Sunteți pe pagina 1din 9

DETAILED ESTIMATE

DETAILED ESTIMATE FOR THE PROPOSED NEW CONSTRUCTION OF RESIDENTIAL BUILDING (GROUND FLOOR ).

OWNER :

SI.No DESCRIPTION OF WORK Nos. L (m) B (m) D (m) QTY REMARK


1 Earth work excavation for hard soil in depth of 4'
including materials and labour charges etc
Foundation
allround 1 16.92 1.10 1.22 22.71
f/r steps 2 1.42 1.60 0.30 1.36
add 0.43
Total 24.50 Cu.m
2 Sand filling for foundation/basement in pure river sand including materials & labour charges etc.
Foundation
allround 1 16.92 1.10 1.22 22.71
f/r steps 2 1.42 1.60 0.15 0.68
Basement -bulding all 1 4.77 2.77 0.80 10.57
33.96
D/F-pcc 1 16.92 1.10 0.15 2.79
D/F-rr footing 1 1 16.92 0.68 0.46 5.29
D/F-rr footing 2 1 16.92 0.45 0.46 3.50
11.59
22.37
add 0.43
Total 22.80 Cu.m
3 P.C.C 1:5:10 mix for foundation , 40mm metal graded including materials & labour charges etc.
Foundation
allround 1 16.92 1.10 0.15 2.79
f/r steps 2 1.42 1.60 0.15 0.68
Basement -bulding all 1 4.77 2.77 0.10 1.32
add 0.11
Total 4.90 Cu.m
4 R.C.C 1:2:4 for Beam, sunshade, loft, roof, using tor steel rods
&mild steel including materials & labour charges etc.
Foundation
PB allround 1 16.92 0.30 0.10 0.51
W-SILL SLAB 2 1.68 0.23 0.05 0.04
LL ALLROUND 1 16.92 0.23 0.15 0.58
W,D-SUNSHAD 4 1.68 0.60 0.06 0.25
LOFT 1 3.00 0.45 0.08 0.10
ROOF SLAB 1 5.46 3.46 0.10 1.89
add 0.03
Total 3.40 Cu.m
5 CENTERING & SCAFFOLDING WORK using tor steel rods
&mild steel including materials & labour charges etc.
w-sill slab 2 1.68 0.05 0.17
lb allround inside 1 16.00 0.15 2.40
lb allround out side 1 17.84 0.15 2.68
lb-w-bottom 2 1.22 0.23 0.56
lb-md-bottom 1 1.22 0.23 0.28
lb-d1-bottom 1 0.91 0.23 0.21
w-sunshad-bottom 2 1.68 0.60 2.02
w-sunshad-3sides 2 2.88 0.08 0.43
d-sunshad-bottom 2 1.68 0.60 2.02
d-sunshad-3sides 2 2.88 0.08 0.43
loft bottom 1 3.00 0.45 1.35

Page 1 of 9
loft 1side 1 3.00 0.08 0.23
ROOF SLAB 1 5.00 3.00 15.00
roOF SLAB 4sides 1 17.84 0.10 1.78
29.55
D/F SUNSHAD SIDE 4 1.68 0.08 0.50
D/F LOFT SIDE 1 3.00 0.08 0.23
0.73
28.82
add 0.58
Total 29.40 Cu.m
REINFORCEMENT WORK
PB 1 0.51 60.00 30.60
SILL SLAB+LB+LOFT+SUNSHAD 1 0.98 60.00 58.80
ROOF SLAB 1 1.89 80.00 151.20
ADD 5.40
246.00 KG
R.R. WORK
Foundation
allround-F1 1 16.92 0.68 0.46 5.29
allround-F2 1 16.92 0.45 0.46 3.50
allround-F2 1 16.92 0.45 0.80 6.09
add 0.21
Total 15.10 Cu.m
Brick work in c.m. 1:5 IN FOUNDATION with chamber bricks for erials & labour charges etc.
Foundation
STEPS 1 2 1.50 1.22 0.15 0.55
STEPS 2 2 1.25 1.22 0.15 0.46
STEPS 3 2 1.00 1.22 0.15 0.37
STEPS 4 2 0.75 1.22 0.15 0.27
STEPS5 2 0.50 1.22 0.15 0.18
STEPS 6 2 0.25 1.22 0.15 0.09
add 0.08
Total 2.00 Cu.m
6 Brick work in c.m. 1:5 with chamber bricks for superstructure including materials & labour charges etc.
Ground floor -
ALLROUND 1 16.92 0.23 3.05 11.87
parapet wall all round 1 16.92 0.23 1.22 4.75
16.62
D/F MD 1 1.22 0.23 2.10 0.59
D/F D1 1 0.91 0.23 2.10 0.44
D/F W 2 1.22 0.23 1.37 0.77
D/F LB 1 16.92 0.23 0.15 0.58
2.38
14.24
add 0.26
Total 14.50 Cu.m
6 DPC
Ground floor -
ALLROUND 1 16.92 0.23 3.89 SQ.M
add 0.11
Total 4.00 SQ.M
7 Plastering for all walls C.M 1:5 mix, 12mm thick thorouly inner &
outer including materials & labour charges etc
inner wall allround 1 16.00 3.05 48.80
outer wall 1 17.84 4.37 77.96
parapet inner 1 16.00 1.22 19.52
parapet top 1 16.92 0.23 3.89
STEPS 1 side 4 1.50 0.15 0.90
STEPS 2 4 1.25 0.15 0.75
STEPS 3 4 1.00 0.15 0.60

Page 2 of 9
STEPS 4 4 0.75 0.15 0.45
STEPS5 4 0.50 0.15 0.30
STEPS 6 4 0.25 0.15 0.15
steps 2 2.40 1.22 5.86
159.18
D/F MD 1 1.22 2.10 2.56
D/F D1 1 0.91 2.10 1.91
D/F W 2 1.22 1.37 3.34
7.82
151.36
add 3.64
Total 155.00 Sq.m

8 Plastering for ceiling in C.M 1:3 mix 10mm thick including materials & labour charges etc.
Ground floor
Roof slab
- building 1 5.00 3.00 15.00
Loft bottom+top+side 1 3.00 0.98 2.93
Sunshad bottom +top+front 4 1.68 1.25 8.40
Sunshad l/r side 8 0.60 0.08 0.36
add 0.81
Total 27.50 Sq.m

Page 3 of 9
9 Tiles flooring using materials & labour charges etc.
Ground floor
- building all 1 5.00 3.00 15.00
add 0.5
Total 15.50 Sq.m
10 Weathering course concrete including materials & labour charges etc.
- building all 1 5.00 3.00 0.08 1.20
- building allround 1 16.00 0.20 0.08 0.26
add 0.04
Total 1.50 Cu.m
10 Weathering course tiles including materials & labour charges etc.
- building all 1 5.00 3.00 15.00
- building allround 1 16.00 0.20 3.20
add 0.40
Total 18.60 Sq.m

11 White wash for Inner & Outer including materials & labour charges etc.
plastering wall inner + outer 155.00
plastering ceilling 27.50
182.50 Sq.m
11 colour wash for Inner & Outer including materials & labour charges etc.
plastering wall inner + outer 155.00 Sq.m

12 Doors & Windows including materials & labour charges etc


L.S
13 Electrical work including materials & labour charges etc
L.S
14 Plumbing work including materials & labour charges etc
L.S
15 Septic tank work including materials & labour charges etc
L.S
16 Bore work arrangements including materials & labour charges etc
L.S
17 Cupboard work arrangements including materials & labour charges etc
L.S
18 Grill works
L.S
19 Elevation item of work
L.S
20 Miscellaneous items of work
L.S
ENGINEER

Page 4 of 9
DETAILED ESTIMATE

DETAILED ESTIMATE FOR THE PROPOSED NEW CONSTRUCTION OF RESIDENTIAL BUILDING (GROUND FLOOR )

OWNER :

SI.No DESCRIPTION OF WORK Nos. L (m) B (m) D (m) QTY REMARK


1 Earth work excavation for hard soil in depth of 4'
including materials and labour charges etc
Foundation 4 1.20 1.20 1.22 7.03
PB1 2 4.03 0.40 0.50 1.61
PB2 2 2.03 0.40 0.50 0.81
f/r steps 2 1.42 1.60 0.30 1.36
add 0.43
Total 11.24 Cu.m
2 Sand filling for foundation/basement in pure river sand including materials & labour charges etc.
Foundation 4 1.20 1.20 1.22 7.03
PB1 2 5.00 0.40 0.10 0.40
PB2 2 3.00 0.40 0.10 0.24
f/r steps 2 1.42 1.60 0.15 0.68
Basement -bulding all 1 5.00 3.00 0.80 12.00
20.35
D/F-pcc 4 1.20 1.20 0.10 0.58
D/F- footing 1 4 1.00 1.00 0.40 1.60
D/F-COLUMN 4 0.23 0.23 0.60 0.13
2.30
18.05
add 0.45
Total 18.50 Cu.m
3 P.C.C 1:5:10 mix for foundation , 40mm metal graded including materials & labour charges etc.
Foundation 4 1.20 1.20 0.10 0.58
PB1 2 5.00 0.40 0.10 0.40
PB2 2 3.00 0.40 0.10 0.24
f/r steps 2 1.42 1.60 0.15 0.68
Basement -FLOORING PCC 1 5.00 3.00 0.10 1.50
add 0.10
Total 3.50 Cu.m
4 R.C.C 1:2:4 for Beam, sunshade, loft, roof, using tor steel rods
&mild steel including materials & labour charges etc.
Foundation 4 1.00 1.00 0.40 1.60
COLUMN 4 0.23 0.23 4.65 0.98
PB1 2 5.00 0.23 0.45 1.04
PB2 2 3.00 0.23 0.30 0.41
W-SILL SLAB 2 1.68 0.23 0.05 0.04
CLB-MD1 1 1.68 0.23 0.15 0.06
CLB-D1 1 1.37 0.23 0.15 0.05
CL for loft 1 3.46 0.23 0.15 0.12
CLB-W 2 1.68 0.23 0.15 0.12
W,D-SUNSHAD 4 1.68 0.60 0.06 0.25
LOFT 1 3.46 0.45 0.08 0.12
ROOF BEAM1 2 5.00 0.23 0.45 1.04
ROOF BEAM2 2 3.00 0.23 0.30 0.41
ROOF SLAB 1 5.00 3.00 0.10 1.50
add 0.00
Total 7.73 Cu.m
4 DUMMY CONCRETE 1:3:6
&mild steel including materials & labour charges etc.
COLUMN 4 0.23 0.23 1.22 0.26

Page 5 of 9
add 0.04
Total 0.30 Cu.m
5 CENTERING & SCAFFOLDING WORK using tor steel rods
&mild steel including materials & labour charges etc.
Foundation 4 4.00 0.40 6.40
COLUMN 4 0.92 4.65 17.11
PB1 4 5.00 0.45 9.00
PB2 4 3.00 0.30 3.60
W-SILL SLAB 4 1.68 0.05 0.34
CLB-MD1-bottom 1 1.22 0.23 0.28
CLB-MD1-side 2 1.68 0.15 0.50
CLB-D1-bottom 1 0.91 0.23 0.21
CLB-D1-side 2 1.37 0.15 0.41
CLB-W-bottom 1 1.22 0.23 0.28
CLB-W-side 2 1.68 0.15 0.50
W,D-SUNSHAD-bottom 4 1.68 0.60 4.03
W,D-SUNSHAD-frent face 4 1.68 0.05 0.34
W,D-SUNSHAD-side 8 0.60 0.08 0.36
LOFT-w-bottom 1 1.22 0.23 0.28
LOFT- cl-side 2 3.00 0.15 0.90
LOFT- bottom 1 3.00 0.45 1.35
LOFT- f+l+r side 1 4.36 0.08 0.33
ROOF BEAM1-bottom 2 5.00 0.23 2.30
ROOF BEAM1-inner side 2 5.00 0.35 3.50
ROOF BEAM1-outre side 2 5.00 0.45 4.50
ROOF BEAM2-bottom 2 3.00 0.23 1.38
ROOF BEAM2-inner side 2 3.00 0.20 1.20
ROOF BEAM2-outre side 2 3.00 0.30 1.80
ROOF SLAB-bottom 1 5.00 3.00 15.00
dummy column 4 0.92 1.22 4.49
80.39
D/F column-pb joint-5m 4 0.23 0.45 0.41
D/F column-pb joint-3m 4 0.23 0.30 0.28
D/F column-rb joint-5m 4 0.23 0.45 0.41
D/F column-rb joint-3m 4 0.23 0.30 0.28
D/F SUNSHAD SIDE 4 1.68 0.08 0.50
D/F LOFT SIDE 1 3.00 0.08 0.23
2.11
78.28
add 0.58
Total 78.86 SQ.M
6 REINFORCEMENT WORK
Foundation 1 1.60 60.00 96.00
column 1 0.98 210.00 205.80
PB 1 1.45 60.00 87.00
ROOF beam 1 1.45 180.00 261.00
ROOF SLAB 1 1.50 80.00 120.00
SILL SLAB+LB+LOFT+SUNSHAD 1 0.75 60.00 45.00
binding wire 1 5.74
ADD 9.26
528.00 KG
7 Brick work in c.m. 1:5 IN FOUNDATION with chamber bricks for erials & labour charges etc.
Foundation
STEPS 1 2 1.50 1.22 0.15 0.55
STEPS 2 2 1.25 1.22 0.15 0.46
STEPS 3 2 1.00 1.22 0.15 0.37
STEPS 4 2 0.75 1.22 0.15 0.27
STEPS5 2 0.50 1.22 0.15 0.18
STEPS 6 2 0.25 1.22 0.15 0.09
add 0.08
Total 2.00 Cu.m

Page 6 of 9
6 Brick work in c.m. 1:5 with chamber bricks for superstructure including materials & labour charges etc.
Ground floor -
ALLROUND 1 16.92 0.23 3.05 11.87
parapet wall all round 1 16.92 0.23 1.22 4.75
16.62
D/F MD 1 1.22 0.23 2.10 0.59
D/F D1 1 0.91 0.23 2.10 0.44
D/F W 2 1.22 0.23 1.37 0.77
D/F LB 1 16.92 0.23 0.15 0.58
2.38
14.24
add 0.26
Total 14.50 Cu.m
6 DPC
Ground floor -
ALLROUND 1 16.92 0.23 3.89 SQ.M
add 0.11
Total 4.00 SQ.M
7 Plastering for all walls C.M 1:5 mix, 12mm thick thorouly inner &
outer including materials & labour charges etc
inner wall allround 1 16.00 3.05 48.80
outer wall 1 17.84 4.37 77.96
parapet inner 1 16.00 1.22 19.52
parapet top 1 16.92 0.23 3.89
STEPS 1 side 4 1.50 0.15 0.90
STEPS 2 4 1.25 0.15 0.75
STEPS 3 4 1.00 0.15 0.60
STEPS 4 4 0.75 0.15 0.45
STEPS5 4 0.50 0.15 0.30
STEPS 6 4 0.25 0.15 0.15
steps 2 2.40 1.22 5.86
159.18
D/F MD 1 1.22 2.10 2.56
D/F D1 1 0.91 2.10 1.91
D/F W 2 1.22 1.37 3.34
7.82
151.36
add 3.64
Total 155.00 Sq.m

8 Plastering for ceiling in C.M 1:3 mix 10mm thick including materials & labour charges etc.
Ground floor
Roof slab
- building 1 5.00 3.00 15.00
Loft bottom+top+side 1 3.00 0.98 2.93
Sunshad bottom +top+front 4 1.68 1.25 8.40
Sunshad l/r side 8 0.60 0.08 0.36
add 0.81
Total 27.50 Sq.m

Page 7 of 9
9 Tiles flooring using materials & labour charges etc.
Ground floor
- building all 1 5.00 3.00 15.00
add 0.5
Total 15.50 Sq.m
10 Weathering course concrete including materials & labour charges etc.
- building all 1 5.00 3.00 0.08 1.20
- building allround 1 16.00 0.20 0.08 0.26
add 0.04
Total 1.50 Cu.m
10 Weathering course tiles including materials & labour charges etc.
- building all 1 5.00 3.00 15.00
- building allround 1 16.00 0.20 3.20
add 0.40
Total 18.60 Sq.m

11 White wash for Inner & Outer including materials & labour charges etc.
plastering wall inner + outer 155.00
plastering ceilling 27.50
182.50 Sq.m
11 colour wash for Inner & Outer including materials & labour charges etc.
plastering wall inner + outer 155.00 Sq.m

12 Doors & Windows including materials & labour charges etc


L.S
13 Electrical work including materials & labour charges etc
L.S
14 Plumbing work including materials & labour charges etc
L.S
15 Septic tank work including materials & labour charges etc
L.S
16 Bore work arrangements including materials & labour charges etc
L.S
17 Cupboard work arrangements including materials & labour charges etc
L.S
18 Grill works
L.S
19 Elevation item of work
L.S
20 Miscellaneous items of work
L.S
ENGINEER

Page 8 of 9
ABSTRACT ESTIMATE

ABSTRACT ESTIMATE FOR THE PROPOSED NEW CONSTRUCTION OF RESIDENTIAL BUILDING (GROUND FLOOR)

OWNER :

ESTIMATE AMOUNT:- Rs. 9,00,000

S.NO DESCRIPTION OF WORKS QTY RATE (Rs) PER AMOUNT ( Rs) REMARKS

1 Earth work excavation for open foundation 100.00 250.00 Cu.m 25,000.00
2 Sand filling for foundation/basement 39.00 380.00 Cu.m 14,820.00
3 P.C.C 1:5:10 for foundation/basement ,40mm metal grade
11.00 2100.00 Cu.m 23,100.00

4
R.C.C lintel,sunshade,loft,R.C.C ROOF1:2:4mix,+Steel 32.00 13500.00 Cu.m 432,000.00
5 R.C.C dummy column 1:3:6 mix,+Steel 1.00 7000.00 Cu.m 7,000.00
6 Brick work in super structure c.m. 1:5 mix 45.00 2300.00 Cu.m 103,500.00
7 Plastering for all walls Inner & outer in c.m 1:5 410.00 110.00 Sq.m 45,100.00
8 Plastering for Ceiling in C.M 1:3 mix 120.00 130.00 Sq.m 15,600.00
9 Tiles flooring finish 43.00 600.00 Sq.m 25,800.00
10 Weathering course arrangements 5.00 2300.00 Cu.m 11,500.00
11 White wash and colour wash inner and outer L.S 35,000.00
12 Doors & Windows Wood work arrangements L.S 40,000.00
13 Electrical work arrangements L.S 45,000.00
14 Plumbing work arrangements L.S 25,000.00
15 Septic tank work arrangements L.S 35,000.00
16 Bore work arrangements L.S 0.00
17 Cupboard work arrangements L.S 5,000.00
18 Grill works L.S 5,000.00
19 Elevation item of work L.S 0.00
20 Miscellaneous items of work L.S 6,580.00

TOTAL 900,000.00

RUPEES: Nine Lakhs only

ENGINEER

Page 1 of 9

S-ar putea să vă placă și