Review Forgemaster Heat Treatment Procedure (H) Not in QCP SOS4592212 Buccioni
(MPE tbc)
# Proposed furnace loading diagram ® Not in QCP SOS4592212 Buccioni
(MPE tbc)
# Heat Treatment Operations - Quench (W), Temper (W) Not in QCP SOS4592212 Buccioni
start and finish, Stress Relieve (W) (MPE tbc)
start and finish.
# Prolongation Removal (H) and Stamping. Not in QCP SOS4592212 Bruno Paoni (
# Mechanical testing and any stamp transfer (H). Not in QCP SOS4592212 Bruno Paoni (
Company require a pre-production meeting (PPM) at the Not in QCP SOS4592212 Bruno Paoni (
forgemaster prior to forging
operations (H)
# Inspection certificates shall be supplied in accordance with Not in QCP SOS4592212 Buccioni tbc
ISO 10474 / EN 10204 - type 3.1
# Positive Material Identification to ASTM E1916 In QCP, it refers to Chemical Buccioni tbc
# Solution Annealing temperatures and time trace Not in QCP SOS4592212 Buccioni tbc
# Quench and tempering temperatures and time trace Not in QCP SOS4592212 Buccioni tbc
# Stress Relaxation temperature and time trace Not in QCP SOS4592212 Buccioni tbc
# Material Composition Certificate Not in QCP SOS4592212 Buccioni tbc
# Dye Penetrant Inspection to ASTM E165 Not in QCP SOS4592212 Buccioni tbc
i) Balance drum diameter (inner / middle / outer) and runoutsNot in QCP SOS4592212 ENG + MFG
Baker Hughes Comments
MPE-Supplier shall prepare a detailed MPP (like the one
submitted during qualification) containing cut operations,
hot working hoperations, heat treatment operations
Se above point
Same as above
Same as above
Same as above
02021002006 HEAT TREATMENT CHART was added on This will be included as Hold Point
rev2
02021002006 HEAT TREATMENT CHART was added on This will be included in QCP
rev2
02021002006 HEAT TREATMENT CHART was added on This will be included in QCP
rev2