OWNERS ENGINEER
CONTRACTOR
SITE / PROJECT
P1-BOP-ELB-V-GGGG-CH-01075 Page 1 of 6
CHANGE ORDER
Code P1-BOP-ELB-VC-GGGG-CH-01075
Revision B
Date 06/06/2018
DESCRIPTION
Commensurate with the ARTICLE 22.2 of the CONTRACT, CONTRACTOR submits herewith
his CHANGE ORDER Request No. 075 (COR075) according to which CONTRACTOR
requests the adjustment of the CONTRACT PRICE, WORKS SCHEDULES, and
COMPLETION DATE of the CONTRACT AGREEMENT No. 2016/06.
COMPANY transmitted information indicating the use of this HVAC Equipment for
Social Buildings (DRI, RM & MHS).
Further to the above, the CONTRACTOR has identified major changes resulting from
executing the items not included in the Original Scope of WORKS such as the Approved Bill
of Quantities and/or the ITB Documents, including but not limited to the following:
P1-BOP-ELB-V-GGGG-CH-01075 Page 2 of 6
- Impacts on the progress of the WORKS.
CONTRACTOR trusts that COMPANY is aware of the criticality and importance of the above
mentioned and duly entitled CHANGE ORDER, and kindly requests COMPANY to expedite
the APPROVAL of the subject CHANGE ORDER.
Notes:
a. Price include the supply, erection and testing of the below elements.
b. Civil Works are excluded and it will be invoiced separately.
c. Not all HVAC equipment for these buildings is included in this COR.
P1-BOP-ELB-V-GGGG-CH-01075 Page 3 of 6
Unit Prices Currency Distribution Total Prices Currency Distribution
Offshore Onshore Onshore Offshore Onshore Onshore
Total
Item Description Quantity Unit Unit Rate ITEM Item Item ITEM Item Item
Amount
($) ($) (DZD) ($) ($) (DZD)
CIAT
Supply, erection, testing and commissioning
of Energy Recovery Air Handling Unit (100%
Outside Air). DX Rooftop Packaged Unit.
Cooling Total Capacity: 38.2kW. Heating
1 2 U $42,983.85 $85,967.70 $28,655.90 $0.00 $14,327.95 $57,311.80 $0.00 $28,655.90
Total Capacity: 39.0kW - as per P1-BOP-IDE-
V-SOCI-DS-8001 rev C - HVAC Equipment
Data Sheet - DRI Social Building - excluding
electrical and control works
Supply, erection, testing and commissioning
of Energy Recovery Air Handling Unit (100%
Outside Air). DX Rooftop Packaged Unit.
Cooling Total Capacity: 38.2kW. Heating
2 2 U $42,983.85 $85,967.70 $28,655.90 $0.00 $14,327.95 $57,311.80 $0.00 $28,655.90
Total Capacity: 39.0kW - as per P1-BOP-IDE-
V-SOCI-DS-8101 rev C - HVAC Equipment
Data Sheet - RM Social Building - excluding
electrical and control works
Supply, erection, testing and commissioning
of Energy Recovery Air Handling Unit (100%
Outside Air). DX Rooftop Packaged Unit.
Cooling Total Capacity: 38.2kW. Heating
3 2 U $42,983.85 $85,967.70 $28,655.90 $0.00 $14,327.95 $57,311.80 $0.00 $28,655.90
Total Capacity: 39.0kW - as per P1-BOP-IDE-
V-SOCI-DS-8201 rev C - HVAC Equipment
Data Sheet - MHS Social Building - excluding
electrical and control works
P1-BOP-ELB-V-GGGG-CH-01075 Page 4 of 6
COST IMPLICATION: YES NO COST (US$)
Engineering:
Procurement:
Construction: X $257,903.10
Supervision:
Others:
New price without any basis for extrapolation from the BOQ, has been done
according to Method 2 of “P1-BOP-IDS-G-GGGG-PP-0027- REV E- Change Order
Procedure for BOP” (see attached: Annex 1: “Method 2 Justification” and
Quotation).
SCHEDULE IMPLICATION
Contractor reserves his rights to entitlement for the schedule impacts and time
related cost associated with this CHANGE ORDER along with the effects of all
events occurred during the execution of the Works.
The schedule impacts and time related cost will be assessed and submitted in due
course in another CHANGE ORDER separately.
ATTACHMENTS
APPROVAL
P1-BOP-ELB-V-GGGG-CH-01075 Page 5 of 6
Annex 1 - Method 2 Justification:
P1-BOP-ELB-V-GGGG-CH-01075 Page 6 of 6
Item 1
Items 2&3