Documente Academic
Documente Profesional
Documente Cultură
I. OBJECTIVES
The primary objective of this study is to properly apply all the appropriate steel
specifications that we discussed under the Steel Design course in designing a steel
formwork system. At the end of this project, the researchers are purposeful to meet
the following specific goals:
● To design a steel formwork system for a 2-m diameter circular column with 8m
height.
● To design a steel formwork system that conforms to the standards stipulated in
the National Structural Code of the Philippines
● To combine the notable lessons from the steel design course
● To devise a cost efficient design of steel formwork system while showing the
realistic approach in construction field
● To exhibit a miniature model of the steel formworks system.
To design a steel formwork system it is expected to be completed within 30
days. This duration includes all unexpected time adjustments due to some
factors. The project starts in February 2020 and must be completed in March
2020. In our case, the timeline of designing this project was delayed because of
the unexpected pandemic that we have right now. The team will do its best effort
to complete the project before the scheduled deadline.
A. Overview
B. Project Design
For the steel formworks, we design it based on the pressure diagram. The
formwork serves as mould for concrete structural components unless such mould
is provided by the soil, other structural components, etc. It moulds the placed
fresh concrete, which in this stage normally is viscous, to the shape specified in
the drawing. Consequently, the formwork must already be available when the
necessary steel reinforcement and concrete mix are placed. Proper making of
formwork decides on the accuracy to size, strength and surface finish of the
concrete components. Formwork is required wherever monolithic concrete and
reinforced concrete structures or structural components are constructed.
Generally, each formwork is of provisional nature and is to be removed after
hardening of the concrete placed. The formwork is not to be built as strong as
possible but as strong as necessary only.
We design our Circular Column Steel Formwork based on what our
Professor gave to us. For the first lift of the circular column formwork we design it
on the computed Pressure Diagram. The 3 meters high first lift and 2 meters
diameter having stiffener rings and the spacing are 46 centimeters, 51 centimeters
and 45 centimeters its width is 100 millimeter and its thickness is 5 millimeter. For
the horizontal stiffener the quantity is 7 and for vertical stiffener the quantity is 14.
The plate thickness is 5 millimeter. The diameter of the bolt and nut is 20
millimeter. Top and bottom flange is 2 the thickness is 12 millimeter and width is
100 millimeter. The dimension of the second lift is the same as the dimension of
the first lift. For the last lift, 2.4 meters high and 2 meters diameter having stiffener
rings and the spacing are 40 centimeter, 42 centimeter and 48 centimeter its width
is 100 millimeter and its thickness is 5 millimeter. For the horizontal stiffener the
quantity is 5 and for the vertical stiffener the quantity is 14. The plate thickness is
5 millimeter. The diameter of the bolt and nut is 20 millimeter. Top and bottom
flange is 2 the thickness is 12 millimeter and width is 100 millimeter.
C. Introduction to Design
The structural design criteria of this project is based on National Structural
Code of the Philippines, 6th edition, 2010, ACI 318-95 Building Code
Requirement for Structural Concrete, AISC Manual of Steel Construction 9th
Edition (LRFD), Uniform Building Code (UBC 97), and Building Code
Requirements for Reinforced Concrete and Commentary-American Concrete
Institute (ACI 318)1999 Edition.
D. Design Parameters
These are the important parameters for designing and installing formworks.
Pressure Diagram
All formwork should be well designed before construction begins. The designing
required will depend on the size, complexity, and materials (considering reuses) of the
form. Formwork should be designed for strength and serviceability. System stability and
member buckling should be investigated in all cases. . Formwork should be designed
well, so that it will safely support all vertical and lateral loads that might be applied until
such loads can be supported by the concrete structure. Loads on the forms include the
weight of reinforcing steel, fresh concrete, the weight of the forms themselves and various
live loads imposed during the construction. In addition an action of the wind may produce
lateral forces which must be resisted by the formwork to prevent lateral failure. Vertical
and lateral loads should be carried to the ground by the formwork system or by the
in-place construction that has adequate strength for that purpose. In this part, we will
discuss the considerations, values, calculations and how we design our circular column
steel formworks, the sheathing design, column form stability, wind load assessment and
shoring design.
a. Sheathing Design
In Formface Sheathing we used 6mm thick and 5mm fillet weld.
The maximum expected sheathing form loading (Wu) , the diameter of
column (ø) and the spacing of the stiffener ring (S) are used to obtain the
maximum tension load (SWL). The highest value of maximum tension
load that we can get using the different value of stiffener ring spacing (S)
will govern and it will become our allowable tension load. For computing
the allowable tensile stress, 0.6 reduction factor was used ( σt = 0.60 Fy).
For the Horizontal Stiffener, we used 5mm thick and 100mm width, the
properties of the material must be known to check if the maximum stress
of it is adequate to the allowable tensile load of the sheathing. We used
5mm fillet weld which can give us an allowable working strength of
420MPa. For Bolts and Nuts (Wall Form Tie Capacity) we used the
standard value of allowable tension based on its diameter and the
maximum spacing of the M20 bolt to get the maximum tension load and if
it is safe. We can get the actual tensile stress by using the formula σt =
q*r / t and comparing it to the allowable tensile stress which is σt = 0.60 Fy
to check if the sheathing design is safe.
Fw = Cp * q * A
where:
Cp = Cs * Ch
Cs - Shape Factor (Circular)
Ch - Height Aspect Factor
q - Design Wind Pressure
A - Windward Area, Wind Load Reduction (Less than a year)
We used 70% for the wind load reduction. The windward area is
the area of the sheathing from the face. Design wind pressure is the
additional formwork load that can be seen in the National Structural Code
of the Philippines.The height aspect factor and shape factor in circular, we
used 1.15 and 0.75 as the standard value from the code.
In this section, we showed the systematic process and calculations of our design.
To build the 8m height circular column, we have three lifts with the combination of
formworks height of 3m, 3m and 2.4m. We assure that the values that we used in this
design are safe and provided by the code.
a. First Lift
b. Second Lift
c. Third Lift
G. Composition
Financial planning of this project is one of the most critical and difficult
part to express, we think of the best alternative way to accomplish this design.
We determined our current financial situation, developed financial goals with
more sets of plans even if we encounter some problems. The most important
part of this plan is reevaluating revising the plan if our budget gets too short.
H. Methodology
b. Fabrication
Construction of the formwork itself consists of panels fabricated out
of thin steel plates into any desired shape and size and held together
through the use of bolts,nuts and welding its stiffener along its side.
Using steel as a formwork is usually used in large scale projects and
most suitable for circular structures. When the construction of circular
steel formwork is done, stiffener will now be modified according to the
pressure that ensued due to concrete loads poured during the
construction. Prior to that, stiffener must be planned relatively to
compute dead loads that will occur. Engineers knew that proper
positioning of support to the face of the uniform pressure will result in
more efficient and economical use of materials and equipment
throughout the process. Stiffeners of a formwork will act as a support
against the pressure and with the relation to Boyles’ Law states that
pressure is directly proportional to its depth especially the vertical
stiffeners, therefore the greater the depth of a fluid will result in higher
pressure that will experience. In this case, the lower part of the
formworks needs a much more
stiffener with less spacing than to
the upper part. We start by
designing first the two circular
formworks with the same height
which is 3 meters, we set the pitch
of each end by 150 meters as the
minimum value of spacing that
stated by one of the field engineers
held to construct the Ortigas-BGC
Bridge. The rest is illustrated by
Figure 2 and it shows that the pitch
of every stiffener decreases from
its preceding value prioritizes the
critical part of the formworks which
is the lower level. Applying the
same aspects and procedure to third and final lift which is a bit shorter
formwork, a 2.4 meters height circular steel formwork shown in Figure
3. These stiffeners both horizontal and vertical made 5mm thick steel
plates will be connected to the circular body by the process of welding
connection with 2mm thick fillet weld and tied with the other half by
20mm bolts and nuts during the assembly process. Thus, designing
formworks minimize the amount of time handling and assembling
required in formwork activity. Further testing, assessment, stability
check and other parameters dealing with the design are addressed in
Chapter F Design Analysis/Calculations.
We started our project a week before the Enhance Community Quarantine, with
the goal that we can deal with our time appropriately. We chose to have groupings to begin the
Steel Column Miniature. All team members have equal ability, equal interest in the project and
work equally hard. Because it's based on successfully finishing the project. A non-contributing
team member can slow down or prevent completion of the work.
We have spent numerous late evenings and eating late just to complete the task. Sadly,
the miniature itself is being pointless since our nation is confronting a pandemic.
That was the challenge we faced during the miniature work. Apparently, in written reports
and documentation it has different challenges also.
● We had a hard time studying the process of steel formwork design because of class
suspension and we also had a hard time on analyzing and deciding the best materials
and best capacity that we can design for the formwork to be efficient and economical, but
thankfully we have a professor that is always available and ready to answer all of our
questions.
● Since we're doing it during lockdown. Most of our guardian priorities to stock more food,
to secure the health of the family. No budget for the load and that results in no access to
the internet. It seems to be pressure for us as a student because we don't have a choice.
we have to make it finish for the sake of our grades.
● It is hard to have a brainstorming session while chatting. So hard to share thoughts
without meeting each other. Each of us has our own priority in this pandemic situation.
Though, we did our best just to finish this work and make our mind at peace. This project
week alloted for completion sounds like a long time, but it goes by quickly. You need an
implementation schedule that allocates reasonable amounts of work throughout the entire week.
Then you must stick to that schedule. Don’t be tempted to postpone work on the project because
your due date seems so far off. All that happens is that during the final few weeks you rush
madly to get something working, and a project implemented in a rush rarely works correctly!
Working together in earnest is about making the most of the fact that you are a team. Honour
your time and efforts by seeing yourself as a full-time member of the team, not just an individual
contributor. Imagine how great it would feel to be part of a team where everyone is thinking of the
team and not just themselves – make that project a success by working together
In this research study we were able to design the formworks of an 8m height column with
2-meter diameter. The column was divided into 3 lifts, which is the most plausible way to
construct considering the height requirement. Our designed steel circular formworks consist of a
combination of 5mm thick steel plate, channels, angles and W-shape connected by welded and
bolts.
This process of designing formworks has provided us with a greater understanding of its
progressive manner and efficiency occurs in the field of civil engineering. This documentation
suggests that the materials, design plan and workflow plays a critical role in preventing any
failures from planning to installing up to the stage of stripping. This activity can delay schedule,
make any cracks to the structures or maybe lead to a loss of life when gone wrong during the
process and really bring a major impact to the project. As an engineer, we must know that
formworks are essential as to designing concrete structures when it comes to planning a detailed
strategic system factoring different kinds of elements.
Circular Column Formwork is engineered to form concrete round columns. The formwork
system is composed of semi-circular metal panels that form the circular mould when joined with a
simple bolted joint. Circular Column Formwork is suitable for round column construction. The
circular column forms of the building are characterized by simple structure, easy manufacture
and convenient assembly and disassembly. It has light weight, industrialized construction,
smooth surface of construction concrete, and its waterproof performance, thermal insulation
performance and corrosion resistance have reached the domestic high quality level. The wood
building circular column formwork has large cladding area, less splicing, no leakage of concrete,
low cost, good toughness, high impact resistance, high strength, strong surface hardness, can be
repeatedly used, and does not occupy construction machinery when assembled.
For a cost efficient miniature model we used varieties of recycled materials such as tin
cans, sticks and leftover paints. The projected cost of our project is Php 876.00, and with the
stated initiatives we were able to reduce our cost by 56%.
VI. References
https://www.safeworkaustralia.gov.au/system/files/documents/1703/guide-formwork.pdf
http://www.mevaformwork.com/meva-media/docs/en/circo-circular-column-formwork-tim.pdf
https://kumarproperties.com/design-of-formwork/
https://www.danterr.com/wp-content/uploads/2019/09/CIRCULAR-COLUMN-FORMWORK.pdf
https://www.google.com/www.thebalancesmb.com
https://www.google.com/url?sa=i&url=https%3A%2F%2Fmfindllc.com%2Fproduct%2Ffabrication
%2F&psig=AOvVaw3cl5e3cQfdtEhNZgEJa0rc&ust=1587715250153000&source=images&cd=vf
e&ved=0CAMQjB1qFwoTCNiosK6K_ugCFQAAAAAdAAAAABAM
https://www.google.com/url?sa=i&url=http%3A%2F%2Fwww.adaptformwork.com%2Fclr-circular-
column-formwork.html