WBS#30-17118 Construction of New Floating Pontoon Coast Guard

MARINE SERVICES CO. TESTING AND INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Grounding and Bonding (S.NO.04) SATIP- P-111- 01 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

WBS#30-17118 Construction of New Floating Pontoon Coast Guard WBS#30-17118 CONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD
CNTRCTR PRC

RECEIVING
1.0
INSPECTION

Storage, Handling, and Preservation


1.1 Visual Inspection for General Electrical SAIC-P-3002 SAIC-P-3002 W S
Equipment

Storage, Handling, and Preservation


1.2
Visual Inspection for Cable
SAIC-P-3201 SAIC-P-3201 W S

Manufactured Electrodes
1.3 Material Receiving SAIC-P-3701 SAIC-P-3701 H W
Visual Inspection for Ground Rods

Grounding Cable
1.4 Material Receiving SAIC-P-3705 SAIC-P-3705 H W
Visual Inspection

Accessories
Material Receiving
1.5
Visual Inspection for Exothermic Welding
SAIC-P-3018 SAIC-P-3018 H W
Materials, Molds, & Tools

2.0 INSTALLATION

Ground Electrode System


Manufactured Electrode
2.1
Installation Visual Inspection for Ground
SAIC-P-3711 SAIC-P-3711 H W
Rods

Electrical System Grounding


Ground Electrode Conductor
2.2 and Main Bonding Jumper Installation SAIC-P-3725 SAIC-P-3725 H W
Visual Inspection for LV Dry Transformer
Grounding
WBS#30-17118 Construction of New Floating Pontoon Coast Guard

MARINE SERVICES CO. TESTING AND INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Grounding and Bonding (S.NO.04) SATIP- P-111- 01 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

WBS#30-17118 Construction of New Floating Pontoon Coast Guard WBS#30-17118 CONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD
CNTRCTR PRC

Electrical System Grounding


Ground Electrode Conductor
2.3
and Main Bonding Jumper Installation
SAIC-P-3726 SAIC-P-3726 H W
Visual Inspection for Panelboard Grounding

Equipment Grounding / Bonding


and Supplementary Grounding
Equipment Ground Conductor
2.4
and Bonding Jumper Installation
SAIC-P-3740 SAIC-P-3740 H W
Visual Inspection for Process Eqpt.
Grounding / Bonding

Equipment Grounding / Bonding


and Supplementary Grounding
Equipment Ground Conductor
2.5
and Bonding Jumper Installation
SAIC-P-3747 SAIC-P-3747 H W
Visual Inspection for Tank Grounding /
Bonding

3.0 PRE-COMMISSIONING

Equipment Grounding / Bonding,


Supplementary Grounding, and
3.1 Electrical System Grounding SATR-P-3704 SATR-P-3704 H W
Ground Continuity Testing
(Installed Cable)

GENERAL NOTES

1 The first three incidents of each Inspection or testing activity listed require 100 % participation by Petro Rabigh Site Inspection Personnel.

2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
3
representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative
4
in attendance.

5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Petro Rabigh.
WBS#30-17118 Construction of New Floating Pontoon Coast Guard

MARINE SERVICES CO. TESTING AND INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Grounding and Bonding (S.NO.04) SATIP- P-111- 01 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

WBS#30-17118 Construction of New Floating Pontoon Coast Guard WBS#30-17118 CONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD
CNTRCTR PRC

Accessories include mechanical fasteners, listed grounding straps and clamps, rubber tape, plastic tape, and coatings (epoxy, aluminum alkyd, zinc chromate, and bituminous coatings).
6
Notify SA PID by RFI on initial receipt of each listed accessory (by type and/or manufacturer).

LEGEND

H Hold Point for QC Inspection/ Test R Review of Documents


W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection