18.1 Locating and Protecting


Existing Utilities 18-1 
18.1.1  Description / General 18-1 
18.1.1.1  Submittals 18-1 
18.1.2  Materials 18-1 
18.1.3  Construction Requirements 18-1 
18.1.4  Method of Measurement 18-1 
18.1.5  Basis of Payment 18-1 
18.1.6  Items in the Bill of Quantities 18-2 

18.2  Removing and Disposing of or


Relocating Existing Utilities 18-2 
18.2.1  General 18-2 
18.2.1.1  Submittals 18-2 
18.2.2  Materials 18-2 
18.2.3  Construction Requirements 18-2 
18.2.4  Method of Measurement 18-3 
18.2.5  Basis of Payment 18-3 
18.2.6  Items in the Bill of Quantities 18-3 

18.3 Future Utility Crossing 18-3 


18.3.1  Description / General 18-3 
18.3.2  Materials 18-3 
18.3.3  Construction Requirements 18-3 
18.3.4  Method of Measurement 18-3 
18.3.5  Basis of Payment 18-3 
18.3.6  Items in the Bill of Quantities 18-4
18.1 Locating and Protecting Existing other forms as instructed by the Engineer or the
Utilities concerned authorities.
3 Before commencing any work on site, the Contractor
18.1.1 Description / General shall send a ‘Notice of Intent’ including two sets of
drawings, plan work, construction method and safety
1 This Sub-section describes requirements for locating measured to all Concerned Authorities and shall obtain
and protecting existing underground services and plant information in the form of a formal notice and/or signed
that are affected by execution of the Works but to remain drawing showing the location of all underground utility
in their position, such as utility lines and underground plant and Falajs. The Contractor shall search for and
water streams (Falajs) etc. The full scope of the protection ascertain the exact location of the plant on site by making
work required will be determined after investigation by the trial pits and shall repair, at his own expense, any damage
Contractor, and he shall prepare working drawings for caused to the plant by his works, to the satisfaction of the
such work as directed by the Engineer. Engineer and the Concerned Authorities.
2 Existing utility services and plant, and Falajs will not 4 Whenever, in the course of the work, water pipes,
be considered as obstructions as defined in Section 1. The irrigation pipes, drainage pipes, sewers, oil, gas pipes,
Contractor shall liaise with the utility owners and other electrical or telephone cables, or other unforeseen items
concerned authorities regarding such utility services, plant are encountered, the Contractor shall inform the Engineer,
and Falajs in all aspects of the work. The cost of locating who shall issue the appropriate instruction for each
and recording their positions and of working around or in individual case.
proximity to them is deemed to be included in the
5 The precise location of existing utilities and Falajs
Contractor’s allowance for his obligations under Section 1.
shall be investigated and established by the Contractor in
18.1.1.1 Submittals consultation with the relevant Utility Operator. Service
supply lines damaged in the course of the search shall be
1 Submit coordination drawings showing pipes and replaced with equivalent approved materials at the
major system components. Indicate interface and spatial Contractor’s expense.
relationship between pipes, system components, adjacent
utilities, and proximate structures. 18.1.4 Method of Measurement
2 Submit shop drawings of existing underground
1 Excavation and backfilling, whether by hand or
services and plant to be protected including plan layout
machinery, for searching and protection of existing utility
and locations, types and sizes.
plant and Falajs including making trial pits shall be
3 At project close-out, submit record drawings measured as described in Sub-section 2.8, Clause 2.8.4.
showing the protected pipes and related components with and 1.8.3.
sufficient details to allow for locating the pipes for future
2 Split pipes shall be measured in linear meters of laid
maintenance.
pipe of the various sizes, measured as a straight line. No
allowance will be made for cut ends and waste.
18.1.2 Materials
3 Concrete surround to pipes and ducts and concrete
1 Concrete shall conform to the requirements of Sub- for inverted box culverts and for blinding shall be
section 5.1 and shall be of the class instructed by the measured as described in Sub-section 5.1, Clause 5.1.5.
Engineer. Reinforcing steel shall comply with Sub-section The volume occupied by the pipe including pipe wall shall
5.2. Reinforced concrete shall comply with the appropriate be deducted from the gross volume of the concrete
requirements of Sub-section 5.3. Metalwork should surround and only the net volume of the concrete
comply with Section 6. surround so calculated shall be paid for.
4 Reinforcing steel shall be measured as described in
18.1.3 Construction Requirements
Sub-section 5.2, Clause 5.2.4.
1 All excavation and backfill shall conform to the
requirements of Sub-Sections 2.3 – ‘Roadway Excavation’ 18.1.5 Basis of Payment
and 2.8 – ‘Earthwork for pipe trenches’.
1 The quantity of completed and accepted work for
2 The protection of existing underground plant and split pipes measured as provided for above will be paid for
Falajs shall be carried out in strict compliance with the at the unit rate in the Bill of Quantities. The unit rate per
requirements of the Concerned Authorities and utility linear meter shall include labor, materials, markers and
owners. The protection shall normally be in the form of warning tape, equipment, transportation to and hauling
encasing the services or plant with a split 100 or 300 mm about the Site, loading, unloading and cutting, machining,
diameter uPVC pipe wrapped with polyethylene sheets etc. of standard length pipes.
and surrounded by concrete Class 15/20 or enclosing such
2 Excavation and backfilling shall be paid for as
plant of large diameter such as oil or water pipes or Falajs
indicated in Clause 2.8.5.
with an inverted concrete box culvert or slab or in any
3 Concrete shall be paid for as indicated in Clause 5.1.6.

♦ 18-1 ♦
4 Reinforcing steel shall be paid for as indicated in 5.2. Reinforced concrete shall comply with the appropriate
Clause 5.2.5. requirements of Sub-section 5.3.
3 Gravity pipes and pressure pipes shall conform to the
18.1.6 Items in the Bill of Quantities requirements of Sub-section 8.2, Clause 8.2.2.

(i) Split pipe (diameter) lin.m 4 Electricity poles, ducts, handholes/manholes and
overhead and underground electricity cables, shall
conform to the requirements of Section 15 and of the
18.2 Removing and Disposing of or Concerned Authority.
Relocating Existing Utilities
5 Telecommunication ducts, handholes/manholes and
cables related to telephone works, shall conform to the
18.2.1 General telecommunication authority specifications and details.
1 This Sub-section describes requirements for removal, 6 Sand and sieved backfill material free from stones or
disposal or relocation/diversion of existing utilities. Full other debris shall be provided for reinstating the trenches
scope of the relocation work required will be determined after the laying of ducts.
after investigation by the Contractor and he shall prepare,
shop/working drawings for the work, as directed by the 18.2.3 Construction Requirements
Engineer. The Contractor shall liaise with the utility
owners and other Concerned Authorities in all aspects of 1 Prior to commencing the work, the Contractor shall
the work. prepare layout drawings, proposed working method and
the time schedule for disconnecting and reconnecting of
2 Permanent removal and, relocation or diversion of
the affected services and shall obtain approval of these
any existing utilities will be ordered by the Engineer where
from the Engineer and Concerned Authorities. During the
they obstruct the permanent work and where such utilities
work, the Contractor shall exercise great care not to cause
need to be maintained in operation as required by the
any damage to the exiting utilities.
utility owner. The Engineer may also order permanent or
temporary diversion of utilities when in his opinion it is 2 Electricity, gas, oil, water, sewage, drainage,
reasonable that this should be done for carrying out the irrigation and telephone service lines which are identified
proposed work, but such orders will not normally be given to be relocated shall be shown on the drawings, along
where the services concerned cross the work area and are with the required re-routing. The full scope of the services
either redundant or can be dealt with by the Contractor in to be relocated cannot be determined at tender stage and
the normal course of work. The diversions ordered by the the Contractor shall allow in his rate for verifying or
Engineer shall be paid for in the Contract, but any other revising the services that should be re-routed and
temporary diversion or removal required shall be at the adjusting the proposed re-routing alignment and for any
Contractor's own expense. variation in quantities, preparation of revised working
drawings, design, etc.
3 No service diversion shall be made without the
approval of the Engineer and the Concerned Authority. 3 The precise locations of existing utilities shall be
investigated and established by the Contractor in
18.2.1.1 Submittals consultation with the relevant utility owner. The
Contractor shall notify and obtain permission from the
1 Submit coordination drawings showing pipes and
Concerned Authority before interrupting any service.
major utility components. Indicate interface and spatial
Service supply lines damaged in the course of the search
relationship between pipes, system components, adjacent
shall be replaced with equivalent approved materials at
utilities, and proximate structures.
the Contractor’s expense.
2 Submit shop drawings of existing underground
4 All excavation and backfill shall conform to the
utilities and plant affected by the work including plan
requirements of Sub-Sections 2.3 – ‘Road Excavation’, 2.7
layout and locations, types and sizes.
– ‘Excavation and Backfilling for Structures’ and 2.8 –
3 At project close-out, submit record drawings ‘Earthwork for Pipe Trenches’.
showing the relocated services and related components
5 Removal of existing utilities shall conform to the
with sufficient details to allow for locating the utility for
requirements of Sub-section 2, Clause 2.2.2. Designated
future maintenance.
salvageable material shall be removed without
unnecessary damage, in sections or pieces, transported or
18.2.2 Materials stored by the Contractor as instructed by the Engineer.
1 All material for relocation/diversion of utilities shall Other material shall be disposed of off-site.
comply with the specifications of the Concerned Authority 6 Utility lines which should remain, but with added
and shall conform to the following listed requirements. protection, shall be shown on the drawings. Cavities left
2 Concrete shall conform to the requirements of Sub- by utilities removal shall be backfilled to the level of the
section 5.1 and shall be of the class instructed by the surrounding ground and compacted.
Engineer. Reinforcing steel shall comply with Sub-section

♦ 18-2 ♦
7 During excavation, warning tiles or tape shall be 2 The Contractor shall be responsible for preparation
retrieved carefully and may be reused. The damaged of shop/working drawings, procurement of material and
warning tiles or tape shall be replaced by the Contractor at for following-up/co-ordination with the concerned
his own cost. Concreting and backfilling operations shall authorities in all matters relating to this work.
be carefully executed to ensure that there shall be no
damage to the utilities. 18.3.2 Materials
1 Concrete shall conform to the requirements of Sub-
18.2.4 Method of Measurement
section 5.1 and shall be of the class instructed by the
1 Removal and disposal of existing redundant utilities Engineer. Reinforcing steel shall comply with Sub-section
ordered by the Engineer under Clause 18.2.1, Item (2), 5.2. Reinforced concrete shall comply with the appropriate
shall be measured in linear meters of the length removed. requirements of Sub-section 5.3.
The rates shall include for all work except excavation as 2 Sleeves/ducts shall be uPVC for small pipes less than
stated in Item (4), below. 400 mm in diameter and concrete for larger pipes. Pipes
2 Removal and relocation of existing utilities shall be shall conform to the requirements of Sub-section 8.2,
measured in linear meters of the length of the relocated Clause 8.2.2.
work. Rates shall include for all work except excavation as 3 Locations and sizes of pipe sleeves are as shown on
stated in Item (4) below. the Drawings.
3 Provision and installation of new utility services shall
be measured in linear meters of the length of new service 18.3.3 Construction Requirements
installed. Rates shall include for all work except excavation
1 Before commencing any work on site, the Contractor
as stated in Item (4) below.
shall send a ‘Notice of Intent’ including two sets of
4 Excavation and backfilling whether by hand or drawings, plan of work, construction method and safety
machinery for removal, relocation/diversion of existing measures to all Concerned Authorities and shall obtain
utilities shall be measured as indicated in Sub-section 2.8, information in the form of a formal notice and/or signed
Clause 2.8.4. drawing showing the required location of sleeves for
5. No work will be measured and no payment made for future connection.
work carried out by the Concerned Authorities nor for any 2 Sleeves/ducts shall be placed prior to or during
work in connection therewith by the Contractor unless construction of the highway. Any piping installed after
prior approval for payment is given by the Engineer completion of the highway construction shall be placed
after jacking (thrust boring) a pipe sleeve under the
18.2.5 Basis of Payment pavement. The Contractor will not be permitted to cut into
1 The amount of completed and accepted work the pavement for pipe installation.
measured as provided for above shall be paid for at the 3 Markers should be placed on both ends of the
unit rate for each service stated in the Bill of Quantities, sleeves/ducts. In addition a rope should be installed inside
which rate shall be considered full compensation for the pipe and tied at both ends to the markers underground
locating, removing, relocating, installing and jointing of concrete support block or to an adjacent landmark.
utilities and for materials, labor, transport, equipment, 4 All excavation and backfill shall conform to the
tools supplies and all other items necessary for the proper requirements of Sub-sections 2.3 – ‘Roadway Excavation’
completion of the work, except excavation which is and 2.7 – ‘Excavation and Backfilling for Structures’.
measured as stated in Clause 18.2.4, Item (4).
18.3.4 Method of Measurement
18.2.6 Items in the Bill of Quantities
1 Sleeves/ducts shall be measured in linear meters of
(i) Remove and dispose of (utility) pipe of the various types, classes and sizes laid, measured
(size/description) lin.m. as a straight line. No allowance will be made for cut ends
(ii) Remove and relocate (utility) (size/ and waste. The rates shall be deemed to include for all
description) lin.m. work including the laying of markers and concrete
(iii) Provide and install new (utility) surrounds, but does not include excavation as stated in
(size/description) lin.m. Item (2) below.
2 Trench excavation and backfilling shall be measured
18.3 Future Utility Crossings and paid for as indicated in Clause 2.8.4 Item (4).

18.3.1 Description / General 18.3.5 Basis of Payment


1 This Sub-section describes requirements for 1 The quantity of completed and accepted work for
provision of pipe sleeves/ducts under pavements for sleeves/ducts pipes measured as provided for above will
future utility crossings. Full scope of the work will be be paid for at the unit rate in the Bill of Quantities, which is
determined according to conditions on Site.

♦ 18-3 ♦
deemed to cover all costs except excavation as stated in
Clause 18.3.4, item (2).

18.3.6 Items in the Bill of Quantities


(i) Sleeves/ducts (type) (diameter) lin.m.