Documente Academic
Documente Profesional
Documente Cultură
TEEE 4204: SAFETY ENGINEERING AND MANAGEMENT
Outline
Introduction. Purpose and steps. Works inspection.
Equipment, sub‐systems, protective and control devices,
energization, performance, acceptance, commissioning tests.
Site inspection and testing.
Testing and commissioning methods for protective systems,
switchgear, transformers, cables, protection. Sequence,
interlock and protection systems.
Commissioning aspects: documentation, safety features and
rules. Safety clearance notice. Observation, trail runs and
handing over to client operating staff.
1
PART 5: TESTING AND COMMISSIONING
2
PART 5: TESTING AND COMMISSIONING
• Basic layout plans showing equipment and materials used
• Process flow
• Information on chemicals
• Storage areas
• Work force size, shifts and supervision
• Workplace rules and regulations
• Job procedures and safe work practices
• Manufacturer's specifications
• Personal Protective Equipment (PPE)
• Engineering controls
• Emergency procedures ‐ fire, first aid and rescue
3
PART 5: TESTING AND COMMISSIONING
5.2 Testing
characteristics or problems.
4
PART 5: TESTING AND COMMISSIONING
5
PART 5: TESTING AND COMMISSIONING
6
PART 5: TESTING AND COMMISSIONING
7
PART 5: TESTING AND COMMISSIONING
8
PART 5: TESTING AND COMMISSIONING
9
PART 5: TESTING AND COMMISSIONING
5.3 Commissioning
10
PART 5: TESTING AND COMMISSIONING
11
PART 5: TESTING AND COMMISSIONING
3. Emergency tests
12
PART 5: TESTING AND COMMISSIONING
13
PART 5: TESTING AND COMMISSIONING
14
PART 5: TESTING AND COMMISSIONING
Observation/DLP:
A defects liability period is a set period of time after a
construction project has been completed during which a
contractor has the right to return to the site to
remedy defects. A typical defects liability period lasts for 12
months.
During the defects liability period, typically:
1. the contractor has the right to return to the site to rectify
defects or complete unfinished work;
2. the principal is entitled to continue holding security, to secure
the contractor’s obligations in respect of incomplete or
defective work; and
3. The superintendent continues to remain involved in the
project.
TEEE 4204: SAFETY ENGINEERING AND MANAGEMENT ‐ WEGULO JG 31
15
PART 5: TESTING AND COMMISSIONING
Observation/DLP:
Under some contracts, if the contractor rectifies a defect
during the defects liability period, there will be a new defects
liability period in respect of that rectification work.
Trail runs:
In effect, trail running provides better strength training
benefits for the legs compared to road running. Trail
running also challenges coordination, agility and balance more
so than running on roads, especially if running on
technical trails full of rocks, roots and uneven terrain.
In much simply terms, its test running the equipment and
exposing it with loadings as if it was in a production
environment but in a non production environment
16
PART 5: TESTING AND COMMISSIONING
17