Sunteți pe pagina 1din 4

Modernisation

increases capacity
and runtime

Case: Tororo Cement, Uganda


Tororo Cement approached FLSmidth to help revive its old plant. The result is a
stable production of more than 1000 tpd and reduced energy consumption.
2

Standard equipment,
non-standard solution

FLSmidth supplied
standard equipment
for this project,
put together in a
non-standard way
to optimally meet
Tororo Cement’s
requirements. FLSmidth collaborated closely with
Tororo Cement’s plant manager to
develop the upgrade
3

The background for the high voltage ABB variable frequency drives supplied
As one of only two cement plants in Uganda, Tororo Cement by FLSmidth, along with the filter bags for the process stacks.
plays a vital role in a volatile market. Significant infrastructure
investment in the country has been fuelling the need for Challenges
cement and producers are expecting demand to exceed the The team encountered a few challenges and the installation
2Mt mark in the near future. took longer than estimated. Since it was an old mill, it was
difficult to retrieve the correct data for the new equipment,
The Tororo Cement plant was purchased second-hand from which meant it had to be slightly modified after installation.
Germany and dates back to 1948. The plant was originally
situated at 0 MSL but it is installed in Uganda at 1300 MSL. The old plant was also in poor condition and finding experi-
This meant that the fans have not worked efficiently and enced local contractors to fabricate and erect the infrastruc-
average output has been much less than the rated production tures, such as heavy cranes, was a big challenge. Sometimes,
level. In addition, the limestone in Germany was very soft even simple bolts are not available in Uganda and everything
but in Tororo it is carbonatite, the hardest form of limestone, had to be imported. There were delays in deliveries because
so the raw mill was also operating at 50% capacity. everything had to be transported by road from Kenya (a journey
of around 1200 km).
The objective
Tororo Cement wanted to achieve stable, uninterrupted The weather in Uganda was also a hindrance, with the rain
operation and increase the capacity of the existing plant, meaning that erection work at heights regularly had to be
with minimum disruption. stopped.

Defining the project “The key to this project was to


Following a process study, it was decided that the best way find the bottlenecks at the plant
to revive the plant to its rated capacity was by upgrading the and pinpoint where the customer
raw mill and replacing all the major process fans. This involved
could gain the most benefit for
exchanging the mill separator along with the raw mill fan,
kiln ID fan, main filter fan and cooler filter fan. Minimising
the least amount of investment.”
downtime was an important consideration in this project.
Frank L. Mortensen,
Project Sales Manager, FLSmidth
The solution
Collaborating closely with Tororo Cement’s plant manager
was crucial and the implemented solution is highly influenced
by some of the plant manager’s ideas. The raw mill upgrade
included:
- 1 SEPAX® separator
- Main process fans
- Engineering of new ducting
- Various transport equipment

To minimise downtime, FLSmidth installed as much equipment


as possible prior to shut down. The engineering of the ducting
was adapted to the site conditions and the team came up
with creative solutions to route the ducts, taking into account
the plant’s limited space.

As well as the main raw mill upgrade, there was additional


modernisation including the kiln inlet-outlet seals, the
hydraulic thrust device, and replacing the damaged kiln shell
under FLSmidth supervision with an FLSmidth® nose ring. An
FLSmidth® Pfister® coal dust firing system was also installed
along with a kiln viewing camera, an XRF/ XRD analyser, a
PXP Process Expert™ System and a Blend Expert™ system.

Tororo Cement also purchased services from FLSmidth for the


maintenance of the slide shoe bearings of the Unidan mill and

The raw mill upgrade included new ducting


Results
Production capacity at Tororo has increased as planned.
Before the upgrade the production was an unstable maximum
of 700 tpd. Following the upgrade, production has been
stable at 1000+ tpd. Furthermore, the plant has set a new
record in continuous running and expects to gain a return
on its investment within 1 year.

An additional benefit is that the new installations are future-


proof, meaning that Tororo Cement can handle any increase
in production in the future.

“FLSmidth brings in solutions


that always display a win – win
situation. The response to any
correspondence is very quick…
and the experts working on-site
are also very flexible and ready
to work at any time.”
Nilesh Modha,
Plant Manager, Tororo Cement

New SEPAX® separator


at Tororo Cement plant

Project Centre Denmark Project Centre USA Project Centre India


FLSmidth A/S FLSmidth Inc. FLSmidth Private Limited
Vigerslev Allé 77 2040 Avenue C FLSmidth House
DK-2500 Valby Bethlehem, PA 18017-2188 34, Egatoor, Kelambakkam
Copenhagen Tel: +1 610-264-6011 (Rajiv Gandhi Salai, Chennai)
Tel: +45 3618 1000 Fax: +1 610-264-6170 Tamil Nadu – 603 103
C 09-13 000-53-ENG

Fax: +45 3630 1820 E-mail: info-us@flsmidth.com Tel: +91-44-4748 1000


E-mail: info@flsmidth.com Fax: +91-44-2747 0301
E-mail: indiainfo@flsmidth.com

Copyright © 2013 FLSmidth A/S. ALL RIGHTS RESERVED. FLSmidth, Pfister, SEPAX, Process Expert and Blend Expert are trademarks of FLSmidth A/S. This brochure makes no
offers, representations or warranties (express or implied), and information and data contained in this brochure are for general reference only and may change at any time. www.flsmidth.com

S-ar putea să vă placă și