Sunteți pe pagina 1din 4

MP Jal Nigam Maryadit P.I.U.

Panna
Name of The Project :- Pawai Dam MVRWSS Distt. Panna (M.P)
Name of The Contractor :- M/S Unipro Techno Infrastructure Pvt. Ltd.
Agreement No.- :- 04/2018/-19 Date 24.05.2018
Work Order No. :- 1946/340/Proc./D&M-1/MPJNM/2017-18 BHOPAL, Dated-20.04.2018
Agreement Amount :- 177.3454545 Cr.
Date of Start of Work :-09.05.2018
Date of Completion :-08.05.2020
Month of April 2020

Targeted Completion
S.No. Activities Progress Status Blance Work Remarks
up to 09 May 2020

1 2 3 4 8
1 Construction of INTAKE WELL - Surveying Completed
23.57 MLD 7 M dia., Approch Bridge 180 mtr Length Soil investigation Completed
Mechanical GA D/D Not Submitted by Firm
Structural D/D Approved
Electrical D/D Not Submitted by Firm Not submitted by
contractor
Instrumentation D/D Not Submitted by Firm
Completion of coffer Dam NA
Structure & Brick Work RCC Stair case and
Intake well up to roof level completed up to Lintel railing work
Beam level
Painting &
Completed Protection work
Completion of Approach Bridge
Pump room allied works Work not start
Erection and instrumentation item of Work not start
-
pump house
2 RAW WATER PUMPING MAIN (K9-500 mm dia. ) - (Qty as Per approved Surveying Completed
design. 1256 Mtrs) Supply of pipes -- Not Started
Soil investigation Completed Supply , Laying &
Jointing work Not
L-Section in Hydraulic Design Completed started at site
Excavation , Laying & Jointing -- Not Started
Hydro testing -- Not Started
Month of April 2020

Targeted Completion
S.No. Activities Progress Status Blance Work Remarks
up to 09 May 2020

3 WATER TREATMENT PLANT- 20.62 MLD / Staff Quarters F, H, G, I Types Surveying Completed
/ Automation / Boundary Wall Soil investigation Completed
Mechanical GA Design &Drawing Not Submitted by Firm
Structural D/D Completed
Electrical D/D Not Submitted by Firm
Instrumentation D/D Not Submitted by Firm
Flash Mixer and Inlet Chamber --
Pre settling tank and Clarifloculator --
Filter House --
Wash Water Tank --
Administrative Block -- Work not started
Clear water sump -- at site
Recycling arrangement --
Pump house --
Boundary Wall & Switch Yard 33KV --
Area Grading & Horticulture --
4 Construction of Master Balancing Resevior
i) MBR1 in Chakarbhata(MBR)i 550 KL Surveying Completed
ii) IPS in Tikariya Village Block Shahnagar,
Soil investigation Completed
Mechanical GA D/D Not Submitted by Firm
Structural D/D Completed
Electrical D/D Not Submitted by Firm
Raft and column structure Work not started
--
at site
5 CLEAR WATER PUMPING MAIN (DI K9) Surveying Completed
a) From Pumping main to village ESR 100 mm to 450 mm dia pipe Supply of pipes 141 Km 116 Km
length (Qty as Per approved design. 257503 Mtrs)
Soil investigation Completed
L-Section & Hydraulic Design Approved
Excavation , Laying & Jointing 58 Km
Hydro testing 18 Km
Month of April 2020

Targeted Completion
S.No. Activities Progress Status Blance Work Remarks
up to 09 May 2020

6 CLEAR WATER GRAVITY MAIN (DI K7) Surveying Completed


a) From Pumping main to village ESR 100 mm to 500 mm dia pipe Supply of pipes 62 Km 25 Km
length (Qty as Per approved design. 87825 Mtrs)
Soil investigation Completed
L-Section & Hydraulic Design Approved
Excavation , Laying & Jointing 28 Km
Hydro testing 3 Km

7 ELEVATED SERVICE RESERVOIRS 55 Nos (100- 390 KL) / GSR / BPT with Surveying Completed
Boundary wall and guard room Soil investigation Completed
Mechanical GA D/D Not Submitted by Firm Out of 53 ESRs and
Structural D/D Approved 2 GLSR only 28 Nos
PCC 4 Nos ESRs Work Started
at site ,Gard Room
GL Brace Beam 7 Nos and Boundry wall
staging and satair case 12 Nos. work still not
bottom ring beam & bottom slab 5 Nos started at site
full vertical wall and top slab or done --
Gard Room and Boundary wall Not started

8 RAW WATER PUMPING UNITS 4 NOS VERTICAL Design and Drawings submission of GA
TURBINE PUMPING UNITS Not Submitted by Firm
drawing
Supply of Pumps & Motors --
Installation of Pumps & motors --
Testing of Pumps and Motors -- Not started

9 CLEAR WATER PUMPING UNITS 17 NOS CENTRIFUGAL PUMPS Design and Drawings submission of GA --
drawing
Supply of Pumps & Motors --
Installation of Pumps & motors --
Testing of Pumps and Motors -- Not started
Month of April 2020

Targeted Completion
S.No. Activities Progress Status Blance Work Remarks
up to 09 May 2020

10 2 Nos of 33 KVA Electrical Sub Station allied works including 6/3 kms Design and Drawings submission of GA dra Not Submitted by Firm
and Transformer of 1.60 MvA cap. Excavation -
Supply of Power Cable, poles, wires, Transf -
PCC M15 grade of concrete - No work
Substation fencing, transfermer foundation -
Erection of Electrical Items -
Other miscellaneous work as per the requi -

11 DISTRIBUTION NETWORK - HDPE PE100- 90, 110,160,200 & 250mm dia Surveying Completed
and DI K7/K9 100 to 150 Dia.- (Qty as Per approved design. 860459 Supply of pipes 467 Km 393 Km
Mtrs)
Soil investigation Completed
L-Section & Hydraulic Design Approved
Excavation , Laying & Jointing 320 Km
Hydro testing 144 Km

12 HOUSE SERVICE CONNECTION(35348 Nos) -- No work Not started


-- Not started
Restoration of Road after House service connection 3.2 % of LS offer) No work