site.
4.1.6 In stairs. 500.00 1084.00 5,42,000.00
4.1.7 In Under ground tanks, S.T.P. & pipe and cable trenches Sqm 7400.00 1084.00 80,21,600.00
4.1.8 RCC WALLS. Sqm 1580.00 1058.00 16,71,640.00
4.1.9 RCC GUTTERS Sqm 1000.00 1156.00 11,56,000.00

STERLING ENGINEERING CONSULTANCY SERVICES PVT LTD Page 6 of 13


NESCO

BILL OF QUANTITIES FOR NESCO EXIBITION HALL NO. 08


CIVIL WORKS Rev. - 2 DATE :- 1-11-2019

Date:- 23-11-2019
S.NO DESCRIPTION UNIT QUANTITY RATE AMOUNT Remarks

Extra over Item No. 4.1 for providing & erecting staging / making platform & removal of same after completion of
work with H frame or cup lock, wooden planks or MS plate including required bracing, labour, lifting shifting of
4.2 staging material for all leads & lifts etc. complete For height above 4.20 m upto 7.00 m ( Design of Formwork,
supporting system and staging to be provided by the contractor and approved by the Consultant prior to
commencement of work). MOM: Plan Area of slab
4.1.1 In Columns. Sqm 1100.00 408.00 4,48,800.00
Quantity will be claimed as per Actual on
4.1.2 In floor slabs. Sqm 3500.00 438.00 15,33,000.00
Sqm
Site.
4.1.3 In floor beams. 2950.00 438.00 12,92,100.00

TOTAL FOR SHUTTERING WORKS 3,20,92,190.00

STERLING ENGINEERING CONSULTANCY SERVICES PVT LTD Page 7 of 13


NESCO

BILL OF QUANTITIES FOR NESCO EXIBITION HALL NO. 08


CIVIL WORKS Rev. - 2 DATE :- 1-11-2019

Date:- 23-11-2019
S.NO DESCRIPTION UNIT QUANTITY RATE AMOUNT Remarks

5 REINFORCEMENT STEEL
Notes:
Reinforcement steel will be measured and certified for payment on actual BBS qty approved. Rolling margin shall
have to be established by the vendor through third party laboratory for every lot of supply and for each dia.
Quantity will be certified based on the rolling margin established at site, on first come first consumed basis.

Quoted rate shall include for cost of materials, labour, loading and unloading charges, hire of machinery, tools &
plants, dewatering, fuel charges, transportation, scaffolding and all other incidental charges etc., with all leads
and lifts, complete, preparation of BBS and as directed by the Engineer-in-charge at all levels.
5.1 Providing & Fixing of High yield deformed cut & bent bars ready to installed at site(ready made cut & bent steel brought to site) conforming
to IS 1786 with yield stress Fe 500 N/mm2 steel reinforcement. The rate for reinforcement bar shall include transporting, loading, unloading,
checking, sorting, storing, fabricating of all sizes, shapes as required for all members etc., wastage, cleaning, hoisting in position with all
necessary spacers, hangers, stools and chair supports, incidentals, sampling and testing as prescribed in IS codes including all charges
thereon for requisite tests, supervision and binding with 18 gauge approved quality GI Annealed binding wire whether or not shown on the
drawings. The measurement shall be as per IS 1200 and reinforcement hooks and bends shall comply with the requirement of IS 2502.The
rate shall include loading & unloading, approved quality Astra make cover blocks or Concrete cover blocks of same grade as structural
member , binding wire, chairs, spacers and pins to be provided as per specifications and will not be measured separately for payment.
Quantity of steel as per structural drawing, approved BBS and with authorized overlaps only shall be measured and paid for for all diameters
for all kinds of works at all heights, depths & leads. Consumption will be actual BBS followed by site execution only .The rolling margin shall (Basic Rate of Steel Reinforcement
be on Contractor's own cost. The rate also includes testing as per IS, protecting the reinforcing bars – in their virgin form or in the fabricated considered is Rs 45000/-MT)
form, or when placed and tied up in position or as dowels left for future continuation of work or at construction joint – against corrosion due
to exposure to weather if left exposed and un-encased for more than three weeks from the date of delivery to the site.Cement wash shall be
given to such bars if they are likely to be exposed for more that three weeks and less than twelve weeks. Process of applicatin of cement
slurry shall be repeated after every twelve weeks if the exposure period is stretched . the rate shall also include necessary welding with prior
approval of consultant the same shall not be paid extra, welding of reinforecement shall be with low hydrogen, low heat welding electrodes
for the welding lenght mentioned in the drawing in place of coventional laps whereever recommended. All works to be carried as per
instructions of PM/EIC. All the main reinforcement bars in column/vertical members, and other members as directed with diameter 16mm
and above shall be necessarily spliced using Type II parallel threaded cold forged couplers (make Dextra, multitech splicing or equivalent
approved make) shall be paid in relevant item.
Quantity will be claimed as per Actual on
5.1.1 At all levels M.T 850.00 70493.00 5,99,19,050.00
Site.

TOTAL FOR REINFORCEMENT STEEL 5,99,19,050.00

STERLING ENGINEERING CONSULTANCY SERVICES PVT LTD Page 8 of 13


NESCO

BILL OF QUANTITIES FOR NESCO EXIBITION HALL NO. 08


CIVIL WORKS Rev. - 2 DATE :- 1-11-2019

Date:- 23-11-2019
S.NO DESCRIPTION UNIT QUANTITY RATE AMOUNT Remarks

6 STRUCTURAL STEEL WORKS


Notes:
Structural steel will be measured based on actual qty placed in position on standard weight basis, no allowance
will be made for rolling margin.
Structural steel will be measured based on the approved shop drawing as prepared by contractor and no
allowance will be made for wastage, weld weights & fasteners.
Quoted rate shall include for cost of materials, labour, loading and unloading charges, hire of machinery, tools &
plants, dewatering, fuel charges, transportation, scaffolding and all other incidental charges etc., with all leads
and lifts, complete and as directed by the Engineer-in-charge at all levels.
6.1 Supplying, fabricating, transporting, hoisting and erecting in position hot rolled structural steel / Tubular steel
sections of rectangular/square etc.members of all type of sections of approved make for portal frame,columns,
beams, plate girders, lattice girders, trusses, purlins, stairs etc., at all locations, levels and heights including
providing and fixing bolts, nuts,welds, washers, angles, channels, joists of various sizes and other structural
elements including cutting, welding, bending to shape, bolting, cleaning the rust and scales to the satisfaction
ofEngineer-in-charge. Rate to include cost of all materials, labourers, tools and tackles, cranes, staging and
scaffolding, devices for erection, shims, non shrink grout and packing pieces which will be required for levelling of
the work. All fabricated structures shall receive one coat of approved quality primer over etching primer at shop
as per specifications and two coats of approved quality finishing paint as per specifications after assembly and
erection. The rate shall include cost of loading and unloading, transportation and all other incidental charges
etc., with all leads and lifts, complete and as directed by the Engineer-in-charge at all levels.

6.1.1 A) EXHIBITION HALL


Tubular Structural elements confirming to latest IS 4923 - Grade Yst310 N/mm2 At all levels -
6.1.1.1 A-1-Portal Frame M.T 430.00 N.A N.A
6.1.1.3 A-2-Steel work in roof M.T 540.00 N.A N.A
6.1.1.4 A-3-Side Cladding--Intermediate columns, wind trusses - Type 'P' & 'Q' M.T 140.00 N.A N.A

Structural elements confirming to latest IS 2062 - Grade Fe-250 At all levels N.A N.A
6.1.1.5 A-4-steel work for side runners and Hanger columns M.T 50.00 N.A N.A

STERLING ENGINEERING CONSULTANCY SERVICES PVT LTD Page 9 of 13


NESCO

BILL OF QUANTITIES FOR NESCO EXIBITION HALL NO. 08


CIVIL WORKS Rev. - 2 DATE :- 1-11-2019

Date:- 23-11-2019
S.NO DESCRIPTION UNIT QUANTITY RATE AMOUNT Remarks

6.1.2 B) Steel work in Annexes adjacent to main Exhibition Hall


Tubular Structural elements confirming to latest IS 4923 - Grade Yst310 N/mm2 At all levels N.A N.A
6.1.2.1 B-1-Steel work in roof over Annexes M.T 110.00 N.A N.A
Structural elements confirming to latest IS 2062 - Grade Fe-250 At all levels N.A N.A
6.1.2.2 B-2-Miscellaneous steel in Brackets and Gutters M.T 40.00 N.A N.A
6.2 Additional for applicaton of fire-proofing material such as spray applied cementitius vermiculite etc. as approved M.T N.A N.A
to achieve minimum 2 hour fire ratings at all locations and levels as specified by EIC 1310.00

6.3 Additional for applicaton of fire-proofing material such as Intumescent paint etc. to achieve minimum 2 hour fire M.T N.A N.A
1310.00
ratings at all locations and levels as specified by Engineer-in-charge

TOTAL FOR STRUCTURAL STEEL N.A

STERLING ENGINEERING CONSULTANCY SERVICES PVT LTD Page 10 of 13


NESCO

BILL OF QUANTITIES FOR NESCO EXIBITION HALL NO. 08


CIVIL WORKS Rev. - 2 DATE :- 1-11-2019

Date:- 23-11-2019
S.NO DESCRIPTION UNIT QUANTITY RATE AMOUNT Remarks

7.0 MISCELLANEOUS
Notes:
Structural steel will be measured based on actual qty placed in position on standard weight basis, no allowance will be
made for rolling margin.
Structural steel will be measured based on the approved shop drawing and no allowance will be made for wastage, weld
weights & fasteners.
Quoted rate shall include for cost of materials, labour, loading and unloading charges, hire of machinery, tools & plants,
dewatering, fuel charges, transportation, scaffolding and all other incidental charges etc., with all leads and lifts,
complete and as directed by the Engineer-in-charge at all levels.
Supplying, fabricating, transporting, hoisting, erecting & installing in position Mild steel insert plates, column protection
edge angles, pipe etc. in concrete or in masonry, flush with surface with necessary hold fasts etc. complete including
7.1 surface preparation by manual wire brushing method, labour, scaffolding, tools & plants, loading and unloading charges, MT 5.00 N.A N.A
welding, devices for erection, finishing, all other incidental charges, etc. complete with lead & lifts at all levels and as
directed by Engineer-in-charge
Supplying, fabricating and errecting miscelleneous structural steel work in ladders, platforms,chequred plate grating
etc.complete as per the drawing. The rate shall be inclusive of application of one coat of zinc chromate primer of approved
7.2 manufacturer and color as per the specifications, cost of materials, labour, tools & plant, consumables, leads and lifts at all MT 10.00 N.A N.A
levels, loading and unloading charges, transportation, scaffolding, all other incidental charges, etc. complete and as
directed by Engineer-in-charge
Providing and fixing , G.I puddle flange for water tank 450mm long,as per IS :1239 (Class C), threaded on both side and
7.3 6mm thick M.S. plate 150mm wide and welded alround the pipe and totally hot dip galvanized as per detail complete in all Q.R.O.
respects.
7.3.1 80 mm dia (Screwed) Nos Q.R.O.
7.3.2 100 mm dia (Flanged) Nos Q.R.O.
7.3.3 150 mm dia (Flanged ) Nos Q.R.O.
7.3.4 200 mm dia (Flanged) Nos Q.R.O.

7.40
Providing & placing PVC pipe sleeves in situ concrete of required length in slabs and beams for fire fighting
conduits or electrical cables as required by Engineer -incharge
7.4.1 75mm dia & 230 - 450 mm long. Nos. Q.R.O. 550.00
7.4.2 100mm dia & 230 - 450 mm long. Nos. Q.R.O. 700.00
7.4.3 150mm dia & 230 - 450 mm long. Nos. Q.R.O. 1050.00
7.4.4 200mm dia & 230 - 450 mm long. Nos. Q.R.O. 1450.00
TOTAL FOR MISCELLANEOUS -

STERLING ENGINEERING CONSULTANCY SERVICES PVT LTD Page 11 of 13


NESCO

BILL OF QUANTITIES FOR NESCO EXIBITION HALL NO. 08


CIVIL WORKS Rev. - 2 DATE :- 1-11-2019

Date:- 23-11-2019
S.NO DESCRIPTION UNIT QUANTITY RATE AMOUNT Remarks

8.0 PRECAST CONCRETE COVERS


Supplying, casting, lifting ,trasporting and placing in place precast concrete trench covers Cum 160.00 - Size, thickness & other details required.

9.0 ANCHORING SYSTEM

9.1 Mechanical Anchoring System


Supplying and providing Mechanical medium duty stud anchors HST type of approved make HILTI or equivalent
for insert plate fixing, column jacketing and staircase fixing etc. which is approved for shock load. The anchor
should be cold formed carbon steel anchor, A4, Galvanised/Stainless steel externally threaded and consists of 3
part expansion sleeve. The installation and the setting instructions should be strictly followed as per the
manufacturers recommendations.
The rate shall include for cost of materials, labour, loading and unloading, transportation, scaffolding and all
other incidental charges etc., with all leads and lifts, complete and as directed by the Engineer-in-charge at all
levels (This item will be paid only in case specific instruction for installing the same is mentioned in the GFC.)

9.1.1 HST M12X115/20 Nos Q.R.O. N.A N.A


9.1.2 HST M16X140/25 Nos Q.R.O. N.A N.A
9.1.3 HST M20X170/30 Nos Q.R.O. N.A N.A
9.1.4 HST M24X200/30 Nos Q.R.O. N.A N.A

9.2 Chemical Anchoring System


Supplying, drilling and providing medium to heavy duty injection adhesive for fixing in Dry conditions with HY 150
for dia 12mm to 40mm of approved make HILTI or equivlent for anchoring the bars ,insert plate fixing and
machinary. The system should be made of two foils consisting of resin and Hardener foil pack. The system can be
used for threaded rods. The installation and the setting instructions should be strictly followed as per the
manufacturers recommendations.
The rate shall include for cost of materials, wastages, labour, loading and unloading, transportation,
scaffolding and all other incidental charges etc., with all leads and lifts, complete and as directed by the
Engineer-in-charge at all levels (This item will be paid only in case specific instruction for installing the same is
mentioned in the GFC.)
9.2.1 10 dia Nos Q.R.O. 230.00
9.2.2 12 dia Nos Q.R.O. 270.00
9.2.3 16 dia Nos Q.R.O. 590.00
9.2.4 20 dia Nos Q.R.O. 980.00
9.2.5 25 dia Nos Q.R.O. 1350.00
9.2.6 32 dia Nos Q.R.O. 2350.00
9.2.7 40 dia Nos Q.R.O.

TOTAL FOR ANCHORING SYSTEM

STERLING ENGINEERING CONSULTANCY SERVICES PVT LTD Page 12 of 13


NESCO

BILL OF QUANTITIES FOR NESCO EXIBITION HALL NO. 08


CIVIL WORKS Rev. - 2 DATE :- 1-11-2019

Date:- 23-11-2019
S.NO DESCRIPTION UNIT QUANTITY RATE AMOUNT Remarks

10.0 WATERPROOFING WORKS

Cleaning the water tank & STP floor with Wire Brushes & scrappers.
Opening the Constructions joints & visible cracks in “V” grooves.
Providing & Filling “MC Expacrete” in the cracks & joints. Applying 2
coats of Dichtament DS2 on the floor @ comsunption of 2.3 Kgs / m2.
10.13 Water proofing treatment at bottom of the water tanks and S.T.P. as per Architect specification. SQ.M 580.00 1056.00 6,12,480.00 While the 2nd coat is still green applying a chhat coat of CM 1:4.
Providing & laying screed of avg 40mm thickness on the floor of
Proportion1:3:2 ( Cement:Sand:10mm metal) admixed with
“Dichtament DM”

Cleaning the external faces of the walls of the water tank & STP with
Wire Brushes & scrappers. Opening the Constructions joints & visible
cracks in “V” grooves. Providing & Filling “MC Expacrete” in the
10.2 Water proofing treatment to external faces of the walls of water tanks and S.T.P. as per Architect's specification. SQ.M 950.00 924.00 8,77,800.00 cracks & joints. Applying 2 coats of Dichtament DS2 on the floor @
comsunption of 2.3 Kgs / m2. While the 2nd coat is still green applying
a chhat coat of CM 1:4. Providing & applying a waterproof Plaster of
avg 20mm thickness on the walls CM 1:4 admixed with “Dichtament
DM”

Cleaning the internal faces of the walls & Top of the base slab of the
water tank with Wire Brushes & scrappers. Opening the Constructions
joints & visible cracks in “V” grooves. Providing & Filling “MC
Expacrete” in the cracks & joints. Applying 2 coats of Dichtament DS2
10.3 Water proofing treatment to internal faces of the walls and top of base slab of water tanks as per Architect's specification. SQ.M 1160.00 957.00 11,10,120.00 on the floor @ comsunption of 2.3 Kgs / m2. While the 2nd coat is still
green applying a chhat coat of CM 1:4. Providing & applying a
waterproof Plaster of avg 20mm thickness on the walls CM 1:4
admixed with “Dichtament DM” on the internal faces of th walls.
Providing & laying a screed of proportion 1:3:2 (Cement:Sand:10mm
metal) and of avg 40mm thickness, admixed with “Dichtament DM”
on the top od the base slab of Water tanks

10.4 Water proofing treatment to internal faces of the walls and top of base slab of S.T.P. as per Architect's specification. SQ.M 1050.00 957.00 10,04,850.00 Same Process as mentioned in above point

Total for water proofing 36,05,250.00

TOTAL AMOUNT ₹ 21,67,00,880.00