Documente Academic
Documente Profesional
Documente Cultură
9.1 MATERIALS
Corrosion protection systems and surface coatings shall in all cases be suitable
for exposure to their contact with environmental conditions which may include
any or all of the following :-
(1) The climatic conditions prevailing in the project area with particular
emphasis on temperature variations, high surface temperatures and high
humidities.
(4) Hydrogen sulfide and other gases emanating from sewage, septic sewage
and sewage sludges.
(5) Saline groundwater with high chloride or sulphate contents both below
the water table and in soil zones above the water table where capillary
action and the presence of oxygen may cause extremely severe
conditions.
9.1.2 Paint
Protective and decorative paint systems including primers and undercoats shall
be obtained ready mixed for use. All containers of paints and other coating
systems shall show date of manufacture, shelf life and pot life where
applicable. Paint shall be applied as per Clause 9.2.2 (refer to Clause 19.4 for
schedules of protective coatings and surface preparations).
The Contractor shall only be allowed to use paints which are delivered to the
site in sealed cans or drums bearing the name of the manufacturer and properly
labeled.
Tints and shades of final coats shall be advised by the Engineer or his
Representative.
PVC sheet materials to be used for lining concrete structures and pipelines
internally shall be manufactured from polyvinyl chloride, plasticisers and
pigments to make permanently flexible sheets.
The PVC sheet shall have a minimum thickness of 1.5 mm and shall be formed
by extrusion to have on one side locking keys or ribs of either ‘T’ or diamond
section at centers not greater than 75 mm. It shall be capable of forming a
continuous 100% effective seal with the use of welding strips or other
approved method and shall be supplied with all materials and tools for making
the joints.
The tensile strength of the material shall be not less than 17000 kN/m2.
All weld strips, patches and other sheets used in the permanent fixing of the
ribbed sheet shall be of a material having the same composition as the ribbed
sheet.
Reinforced plastic liners to be used for lining pumping stations and manholes
shall be manufactured (as per Clause 19.1.4) to the dimensions given on the
Drawings, within the following tolerances :-
(1) The work size, which is defined as the internal diameter as specified by
the manufacturer, shall be declared and shall not differ from the normal
diameter by more than ± 1%.
9/2
SECTION 9
(5) The deviation from straightness of the bore of the liner shall not exceed
20 mm.
Although the liners are not designed to be structural, they shall have a
sufficient stiffness to withstand :-
Prior to grouting of the manhole liner at least 24 hours shall be allowed for
temperature equalization between the manhole structure and the reinforced
plastic liner.
The manufacturer shall provide shop drawings of the proposed top slab liners
prior to manufacture for approval.
The manufacturer shall stipulate the maximum deflection of the slab liner
permitted without causing surface cracking to the gel coat. The Contractor
must take care not to exceed this limit, and any surface cracking that occurs
will be repaired.
(3) Bisphenol polyester resin with heavy duty glass cloth inclusion.
9/3
SECTION 9
A mortar consisting of an epoxy resin and hardener shall be mixed with a filler
material to produce a thixotropic dense trowel suited mix.
The mortar shall be manually applied to all internal surfaces and left at least
15 minutes.
Firstly the surface of the manhole walls and the surface of the cover slab soft,
benching and channel (concrete) shall be coated with isophthalic resin.
Three layers of 600 gm/m2 glass chopped strand mat shall then be applied and
impregnated with isophthalic resin to provide an approximate thickness of 5
mm.
Next one layer of 600 gm/m2 and one layer of 300 gm/m2 glass chopped strand
mat shall be applied and impregnated with vinylester resin.
Following this two layers of glass veil shall be applied and impregnated with
vinylester resin.
Bisphenol Polyester Resin with Heavy Duty Glass Cloth Inclusion System
All cleaned surfaces shall be primed with a polyester based primer to seal the
surface and aid the application of the lining.
The base coat of resin reinforced with filler shall be trowel applied to
approximately 1.5 mm thick. The reinforcing cloth shall be consolidated into
the first trowel coat with particular attention being paid to ensure that the cloth
is fully wetted out. This application shall be allowed to cure overnight before
applying the top coat of resin. This resin reinforced with the same filler shall
be troweled on and dressed with a rolling aid.
9/4
SECTION 9
The epoxy mortar system shall be a trowellable, two component epoxy resin
system consisting of a prefilled base and unfilled reactor which when mixed
shall produce a high strength, impermeable and chemically resistant mortar.
The epoxy mortar system shall have excellent chemical resistance to sodium
chloride and sulphuric acid (shall pass the relevant chemical resistence test),
and shall have high impact resistance. Typical properties are given in the
following table:
When placed on a concrete substrate the epoxy mortar system shall have an
adhesive strength of not less than the internal cohesive strength of concrete.
The epoxy mortar, or the primer where required, shall be suitable for application
onto a substrate with a moisture content of 4% or less as measured by the
"wet-check" Moisture Meter or other instruments approved by the Engineer.
The pot-life of the mixed mortar shall not be less than one hour at the
temperature at the place of application at the time of mixing. The Engineer may
9/5
SECTION 9
There shall be strict control of surface cleanliness between primer and epoxy
mortar and between coats of the same. Vacuum removal of dust and sand shall
be employed and water soluble contamination shall be removed as specified
above. Where dirt or dust has become trapped in the primed surface it shall be
removed with suitable abrasive paper. The surface being primed shall be free of
visible moisture throughout these operations.
The mortar manufacturer shall stipulate primer and epoxy re-coat intervals for
all curing temperatures likely to be encountered and these shall be adopted with
a maximum tolerance of +4 hours. Where this is exceeded the surfaces to be
re-coated shall be suitably abraded to remove gloss.
Bituminous emulsion shall be to the approved standard and shall not contain
less than 53 % of bitumen.
9/6
SECTION 9
9.2.1 General
The permissible rate of permeation of all protection systems shall not exceed
0.0027 per inches (ASTM, 1 per inch = 1 gramme of water per hour per square
foot (0.0929 m2) per mil (0.0254 mm) of thickness for a 1 inch (25.4 mm)
difference in Hg vapour pressure on each side of a membrane.
9/7
SECTION 9
The membrane shall be tropical grade, cross laminated to have high tear
strength; and puncture and impact resistance and shall be chemically
resistant for protection against aggressive soils and contaminated
groundwater.
2
Tape Strength ASTM D638 Long 4.2 N/mm2
Trans 4.8 N/mm2
The surface shall first be wire brushed and all dust and loose scale
removed. Three coats of bituminous rubber emulsion paint shall then be
applied. The second coat shall not be the same colour as either the 1st or
3rd.
The surface shall first be wire brushed and all dust and loose scale
removed (refer to Clause 19.4 for schedule of surface preparations). An
epoxy resin or other primer/sealer (for concrete and allied substrates)
shall then be applied followed by coats of high build epoxy airless spray
or other coatings to give a minimum dry film thickness (dft) of 300
microns. Freedom from pinholes shall be established by use of a spark
tester. The approved paint system must have adequate flexibility to suit
the thermal movements of the concrete without cracking whilst
maintaining an effective bond.
The PVC sheet lining shall be fixed such that the keys or ribs are cast
into the concrete surface. The lining shall be capable of taking up the
same profile as the concrete substrate as indicated on the Drawings.
9/9
SECTION 9
In particular:-
The manufacturer shall visit the site to demonstrate to the Contractor in the
presence of the Engineer's Representative the methods of handling and
lifting, including formation of the joints between the chamber liner.
The Contractor is reminded that these liners are not designed to withstand
pressure exerted by the concrete during construction.
Where the Contractor is required for any reason to cut reinforced plastic
liners, he shall seal the exposed ends with an approved resin before
incorporating the cut reinforced plastic in the work. No cut reinforced plastic
shall be used until the resin has cured.
9/10
SECTION 9
9.3.1 General
The Contractor shall provide the labor, materials and equipment necessary to
install and test the odor control facilities as shown on the Contract Drawings
and as specified herein. The odor control units shall be either of the
activated carbon filter types or of the natural soil filter bed types as indicated
in the Drawings.
The activated carbon odor control filter shall be furnished and installed in
accordance with Clause 17.2.48. The air blowers for the odor control unit
shall be as specified in Clause 17.2.17.
9.3.4.1 Materials
The HDPE liner shall be furnished and installed in accordance with Clauses
19.3.4 and 19.2.13 and as shown on the Contract Drawings.
Washed Stone
Stone for the air plenum shall be washed, rounded, uncrushed, well graded in
size from 20 mm to 25 mm and consisting of clean, and durable particles free
from dirt, vegetation or other objectionable matter and free from an excess of
9/11
SECTION 9
Wood Chips
Soil Filter
The soil filter shall be a mixture of approved natural sand or sandy loam and
treated compost. The compacted soil/compost mix shall have a 50 percent
porosity. The compost shall be a product of thermophilic aerobic
stabilization. It shall be adequately stabilized, so as to be completely free of
any odors. The compost shall be friable, pass through a 13 mm mesh screen,
and be free of stones, stocks and all objectionable debris. Compost shall have
a pH of 5.5 to 8.0 and no less than 25 percent volatile solids. The compost
source is subject to the review of the Engineer. All compost shall be "cured"
to the point that it is no longer self heating.
9.3.4.2 Installation
The Contractor shall place the stone, wood chips, soil and compost in layers
of uniform thickness as indicated on the Contract Drawing(s) or as directed
by the Engineer. The stone, wood ships, soil and compost shall be placed so
as not to damage the aeration piping. Damaged piping is to be replaced by
the Contractor at no additional cost to the owner.
9.3.4.3 Monitoring
The Contractor shall perform the following selected soil and atmospheric
analyses at the direction of the Engineer, but not more than once per week
with the exception of soil moisture and pH, for the length of the natural soil
filter maintenance period. The results of the analyses shall be recorded and
presented to the Engineer at the end of each month. Soil samples must be
taken so as not to disrupt the even distribution of air through the odor control
filter.
9/12
SECTION 9
9.3.4.4 Maintenance
The Contractor shall test the porosity of the compacted soil/compost mixture
before placement and provide the results of the test to the Engineer.
9/13