Documente Academic
Documente Profesional
Documente Cultură
8 kV
MAA SUBSTATION, DAVAO CITY”
(REVISION 2)
A TECHNICAL REPORT
PRESENTED TO
THE PROFESSIONAL REGULATORY
BOARD OF ELECTRICAL ENGINEERING
SUBMITTED BY:
REE xxxxxx
AUGUST 2016
LETTER OF TRANSMITTAL
Dear Sirs:
I wish to thank my family and Joan Bab, for their constant support,
patience and understanding. Also, I wish to thank my bosses and
colleagues in LIGHT, especially to Engr. Reynold Felix, Engr.
COVER LETTER i
LETTER OF TRANSMITTAL ii
LETTER OF TER APPROVAL iii
PREFACE iv
TABLE OF CONTENTS vi
LIST OF FIGURES ix
LIST OF TABLES xii
EXECUTIVE SUMMARY xvii
CHAPTER 1: INTRODUCTION 1
1.1 Background 1
1.2 Objectives of the Technical Report 4
1.3 Scope and Limitations 5
1.4 Significance of the Study 5
1.5 Conceptual Framework 7
CHAPTER 2: SUBSTATION DESIGN CONSIDERATIONS 8
2.1 The Role of a Substation in the Power System 8
2.2 Types of Distribution System 9
2.3 Energy Regulatory Commission 11
2.4 Performance Based Regulation 12
2.5 Philippine Distribution Code 12
2.6 Philippine Electrical Code 13
2.7 Distribution Planning 14
2.8 Load Forecasting 15
2.9 Transformer 15
2.10 Circuit Breaker 16
2.11 69 kV Bus Design 18
2.12 Protection System 18
2.13 Characteristics of the Relay 20
2.14 Overcurrent Relay 21
PEE 1 262
PEE 2 264
PEE 3 266
The 33-MVA Maa substation’s 13.8 kV bus had a short circuit current
calculated approximately as 9,683 A caused by single-line-to-ground
fault and 2,766.56 A for three-phase fault at 69 kV bus, both were
generated by Davao Line 1 source where it is connected. The resulting
fault currents for single-line-to-ground and three-phase have been
the basis of the rating of the other major electrical equipment such
as the circuit breaker.
On the other hand, the proposed protection system for the substation
satisfied the basic requirements in the protection design. The selected
CT ratios to be used by the protective devices were having equivalent
knee-point voltages way above from the calculated knee-point
voltages and adequate to sustain maximum short circuit currents
without CT saturation. The 13.8 kV feeders are protected by
overcurrent relays and its calculated settings were maintained to
coordinate with respect to upstream and downstream overcurrent
protective devices.
CHAPTER 1
INTRODUCTION
1.1. Background
Distribution systems provide a very important role in the power
system since it is the main channel of sending the usable power to
the consumers. It is a complex system composed of different
equipment and devices that are linked together to deliver power to
customers. Since electricity is an essential commodity to the
economy, its absence for a short period of time creates discomfort in
everybody’s life. It gets worse if the unscheduled power interruption
is caused by equipment failures in the power system which takes
some time before it gets repaired and restored. Moreover, with the
increasing demand on the use of electricity, any failure in the
substation components is not acceptable to the customers as well as
to the utility owner.
Under the Philippine Distribution Code (PDC), the Distribution utilities
(DU) are mandated to provide reliable and quality power for the
customers. Thus, power distribution planners and designers are
challenged to increase system performance and continuously look for
ways to improve reliability.
From then on, with the knowledge gained from advanced power
system protection training, and exposure in handling protection
issues and problems; the protection engineers were able to solve and
provide solutions to the challenges. Comprehensive audit and review
on protection system and its coordination is done periodically based
on the company’s protection philosophy. Setting recommendations
and modifications are also given and implemented when required.
Substation Rating
Bangkal 12 MVA
Matina 25 MVA
Ecoland 33 MVA
Table 1.1 presents the City South substations existing rating. The
loading of the existing substation will be evaluated if it can still carry
additional load in anticipation of the fast growth in the area.
connected in the city south area. The author would like to present
this technical report to design the 33MVA 69/13.8 kV Maa Substation
in Davao City.
CHAPTER 2
SUBSTATION DESIGN CONSIDERATIONS
Under PBR, the proposed projects, especially the major CAPEX, are
submitted to regulators for evaluation and approval if found efficient.
It should be emphasized that not all projects submitted were
approved due to lack of justifications and possible large increase in
the electricity rates.
2.9. Transformer
Faults can occur in any component in the electrical system and it can
be caused by bad weather, equipment failure, vegetation contact and
public contact. All of these causes create disturbance to the system,
thus protective systems are applied to sense short circuit conditions
and clear faults without false tripping which limits the interruption to
the faulted line or equipment only.
Calculations of the system fault currents are done through the use of
symmetrical components method. Symmetrical components are a
mathematical tool used to calculate the effects of balanced and
unbalanced fault conditions on three-phase distribution system. The
tools for computing can be manually done, but for large power system
such as for LIGHT and Power Company, it uses a software (ETAP
14.0) to model the three-phase power system impedance
characteristics, and calculate short circuit currents.
Speed refers to the ability of the relay to operate in the required time
period. Speed is important in clearing a fault since it has a direct
effect on the damage done by the short circuit current to the
The maximum current that the power transformer and conductor can
carry and withstand is defined by their I2t characteristic. Maximum
currents maybe described as overload and short circuit current where
the equipment reaches its damage point. The overcurrent relay in a
predetermined setting must be able to protect and cut-off the
People often assume that any grounded object can be safely touched.
A low substation ground resistance is not a guarantee of safety. There
is no simple relation between the resistance of the ground system as
a whole and the maximum shock current to which a person might be
exposed. Therefore, a substation of relatively low ground resistance
may be dangerous while another substation with very high resistance
may be safe or can be made safe by careful design.
In either case, the effect of that portion of fault current that enters
the earth within the substation area should be further analyzed. If
the geometry, location of ground electrodes, local soil characteristics,
and other factors contribute to an excessive potential gradient at the
earth’s surface, the grounding system may be inadequate despite its
capacity to carry the fault current in magnitudes and durations
permitted by protective relays.
There are many indices for measuring reliability. The three most
common are referred to as SAIFI, SAIDI, and CAIDI, defined in IEEE
Standard 1366). System Average Interruption Frequency Index
(SAIFI) is the average frequency of sustained interruptions per
customer over a predefined area. It is the total number of customer
interruptions divided by the total number of customers served.
defined in IEEE Std. 1366 as those that result from each single
operation of an interrupting device such as a recloser.
CHAPTER 3
METHODOLOGY
This chapter presents the methodology used in this technical report.
Simple regression (SR) was used in the forecasting. The 5% > MAPE
criteria was used based on the Electric Cooperatives Distribution
Utility Planning Manual.
The planning criteria for Normal and N-1 Loading of overhead lines
must be equal or less than 100% of line capacity. Likewise,
Transformers must be loaded less than or equal to its 100% of its
maximum rating. If substation transformers is loaded more than
90%, then it is categorized in critical loading and will be considered
for upgrading of substation or capacity addition where the load center
is located.
The base values were selected and other values were calculated.
Typical base power use is 100 MVA and for base voltage, the nominal
voltage rating of the system was chosen. The base currents and base
impedance were calculated. Afterwards, sequence impedances of
source, sub-transmission and distribution line, transformer and
feeders were calculated and converted to new base values. Carson’s
equation was used to determine the zero sequence impedance of the
overhead lines. After converting all impedances to its new bases, the
sequence impedance diagram was drawn.
The PDC and PBR required DU to comply the voltage standard. For
69 kV system, voltage must be ±5 % of the nominal voltage.
However, for 13.8 kV system, the voltage must be ±10 % of the
nominal voltage.
The ladder iterative technique was used in this analysis. The single
phase loads of 2016 to 2025 were calculated and converted to per
unit. The loads of nearby substations that are connected to the same
source were lumped to their respective tapping point in the 69 kV
line. The longest feeder was modelled separately using the exact
lumped method. The farthest end and other feeder loads of the
substation were lumped at the 13.8 kV bus of the Maa substation.
3.11. Optimization
The data of conductors were gathered and prepared. Using the
conductor resistance, determine the losses caused by 8760 hours of
load, at the input load factor, with variable peak load transmitted
1km along each conductor. Also compute the power delivered at the
conductor’s thermal limit. Compute the Present Value (PV) of the
losses.
CHAPTER 4
ELECTRICAL CALCULATIONS
In this chapter, the detailed calculations in forecasting, system
modeling, short circuit calculation, power transformer specification,
69 kV circuit breaker justification, assessment of current
transformers; and overcurrent protection setting and coordination of
the 33 MVA 69kV/13.8 kV Maa substation are discussed, described,
illustrated, and presented in tabular and graphical forms.
Demand (MW)
Year
Bangkal Matina Ecoland Davao Line 1
2008 7.633 11.450 21.091 40.175
2009 8.872 10.411 22.664 41.947
2010 9.291 11.855 22.967 44.113
2011 7.583 14.131 26.164 47.877
2012 9.872 13.773 25.321 48.966
2013 8.442 12.492 24.262 45.197
2014 9.724 13.545 25.556 48.825
4.1.3. Method
Demand data for the past 7 years was prepared. The simple
regression forecast method and double exponential smoothing
were used to determine the fitted values for the initialization of
data set. Then, the forecast technique with the lowest MAPE was
used to forecast the test data set and determine the forecast
errors. The errors were evaluated using Mean Square Error (MSE),
Mean Absolute Deviation (MAD) and Mean Absolute Percentage
Error (MAPE).
Formula:
Forecast = B0 + (B1 x Z)
ΣY − (B1 x ΣZ)
B0 =
n
SSZY
B1 =
SSZZ
ΣZxΣY
SSZY = ΣZY −
n
(ΣZ)2
SSZZ = ΣZ2 −
n
Data
Year Z Y Z2 ZY
(MW)
2008 40.175 1 40.175 1 40.175
2009 41.947 2 41.947 4 83.894
2010 44.113 3 44.113 9 132.339
2011 47.877 4 47.877 16 191.509
2012 48.966 5 48.966 25 244.832
2013 45.197 6 45.197 36 271.183
2014 48.825 7 48.825 49 341.776
Total 28 317.101 140 1,305.708
Z2014 = 7
Y2014 = 317.701
Z22014 = 72 = 49
ZY2014 = 7 x 48.825 = 341.776
SSZY = Σ ZY – [(Σ Z x Σ Y) / n]
SSZY = 1,305.708 – [(28 x 317.101) / 7]
SSZY = 37.304
B1 = SSZY / SSZZ
B1 = 37.304 / 28
B1 = 1.332
ΣY − (B1 x ΣZ)
B0 =
n
317.101 − (1.332 x 28)
B0 =
7
B0 = 39.971
MAD = Σ│Error│/ n
MAD = 10.113 / 7
MAD = 1.445
MAPE = Σ APE / n
MAPE = 22.02% / 7
MAPE = 3.15%
Note, MAPE should not exceed 5% based on Electric
Cooperatives Distribution Utility Planning Manual (2009),
chapter 2, page 13.
Forecast Formula:
Source:http://cms3.minitab.co.kr/board/minitab_data/5.%20
StatisicsAllTopics.pdf (Statistics, page 230)
Ft = Level t-1 + p1 x Trend t-1
Level t2 = Smooth t2
where:
Ft = forecast value at time t
p = time period
B0 = 39.971 (derived in method 1)
B1 = 1.332 (derived in method 1)
Level t = Level at time t
Trend t = Trend at time t
Smooth t = same as Trend t
Fits = Fitted Value or one-step ahead forecast
α = alpha is weight for the level, use=0.5
β = weight for the trend, use = 0.1
= 1.272
Fitst2 = Forecastt2= Levelt-1 + Trendt-1
= 40.739 + 1.276 = 349,681
Table 4.1.7: 2008 to 2014 Smooth, Level, Trend, and Fits values
Year Data Z Smooth Level Trend Forecast
(MW) (Fits)
2008 40.175 1 40.739 40.739 1.276
2009 41.947 2 41.981 41.981 1.272 42.015
2010 44.113 3 43.683 43.683 1.315 43.253
2011 47.877 4 46.438 46.438 1.459 44.999
2012 48.966 5 48.432 48.432 1.513 47.897
2013 45.197 6 47.571 47.571 1.275 49.945
2014 48.825 7 48.836 48.836 1.274 48.846
Period Forecast
Year
(p) (MW)
2015 1 50.110
2016 2 51.385
2017 3 52.659
2018 4 53.933
2019 5 55.208
2020 6 56.482
2021 7 57.757
2022 8 59.031
2023 9 60.305
2024 10 61.580
2025 11 62.854
2026 12 64.129
2027 13 65.403
2028 14 66.677
2029 15 67.952
It can be shown from the tables above that the 12 MVA Bangkal
Substation and 33 MVA Ecoland Substation are already in a
overloaded in terms of loading since 2009 if the 70% loading limit
applied. Although the 25 MVA Matina Substation is still capable of
accommodating slight load transfers within the city south cluster.
Formula:
Substation Loading of Bangkal Substation in 2029
= Demand2029 /Capacity Rating at 70% Loading Limit
= 13.108 / 7.98 = 164.26%
Formula:
Unserved Demand (kW) = Annual Forecasted Demand - Capacity
Rating at 70% Loading Limit
Total Unserved Demand = Unserved demand for the cluster
= Unserved demand for Bangkal Substation
+ Unserved demand for Matina Substation
+ Unserved demand for Ecoland Substation
From Table 4.1.19, it can initially be noted that the 33MVA size of
the new Maa Substation power transformer is within the 70%
loading reached in the 10 years planning horizon (16.30 MW
In this study, three contingency scenarios are run: the first is when
Bangkal Substation goes out due to failure or maintenance, second
is when Matina Substation goes out due to failure or maintenance
and lastly when Ecoland Substation goes out with the same reason
as above.
It can be noted from this scenario that in the city south cluster
when Matina Substation is out due to failure or during
maintenance shutdown, Maa Substation will reach the established
full loading criteria (70% of rated FA2 capacity) by 2017.
Formula:
LossYEAR = LossPREVIOUS YEAR – ((LossPREVIOUS YEAR - No load loss) x load
growth (%))
Energy Sales benefitYEAR = Loss x 24 hours x 365 days x load
growth
Sample computations:
For 2016,
Loss2016 = 87 – ((87 - 19.65) x 0.2636) = 69.25
Energy Sales benefit2016 = 69.25 x 24 x 365 x 0.55
= 333,630 kWh
Considering the utility's distribution charge of Php 1.73/kWh,
Energy Sales benefit2016 = 366,630 x 1.73 = Php 634,269.90
Sample Computation:
Annual Energy Sales2017 (in Php) = Unserved Energy (MWh)
* 1000
Formula:
Straight Line Depreciation = Asset Cost / Asset Life in Years
Reference: Accounting Tools at http://accountingtools.com/
straight-line-depreciation
Sample Computations:
Depreciation Cost SITE DEVELOPMENT = 12,254,400 / 40 = P 306,360
E. Operating Cost
Formula:
NPV = Initial Cash Outlay + FV1 (1+K)-1 + FV2 (1+K)-2 +
FV3 (1+K)-3 +...+ FVn (1+K)-n
where
NPV = Net Present Value
FV1 = Operating Cash Flow at Period 1
FV2 = Operating Cash Flow at Period 2
FV3 = Operating Cash Flow at Period 3
FVn = Operating Cash Flow at Period n
K = interest rate of return
= assumed at 12%
Initial Cash Outlay = Project Cost
It should be noted in the equation that the future values (FV) are
the operating cash flow as a result of the project as defined in the
equations below.
D12=D23=7 ft D13=14 ft
D12=D23=7 ft D13=14 ft
B. For 69 kV System:
Vbase-LL = 69 kV
Zbase = kV2base-LL / Sbase-3φ
Zbase = 692 / 100 = 47.61 ohms
Ibase = Sbase-3φ x 1000 / (√3 x kVbase-LL)
Ibase = 100 x 1000 / (√3 x 69) = 836.76 A
D. Summary of Bases:
Base Values
X
tan Ɵ =
R
V
IL−L = √3I1F = √3 ( )(IBase )
Z 1F +Z2F
√3 (IBase )
Z2 = ( ) − Z1
IL−L
V
ISLG = 3I1F = 3 ( )I
Z1 + Z2 + Z0 Base
where: V=10, thus;
3(IBase )
Z0 = ( ) − Z1 − Z2
ISLG
5.5334
tan Ɵ =
0.77066
Ɵ = 82.07o
√3 (IBase ) √3(836.76)
Z2 = ( ) − Z1 = ( ) − 0.117
IL−L 6193.55
Z2 = 0.117 82.07o p.u.
Z2 = 0.01614 + j 0.11588
Source Z1 Z2 Z0
Z1 = Z2 = Ri + jXi; ohm/mi
Xi = 2fL
GMD
L = 2 x 10−7 ln GMRij
i
Z1
Z1 (p. u. ) = Z2 (p. u. ) =
ZBase
where:
R1 = conductor resistance per length, ohm/mi
GMRi = Geometric Mean Radius, ft
GMDij = Geometric Mean Distance, ft
= (D12 x D23 x D13)1/3
GMDij
Z1 = Z2 = R1 + j 0.12132 ln
GMRi
8.819
= 0.1288 + j 0.12132 ln
0.0375
ohm
= 0.1288 + j 0.6624
mi
ohm 1 mi
= (0.1288 + j 0.6624) ( )
mi 1.609 km
ohm
= (0.080 + j 0.4117) (10.15 km)
km
1 p.u.
= (0.812 + j 4.17876)ohm ( )
47.61 ohm
Z1 = Z2 = 0.01705 + j0.08777 p. u.
GMDij
Z1 = Z2 = R1 + j 0.12132 ln
GMRi
8.819
Z1 = Z2 = 0.1288 + j 0.12132 ln
0.0375
ohm
Z1 = Z2 = 0.1288 + j 0.06624
mi
ohm 1 mi
Z1 = Z2 = (0.1288 + j 0.06624) ( )
mi 1.609 km
ohm
Z1 = Z2 = (0.080 + j 0.4117) (1.92 km)
km
1 p. u.
Z1 = Z2 = (0.15360 + j 0.79046)ohm ( )
47.61 ohm
Z1 = Z2 = 0.00322 + j0.01659 p. u.
GMDij
Z1 = Z2 = R1 + j 0.12132 ln
GMRi
8.819
Z1 = Z2 = 0.1288 + j 0.12132 ln
0.0375
ohm
Z1 = Z2 = 0.1288 + j 0.06624
mi
ohm 1 mi
Z1 = Z2 = (0.1288 + j 0.06624) ( )
mi 1.609 km
ohm
Z1 = Z2 = (0.080 + j 0.4117)
km
Z1 = Z2 = 0.00591 + j0.03044 p. u.
Z1 = Z2 = 0.01243 + j0.064p. u.
ohm
Z1 = Z2 = 0.306 + j 0.61694
mi
ohm 1 mi
Z1 = Z2 = (0.306 + j 0.61694) ( )
mi 1.609 km
ohm
Z1 = Z2 = (0.19018 + j 0.38343)
km
1 p. u.
Z1 = Z2 = (0.67514 + j 1.36118)ohm ( )
1.90 ohm
Z1 = Z2 = 0.35534 + j0.71641 p. u.
1 p. u.
Z1 = Z2 = (0.55342 + j 1.11578)ohm ( )
1.90 ohm
Z1 = Z2 = 0.29128 + j0.58725 p. u.
1 p. u.
Z1 = Z2 = (0.71508 + j 1.44170)ohm ( )
1.90 ohm
Z1 = Z2 = 0.37636 + j0.75879 p. u.
Z1 = Z2 = 0.25324 + j0.51058 p. u.
Z1 = Z2 = 0.17616 + j0.35517 p. u.
Z1 = Z2 = 0.20319 + j0.40966 p. u.
(Zin )2
Z0 = Zii + 2Zij − 3
Znn
= (0.2241 + j 1.25171) + 2(0.0953 + j 0.6984) − 3 (−0.080
+ j 0.08209)
ohm
= 0.6547 + j 2.40224
mi
ohm 1 mi
= (0.6547 + j 2.40224) ( )
mi 1.609 km
ohm
= (0.40689 + j 1.4930) (10.15 km)
km
1 p.u.
= (4.12993 + j 15.15395)ohm ( )
47.61 ohm
Z0 = 0.08674 + j0.31829 p. u.
2
Zin −0.38885 + j0.12023
=
Znn 3.1553 + j1.71117
2
Zin ohm
= −0.07926 + j 0.08108
Znn mi
(Zin )2
Z0 = Zii + 2Zij − 3
Znn
ohm
Z0 = (0.40552 + j 1.49489) (1.92 km)
km
1 p.u.
Z0 = (0.77860 + j 2.87019)ohm ( )
47.61 ohm
Z0 = 0.01635 + j0.06029 p. u.
(Zin )2
Z0 = Zii + 2Zij − 3
Znn
Z0 = (0.2241 + j 1.25171) + 2(0.0953 + j 0.6984) − 3 (−0.080
+ j 0.08209)
ohm
Z0 = 0.6547 + j 2.40224
mi
ohm 1 mi
Z0 = (0.6547 + j 2.40224) ( )
mi 1.609 km
ohm
Z0 = (0.40689 + j 1.4930) (7.72 km)
km
Z0 = 0.03008 + j0.11038 p. u.
Z0 = 0.06316 + j0.23174 p. u.
2
Zin −0.50383 + j0.13650
=
Znn 0.6873 + j1.54622
2
Zin ohm
= −0.04723 + j 0.30485
Znn mi
(Zin )2
Z0 = Zii + 2Zij − 3
Znn
= (0.4013 + j 1.30385) + 2(0.0953 + j 0.79609) − 3 (−0.04723
+ j 0.30485)
ohm
= 0.73359 + j 1.98148
mi
ohm 1 mi
= (0.73359 + j 1.98148) ( )
mi 1.609 km
ohm
= (0.45593 + j 1.23149)
km
Z0 = 0.85187 + j2.30094 p. u.
Z0 = 0.69829 + j1.88612 p. u.
Z0 = 0.90226 + j2.43705p. u.
Z0 = 0.60711 + j1.63982 p. u.
Z0 = 0.42233 + j1.14075 p. u.
Z0 = 0.48712 + j1.31575 p. u.
Ztransformer j 0.232
Ztransformer j 0.232
Ztransformer j 0.232
Z1F = 0.3024580.21o pu
j 0.06400 + j 0.232
Z2F = 0.05153 + j 0.53009
Z2F = 0.53259 84.45o pu
Formula:
ISLG = 3 x I1F = 3 x [V / (Z1F + Z2F + Z0F)] p.u.
ISLG = 3 x I1F = 3 x [V / (Z1F + Z2F + Z0F)] x Ibase A
where:
V = prefault voltage, 10° pu
Z1F = positive sequence thevenin’s impedance, pu
Z2F = negative sequence thevenin’s impedance, pu
Z0F = zero sequence thevenin’s impedance, pu
Z0F = j 0.232
Z0F = 0.232 90o pu
Formula:
I1F = V / (Z1F + (Z2FZ0F/(Z2F + Z0F)) p.u.
I0F = (- I1F (Z2F))/ (Z2F + Z0F)
IDLG = 3I0F x IBase A
where:
V = prefault voltage, 10° pu
Z1F = positive sequence thevenin’s impedance, pu
Z2F = negative sequence thevenin’s impedance, pu
Z0F = zero sequence thevenin’s impedance, p
j 0.23174
Z0F = 0.18305 + j 0.70901
Z0F = 0.73226 75.52o pu
1 0o
I1F =
(−0.20192 + j0.09110)
(0.05143 + j 0.29805) +
(0.23458 + j 1.0071)
Z1F = 0.5325384.45o pu
Z0F = j 0.232
Z0F = 0.232 90o pu
1 0o
I1F =
(−0.12299 + j 0.01195)
(0.05143 + j 0.53005) +
(0.05153 + j 0.76209)
I1F = 0.11662 − j 1.43613
I1F = 1.441 − 85.36o pu
1 0o
I1F =
(−1.11908 + j 0.68643)
(0.22759 + j 0.88522) +
(0.65002 + j 2.25801)
A. Rating
Three Phase 20/26/33 MVA with OA/FA1/FA2 type
suitable for outdoor installation.
B. Frequency
60 Hz is used as this is the standard frequency in the
Philippines.
C. Impedance
8.12 %
D. Primary Voltage / Secondary Voltage
67 kV/13.8 kV
E. Basic Insulation Level (BIL) Primary/Secondary
350 kV/110 kV
F. Primary Connection
Delta
G. Secondary Connection
WYE with Neutral brought to a bushing and connected to
a copper conductor equivalent to 4/0 AWG Cu for
grounding
H. Polarity /Vector Group
Dyn1 (30 Deg. Angular displacement)
I. Insulating Fluid
Mineral Oil. The oil will have the properties specified in
CNS 3070 and CNS 1326 or IEC 296 or JIS C2320 No. 2.
J. Sound Level
70 dB @ 33MVA full load capacity.
K. Winding Temperature Rise
65 oC
L. Oil Temperature Rise
65 oC
M. Tap-changer
On-Load Tap Changer - Maschinefabrik Reinhausen (MR)
A. Core
The core of the transformer will be constructed of the highest
quality, non-aging high permeability, cold-rolled gain-
oriented silicon steel sheet especially suitable for the
purpose. Every care will be taken during slitting and cutting
process to avoid burrs. Both sides of each sheet will be
special glass film insulated on to minimize eddy current
losses. The cores will be carefully assembled and rigidly
clamped to ensure adequate mechanical strength to support
the windings and also reduced vibration to minimum under
operating conditions.
B. Winding Characteristics
The winding for the transformer shall be made of high tensile
strength electrolytic copper of high conductivity (Class A, in
accordance with ANSI) and insulation, material of high
quality shall be free from burrs.
The insulation material of windings and connections shall not
shrink, soften or collapse during service. Thermally
upgraded paper shall be used for conductor insulation. The
design, construction and treatment of windings shall give
proper consideration to all service factors, such as high
dielectric and mechanical strength of insulation, coil
characteristics, uniform electrostatic flux distribution,
prevention of corona formation, and minimum restriction to
oil flow.
Adequate barriers shall be provided between windings and
core as well as between high voltage and low voltage
windings. All leads or bars from the windings to the terminal
boxes and bushings shall be rigidly supported.
E. Overload Capability
The short-time overload rating and operation of the
transformer shall be in accordance with ANSI C57.92 or IEC
354. All other auxiliary equipment (bushings, CT's, etc)
affected shall be rated to match the transformer overload
rating.
F. Transformer Tanks
The tank should have sufficient strength to withstand full
vacuum and internal pressure of 1.0 kg/cm2, with cooling
equipment & conservator connected. The tank cover will be
clamped with bolts and nuts, and will be provided with
G. Bushing Assembly
High Voltage Side – ABB model: GOB 325/800LF123027-K
72.5 kV, 800 Amps, 350 kV BIL, Creepage Distance:
1980mm, Condenser type with 1 unit bushing for spare. Test
tap should be provided for each unit.
Low Voltage Side - 2000 Amps, 15.5 kV, 110 kV BIL with 1
unit bushing for spare, Creepage Distance: 400mm. Test tap
should be provided for each unit.
H. Cooling Systems
The transformer will be provided with sets of radiators for
self-cooled (OA) operation with equal sets on both side of
the tank. The radiator will be installed on the tank via
radiator valves, so that each radiator can be detached from
the tank independently of the oil in the main tank. The
radiator valves will have the open and close positions clearly
marked. Radiators will be equipped with provisions for
draining. Radiators shall be made of galvanized steel. For
future forced-air-cooled operation, transformer must have
cooling-fans mounting provision on the radiators and its
control box.
I. Forced-air-cooling system
For forced-air-cooled (FA) operation, the transformer will be
provided with automatically controlled three phase motor-
fans actuated from winding temperature. The cooling-fans
will be mounted on the radiators and the control box will be
mounted on the wall of the tank. Motor voltage should be
230 VAC, 3 phase, 60 Hz. Every cooling fan should have a
separate circuit breaker.
J. Gaskets
The gaskets shall be compatible for the insulating fluid in the
transformer tank. Metal surfaces to which gaskets are
applied shall be smooth and shall have sufficient rigidity to
assure proper compression of the gaskets.
K. Grounding Provisions
All non-energized metallic components of the transformer
shall be grounded. Tank grounding provisions shall consist
of two ground pads, welded to the base or to the tank wall
near the base on diagonal corners. The ground pads shall
be copper-faced or stainless steel with two holes spaced
horizontally at 1.75-inch centers and tapped for 0.5 inch 13-
UNC tread.
L. Wiring
All devices mounted on the transformer, including current
transformer secondary circuits, shall be wired to the control
cabinet.
All control wiring shall be a minimum of #14 AWG SIS and
#12 AWG for current transformers. Wiring between gauges
and the control box can be #14 AWG SO cable.
M. Painting
The standard finish will consist of one rust resisting primary
coat and two finish coats of paint. The paint will be applied
after the steel surface had been thoroughly cleaned by shot
blasting and treated with rust inhibitor. The color of the final
coat for transformer will be ANSI 70 light gray.
O. Nameplates
Transformer shall be furnished with a non-corrosive
diagrammatic nameplate, permanently attached with non-
corrosive hardware. The diagrammatic nameplate shall
include the name of the manufacturer of the equipment as
well as the location where the transformer was
manufactured and tested.
The nameplate shall contain all connection and rating
information in accordance with ANSI C57.12.00 nameplate
P. Accessories
1. Dial type oil level indicator with contacts for alarm
2. Oil temperature indicator and relay type AKM OTI series
34, with alarm & trip contacts; AKM OTI remote mount
thermometers remote output: current loops: 4 to 20mA
; Resistive Pt 100
3. Two (2) winding temperature indicators and relays for
HV and LV windings, with three (3) contacts each for
alarm, tripping & fan control, AKM type WTI series 35;
AKM WTI remote mount thermometers
4. Pressure Relief Device with Trip contact (Qualitrol, self
resealing type)
5. Buchholz relay with alarm and trip contacts
R1 = 0.05143
B. Single-Line-to-Ground Fault
X/R = (0.29805 + 0.29809 + 0.70901)/
(0.05143 + 0.05153 + 0.18305)
X/R = 4.56330
Since both are less than 17, then the 40 kA rating of the
breaker is adequate.
These values are way lower than the 108 kA peak for the
specification of the breaker.
Figure 4.5.6 : One Line Diagram showing Major Electrical Equipment (69 kV Side)
A. Current Transformers
A.1. 69 kV Overcurrent Relay (OCR) CTs: (proposed)
2-sets 2000:5 A Multi-tap, C-400, Bushing Current
Transformer, 72.5 kV, 400 VA Burden,
Relaying Class, Available Taps: 2000A, 1600A, 1500A,
1200A, 1100A, 800A, 500A, 400A, 300A.
B. Protective Relays
B.1. 69 kV OCR: (proposed)
1-unit SEL-751A, 5A current input, <0.1 VA burden per
phase, 24-48 Vdc / 110-250 Vac power supply
CT TAP CT RATIO
LOCATION RELAY CLASS
(to be used) (Full Tap)
69 kV 400:5 A
SEL 751 A 2000:5 A C400
(50/51) X1:X2
Transformer
1500:5 A
Neutral SEL 787 2000:5 A C400
X3:X5
(51G)
B. CT Winding Resistance
The following values of winding resistance of CT used in the
calculation are based on the test results from Omicron CPC-100
equipment. To simplify, the values presented are the maximum
winding resistances for which the protective devices are
connected.
1. Bushing Current Transformers of 69kV SF6 Circuit Breaker
(for
50/51)
Tap – 400:5 A
Winding Resistance = 0.181 ohm
C. Relay Burden
The VA burden of relay to be used is based on the relay manual
and the resistance being derived using the secondary of 5A.
The load of the relay current elements was also accounted.
1. 69 kV 50P/51P & 50N/51N:
Relay Model: SEL-751A
VA Burden: 0.1 at 5A
RR-751A = VA / A2 = 0.1 / 52
RR-751A = 0.004 ohm
RR-751 = VA / A2 = 0.1 / 52
RR-751 = 0.004 ohm
4. 13.8 kV 51G:
Relay Model: SEL-787 (neutral element only will be
used)
VA Burden: 0.1 at 5A
RR-787 = VA / A2 = 0.1 / 52
RR-787 = 0.004 ohm
A. Connected Resistance/Load
A.1. 69 kV Overcurrent Relay: 50P/51P & 50N/51N
RL_69kV-751A = 0.51148 ohm
RCT = 0.181ohm
RR-751A = 0.004 ohm
VS = IF x (RCT + RL + RRELAY)
= (7,856.36 /300) x (0.254+ 0.12114 + 0.004)
= 9.932V
VK > 2VS = 2 x 9.932
VK = 19.863 V
For SLG fault current = 9,683 A
CTR to use = 1500:5 = 300
VS = IF x (RCT + 2RL + RRELAY)
= (9,683/300) x (0.3+ (2 x 0.12114) + 0.004)
= 17.63 V
VK > 2VS = 2 x 17.63
VK = 35.26 V
VK = 99.013 V
69 kV 400:5 A
56.947 1,878.53 SLG C400
(50/51) X1:X2
13.8 kV 1500:5
Main A 35.26 9,683 SLG C400
(50/51) X3:X5
13.8 kV
600:5 A
Feeder 99.013 9,683 SLG C400
X1:X2
(50/51)
Transformer 1500:5
Neutral A 104.96 9,683 SLG C400
(51G) X3:X5
Setting Calculation
The calculated short circuit currents were used in the relay setting
calculation.
A. Lateral Fuse
The total clearing time must be determined first when a
short circuit current occurs for both 3-P and SLG faults at
the load side of the fuse. These fuses are usually located
along the distribution lines. The nearest lateral fuse is
located 183 meters away from the substation. It is
necessary to refer the minimum melting time and clearing
time characteristic curves of Type K fuse to be used from the
fuse manufacturer. (100A Type K Fuse, AB Chance)
At Three-Phase Fault = 7,856.36 A
Clearing Time (tFCT-3P) = 0.015 s (for 100K fuse, from AB
Chance TCC Curve)
Setting:
Pick-Up Current = 100% x Line Capacity
Setting:
Pick-Up Current = 100% x Line Capacity
Set Pick-Up Current =530 A (336.4 ACSR=530 A)
= 530/CTR = 530/120= 4.42A
Setting:
Pick-Up Current = 100% x Transformer Full Load Current
(FA2 Rating) @ 13.8 kV side
Set Pick-Up Current =1,381 A
= 1,381/CTR = 1,381/300= 4.6 A
Setting:
Pick-Up Current = 100% x Transformer Full Load Current
(FA2 Rating) @ 67 kV side
where:
Transformer Normal Full Load Current is the current
at Oil-immersed, self-cooled (OA) rating.
Setting:
Pick-Up Current = 50% x Line Capacity
Set Pick-Up Current = 265 A (0.5 x 530 A)
= 265/CTR= 265/2000 = 0.1325 A
Since the recloser is the last protective device for this feeder,
we choose the lowest time dial available which is 0.05 to
allow easy adjustment of the CTI in the future if additional
reclosers will be installed along the feeder.
Use TD = 0.05
Top = TD x (13.5 / (M – 1))
Top = 0.05 x (13.5 / ((3,846.13/265) – 1))
Top = 0.05 s
Setting:
Pick-Up Current = 50% x Line Capacity
Set Pick-Up Current = 265 A (0.5 x 530 A)
= 265/CTR= 265/120 = 2.21A
IEC VI Formula:
Top = TD x (13.5 / (M – 1))
where:
M = multiples of pick-up current
= IF / Pick-up
TD = 0.25
Setting:
Pick-Up Current = 35% x Transformer Full Load Current
(FA2 Rating) @ 13.8 kV side
IEC VI Formula:
Top = TD x (13.5 / (M – 1))
where:
M = multiples of pick-up current
= IF / Pick-up
Setting:
Pick-Up Current = 30% - 50% x Transformer’s FLA at
13.8kV
Set Pick-Up Current = 0.35 x 1,381
= 480/CTR
= 480/300 = 1.6 A
Information:
CTR = 400:5 = 80
SLG Fault = 1,878.53 A (at 69kV bus)
Setting:
Pick-Up Current = 30%-50% x 69 kV-51P
Set Pick-Up Current = 0.50 x 284 = 142 A
Equipment Data
At the primary side (69kV)
2-units SF6 Circuit Breaker, Alstom, Type DT1-72.5FK F1, 72.5
kV , 2000 A, 40 kAIC
The 90% limit of fault duty to kAIC rating is set as guideline by ERC
Resolution 17 (resolution adopting the investor-owned electric
distribution planning manual, Section 3.4 under Safety Analysis.
A. Design Data
I base
I0
X1 X 2 X 0
Therefore,
I1F = [IBASE / (Z1F + Z2F + Z0F)]
I1F = [4,183.82/ (0.246 + 0.246 + 0.246)]
I1F = 5,669.13 A
ISLG = 3 x I1F = 3 x 5,669.13 = 17,007.4 A
If infinite bus = 17,007.4 A
Akcmil I f K f t c
= 84.18 kcmil
= 42.56 mm2
d 2
Amm 2
4
d = 7.36 mm required diameter
k
IB
ts
where
IB = rms magnitude of the current thru the
body in amps
ts = duration of the current exposure in
seconds
= equivalent to the fault clearing time, 0.5 sec
k= constant related to electric shock energy
Estep ( RB 2R f ) * I B
Rf
Etouch ( RB )* IB
2
9276
E touch (1000 ) * 0.164
2
Etouch = 925 volts Touch Potential Limit
A = 1,530 m2
h = 0.65 m
LT = 1,172 m
1 1 1
Rg 1
LT 20 A 1 h 20 / A
Figure 4.6.2
Km Ki IG
Em
LT
1 D2 ( D 2 * h) 2 h K ii 8
Km ln * ln
2 * 16 * h * d 8* D * d 4 * d Kh (2 * n 1)
h
Kh 1
h0
h0 = 1 m (grid reference depth)
0.65
Kh 1
1.0
Kh = 1.285
n = na * nb * nc * nd
where na = 2*Lc / Lp
= 2*(1,172/220)
na = 10.65
Ki = 0.644 + 0.148 n
= 0.644 + 0.148 (10.65)
Ki = 2.22
Solving for Km
1 42 (4 + (2 ∗ 0.65))2 0.65 1
𝐾𝑚 = [𝑙𝑛 [ + − ]+
2 16(0.65)(0.01168) (8 ∗ 4 ∗ 0.01168) (4 ∗ 0.01168) 1.285
8
∗ 𝑙𝑛 [ ]]
((2 ∗ 10.65) − 1)
Km = 0.71
Km Ki IG
Em
LT
16.78 ∗ 0.71∗ 2.22 ∗ 11,905.18
𝐸𝑚 =
1,172
Em = 268.66 Volts
K s Ki I G
Es
Ls
1 1 1 1
Ks (1 0.5n2 )
2h D h D
1 1 1 1
𝐾𝑠 = [ + (4+0.65) + (1 − 0.5(10.65−2) )]
2∗0.65 4
Ks = 0.3926
K s Ki I G
Es
Ls
Es = 148.56 Volts
Comparing the Design Step Voltage (Es) with the Step Potential
(EStep), where EStep = 3,207 V and Es = 148.56 V, it can be seen that
Es < EStep. The design, therefore, passes the step potential test.
The procedure done in this section proves that the design using the
criteria below is acceptable and will provide safety of personnel and
equipment within the substation area. The design further provides
for future expansion of the substation and growth in the distribution
network of LIGHT within the cluster where Maa Substation is
connected.
Formula:
SAIFI = Total Number of Customer Interruptions per year
Total Number of Customers Served
SAIDI = Customer Interruption Durations in hours per year
Total Number of Customers Served
CAIDI = SAIDI in hours per interruption
SAIFI
The calculations for arc flash analysis are based on IEEE Std 1584-
2002 and are summarized into the succeeding steps.
Ia = 10 log Ia
where
log = log 10
Ia = 10 log Ia
Ia = 10 0.43836
Ia = 2.7438 kA
Ia = 10 log Ia
Ia = 10 0.885
Ia = 7.656 kA
where
E = incident energy (cal/cm2)
t = arcing time (seconds)
D = distance from the possible arc point to the
person (mm)
= assumed at 750 mm
Ibf = bolted fault current for 3-phase fault (kA)
V = system voltage
The arcing time t is the clearing time for the source-side protecting
device that clears the fault first.
where:
En = is the incident energy (cal/cm2) normalized for time
and distance
Ia = arcing fault current (kA)
G = gap between conductors in mm (see table 4.13.1)
K1 = is -0.792 for open configurations
Solving for E,
E = 5.12 x 105 V Ibf (t/D2)
E = (5.12 x 105) (69) (2.766) (0.06/7502)
E = 10.42 cal/cm2
Solving for E,
log En = K1 + K2 + 1.081log Ia + 0.0011G
log En = -0.555 + (-0.113) + 1.081log 7.656 + 0.0011(153)
log En = 2.857
t 610x
E = Cf En ( )( )
0.2 Dx
0.06 6100.973
E = (1)(2.857)( )( )
0.2 (750)0.973
E = 0.70 cal/cm2
t
DB 5.12x105VI bf
B
E
where
DB = distance of the boundary from the arcing point
(mm)
Ibf = bolted fault current for three phase fault (kA)
V = system voltage (kV)
EB = incident energy in cal/cm2 at the boundary
Distance
On the other hand, the following formula is used for locations with
voltages 15 kV and below.
1
t 610x x
DB = [Cf En ( )( )]
0.2 EB
t
DB 5.12x105VI bf
EB
0.06
DB = √(5.12 x 105 )(69)(2.766)( )
1.2
DB = 2,210.4 mm
DB = 431.64 mm
Figure 4.14.1 illustrates the impedance diagram with the single phase
loads of Bangkal, Matina and Ecoland substation. The model was used
to simulate the effects of the existing and future loads of the power
system.
B. Bangkal (S1), Matina (S2) and Ecoland (S3) complex power were
obtained.
C. Maa substation loads were allocated to S4, S5, and S6. Feeder 1,
Feeder 2 and Feeder 4 loads (S4) were lumped at the main 13.8
kV bus with a percent allocation of 62.36%, while the remaining
37.64% loads was allocated to the longest feeder, Feeder 3. The
allocation factor was determined using the actual average loading
per feeders.
Feeder 3 loads (S5 and S6) were determined using the exact lumped
method. S5 and S6 is 2/3 and 1/3 of the longest feeder total load and
loads were lumped at ¼ and ¾ of total feeder length respectively.
ZLine9 = 1/4 (ZLine7) ZLine10 = 3/4 (ZLine7)
D. The loads were then converted to per unit using a 100 MVA base.
Iteration 1:
Set V6 = 10O
Calculate current at node 6:
I6 = (S6/V6) = (0.008951 - j0.00294) / 10O
I6 = 0.008951 - j0.00294
V5 = (I6 x ZLine10) + V6
V5 = (0.008951 - j0.00294)(0.28227 + j 0.5691) + 10O
V5 = 1.0042 + j0.00426
V4 = ((I4-5) x ZLine9)+ V5
V4 = ((0.02675 – j0.00887) x (0.09409 + j0.18969))
+ 1.0042 + j0.00426
V4 = 1.00840 + j0.00850
V2 = (I2-3 (ZLine3) + V3
V2 = (0.14198 - j0.04944)(0.00591 + j0.0304) +
(1.0163 + j0.02915)
V2 = 1.01865 + j0.03317
V1 = (I1-2 x ZLine2 ) + V2
V1 = (0.19574 - j0.06907)(0.00322 + j0 .0166) +
(1.01865 + j0.03317)
V1 = 1.02043 + j0.03620
I1 = (S1/V1)
I1 = (0.0266 - j0.00874) / (1.02043 + j0.03620)
I1 = 0.02573 - j0.00948
IS = I1-2 + I1
VS = (IS (ZLine1)) + V1
VS = (0.22147 - j0.07855)(0.01705 + j0.0878) +
(1.02043 + j0.03620)
VS = 1.03110 + j0.05430
V2 = V1 - (I1-2 x ZLine2 )
V2 = (0.98932 - j0.01809) - (0.19574 - j0.06907)
(0.00322 + j0.0166)
V2 = 0.98755 - j0.02112
V3 = V2 - (I2-3 (ZLine3)
V5 = V4 - ((I4-5) x ZLine9)
V5 = (0.97730 – j0.04579) - (0.02675 – j0.00887)
(0.09409 + j0.18969)
V5 = 0.97309 – j0.05003
V6 = V5 - (I6 x ZLine10)
V6 = (0.97309 – j0.05003) - (0.008951 - j0.00294)
(0.28227 + j 0.5691)
V6 = 0.96889 – j0.05430
│V6│= │0.96889 – j0.05430│ = 0.97041 p.u.
where:
MAPt = this year’s price per unit of electricity
MAPt-1 = previous year’s price per unit of electricity
CWIt = index of change in consumer prices (60% CPI) and
also US dollar/Philippine peso exchange rate
(40% Exchange)
X = efficiency of smoothing factor
St = service performance incentive factor
Kt = correction for revenue over or under recovery in
previous year
ITAt = correction for tax over or under recovery in
previous year
where
ARRt = allowed annual revenue for Regulatory year t
FQt = total amount of energy (kWh) that is forecasted to be
delivered to Connection Points through the Regulated
Distribution System during Regulatory year t, with the
forecast as approved by the ERC
CHAPTER 5
SUMMARY OF FINDINGS, CONCLUSIONS AND
RECOMMENDATIONS
11. Based on the calculations, the limits of the step and touch
voltage is 3,207 volts and 925 volts respectively. The grounding
system design used in Maa substation had a resulting step and
touch voltage of 148.56 volts and 268.66 volts respectively.
12. The average SAIFI, SAIDI and CAIDI of the city south cluster
are 0.2238, 0.00471 and 3.25804 respectively. It passed the PBR
criteria where the performance of the city south cluster is as per
expectation.
13. The arcing current of the 69 kV bus is 2.7438 kA and for the
13.8 kV bus is 7.656 kA when arc flash analysis is conducted. The
incident energy at the 69 kV bus is 10.42 cal/cm2 while for the
13.8 kV bus is 0.70 cal/cm2. Lastly, the flash boundary at the 69
kV breaker is 2,210.4 mm while for the 13.8 kV switchgear is
431.64 mm.
14. The farthest end of the substation feeder will have a receiving
voltage of 98.65% in 2016 and will become 97.3% in 2029. This
is within the limits set by the Philippine Distribution Code (PDC).
5.2. Conclusions
Based on the findings, the following conclusions are formulated:
1. An additional 33 MVA capacity for Maa substation is needed in
order to cater the future loads in the city south area without
overloading all the existing substations connected to Davao
Line 1.
2. The construction of a new substation in the city south area is a
good investment for the company as shown in the results of the
financial economic analysis where it will have a net present
value of P164,742,773.
3. The 33-MVA Maa substation’s 69 kV bus had a maximum short
circuit current calculated as 2,766.56 A for three phase fault
and 9,683 A caused by single-line-to-ground fault at the 13.8
kV bus, both were generated by Davao Line 1 source where it
is connected. Thus, it was safe to use the maximum short
circuit currents for power transformer and 69 kV circuit breaker
11. The target SAIFI. SAIDI and CAIDI must always be achieved in
order for the utility to avail the incentives as determined by PBR
for maintaining or improving the system indices within the
acceptable level.
12. Copper grounding rods are needed in order to satisfy the design
mesh voltage of the substation grounding system design. The
touch and step potential test will fail if copper rods will not be
installed in the substation.
13. The current SAIFI, SAIDI and CAIDI of the city south cluster is
within the limit set by PBR as its performance is as expected.
The construction of the Maa Substation should help improve the
system indices of LIGHT.
14. The arc flash analysis conducted is very relevant in order to
secure the safety of the personnel where we can determine the
appropriate suit to be purchased for personnel working at live
conditions and the flash boundary where unprotected personnel
can stay.
15. The receiving voltage of the customers is enough and will not
cause an undervoltage condition in the farthest end of the
substation.
5.3. Recommendations
After a careful review of the findings and conclusions of the technical
report, the following recommendations were drawn:
1. A new 33 MVA power transformer with the specifications in
chapter 4 should be purchased for the new Maa substation.
2. The short circuit interrupting current of the new 2 units - 69 kV
circuit breaker should be 40 kA.
3. The design of the 69 kV bus and steel structure must be
followed to secure that all electrical equipment are safe and has
no capacity constraint for future load growth.
breaker can also be used for the 13.8 kV switchgear thus there
is no further need to purchase a suit rated for the 13.8 kV
incident energy.
IEEE. (2000). IEEE Std C37.06-2000, IEEE Guide for AC High Voltage
Circuit Breakers Rated. New York, USA: Institute of Electrical and
Electronics Engineers, Inc.
IEEE. (2000). IEEE Std C37.91-2000, IEEE Guide for Protective Relay
Applications to Power Transformers. New York, USA: Institute of
Electrical and Electronics Engineers, Inc.
cdfafsdfd
adasfdfdfdsfdsfdsfd fdsfdsfdsfd
dfdfsdfdsf
fsdfsdf ffsdff
fsdfsdfds
ffsdfdsf ffsdsdf
I. PERSONAL
Date of Birth
Age
Sex
Height
Weight
Place of Birth
Nationality
Civil Status
Profession
Home Address
Homes
Contact Number
Email Address
Company
Designation
Office Address
Phone
Recommends
technical
specifications of
overcurrent, and
transformer
differential relays.
Conducts short
circuit study and
analysis
Conducts Post-Fault
Analysis
January June Planning and Project Engineer of
2014 2015 Design several substation
Engineer projects who
Substation monitors the
Section - project progress,
Power Systems running cost,
Design material usage and
Department manpower
LIGHT and requirements.
Power Serves as the
Company Quality Assurance
Inc. Engineer on the
Davao City activities included
in the project.
Creates the design
for substation
Electrical Works